CN113404312A - Temporary unloading platform for building construction floor - Google Patents
Temporary unloading platform for building construction floor Download PDFInfo
- Publication number
- CN113404312A CN113404312A CN202110866065.4A CN202110866065A CN113404312A CN 113404312 A CN113404312 A CN 113404312A CN 202110866065 A CN202110866065 A CN 202110866065A CN 113404312 A CN113404312 A CN 113404312A
- Authority
- CN
- China
- Prior art keywords
- bottom plate
- building construction
- temporary
- stacking
- weight
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009435 building construction Methods 0.000 title claims abstract description 24
- 238000007599 discharging Methods 0.000 claims description 12
- 238000010276 construction Methods 0.000 claims description 7
- 230000003750 conditioning effect Effects 0.000 claims description 3
- 238000005303 weighing Methods 0.000 claims 2
- 238000000034 method Methods 0.000 description 3
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000006243 chemical reaction Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/166—Landings, receiving platforms
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01G—WEIGHING
- G01G19/00—Weighing apparatus or methods adapted for special purposes not provided for in the preceding groups
- G01G19/52—Weighing apparatus combined with other objects, e.g. furniture
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01G—WEIGHING
- G01G23/00—Auxiliary devices for weighing apparatus
- G01G23/18—Indicating devices, e.g. for remote indication; Recording devices; Scales, e.g. graduated
- G01G23/36—Indicating the weight by electrical means, e.g. using photoelectric cells
- G01G23/365—Indicating the weight by electrical means, e.g. using photoelectric cells involving comparison with a reference value
-
- G—PHYSICS
- G08—SIGNALLING
- G08B—SIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
- G08B21/00—Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
- G08B21/18—Status alarms
- G08B21/24—Reminder alarms, e.g. anti-loss alarms
-
- G—PHYSICS
- G08—SIGNALLING
- G08B—SIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
- G08B3/00—Audible signalling systems; Audible personal calling systems
- G08B3/10—Audible signalling systems; Audible personal calling systems using electric transmission; using electromagnetic transmission
-
- G—PHYSICS
- G08—SIGNALLING
- G08B—SIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
- G08B7/00—Signalling systems according to more than one of groups G08B3/00 - G08B6/00; Personal calling systems according to more than one of groups G08B3/00 - G08B6/00
- G08B7/06—Signalling systems according to more than one of groups G08B3/00 - G08B6/00; Personal calling systems according to more than one of groups G08B3/00 - G08B6/00 using electric transmission, e.g. involving audible and visible signalling through the use of sound and light sources
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Electromagnetism (AREA)
- Business, Economics & Management (AREA)
- Emergency Management (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Burglar Alarm Systems (AREA)
Abstract
The invention discloses a temporary unloading platform for building construction floors, which comprises two horizontally arranged main beams, wherein the two main beams are arranged in parallel and have the same height, horizontal bearing bottom plates are laid at the tail ends of the two main beams, horizontal stacking bottom plates are arranged on the bearing bottom plates, a weight sensor is arranged between the bearing bottom plates and the stacking bottom plates and used for detecting the weight of stacked materials on the stacking bottom plates, and the temporary unloading platform also comprises a controller connected with the weight sensor and an alarm connected with the controller. Form double-deck bottom plate structure through bearing bottom plate and stack bottom plate to set up weight sensor between two-layer bottom plate, the girder is connected to the bearing bottom plate, stacks the material on the bottom plate, with pressure transfer to weight sensor, real-time supervision stacks material weight, starts the warning when stacking the material and reaching or surpassing the allowable weight, ensures the security of the platform use of unloading.
Description
Technical Field
The invention relates to the field of building construction, in particular to a temporary discharging platform for a building construction floor.
Background
At present, a bottom plate is laid on a main beam of a floor temporary unloading platform of a building construction site, materials are stacked on the bottom plate, but the main beam and the bottom plate are limited in strength, so that the materials cannot be stacked without an upper limit.
In order to limit the upper weight limit of the stacked materials on each bottom plate, in the prior art, the amount of the stacked materials is controlled by hanging weight limit cards, and the upper weight limit is calculated and then marked on the weight limit cards. However, the above method cannot monitor whether the weight of the actually stacked material is overweight, and overweight conditions may occur, so that the safety has great hidden danger.
Therefore, how to provide a stable and safe temporary discharging platform for the construction floor is a technical problem to be solved by those skilled in the art at present.
Disclosure of Invention
The invention aims to provide a temporary unloading platform for a building construction floor, which has a double-layer bottom plate structure, wherein a weight sensor is arranged between two bottom plates, so that an alarm can be started when the weight of stacked materials reaches or exceeds the allowable weight, the weight of the stacked materials is monitored in real time, and the use safety of the unloading platform is ensured.
In order to solve the technical problem, the invention provides a temporary unloading platform for a building construction floor, which comprises two horizontally arranged main beams, wherein the two main beams are arranged in parallel and have the same height, horizontal bearing bottom plates are laid at the tail ends of the two main beams, horizontal stacking bottom plates are arranged on the bearing bottom plates, weight sensors are arranged between the bearing bottom plates and the stacking bottom plates and used for detecting the weight of stacked materials on the stacking bottom plates, and the temporary unloading platform also comprises a controller connected with the weight sensors and an alarm connected with the controller.
Preferably, a plurality of said weight sensors are evenly distributed under said stacking floor.
Preferably, guardrails are arranged above the two side edges and the tail end edge of the stacking bottom plate.
Preferably, protection plates attached to the guardrails are installed above the edges of the two sides and the edge of the tail end of the stacking bottom plate.
Preferably, the controller and the alarm are mounted on the upper portion of the protection plate.
Preferably, the guardrail inboard is provided with the locating part, girder middle part below is provided with the baffle.
Preferably, the guard rail comprises a plurality of cross bars and vertical bars arranged in a staggered manner.
Preferably, the weight sensor is connected with the controller through a conditioning conversion circuit.
Preferably, the alarm is embodied as an audible alarm.
Preferably, the main beam is provided with an unloading hanging ring and a hoisting hanging ring.
The invention provides a temporary unloading platform for a building construction floor, which comprises two horizontally arranged main beams, wherein the two main beams are arranged in parallel and have the same height, horizontal bearing bottom plates are laid at the tail ends of the two main beams, horizontal stacking bottom plates are arranged on the bearing bottom plates, a weight sensor is arranged between the bearing bottom plates and the stacking bottom plates and used for detecting the weight of stacked materials on the stacking bottom plates, and the temporary unloading platform also comprises a controller connected with the weight sensor and an alarm connected with the controller.
Form double-deck bottom plate structure through bearing bottom plate and stack bottom plate to set up weight sensor between two-layer bottom plate, the girder is connected to the bearing bottom plate, stacks the material on the bottom plate, with pressure transfer to weight sensor, real-time supervision stacks material weight, starts the warning when stacking the material and reaching or surpassing the allowable weight, ensures the security of the platform use of unloading.
Drawings
Fig. 1 is a front sectional view of a temporary discharging platform for a construction floor according to an embodiment of the present invention;
FIG. 2 is an external elevation view of one embodiment of a temporary discharge platform for a construction floor provided in accordance with the present invention;
fig. 3 is a schematic top view of a temporary discharging platform for a building construction floor according to an embodiment of the present invention.
Detailed Description
The core of the invention is to provide a temporary unloading platform for a building construction floor, a weight sensor is arranged between two bottom plates through a double-layer bottom plate structure, and the temporary unloading platform can start an alarm when the weight of stacked materials reaches or exceeds the allowable weight, monitor the weight of the stacked materials in real time and ensure the use safety of the unloading platform.
In order that those skilled in the art will better understand the disclosure, the invention will be described in further detail with reference to the accompanying drawings and specific embodiments.
Referring to fig. 1 to 3, fig. 1 is a front sectional view of a temporary discharging platform for a building construction floor according to an embodiment of the present invention; FIG. 2 is an external elevation view of one embodiment of a temporary discharge platform for a construction floor provided in accordance with the present invention; fig. 3 is a schematic top view of a temporary discharging platform for a building construction floor according to an embodiment of the present invention.
The invention provides a temporary unloading platform for a building construction floor, which comprises two horizontally arranged main beams 1, wherein the two main beams 1 are arranged in parallel and have the same height, the head ends of the main beams 1 are used for fixed connection, the tail ends of the two main beams 1 are paved with horizontal bearing bottom plates 2, namely the bearing bottom plates 2 are rectangular plates, the two main beams 1 are arranged below one group of opposite edges in the bearing bottom plates 2 and are in contact fixed connection with the main beams 1, the distance between the two main beams 1 is equal to the width of the bearing bottom plate 2, and the head ends and the tail ends of the bearing bottom plates 2 are arranged on the other group of opposite edges. Other arrangement modes can be adopted, and the connection modes can be adjusted according to conditions, for example, the two side edges of the bearing bottom plate 2 exceed the main beam 1, and the invention is within the protection scope.
Meanwhile, a horizontal stacking bottom plate 3 is arranged on the bearing bottom plate 2, a gap is arranged between the bearing bottom plate 2 and the stacking bottom plate 3, a weight sensor 4 is installed in the gap, namely the weight sensor 4 is installed between the bearing bottom plate 2 and the stacking bottom plate 3 and used for detecting the weight of stacked materials on the stacking bottom plate 3, and the stacking bottom plate further comprises a controller 5 connected with the weight sensor 4 and an alarm 6 connected with the controller 5.
Form double-deck bottom plate structure through bearing bottom plate 2 and stacking bottom plate 3, and set up weight sensor 4 between two-layer bottom plate, girder 1 is connected to bearing bottom plate 2, stack the material on the bottom plate 3, transmit pressure to weight sensor 4, real-time supervision stacks material weight, weight sensor 4 will detect data and send to controller 5, after reaching predetermined numerical value, controller 5 control alarm 6 sends out the police dispatch newspaper, remind personnel not to add the material again, start the warning when stacking the material and reach or exceed and allow weight, ensure the security of the platform use of unloading.
Specifically, weight sensor 4 is through conditioning converting circuit 11 connection director 5, and controller 5 is single chip microcomputer control, and wherein, alarm 6 specifically is sound alarm, reminds personnel through sound, also can adopt light alarm, further promotes alarm effect, still can increase a display, can show weight detection result in real time.
In the temporary discharging platform for the building construction floor provided by the embodiment of the invention, a plurality of weight sensors 4 are uniformly distributed below the stacking bottom plate 3, so that stable support is provided, system redundancy is provided, and the reliability of the system is ensured. Specifically, four weight sensors 4 may be provided, evenly arranged along the extending direction of the main beam 1.
In order to improve the safety of use, guardrails 7 are arranged above the two side edges and the tail end edge of the stacking bottom plate 3. Further, protection plates 8 are arranged above the edges of the two sides and the edge of the tail end of the stacking bottom plate, and the protection plates 8 are attached to the guardrails 7. The inner side of the guardrail 7 is provided with a limiting part 9, and the middle lower part of the main beam 1 is provided with a baffle plate 10.
Specifically, guardrail 7 is including a plurality of horizontal poles and the montant of staggered arrangement, and horizontal pole and montant form the rectangular frame who splices in proper order, promote support stability, also can adopt other arrangement methods, like the triangle-shaped frame, stability is better.
Install controller 5 and alarm 6 on 8 upper portions of guard plate, protection device prevents to collide with, and alarm 6 sets up in the top can arouse personnel's attention better simultaneously.
On the basis of the temporary unloading platform of the building construction floor provided by each specific embodiment, the main beam 1 is provided with an unloading hanging ring 12 and a hoisting hanging ring 13 for unloading and hoisting each part. The components can be connected by welding, clamping or bolt connection, and the invention is in the protection scope.
The temporary discharging platform for the building construction floor provided by the invention is described in detail above. The principles and embodiments of the present invention are explained herein using specific examples, which are presented only to assist in understanding the method and its core concepts. It should be noted that, for those skilled in the art, it is possible to make various improvements and modifications to the present invention without departing from the principle of the present invention, and those improvements and modifications also fall within the scope of the claims of the present invention.
Claims (10)
1. The utility model provides a building construction floor platform of unloading temporarily, its characterized in that, including two girder (1) that the level set up, two girder (1) set up side by side and highly the same, two horizontal bearing bottom plate (2) are laid to girder (1) end, be provided with horizontally stack bottom plate (3) on bearing bottom plate (2), bearing bottom plate (2) with stack and install weighing transducer (4) between bottom plate (3) for detect stack the weight of stacking the material on bottom plate (3), still including connecting controller (5) and the connection of weighing transducer (4) alarm (6) of controller (5).
2. Construction floor temporary discharge platform according to claim 1, characterized in that a plurality of said weight sensors (4) are evenly distributed under said stacking floor (3).
3. The temporary discharging platform for building construction floors as claimed in claim 1, wherein guardrails (7) are provided above both side edges and a distal edge of the stacking bottom plate (3).
4. A temporary discharge platform for building construction floors according to claim 3, wherein protection plates (8) attached to the guardrails (7) are installed above both side edges and the end edge of the stacking bottom plate (3).
5. A temporary discharge platform for building construction floors according to claim 4, characterized in that the controller (5) and the alarm (6) are installed on the upper portion of the protection plate (8).
6. The temporary discharging platform for building construction floors according to claim 5, wherein a limiting piece (9) is arranged inside the guardrail (7), and a baffle (10) is arranged below the middle part of the main beam (1).
7. Construction floor temporary discharge platform according to claim 6, characterized in that said guardrail (7) comprises a plurality of cross bars and vertical bars arranged in a staggered manner.
8. The construction floor temporary discharge platform according to claim 1, characterized in that said weight sensor (4) is connected to said controller (5) through a conditioning and switching circuit (11).
9. The building construction floor temporary discharge platform according to claim 1, characterized in that said alarm (6) is embodied as an acoustic alarm.
10. The temporary discharging platform of a building construction floor according to any one of claims 1 to 9, characterized in that the main beam (1) is provided with a discharging lifting ring (12) and a lifting ring (13).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110866065.4A CN113404312A (en) | 2021-07-29 | 2021-07-29 | Temporary unloading platform for building construction floor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110866065.4A CN113404312A (en) | 2021-07-29 | 2021-07-29 | Temporary unloading platform for building construction floor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN113404312A true CN113404312A (en) | 2021-09-17 |
Family
ID=77688014
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110866065.4A Pending CN113404312A (en) | 2021-07-29 | 2021-07-29 | Temporary unloading platform for building construction floor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113404312A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN206591841U (en) * | 2017-02-14 | 2017-10-27 | 榆钱(北京)科技有限公司 | A kind of discharging platform with warning function |
CN208734101U (en) * | 2018-07-30 | 2019-04-12 | 云南建投第十三建设有限公司 | A kind of high-building construction overhanging unloading platform device |
CN210530368U (en) * | 2019-08-09 | 2020-05-15 | 天一建设发展有限公司 | Telescopic construction platform of unloading |
CN210858055U (en) * | 2019-08-20 | 2020-06-26 | 广东中邺山河建筑工程有限公司 | Convenient type construction platform of unloading |
CN215907455U (en) * | 2021-07-29 | 2022-02-25 | 中建八局第四建设有限公司 | Temporary unloading platform for building construction floor |
-
2021
- 2021-07-29 CN CN202110866065.4A patent/CN113404312A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN206591841U (en) * | 2017-02-14 | 2017-10-27 | 榆钱(北京)科技有限公司 | A kind of discharging platform with warning function |
CN208734101U (en) * | 2018-07-30 | 2019-04-12 | 云南建投第十三建设有限公司 | A kind of high-building construction overhanging unloading platform device |
CN210530368U (en) * | 2019-08-09 | 2020-05-15 | 天一建设发展有限公司 | Telescopic construction platform of unloading |
CN210858055U (en) * | 2019-08-20 | 2020-06-26 | 广东中邺山河建筑工程有限公司 | Convenient type construction platform of unloading |
CN215907455U (en) * | 2021-07-29 | 2022-02-25 | 中建八局第四建设有限公司 | Temporary unloading platform for building construction floor |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN215907455U (en) | Temporary unloading platform for building construction floor | |
CN113404312A (en) | Temporary unloading platform for building construction floor | |
CN114291705A (en) | Super high-rise self-lifting attached overhanging type interlayer material transfer platform | |
CN103967263A (en) | Novel hydraulic automatic climbing discharging platform | |
CN203947758U (en) | Novel hydraulic automatic climbing discharging platform | |
CN220376075U (en) | Building block hoist and mount guard box | |
CN114232970A (en) | Installation method of super high-rise self-lifting attached overhanging type interlayer material transfer platform | |
CN216737255U (en) | Building tower crane with safety monitoring system | |
CN207739649U (en) | A kind of construction discharging platform | |
CN206591841U (en) | A kind of discharging platform with warning function | |
CN212129859U (en) | Detachable steel structure aerial work operating platform | |
CN216616897U (en) | Overload alarm type overhanging discharging platform | |
CN201694208U (en) | Impurity intrusion detection device | |
CN112814409A (en) | Construction site faces limit and prevents ground bed board and system that falls | |
CN215168192U (en) | Overhanging type discharging platform | |
CN202830787U (en) | Duplex beam for bridge construction | |
CN213573073U (en) | Discharging platform device | |
CN207739607U (en) | A kind of elevator well crosshead | |
CN203729571U (en) | Tool type crawling ladder used for construction site | |
CN211761382U (en) | Platform is stacked to modularization reinforcing bar | |
CN213301456U (en) | Bridge monitoring alarm based on internet of things | |
CN207619814U (en) | Steel suspension bridge | |
CN206346507U (en) | A kind of steel truss girder bridge construction safe passageway system | |
CN220392723U (en) | Overload alarm type cantilever unloading platform | |
CN212507692U (en) | External hanging type integral lifting enclosure system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |