CN107165062A - A kind of method for removing Existing Railway Line gate-type pier capping beam protecting canopy frame - Google Patents

A kind of method for removing Existing Railway Line gate-type pier capping beam protecting canopy frame Download PDF

Info

Publication number
CN107165062A
CN107165062A CN201710548953.5A CN201710548953A CN107165062A CN 107165062 A CN107165062 A CN 107165062A CN 201710548953 A CN201710548953 A CN 201710548953A CN 107165062 A CN107165062 A CN 107165062A
Authority
CN
China
Prior art keywords
crossbeam
steel
steel pipe
jack
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710548953.5A
Other languages
Chinese (zh)
Other versions
CN107165062B (en
Inventor
付健鹏
孙勇刚
夏建松
周伟
雷兵
王党峰
张波
米艳琳
赵学
黄朝阳
李建新
李长白
乔非超
崔红云
张璐璠
王素灵
赵玉洁
王红叶
何军
夏绍见
何国强
高子玉
连孝隆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cr7bg No1 Engineering Co Ltd
First Engineering Co Ltd of China Railway Seventh Group Co Ltd
Original Assignee
Cr7bg No1 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cr7bg No1 Engineering Co Ltd filed Critical Cr7bg No1 Engineering Co Ltd
Priority to CN201710548953.5A priority Critical patent/CN107165062B/en
Publication of CN107165062A publication Critical patent/CN107165062A/en
Application granted granted Critical
Publication of CN107165062B publication Critical patent/CN107165062B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

A kind of method for removing Existing Railway Line gate-type pier capping beam protecting canopy frame, it is related to construction of railways field, the present invention is using steel pipe column fluting, allowing D types, just beam longeron is fallen into the steel pipe column groove of opening, so as to which protecting canopy frame be reduced, to remove D types just beam crossbeam, crossbeam brace, which is removed, provides working space, not only it ensure that Existing Railway Line safety but also solved protecting canopy frame and bear bent cap and pushed down the problem that can not be taken out, the present invention is after transom pier Coping Construction is complete, ensure in the case of Existing Railway Line safety to the D types of bent cap bottom just beam, steel pipe column, I-steel, scaffold etc. carries out safety, quickly remove, it is adapted to large-scale promotion and application.

Description

A kind of method for removing Existing Railway Line gate-type pier capping beam protecting canopy frame
【Technical field】
The present invention relates to construction of railways field, and in particular to a kind of side of dismounting Existing Railway Line gate-type pier capping beam protecting canopy frame Method.
【Background technology】
Known, to adapt to the target call built a well-off society in an all-round way, the railway network will expand scale, and perfect frame improves matter Amount, rapid expansion transport capacity improves rapidly equipment.The year two thousand twenty is expected, china railway revenue kilometres reach that 120,000 is public In, main busy trunk lines are realized and separated lines for passenger and freight, and complex line rate and electrochemical rate respectively reach 50% and more than 60%, and transport capacity meets state People's economy and social development need, and major technique equipment reaches or approaches advanced international standards.Railway is in actual work progress In, particularly larger in the special region difficulty of construction of some environment, working security is also poor, with white mountain village two-wire grand bridge Exemplified by line construction, white mountain village two-wire grand bridge total length 3612.179m, wherein 37#, 38# pier are across existing in transom pier box beam Hunan and Guangxi railway, bridge and existing Hunan and Guangxi railway angle are 12 °, and transom pier and existing Hunan and Guangxi railway angle are 102 °, 37#, 38# Formula pier capping beam is designed as post stretching C50 prestressed reinforced concretes, and sectional dimension is 3 × 2.5 meters, and 37# pier capping beams bottom is away from existing Line rail level clear height is 7.982m;38# pier capping beams bottom is 8.144m away from both wired rail level clear height.Because white mountain village two-wire grand bridge 37#, Across existing Hunan and Guangxi railway on 38# transom piers, bent cap weighs 480 tons, and existing Bailey beam and rice steelframe can not be used by being limited by clear height Sky construction, difficulty of construction and very risky, therefore, applicant investigated the construction method of a kind of both wired transom pier bent cap, But after the completion of transom pier Coping Construction, need in the case where ensureing Existing Railway Line safety to the D types of bent cap bottom just beam, Steel pipe column, I-steel, scaffold etc. are removed, then how to be provided a kind of relatively reasonable construction method and also seemed have particularly It is important.
【The content of the invention】
It is not enough present in background technology to overcome, remove Existing Railway Line gate-type pier capping beam protection canopy the invention provides one kind The method of frame, the present invention is after transom pier Coping Construction is complete, it is ensured that to the D types of bent cap bottom in the case of Existing Railway Line safety Just beam, steel pipe column, I-steel, scaffold etc. carry out safety, quickly removed.
To realize goal of the invention as described above, the present invention uses technical scheme as described below:
A kind of method for removing Existing Railway Line gate-type pier capping beam protecting canopy frame, methods described specifically includes following steps:
The first step, removes chamfering scaffold:
Warning is set when removing scaffold first, eye-catching caution notice is hung, forbids non-operator and ground construction personnel It is current, and there is special messenger to be responsible for warning;Wherein long vertical rod, the dismounting of brace are carried out with two people, it is impossible to separate operaton, when coming off duty It should check whether firmly, or add interim fixed support, prevent accident;When removing outrigger, steel pipe and fastener had forbidden intrusion both Wired roadbed, the steel pipe of dismounting is placed in away from roadbed side, is torn open afterwards by first filling from top to bottom, the order first torn open is filled afterwards;Specifically Dismounting order be:Safety net, bridging, leger, small cross bar, vertical rod, are removed from top to bottom, and a step one is clear, must not use and step on Step formula is removed, and is forbidden upper and lower while operation;Meeting high wind, rainy weather, it is impossible to carry out outrigger dismounting;The steel pipe of dismounting and buckle Part classification is stacked, and forbids high-altitude throwing;
Second step, hangs out pavement job platform:
In vertical skylight point job platform is hung out using crane;
D types just beam, drops in the 3rd step:
First in the fulcrum of transom pier two respectively with jack connection ¢ 36mm~just beam is caught 50mm steel wire ropes by D types, uses jack Steel wire rope is tensed, power is able to eat, jack pocket D types just beam;Then with four welding gun along along the first transverse cuts transom pier in I-steel side The steel pipe column top ring flange of side four, notes cutting along I-steel flange plate during cutting, while keeping cut surface to get out of the way I-shaped Steel 2~3cm of flange plate, must not burn I-steel, finally four steel pipe column ring flanges on the outside of transverse cuts transom pier again;Transom pier After two ends ring flange has been cut, four steel pipe columns on the inside of cutting transom pier are first found, then found four steel on the outside of cutting transom pier Tubing string, cuts 1~2cm every time, and transom pier two ends symmetrically wait height to cut, allow I-steel uniform settlement into steel pipe column otch, Every steel pipe column cut height reaches 10cm~20cm and completes to stop cutting after beam;
4th step, removes D types just beam crossbeam brace:
In skylight point, the lumps of wood is completely spread on girder falling, the lumps of wood is fixed on girder falling with iron wire, workman lies on the lumps of wood and torn open Except brace, brace moves to both sides after dismantling, then hang brace onto ground, to prevent bolt from dropping to both wired sides in full paving The wooden both sides binding lumps of wood is used as baffle plate;
5th step, removes D types just beam crossbeam:
Before just beam crossbeam is removed in D types first, bent cap bed die and the lumps of wood are plucked out;The dismounting of crossbeam, is constructed using skylight point, tears horizontal stroke open Liang Shi, first skylight point, from span centre toward two ends, first removes connection metal plate to unload based on bolt, then loosens vertical bolt, to prevent During removal bolt, bolt falls into both wired and influences both wired traffic safety, the lumps of wood ability after removal crossbeam on girder falling Remove, after whole vertical bolt loosenesses, then by vertical disassembling bolts, but the two ends of every crossbeam each remain a vertical bolt Do not unload, laid down again when the root crossbeam slides, take out crossbeam operation and completed successively in follow-up skylight point, from two ends to span centre direction Removed by root;The method that crossbeam is exited from just beam is:Anti-fall back is less than crossbeam bottom, in order to avoid crossbeam pounds anti-during falling beam Fall beam, the instrument used is:It is connected with jack with crossbeam two ends, connecting plate, bracket, the bolt of crossbeam are slowly loose after all coming loose Jack is driven, crossbeam is put on the lumps of wood on girder falling, then with jack support to job platform, is hung out crossbeam with crane;It is horizontal Beam will prevent D type beams from toppling over when removing in the middle of remaining last two, now should all loosen jack and be taken with the lumps of wood at its two ends Bearing diagonal is by D type beam supporting & stablizings;
6th step, hangs out D types just beam longeron:
Crossbeam removes crossbeam as early as possible after disintegrating with longeron, unclamp jack, hang out longeron, and just the longeron of beam removes block circuit, Hung out using crane, just beam longeron is hung out in two times, unclamp side jack and hang out a side girder, then unclamp opposite side jack, Hang out another side girder;
7th step, removes sleeper, H profile steel, girder falling, I-steel:
Using skylight point, the sleeper of steel pipe column branch pier top, H profile steel, I-steel are hung down with crane, by bent cap bottom girder falling H profile steel is removed with jack, and application block point is hung to ground;
8th step, removes steel pipe column buttress:
Using skylight point, fixing bolt on ring flange is first removed, steel pipe column is hauled with crane, then dismantle the angle being connected with pier stud Steel, finally hangs out steel pipe column buttress.
The method of described dismounting Existing Railway Line gate-type pier capping beam protecting canopy frame, the crane is 100T cranes.
The method of described dismounting Existing Railway Line gate-type pier capping beam protecting canopy frame, the size of the lumps of wood for 10cm × 10cm。
In the method for described dismounting Existing Railway Line gate-type pier capping beam protecting canopy frame, the 6th step block circuit when Between be 60 minutes.
Using technical scheme as described above, the present invention has superiority as described below:
A kind of method for removing Existing Railway Line gate-type pier capping beam protecting canopy frame of the present invention, the present invention is opened using steel pipe column Groove, allowing D types, just beam longeron is fallen into the steel pipe column groove of opening, so as to protecting canopy frame be reduced, to remove D types just beam crossbeam, horizontal stroke Beam brace, which is removed, provides working space, not only ensure that Existing Railway Line safety but also had solved protecting canopy frame and bear bent cap and has pushed down nothing The problem that method is taken out, the present invention is after transom pier Coping Construction is complete, it is ensured that to bent cap bottom in the case of Existing Railway Line safety D types just beam, steel pipe column, I-steel, scaffold etc. carry out safety, quickly remove, be adapted to large-scale promotion and application.
【Embodiment】
The present invention can be explained in more detail by the following examples, the invention is not limited in the following examples;
It is of the present invention it is a kind of remove Existing Railway Line gate-type pier capping beam protecting canopy frame method, methods described specifically include as Lower step:
The first step, removes chamfering scaffold:
Warning is set when removing scaffold first, eye-catching caution notice is hung, forbids non-operator and ground construction personnel It is current, and there is special messenger to be responsible for warning;Wherein long vertical rod, the dismounting of brace are carried out with two people, it is impossible to separate operaton, when coming off duty It should check whether firmly, or add interim fixed support, prevent accident;When removing outrigger, steel pipe and fastener had forbidden intrusion both Wired roadbed, the steel pipe of dismounting is placed in away from roadbed side, is torn open afterwards by first filling from top to bottom, the order first torn open is filled afterwards;Specifically Dismounting order be:Safety net, bridging, leger, small cross bar, vertical rod, are removed from top to bottom, and a step one is clear, must not use and step on Step formula is removed, and is forbidden upper and lower while operation;Meeting the weathers such as high wind, rain, it is impossible to carry out outrigger dismounting;The steel pipe of dismounting and buckle Part classification is stacked, and forbids high-altitude throwing;
Second step, hangs out pavement job platform:
In vertical skylight point job platform is hung out using 100T cranes;
D types just beam, drops in the 3rd step:
First three point one of two fulcrum of transom pier across, 2/3rds across place, it is each with a 10T jacks connection ¢ 36mm~50mm steel By D types, just beam is caught cord, is tensed steel wire rope with jack, is able to eat power, jack pocket D types just beam;Then with four welding gun along work Four steel pipe columns on the inside of word steel side elder generation transverse cuts transom pier(Left two, pier, right two, pier)Ring flange is pushed up, noting during cutting will Cut along I-steel flange plate, while keeping cut surface to get out of the way I-steel 2~3cm of flange plate, must not burn I-steel, finally Four steel pipe columns on the outside of transverse cuts transom pier again(Left two, pier, right two, pier)Ring flange;The ring flange cutting of transom pier two ends After complete, four steel pipe columns on the inside of cutting transom pier are first found, then found four steel pipe columns on the outside of cutting transom pier, 1 is cut every time ~2cm, transom pier two ends symmetrically wait height to cut, and allow I-steel uniform settlement into steel pipe column otch, every steel pipe column otch Highly reach 10cm~20cm and complete to stop cutting, the wherein preferred 10cm of cut height after beam;
4th step, removes D types just beam crossbeam brace:
In skylight point, 10cm × 10cm lumps of wood is completely spread on girder falling, the lumps of wood is fixed on girder falling with iron wire, workman lies Brace is removed on the lumps of wood, brace moves to both sides, then hangs brace onto ground after dismantling, to prevent bolt from dropping to both wired Baffle plate is used as in lumps of wood both sides binding 10cm × 10cm lumps of wood of full paving;
5th step, removes D types just beam crossbeam:
Before just beam crossbeam is removed in D types first, bent cap bed die and 10cm × 10cm lumps of wood are plucked out;The dismounting of crossbeam, utilizes skylight Point construction, when tearing crossbeam open, first skylight point is to unload based on bolt, from span centre toward two ends, first removes connection metal plate, then loosen vertical Bolt, to prevent during removal bolt, bolt falls into both wired and influences both wired traffic safeties, after removal crossbeam on girder falling The lumps of wood could remove, after whole vertical bolt loosenesses, then by vertical disassembling bolts, but the two ends each surplus one of every crossbeam The vertical bolt of root is not unloaded, and is laid down again when the root crossbeam slides, and is taken out crossbeam operation and is completed successively in follow-up skylight point, by two ends Removed to span centre direction by root;The method that crossbeam is exited from just beam is:Anti-fall back is less than crossbeam bottom, in order to avoid falling the beam phase Between crossbeam pound girder falling, the instrument used is:It is connected with 1.5T jacks with crossbeam two ends, connecting plate, bracket, the bolt of crossbeam Come up jack after all coming loose, and crossbeam is put on the lumps of wood on girder falling, then with jack support to job platform, uses crane Crossbeam is hung out;Crossbeam will prevent D type beams from toppling over when removing in the middle of remaining last two, now jack should all be loosened into use side Wood takes bearing diagonal at its two ends by D type beam supporting & stablizings;
6th step, hangs out D types just beam longeron:
Crossbeam removes crossbeam as early as possible after disintegrating with longeron, unclamp jack, hang out longeron, and just the longeron of beam removes block circuit 60 Minute, hung out using 100T cranes, just beam longeron is hung out in two times, unclamp side jack and hang out a side girder, then unclamp another Side jack, hangs out another side girder;
7th step, removes sleeper, H profile steel, girder falling, I-steel:
Using skylight point, the sleeper of steel pipe column branch pier top, H profile steel, I-steel are hung down with crane, by bent cap bottom girder falling Two H profile steels are removed with jack, and application block point is hung to ground;
8th step, removes steel pipe column buttress:
Using skylight point, fixing bolt on ring flange is first removed, steel pipe column is hauled with crane, then dismantle the angle being connected with pier stud Steel, finally hangs out steel pipe column buttress.
Part not in the detailed description of the invention is prior art.
The embodiment selected herein for the open purpose of the present invention, is presently considered to be suitable, still, Ying Liao Solution, it is contemplated that all changes and improvement including all embodiments belonged in this design and invention scope.

Claims (4)

1. a kind of method for removing Existing Railway Line gate-type pier capping beam protecting canopy frame, it is characterized in that:Methods described specifically include as Lower step:
The first step, removes chamfering scaffold:
Warning is set when removing scaffold first, eye-catching caution notice is hung, forbids non-operator and ground construction personnel It is current, and there is special messenger to be responsible for warning;Wherein long vertical rod, the dismounting of brace are carried out with two people, it is impossible to separate operaton, when coming off duty It should check whether firmly, or add interim fixed support, prevent accident;When removing outrigger, steel pipe and fastener had forbidden intrusion both Wired roadbed, the steel pipe of dismounting is placed in away from roadbed side, is torn open afterwards by first filling from top to bottom, the order first torn open is filled afterwards;Specifically Dismounting order be:Safety net, bridging, leger, small cross bar, vertical rod, are removed from top to bottom, and a step one is clear, must not use and step on Step formula is removed, and is forbidden upper and lower while operation;Meeting high wind, rainy weather, it is impossible to carry out outrigger dismounting;The steel pipe of dismounting and buckle Part classification is stacked, and forbids high-altitude throwing;
Second step, hangs out pavement job platform:
In vertical skylight point job platform is hung out using crane;
D types just beam, drops in the 3rd step:
First in the fulcrum of transom pier two respectively with jack connection ¢ 36mm~just beam is caught 50mm steel wire ropes by D types, uses jack Steel wire rope is tensed, power is able to eat, jack pocket D types just beam;Then with four welding gun along along the first transverse cuts transom pier in I-steel side The steel pipe column top ring flange of side four, notes cutting along I-steel flange plate during cutting, while keeping cut surface to get out of the way I-shaped Steel 2~3cm of flange plate, must not burn I-steel, finally four steel pipe column ring flanges on the outside of transverse cuts transom pier again;Transom pier After two ends ring flange has been cut, four steel pipe columns on the inside of cutting transom pier are first found, then found four steel on the outside of cutting transom pier Tubing string, cuts 1~2cm every time, and transom pier two ends symmetrically wait height to cut, allow I-steel uniform settlement into steel pipe column otch, Every steel pipe column cut height reaches 10cm~20cm and completes to stop cutting after beam;
4th step, removes D types just beam crossbeam brace:
In skylight point, the lumps of wood is completely spread on girder falling, the lumps of wood is fixed on girder falling with iron wire, workman lies on the lumps of wood and torn open Except brace, brace moves to both sides after dismantling, then hang brace onto ground, to prevent bolt from dropping to both wired sides in full paving The wooden both sides binding lumps of wood is used as baffle plate;
5th step, removes D types just beam crossbeam:
Before just beam crossbeam is removed in D types first, bent cap bed die and the lumps of wood are plucked out;The dismounting of crossbeam, is constructed using skylight point, tears horizontal stroke open Liang Shi, first skylight point, from span centre toward two ends, first removes connection metal plate to unload based on bolt, then loosens vertical bolt, to prevent During removal bolt, bolt falls into both wired and influences both wired traffic safety, the lumps of wood ability after removal crossbeam on girder falling Remove, after whole vertical bolt loosenesses, then by vertical disassembling bolts, but the two ends of every crossbeam each remain a vertical bolt Do not unload, laid down again when the root crossbeam slides, take out crossbeam operation and completed successively in follow-up skylight point, from two ends to span centre direction Removed by root;The method that crossbeam is exited from just beam is:Anti-fall back is less than crossbeam bottom, in order to avoid crossbeam pounds anti-during falling beam Fall beam, the instrument used is:It is connected with jack with crossbeam two ends, connecting plate, bracket, the bolt of crossbeam are slowly loose after all coming loose Jack is driven, crossbeam is put on the lumps of wood on girder falling, then with jack support to job platform, is hung out crossbeam with crane;It is horizontal Beam will prevent D type beams from toppling over when removing in the middle of remaining last two, now should all loosen jack and be taken with the lumps of wood at its two ends Bearing diagonal is by D type beam supporting & stablizings;
6th step, hangs out D types just beam longeron:
Crossbeam removes crossbeam as early as possible after disintegrating with longeron, unclamp jack, hang out longeron, and just the longeron of beam removes block circuit, Hung out using crane, just beam longeron is hung out in two times, unclamp side jack and hang out a side girder, then unclamp opposite side jack, Hang out another side girder;
7th step, removes sleeper, H profile steel, girder falling, I-steel:
Using skylight point, the sleeper of steel pipe column branch pier top, H profile steel, I-steel are hung down with crane, by bent cap bottom girder falling H profile steel is removed with jack, and application block point is hung to ground;
8th step, removes steel pipe column buttress:
Using skylight point, fixing bolt on ring flange is first removed, steel pipe column is hauled with crane, then dismantle the angle being connected with pier stud Steel, finally hangs out steel pipe column buttress.
2. the method according to claim 1 for removing Existing Railway Line gate-type pier capping beam protecting canopy frame, it is characterized in that:It is described Crane is 100T cranes.
3. the method according to claim 1 for removing Existing Railway Line gate-type pier capping beam protecting canopy frame, it is characterized in that:It is described The size of the lumps of wood is 10cm × 10cm.
4. the method according to claim 1 for removing Existing Railway Line gate-type pier capping beam protecting canopy frame, it is characterized in that:It is described The time that circuit is blocked in 6th step is 60 minutes.
CN201710548953.5A 2017-07-07 2017-07-07 A method of removing Existing Railway Line gate-type pier capping beam protecting canopy frame Active CN107165062B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710548953.5A CN107165062B (en) 2017-07-07 2017-07-07 A method of removing Existing Railway Line gate-type pier capping beam protecting canopy frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710548953.5A CN107165062B (en) 2017-07-07 2017-07-07 A method of removing Existing Railway Line gate-type pier capping beam protecting canopy frame

Publications (2)

Publication Number Publication Date
CN107165062A true CN107165062A (en) 2017-09-15
CN107165062B CN107165062B (en) 2019-03-12

Family

ID=59822988

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710548953.5A Active CN107165062B (en) 2017-07-07 2017-07-07 A method of removing Existing Railway Line gate-type pier capping beam protecting canopy frame

Country Status (1)

Country Link
CN (1) CN107165062B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108868192A (en) * 2018-07-13 2018-11-23 中铁六局集团有限公司 Short distance overcrossing railway both wired transom pier overarm brace Demolition Construction engineering method
CN110273385A (en) * 2019-04-03 2019-09-24 中铁大桥局武汉桥梁特种技术有限公司 A kind of across concrete box girder method for dismounting in cross-line hole
CN112727132A (en) * 2020-12-10 2021-04-30 中铁五局集团建筑工程有限责任公司 Method for dismantling existing canopy of overhead operation subway station
CN113005900A (en) * 2019-12-20 2021-06-22 中交第一航务工程局有限公司 Inverted protection shed and mounting and dismounting method thereof
CN113216693A (en) * 2021-04-09 2021-08-06 中铁六局集团有限公司 Construction method for statically dismantling open cut tunnel of up-crossing railway business line
CN114457708A (en) * 2022-02-23 2022-05-10 浙江交工金筑交通建设有限公司 Construction method for removing bracket system of widened overpass group of highway

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101838968A (en) * 2010-05-19 2010-09-22 中铁二十局集团有限公司 Double track bridge construction process crossing existing railway operational lines
CN201671062U (en) * 2010-05-19 2010-12-15 中铁二十局集团有限公司 D-type temporary beam for construction of dual-line portal type pier cap beam spanning existing line
CN203487475U (en) * 2013-10-11 2014-03-19 中铁一局集团有限公司 Line suspending and reinforcing structure for existing line jacking bridge and culvert construction
CN104480868A (en) * 2014-12-13 2015-04-01 中铁十九局集团第二工程有限公司 Beam detaching method for road bridge overpassing operation railway
KR20160004190A (en) * 2015-04-13 2016-01-12 고재용 Drain pipeline system useful in a bridge
CN205443948U (en) * 2016-01-05 2016-08-10 中铁十六局集团第四工程有限公司 On stride electric Railway steel bearing structure and synthesize and to prevent electric installation
CN205775880U (en) * 2016-07-01 2016-12-07 中铁二十局集团市政工程有限公司 Across the most wired steel bent cap lifting construction structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101838968A (en) * 2010-05-19 2010-09-22 中铁二十局集团有限公司 Double track bridge construction process crossing existing railway operational lines
CN201671062U (en) * 2010-05-19 2010-12-15 中铁二十局集团有限公司 D-type temporary beam for construction of dual-line portal type pier cap beam spanning existing line
CN203487475U (en) * 2013-10-11 2014-03-19 中铁一局集团有限公司 Line suspending and reinforcing structure for existing line jacking bridge and culvert construction
CN104480868A (en) * 2014-12-13 2015-04-01 中铁十九局集团第二工程有限公司 Beam detaching method for road bridge overpassing operation railway
KR20160004190A (en) * 2015-04-13 2016-01-12 고재용 Drain pipeline system useful in a bridge
CN205443948U (en) * 2016-01-05 2016-08-10 中铁十六局集团第四工程有限公司 On stride electric Railway steel bearing structure and synthesize and to prevent electric installation
CN205775880U (en) * 2016-07-01 2016-12-07 中铁二十局集团市政工程有限公司 Across the most wired steel bent cap lifting construction structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108868192A (en) * 2018-07-13 2018-11-23 中铁六局集团有限公司 Short distance overcrossing railway both wired transom pier overarm brace Demolition Construction engineering method
CN108868192B (en) * 2018-07-13 2020-07-10 中铁六局集团有限公司 Construction method for dismantling close-distance over-railway existing line gate-type pier beam support
CN110273385A (en) * 2019-04-03 2019-09-24 中铁大桥局武汉桥梁特种技术有限公司 A kind of across concrete box girder method for dismounting in cross-line hole
CN113005900A (en) * 2019-12-20 2021-06-22 中交第一航务工程局有限公司 Inverted protection shed and mounting and dismounting method thereof
CN112727132A (en) * 2020-12-10 2021-04-30 中铁五局集团建筑工程有限责任公司 Method for dismantling existing canopy of overhead operation subway station
CN113216693A (en) * 2021-04-09 2021-08-06 中铁六局集团有限公司 Construction method for statically dismantling open cut tunnel of up-crossing railway business line
CN114457708A (en) * 2022-02-23 2022-05-10 浙江交工金筑交通建设有限公司 Construction method for removing bracket system of widened overpass group of highway

Also Published As

Publication number Publication date
CN107165062B (en) 2019-03-12

Similar Documents

Publication Publication Date Title
CN107165062B (en) A method of removing Existing Railway Line gate-type pier capping beam protecting canopy frame
CN101265690B (en) Method for protectively dismantling arch bridge
CN208122371U (en) On across the high-speed rail safe guarding shed fast dismounting device of operation line
CN111155451A (en) Method for dismantling highway-span iron bridge
CN109797649B (en) Maintenance vehicle hoisting scheme without influence on bridge floor traffic
CN106592962A (en) Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus
CN110512517B (en) Bridge engineering construction platform
CN109208471A (en) A kind of bridge maintenance nacelle construction platform
CN208346656U (en) A kind of hanging basket for the construction of bridge coping prestress wire two times tensioning
CN205934735U (en) A operation platform for stretch -draw of cantilever bent cap
CN106120570B (en) A kind of job platform for the secondary construction of cap
CN107366229A (en) Both a kind of construction method of wired transom pier bent cap
CN108277994A (en) On across the high ferro safe guarding shed quick method for dismounting of operation line
CN111979935A (en) Dismantling construction method for bridge superstructure
CN204212065U (en) Bridge crossing anticollision barrier punching block erection equipment
CN108868192B (en) Construction method for dismantling close-distance over-railway existing line gate-type pier beam support
CN203682931U (en) Wharf building crane
CN107217912B (en) A kind of superelevation physical isolation construction method for neighbouring high-speed rail Business Line construction
CN202039299U (en) Totally-closed hanging basket
CN205907586U (en) Device for conveying concrete on wide river water surface high platform
CN212742228U (en) Integrated safety protection platform for bent cap construction
CN212404859U (en) Auxiliary device for falling of bottom die of bent cap
CN111593681B (en) Pier stud retaining cast-in-place box girder ecological dismantling system and construction method
CN110273385B (en) Method for dismantling cross-line hole cross-concrete box girder
CN210563531U (en) Steel structure support for building protection

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant