CN108277994A - On across the high ferro safe guarding shed quick method for dismounting of operation line - Google Patents
On across the high ferro safe guarding shed quick method for dismounting of operation line Download PDFInfo
- Publication number
- CN108277994A CN108277994A CN201810229413.5A CN201810229413A CN108277994A CN 108277994 A CN108277994 A CN 108277994A CN 201810229413 A CN201810229413 A CN 201810229413A CN 108277994 A CN108277994 A CN 108277994A
- Authority
- CN
- China
- Prior art keywords
- column
- track
- platform
- moulding bed
- safe guarding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/32—Safety or protective measures for persons during the construction of buildings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/32—Safety or protective measures for persons during the construction of buildings
- E04G21/3204—Safety or protective measures for persons during the construction of buildings against falling down
- E04G21/3252—Protections, e.g. cover, caps, against impaling on starter reinforcement bars
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
本发明涉及一种上跨高铁营运线安全防护棚快速拆除方法,首先制作和安装上跨高铁营运线安全防护棚快速拆除装置,拆除安全防护棚屋面板和纵向次梁时,通过防护棚两侧的快速拆除装置在轨道上移动,将拆除的防护棚屋面板、次梁等构件人工移动到快速拆除装置上,进行拆解外运。横向主梁拆除时,利用快速拆除装置上的悬臂吊,水平移动主梁至临近站房预留操作平台进行拆解。本发明解决了一些实际施工现场空间不足无法使用吊机的问题,且操作简单,施工效率高。
The invention relates to a method for quickly dismantling a safety shed on a high-span high-speed rail operation line. Firstly, a quick dismantling device for a safety shed on an upper-span high-speed rail operation line is manufactured and installed. The quick dismantling device moves on the track, and the removed protective shed panels, secondary beams and other components are manually moved to the quick dismantling device for disassembly and transportation. When dismantling the transverse main girder, use the cantilever crane on the quick dismantling device to move the main girder horizontally to the reserved operating platform adjacent to the station building for disassembly. The invention solves the problem that the crane cannot be used due to insufficient space in some actual construction sites, and has simple operation and high construction efficiency.
Description
技术领域technical field
本发明涉及一种安全防护棚拆除装置,特别涉及一种上跨高铁营运线安全防护棚快速拆除方法。The invention relates to a device for removing a safety protection shed, in particular to a method for quickly removing a safety protection shed on an upper-span high-speed rail operation line.
背景技术Background technique
由于铁路线路的增多,难免要遇到从上跨越既有线路修建新建筑的情况,这在多条线路交汇的车站处尤为常见,通常做法是在既有线路上设置安全防护棚。设置安全防护棚可避免邻近或上跨工程施工对既有线路的正常运营造成影响。当前关于上跨正常运营既有线路的安全防护棚施工主要是针对安装施工,但安全防护棚作为临时性结构,在工程施工结束后必须拆除。传统的安全防护棚拆除都是利用汽车吊或塔吊进行施工,但这些吊机会妨碍既有线路的运营安全,且车站安全防护棚的拆除受限于施工现场的空间,无法让大型吊机进场辅助施工,这就给安全防护棚的拆除工作带来了极大的影响。Due to the increase of railway lines, it is inevitable to encounter the situation of building new buildings across existing lines from above. This is especially common at stations where multiple lines meet. The usual practice is to set up safety shelters on existing lines. Setting up a safety shed can prevent the construction of adjacent or upper-span projects from affecting the normal operation of existing lines. At present, the construction of safety sheds on the existing lines in normal operation on the upper span is mainly for installation and construction, but as a temporary structure, the safety shed must be dismantled after the construction is completed. The traditional safety shelters are demolished by truck cranes or tower cranes, but these cranes will hinder the operation safety of existing lines, and the demolition of the station safety shelters is limited by the space on the construction site, making it impossible to allow large cranes to enter the site Auxiliary construction, which has brought a great impact on the demolition work of the safety shelter.
基于此,目前亟需寻求一种上跨高铁营运线安全防护棚快速拆除装置及拆除方法就显得十分重要。Based on this, it is very important to seek a fast dismantling device and dismantling method for a safety shed on the high-speed rail operation line at present.
发明内容Contents of the invention
本发明的目的就是克服上述缺陷,提供一种上跨正常运营既有线安全防护棚快速拆除装置。The purpose of the present invention is to overcome the above-mentioned defects, and to provide a quick dismantling device for the safety protection shed of the existing line in normal operation.
本发明的目的是通过以下技术方案实现的:The purpose of the present invention is achieved through the following technical solutions:
上跨高铁营运线安全防护棚快速拆除方法,其特征在于,包括以下的步骤:The method for quickly dismantling the safety shelter of the high-speed rail operation line is characterized in that it includes the following steps:
1)上跨高铁营运线安全防护棚快速拆除装置的制作和安装:首先制作一榀框架,所述框架由轨道工装胎架主梁3和轨道工装胎架柱5焊接而成;在上下层轨道工装胎架主梁3之间设置支撑杆6,框架共制作四榀;将四榀框架通过轨道工装胎架主梁3焊接连接;在轨道工装胎架柱5旁边设置悬臂吊2,通过连接钢板与轨道工装胎架主梁3固定,悬臂吊2由悬臂吊立柱14、悬臂吊梁15、双吊钩7和手拉葫芦8组成,双吊钩7,悬臂吊立柱14顶端设置悬臂吊梁15,双吊钩7设于悬臂吊梁15上;在顶层横向轨道工装胎架主梁3之间间隔设置轨道工装胎架次梁4,然后铺设屋面压型钢板作为操作平台9;在底层轨道工装胎架主梁3上安装滑轮10和水平限滑装置12;在快速拆除装置上靠近站台平面标高位置设置配重11,整体架构为站台方向偏心布置;在站台17上设临时轨道18,与装置底部的两滑轮10形成三支点;快速拆除装置在当天施工完成后,用缆风绳13进行固定,缆风绳13锚固点设在站台的圆钢柱底部;1) Fabrication and installation of the quick removal device for the safety shed on the upper-span high-speed rail operation line: first, a frame is made, and the frame is welded by the main beam 3 of the track tooling tire frame and the track tooling tire frame column 5; Support rods 6 are set between the main beams 3 of the tooling tire frame, and four frames are made in total; the four frame frames are welded and connected by the main beam 3 of the track tooling frame; Fixed with the main beam 3 of the track tooling tire frame, the cantilever crane 2 is composed of a cantilever suspension column 14, a cantilever suspension beam 15, double hooks 7 and a chain block 8, double hooks 7, and a cantilever suspension beam 15 is set on the top of the cantilever suspension column 14 , the double hook 7 is located on the cantilever beam 15; the track tooling frame secondary beam 4 is arranged at intervals between the top horizontal track tooling frame main beam 3, and then the roof profiled steel plate is laid as the operating platform 9; the bottom track tooling frame A pulley 10 and a horizontal slip limiting device 12 are installed on the main girder 3 of the frame; a counterweight 11 is installed on the quick release device close to the elevation of the platform, and the overall structure is arranged eccentrically in the direction of the platform; The two pulleys 10 form three fulcrums; the quick release device is fixed with the cable wind rope 13 after the construction is completed on the same day, and the cable wind rope 13 anchor points are located at the bottom of the round steel column of the platform;
2)拆除安全防护棚屋面板:上跨高铁营运线安全防护棚快速拆除装置安装检验完毕,开始安全防护棚16屋面板的拆除,从远离站房最边缘处开始,向站房方向拆除,预留几跨做临时操作平台用;2) Remove the roof panel of the safety protection shed: After the installation and inspection of the quick removal device for the safety protection shed on the high-speed rail operation line, start the removal of the 16 roof panels of the safety protection shed, starting from the farthest edge of the station building and dismantling towards the station building. A few spans are reserved for temporary operation platforms;
3)接着拆除纵向次梁:顺线路方向从远离站房端防护棚开始拆除,向站房方向顺序拆除;垂直轨道方向,从中间向两侧方向拆除;3) Then remove the longitudinal secondary beam: along the direction of the line, remove the protective shed away from the end of the station building, and remove it sequentially toward the station building; vertically to the track direction, remove it from the middle to both sides;
4)然后拆除横向主钢梁:利用安全吊篮和快速拆除装置进行拆除作业,拆除顺序与屋面板或次梁相反;4) Then remove the horizontal main steel beam: use the safety basket and the quick removal device to carry out the removal operation, and the removal sequence is opposite to that of the roof panel or the secondary beam;
5)再拆除安全防护棚立柱:利用悬臂吊2将立柱吊起,并利用缆风绳控制立柱的位置,将立柱底部割离后吊至安全防护棚外侧进行拆解;5) Remove the column of the safety shed: use the cantilever crane 2 to lift the column, and use the cable wind rope to control the position of the column, cut off the bottom of the column and hang it to the outside of the safety shed for disassembly;
6)最后拆除预留操作平台:剩余的屋面板,柱、梁拆除操作同上,最终完成安全防护棚的全部拆除工作。6) Finally, dismantle the reserved operation platform: the remaining roof panels, columns and beams are dismantled as above, and finally complete the dismantling of the safety shed.
悬臂吊2既可以垂直上下升降,也可以360°旋转;双吊钩7作用分别为作业吊钩,导钩与保险作用。The cantilever crane 2 can be lifted up and down vertically, and can also be rotated 360°; the functions of the double hooks 7 are operation hooks, guide hooks and safety functions respectively.
进一步地,滑轮10可在轨道上滑动,滑轮10两侧设置有水平限滑装置12,以防止快速拆除装置在滑行过程中脱轨;此外,站台17上要设有临时轨道18,与轨道工装胎架1底部的两滑轮10形成三支点,保证装置的稳定。Further, the pulley 10 can slide on the track. Horizontal slip-limiting devices 12 are provided on both sides of the pulley 10 to prevent the quick release device from derailing during the sliding process; in addition, a temporary track 18 will be provided on the platform 17, which is compatible with the track tooling tire. Two pulleys 10 at the bottom of the frame 1 form three fulcrums to ensure the stability of the device.
快速拆除装置底部第二层位置靠近站台平面标高位置设有配重11,整体架构为站台方向偏心布置,可进一步增加快速拆除装置的自身稳定性。A counterweight 11 is provided on the second floor at the bottom of the quick dismantling device close to the level of the platform, and the overall structure is arranged eccentrically in the direction of the platform, which can further increase the self-stability of the quick dismantling device.
上跨高铁营运线安全防护棚快速拆除装置在当天施工完成后,需用缆风绳13进行固定,缆风绳13锚固点设在站台的圆钢柱底部。每个快速拆除装置在靠站台侧各拉两根缆风绳13,并用手拉葫芦8拉紧。After the quick removal device for the safety shelter of the upper-span high-speed rail operation line is completed on the same day, it needs to be fixed with the cable wind rope 13, and the anchor point of the cable wind rope 13 is set at the bottom of the round steel column of the platform. Each quick dismantling device respectively draws two cable wind ropes 13 on the side of the platform, and pulls them tightly with a hand chain block 8.
本发明具有如下特点和有益效果:The present invention has following characteristics and beneficial effect:
本发明的上跨高铁营运线安全防护棚快速拆除装置,可解决某些时间施工现场空间不足,无法使用吊机的问题。The quick removal device for the safety shelter of the upper-span high-speed rail operation line of the present invention can solve the problem of insufficient space at the construction site and the inability to use a crane at certain times.
本发明设置的悬臂吊,可上下伸缩,360°旋转,拆除横向主梁时,可利用悬臂吊将主梁转移至预留操作平台处进行拆除。The cantilever crane provided by the present invention can be stretched up and down and rotated 360°. When removing the transverse main girder, the cantilever crane can be used to transfer the main girder to the reserved operating platform for dismantling.
采用快速拆除装置拆除上跨高铁营运线安全防护棚,操作简单,施工效率高。The quick dismantling device is used to dismantle the safety protection shed of the upper-span high-speed rail operation line, which is easy to operate and high in construction efficiency.
附图说明Description of drawings
图1是快速拆除装置拆除次梁站位图;Fig. 1 is a site diagram for removing the secondary beam by the quick dismantling device;
图2是快速拆除装置俯视图;Fig. 2 is a top view of the quick dismantling device;
图3是快速拆除装置正视图;Figure 3 is a front view of the quick release device;
图4是快速拆除装置三维示意图;Fig. 4 is a three-dimensional schematic diagram of the quick removal device;
图5是快速拆除装置悬臂吊示意图;Fig. 5 is a schematic diagram of the cantilever crane of the quick removal device;
图6是快速拆除装置水平限滑装置示意图;Fig. 6 is a schematic diagram of the horizontal slip limiting device of the quick release device;
图7是快速拆除装置侧视图。Figure 7 is a side view of the quick release device.
图中,2—悬臂吊;3—轨道工装胎架主梁;4—轨道工装胎架次梁,5—轨道工装胎架柱,6—支撑杆;7——双吊钩;8—手拉葫芦;9—操作平台;10—滑轮;11—配重;12—水平限滑装置;13—缆风绳;14—悬臂吊立柱;15—悬臂吊梁;16—安全防护棚;17—站台;18-临时轨道。In the figure, 2—cantilever crane; 3—main beam of track tooling tire frame; 4—secondary beam of track tooling tire frame, 5—track tooling tire frame column, 6—support rod; 7—double hook; 8—chain block ;9—operating platform; 10—pulley; 11—counterweight; 12—horizontal slip limiting device; 13—cable wind rope; 14—cantilever hanging column; 15—cantilever beam; 16—safety protection shed; 18 - Temporary track.
具体实施方式:Detailed ways:
首先制作如图3所示的一榀框架,共制作4块,框架由轨道工装胎架主梁3和轨道工装胎架柱5焊接而成。框架底部宽3200mm,顶部宽4000mm,各层层高为1120mm、1900mm、1900mm、2180mm与1620mm,轨道工装胎架柱5总高8720mm,均采用H型钢焊接而成,尺寸为HW200x200x8x12,上几层在横向的轨道工装胎架主梁3中点处设置支撑杆6,支撑杆6采用圆钢管,规格为φ89x4,下面同,倒数第二层在3200mm处设置支撑杆,底层分别在1007mm、1600mm和2194mm处设置支撑杆。At first make a frame as shown in Figure 3, make 4 altogether, frame is welded by track tooling tire frame girder 3 and track tooling tire frame column 5. The width of the bottom of the frame is 3200mm, the width of the top is 4000mm, and the height of each layer is 1120mm, 1900mm, 1900mm, 2180mm and 1620mm. The support bar 6 is set at the midpoint of the main beam 3 of the horizontal track tooling tire frame. The support bar 6 is made of round steel pipe with a specification of φ89x4, the same as below. The penultimate layer is set at 3200mm, and the bottom layer is 1007mm, 1600mm and 2194mm respectively. Set up support rods.
将上一步制得的4榀框架通过纵向轨道工装胎架主梁3焊接连接,间隔3000mm,共三跨9000mm;并在1、3跨中点处设置支撑杆,得到如图7所示结构。The 4 frames prepared in the previous step are welded and connected by the main beam 3 of the longitudinal track tooling tire frame, with an interval of 3000mm, and a total of three spans of 9000mm; and a support bar is set at the midpoint of the 1st and 3rd spans, and the structure shown in Figure 7 is obtained.
在所形成结构的轨道工装胎架柱5边上,设置悬臂吊2,如图5所示,悬臂吊立柱14采用圆钢管制作,尺寸为φ245x12,悬臂吊梁15采用矩形管,规格为口300x200x10x10。悬臂吊长2m,可垂直升降0-1.6m,360度旋转,悬臂吊梁15前端设双吊钩7,一个作为作业吊钩,另一个作为导钩和保险,并配备2T手拉葫芦8。On the 5 sides of the track tooling frame column of the formed structure, a cantilever crane 2 is set, as shown in Figure 5, the cantilever crane column 14 is made of a round steel pipe, and the size is φ245x12, and the cantilever beam 15 adopts a rectangular tube, and the specification is 300x200x10x10 . The length of the cantilever is 2m, it can vertically lift 0-1.6m, and it can rotate 360 degrees. The front end of the cantilever beam 15 is equipped with double hooks 7, one as a working hook, the other as a guide hook and safety, and equipped with a 2T chain hoist 8.
接下去在所形成结构三跨的各跨中部设置轨道工装胎架次梁4,轨道工装胎架次梁4也采用H型钢,截面尺寸略小于轨道工装胎架主梁3即可,之后在结构顶面铺设屋面压型钢板作为操作平台9,如图2所示。Next, in the middle of each span of the formed three-span structure, set the secondary beam 4 of the track tooling frame. The secondary beam 4 of the track tooling frame is also made of H-shaped steel, and the cross-sectional size is slightly smaller than the main beam 3 of the track tooling frame. Lay roof profiled steel plate as operating platform 9, as shown in Figure 2.
在上述结构底部安装好滑轮10与水平限滑装置12,在快速拆除装置上靠近站台平面标高位置设置配重11,整体架构为站台方向偏心布置;在站台17上设临时轨道18,与装置底部的两滑轮10形成三支点;快速拆除装置在当天施工完成后,用缆风绳13进行固定,缆风绳13锚固点设在站台的圆钢柱底部;最终得到图4所示的上跨高铁营运线安全防护棚快速拆除装置。The pulley 10 and the horizontal slip limiting device 12 are installed at the bottom of the above structure, and the counterweight 11 is set on the quick release device close to the elevation of the platform. The overall structure is arranged eccentrically in the direction of the platform; The two pulleys 10 form three fulcrums; the quick release device is fixed with the cable wind rope 13 after the construction is completed on the same day, and the anchor point of the cable wind rope 13 is set at the bottom of the round steel column of the platform; finally, the upper-span high-speed rail as shown in Figure 4 is obtained Quick dismantling device for the safety shelter of the operation line.
上跨高铁营运线安全防护棚拆除方法如下:The removal method of the safety shed on the upper-span high-speed rail operation line is as follows:
拆除工作第一步是进行安全防护棚16屋面板的拆除,从远离站房的最边缘处向站房方向拆除,预留几跨可做临时操作平台用。屋面压型钢板拆除前需先将栓钉拆除,不拆除屋面板的部分不拆栓钉,以确保点外行车安全。单块屋面压型钢板拆除时将其跨中割断,然后将分割后第1块、第2块的屋面板采用人工分别拖移至两侧的快速拆除装置上,最后在快速拆除装置上分解后转运出场。The first step of the demolition work is to remove the 16 roof panels of the safety shed, which is removed from the edge far away from the station building to the station building direction, and a few spans are reserved to be used as a temporary operating platform. The studs must be removed before the roof profiled steel plate is removed, and the studs will not be removed for the part of the roof panel that is not removed, so as to ensure the safety of driving outside the point. When removing a single roof profiled steel plate, cut it in the middle of the span, then manually drag the first and second roof panels to the quick-release devices on both sides, and finally decompose them on the quick-release devices Transfer out.
接着拆除安全防护棚次梁,次梁采用点焊方式与主梁连接,拆除施工主要采用乙炔氧气割枪进行施工作业,此时快速拆除装置站位如图1所示。采用氧气乙炔割枪将次梁与主梁连接位置处切割开来,安全防护棚次梁拆除时从跨中往两侧进行拆除,利用快速拆除装置和尚未拆除的次梁作为支撑点,采用木板和模板在安全防护棚次梁之间搭设临时操作平台,作为搬运至平台车的通道,每拆除一根次梁后,将次梁从防护棚两侧搬运至快速拆除装置操作平台9上,同时操作平台9往拆除方向后平移一个次梁间距,直至两侧各剩余一根次梁,保留两侧钢柱最外侧的次梁,确保主梁连接稳固。次梁在工装胎架的操作平台上拆解完毕后,利用悬臂吊2吊至站台上,悬臂吊结构如图5所示。Then remove the secondary beam of the safety protection shed. The secondary beam is connected to the main beam by spot welding. The demolition construction mainly uses acetylene oxygen torch for construction work. At this time, the station of the quick removal device is shown in Figure 1. Oxygen acetylene torch is used to cut the connection position between the secondary beam and the main beam. When removing the secondary beam of the safety protection shed, it is removed from the mid-span to both sides. The quick dismantling device and the unremoved secondary beam are used as supporting points, and wooden boards are used. Set up a temporary operating platform with the formwork between the secondary beams of the safety protection shed as a passage for transporting to the platform truck. The operating platform 9 is moved in the direction of removal by one secondary beam spacing until one secondary beam remains on both sides, and the outermost secondary beams of the steel columns on both sides are retained to ensure that the main beams are connected firmly. After the secondary beam is disassembled on the operating platform of the tooling tire frame, it is hoisted to the platform by the cantilever crane 2. The structure of the cantilever crane is shown in Figure 5.
然后拆除横向主钢梁,将快速拆除装置利用底部的滑轮10,移动至待拆除钢梁的两端,滑轮10两侧设有水平限滑装置12,如图6所示,以避免滑轮出现脱轨。单个防护棚主钢梁拆除顺序为靠近站房向外侧依次进行拆除,与屋面板和次梁整体顺序相反。单根主梁拆除前,先将用于稳定结构的两根次梁拆除至快速拆除装置上,在将钢梁上翼缘板割除20cm长度,然后在每端腹板上分别打两个孔作为吊耳,通过两个卡环,分别与悬臂吊梁15上的双吊钩7进行固定连接(一主一备),固定牢固后开始下一步作业;主梁与悬臂吊梁固定牢固后,将主钢梁端部与柱之间的钢管斜撑拆除,接着拆除主梁与钢柱柱顶连接的螺栓,将柱子与主梁分离;主梁与柱子的连接螺栓割除后,主梁与柱子分离,主梁与快速拆除装置一起向往站房方向滑移,滑移至预留平台上进行分解,随后从高架悬挑平台转运出场。Then remove the horizontal main steel beam, and move the quick removal device to the two ends of the steel beam to be removed by using the pulley 10 at the bottom. Horizontal slip limiting devices 12 are provided on both sides of the pulley 10, as shown in Figure 6, to avoid derailment of the pulley . The order of removal of the main steel beams of a single protective shed is to remove them from the station building to the outside, which is opposite to the overall order of the roof panels and secondary beams. Before removing the single main girder, remove the two secondary girders used for stabilizing the structure to the quick dismantling device, cut off the upper flange plate of the steel girder to a length of 20 cm, and then punch two holes on the web at each end as lifting lugs , through two snap rings, respectively fixedly connected with the double hooks 7 on the cantilever beam 15 (one main and one standby), and start the next step after being fixed firmly; after the main beam and the cantilever beam are fixed firmly, the main steel The steel pipe diagonal brace between the beam end and the column is removed, and then the bolts connecting the main beam and the steel column top are removed to separate the column from the main beam; after the connecting bolts between the main beam and the column are cut off, the main beam is separated from the column, The beam slides towards the station building together with the quick dismantling device, slides to the reserved platform for disassembly, and then is transported out of the site from the elevated suspension platform.
再拆除安全防护棚立柱,立柱拆除采用快速拆除装置将立柱吊起,通过两道揽风绳控制立柱位置,底部割断后,通过手拉葫芦8,将立柱放到在防护棚外侧的线路间进行拆解。Then remove the column of the safety shelter. The column is removed by using a quick removal device to lift the column, and the position of the column is controlled by two wind ropes. Disassemble.
最后拆除预留操作平台,屋面板、次梁、主梁、柱子拆除方法同上,主梁可直接通过快速拆除装置悬臂吊提升至高架层悬挑楼面标高,然后通过旋转将主梁放置在高架路面上,再将主梁分解运出。Finally, the reserved operation platform is dismantled, and the roof panel, secondary beams, main beams, and columns are removed in the same way as above. The main beam can be directly lifted to the elevation of the cantilevered floor of the elevated floor by the cantilever crane of the quick removal device, and then the main beam is placed on the elevated road by rotation. surface, and then the main girder is decomposed and transported out.
Claims (3)
- Across the high ferro safe guarding shed quick method for dismounting of operation line on 1., which is characterized in that include the following steps:1) making and installation of across the high ferro safe guarding shed fast dismounting device of operation line on:A Pin frames are made first, it is described Frame is welded by track tooling moulding bed girder (3) and track tooling moulding bed column (5);In levels track tooling moulding bed girder (3) supporting rod (6) is set between, and frame makes four Pin altogether;Four Pin frames are welded by track tooling moulding bed girder (3) and are connected It connects;The setting cantilever crane (2) beside track tooling moulding bed column (5), it is solid by junction steel plate and track tooling moulding bed girder (3) Fixed, cantilever crane (2) is made of cantilever crane column (14), cantilever hanging beam (15), double-hung (7) and chain block (8), double-hung (7), cantilever crane column (14) top setting cantilever hanging beam (15), double-hung (7) are set on cantilever hanging beam (15);In top layer transverse direction Interval setting track tooling moulding bed secondary beam (4) between track tooling moulding bed girder (3) is then laid with roofing profiled sheet as behaviour Make platform (9);Pulley (10) and the sliding device (12) of horizontal limit are installed on bottom track tooling moulding bed girder (3);Quickly tearing open Except, close to platform plane elevation location setting counterweight (11), overall architecture is platform direction arranged off-centre on device;In platform (17) temporary track (18) is set on, and three fulcrums are formed with two pulleys (10) of bottom of device;Fast dismounting device is constructed on the day of After the completion, it is fixed with cable wind rope (13), cable wind rope (13) anchor point is located at the round steel column bottom of platform;2) safe guarding shed roof boarding is removed:On the safe guarding shed fast dismounting device installation of across high ferro operation line be verified, The dismounting for starting safe guarding shed (16) roof boarding is removed since far from station most edge to station direction, reserve it is several across Do temporary operating platform use;3) longitudinal secondary beam is then removed:It removes since far from station end protection canopy along line direction, is torn open to station direction sequence It removes;Vertical track direction is removed from centre to two side directions;4) and then laterally main girder steel is removed:Dismounting operation, dismounting sequence and room are carried out using safety hanging cradle and fast dismounting device Panel or secondary beam are opposite;5) safe guarding shed column is removed again:Column is sling using cantilever crane (2), and utilizes the position of cable wind rope control column It sets, safe guarding shed outside is hung to after column bottom is cut off and is disassembled;6) reservation operations platform is finally removed:Remaining roof boarding, column, beam dismantling operation are same as above, are finally completed safe guarding shed Whole remove work.
- 2. construction method according to claim 1, it is characterised in that:Pulley (10) both sides are provided with the sliding device of horizontal limit (12)。
- 3. construction method according to claim 2, it is characterised in that:It quickly tears open upper across high ferro operation line is safe guarding shed Except device is equipped with cable wind rope (13), cable wind rope (13) anchor point is located at the circular steel column column bottom of platform.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810229413.5A CN108277994B (en) | 2018-03-20 | 2018-03-20 | Method for quickly dismantling safety protection shed of overhead high-speed rail operation line |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810229413.5A CN108277994B (en) | 2018-03-20 | 2018-03-20 | Method for quickly dismantling safety protection shed of overhead high-speed rail operation line |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN108277994A true CN108277994A (en) | 2018-07-13 |
| CN108277994B CN108277994B (en) | 2020-03-27 |
Family
ID=62810008
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810229413.5A Active CN108277994B (en) | 2018-03-20 | 2018-03-20 | Method for quickly dismantling safety protection shed of overhead high-speed rail operation line |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108277994B (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110158988A (en) * | 2019-06-28 | 2019-08-23 | 中冶建工集团有限公司 | A kind of building protection steel structure support and its quick method for dismounting |
| CN112727132A (en) * | 2020-12-10 | 2021-04-30 | 中铁五局集团建筑工程有限责任公司 | Method for dismantling existing canopy of overhead operation subway station |
| CN114876239A (en) * | 2022-05-11 | 2022-08-09 | 北京市第三建筑工程有限公司 | Closed protection dismantling system for high-altitude cantilever structure and construction method thereof |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201082948Y (en) * | 2007-07-17 | 2008-07-09 | 贺东贤 | Over electrified railway overpass construction protecting canopy |
| US20130331239A1 (en) * | 2012-05-21 | 2013-12-12 | Todd Richards | Weight Lifting Machines and Methods |
| CN107338727A (en) * | 2016-12-28 | 2017-11-10 | 广西路建工程集团有限公司 | A kind of overall demolition, installation anticollision wall form and its walking track crane move system |
| CN107630458A (en) * | 2017-10-26 | 2018-01-26 | 汪成立 | A kind of filling concrete protective plate automatic disassembling machine of high-speed railway rail bridge pile foundation |
| CN107806009A (en) * | 2017-10-27 | 2018-03-16 | 中铁五局集团有限公司 | A kind of across the Existing Railway Line contact net protection canopy of highway and its construction method |
-
2018
- 2018-03-20 CN CN201810229413.5A patent/CN108277994B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201082948Y (en) * | 2007-07-17 | 2008-07-09 | 贺东贤 | Over electrified railway overpass construction protecting canopy |
| US20130331239A1 (en) * | 2012-05-21 | 2013-12-12 | Todd Richards | Weight Lifting Machines and Methods |
| CN107338727A (en) * | 2016-12-28 | 2017-11-10 | 广西路建工程集团有限公司 | A kind of overall demolition, installation anticollision wall form and its walking track crane move system |
| CN107630458A (en) * | 2017-10-26 | 2018-01-26 | 汪成立 | A kind of filling concrete protective plate automatic disassembling machine of high-speed railway rail bridge pile foundation |
| CN107806009A (en) * | 2017-10-27 | 2018-03-16 | 中铁五局集团有限公司 | A kind of across the Existing Railway Line contact net protection canopy of highway and its construction method |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110158988A (en) * | 2019-06-28 | 2019-08-23 | 中冶建工集团有限公司 | A kind of building protection steel structure support and its quick method for dismounting |
| CN112727132A (en) * | 2020-12-10 | 2021-04-30 | 中铁五局集团建筑工程有限责任公司 | Method for dismantling existing canopy of overhead operation subway station |
| CN114876239A (en) * | 2022-05-11 | 2022-08-09 | 北京市第三建筑工程有限公司 | Closed protection dismantling system for high-altitude cantilever structure and construction method thereof |
| CN114876239B (en) * | 2022-05-11 | 2023-08-18 | 北京市第三建筑工程有限公司 | High-altitude overhanging structure closed protection dismantling system and construction method thereof |
Also Published As
| Publication number | Publication date |
|---|---|
| CN108277994B (en) | 2020-03-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN208122371U (en) | On across the high-speed rail safe guarding shed fast dismounting device of operation line | |
| CN201158933Y (en) | High-rise maintaining scaffold device with extruding structure | |
| CN100476076C (en) | Mobile integral construction platform, construction method and special spreader | |
| CN104695337B (en) | Self-lifting sliding and turnover construction system and construction method | |
| CN102653938B (en) | Offshore dismantling construction method for descending movable formwork | |
| CN106592962A (en) | Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus | |
| CN107447973B (en) | Unilateral suspension type air mobile steel platform | |
| CN116732887A (en) | Bottom die bent construction method for super-high beam of super-large bridge main tower | |
| CN103758045B (en) | Box girder wet joint formwork construction method under space limitation condition | |
| CN206562264U (en) | A kind of hanging device for transport outside high-rise building | |
| CN108277994A (en) | On across the high ferro safe guarding shed quick method for dismounting of operation line | |
| CN202416191U (en) | Lifting device of main girder for offshore demolition of downward mobile formwork | |
| CN116853963B (en) | A hoisting device and hoisting method for main beam of cable-stayed bridge | |
| CN106522566A (en) | Roof steel truss slipping rail and dismounting and installing method thereof | |
| CN217517371U (en) | Concrete box type arch bridge cantilever is pour with falling triangle and is hung basket | |
| CN111455854A (en) | Semi-automatic protective scaffolding and erection method for the construction of viaducts across railways | |
| CN116241061A (en) | A reusable vertical operation platform setting method | |
| CN214329956U (en) | Ring rail hoisting device for curtain wall installation | |
| CN220246713U (en) | Beret beam rapid dismantling system for railway protection shed tunnel adding project under limited space | |
| CN220364880U (en) | Suspension bridge catwalk surface net gliding trolley | |
| CN117144815B (en) | A construction method for dismantling a diamond-shaped hanging basket | |
| CN215331380U (en) | Rail type suspension platform | |
| CN116902740A (en) | Prefabricated T-beam template hoisting auxiliary device and use method | |
| CN209742334U (en) | Steel structure corridor bottom curtain wall construction platform | |
| CN213653209U (en) | An integrated construction activity platform for bridge flange plates |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| PP01 | Preservation of patent right | ||
| PP01 | Preservation of patent right |
Effective date of registration: 20250813 Granted publication date: 20200327 |
|
| PD01 | Discharge of preservation of patent | ||
| PD01 | Discharge of preservation of patent |
Date of cancellation: 20250903 Granted publication date: 20200327 |