CN204023410U - Winter deck paving heat preservation construction device - Google Patents

Winter deck paving heat preservation construction device Download PDF

Info

Publication number
CN204023410U
CN204023410U CN201420333559.1U CN201420333559U CN204023410U CN 204023410 U CN204023410 U CN 204023410U CN 201420333559 U CN201420333559 U CN 201420333559U CN 204023410 U CN204023410 U CN 204023410U
Authority
CN
China
Prior art keywords
support system
construction
insulating support
roof insulating
heat preservation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420333559.1U
Other languages
Chinese (zh)
Inventor
李晓超
王克勤
祁玺剑
赵香萍
周高峰
张智怀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201420333559.1U priority Critical patent/CN204023410U/en
Application granted granted Critical
Publication of CN204023410U publication Critical patent/CN204023410U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to field of bridge construction, be specially one deck paving heat preservation construction device in winter, solve existing construction and adopt stove insulation, there is complex operation, contaminated environment, the problems such as homogeneous heating degree is bad, comprise by column, longeron, truss crossbeam and cross binding, the roof insulating support system that vertical supporting forms, two sides of roof insulating support system, two end faces and end face are coated with geotextiles insulation layer from inside to outside successively, Polypropylence Sheet insulation layer and tarpaulin waterproofing course, warm-air drier is installed in roof insulating support system inner side, the low bending in high two ends in the middle of all truss beam weldings become, road wheel is installed in roof insulating support system below, make temperature of shed reach code requirement, can reach the effect that bridge deck concrete in construction adds gentle moisturizing, attemperator need to be able to be moved according to construction, can have enough to meet the need use, peace is torn open conveniently, there is cost low, convenient construction, improve the advantages such as work efficiency.

Description

Winter deck paving heat preservation construction device
Technical field
The utility model relates to field of bridge construction, is specially one deck paving heat preservation construction device in winter.
Background technology
In bridge construction, the concrete of deck paving is because area is large and thin thickness, especially winter construction and health have certain difficulty, concrete is ability setting and harden under certain temperature condition in addition, carry out bridge deck concrete construction winter and can make concrete endure cold, and cannot make concrete coagulation, the contained moisture freezes such as soil, concrete, mortar, the easy embrittlement of constructional materials, brings many difficulties to building operations.Traditional cold weather concrete insulation protection adopts stove heat preservation construction, and the problem of its existence has: in (1) construction and need continuous coal in insulating process, complex operation, impact construction; (2) insulation stove produces volume of smoke, and construction environment is stuff, and easily poisoning, air pollution is serious; (3) near insulation stove local temperature higher, and away from local temperature lower, the uniformity of heating is bad, cause concrete construction quality be difficult to ensure.
Summary of the invention
The utility model adopts stove insulation in order to solve Deck Concrete Pavement construction in existing winter, has the problems such as complex operation, contaminated environment, homogeneous heating degree be bad, provide a kind of winter deck paving heat preservation construction device.
The utility model is to adopt following technical scheme to realize: winter deck paving heat preservation construction device, comprise by column, longeron, interval and be connected in the roof insulating support system that two truss crossbeams between longeron and some cross binding, vertical supporting form, two sides of roof insulating support system, two end faces and end face are coated with geotextiles insulation layer, Polypropylence Sheet insulation layer and tarpaulin waterproofing course from inside to outside successively, and inner side, roof insulating support system one end is provided with warm-air drier.
Described all truss beam weldings become the low bending in middle high two ends, at utmost increase the interior construction space of roof insulating in the situation that taking into account ceiling draining.
Described roof insulating support system below is installed and is laid on the road wheel that the guide rail on bridge floor cooperatively interacts, and like this, the construction speed that whole heat preservation construction device can be laid with bridge floor arbitrarily moves along track, easy to operate, time saving and energy saving.
Adopt structure design of the present utility model, adopt warm-air drier to heat environment in bridge floor and canopy, make temperature of shed reach code requirement, can reach the effect that bridge deck concrete in construction adds gentle moisturizing, in addition, insulation is made system bottom road wheel is installed, thereby attemperator need to be able to be moved according to construction, can have enough to meet the need use, peace is torn open conveniently, has the advantages such as cost is low, convenient construction, raising work efficiency.Adopting heat preservation construction device described in the utility model to carry out winter Surfacing Construction is a kind of novel construction method, compare former stove heating and thermal insulation, control insulation temperature of shed that can be more stable, and in roof insulating, be to heat more uniformly, can effectively ensure the concrete quality of deck paving.
Brief description of the drawings
Fig. 1 is the floor map of the utility model insulation support system;
Fig. 2 is facade structures schematic diagram of the present utility model;
In figure: 1-column; 2-longeron; 3-truss crossbeam; 4-geotextiles insulation layer; 5-Polypropylence Sheet insulation layer; 6-tarpaulin waterproofing course; 7-warm-air drier; 8-road wheel.
Detailed description of the invention
Winter deck paving heat preservation construction device, as shown in Figure 1, 2, comprise by column 1, longeron 2, interval and be connected in the roof insulating support system that two truss crossbeams 3 between longeron and some cross binding, vertical supporting form, two sides of roof insulating support system, two end faces and end face are coated with geotextiles insulation layer 4, Polypropylence Sheet insulation layer 5 and tarpaulin waterproofing course 6 from inside to outside successively, and inner side, roof insulating support system one end is provided with warm-air drier 7.The low bending in high two ends in the middle of all truss crossbeams 3 are welded into.Roof insulating support system below is installed and is laid on the road wheel 8 that the guide rail on bridge floor cooperatively interacts.
When concrete making, warm-air drier employing section gold warm air curtain, product type: D-30, air quantity: 2500m3/h, wind speed: 2-3m/s, power of motor: 250W, heating power: 30KW.Roof insulating adopts diameter ф 50, ф 20 steel pipe weldings to be connected into support system, and outsourcing trilaminate material, is respectively building cloth, plastic sheeting and water-proof tarpaulin, roof insulating 4 root posts adopt ф 50 steel pipes, and 4 road wheels are installed under steel pipe, to promote when mobile roof insulating.Other columns and horizontal vertical supporting adopt ф 20 steel pipes, every a truss crossbeam of 3 meters of designs, truss crossbeam is also formed by ф 20 steel-pipe weldings, the low bending in high both sides in the middle of truss beam welding becomes, the maximum interior construction space that increases in the situation that taking into account ceiling draining.
Warm-air drier heat preservation construction step:
(1) beam face cleaning
To bridge deck dabbing, with artificial floating bits and the drifting dust removed, then clean bridge floor with giant.
Before mating formation, beam face is checked, bridge floor should be smooth, coarse, dry, clean and tidy, must not have dust, foreign material or greasy dirt, and deck transverse slope should meet the requirements.Undesirable processing, is polished or is studied for a second time courses one has flunked thin projections or pit.
(2) mobile heat preservation construction device of the present utility model
Mobile heat preservation construction device, to the beam face of having cleared up, is then installed warm-air drier, when installation, will carry out earth leakage protective measure.After warm-air drier Installation and Debugging, open warm-air drier, keep temperature of shed 10 DEG C of left and right.
(3) Surfacing Construction
Waterproof Layer Spreading of Bridge Surface adopts Chlorinated polyethylene plastic sheets for waterproofing, and topping adopts C40 microlith fibrous concrete.
When construction on the beam face of having cleared up evenly brushing one deck polyurethane water-proof paint as cementing agent, brushing thickness is not less than 1.5mm, then the surperficial paving Chlorinated polyethylene plastic sheets for waterproofing brushing in painting, installation of membrane is from one end, and bridge floor laterally sequentially carries out paving from low to high.Waterproof roll edge and beam body seam crossing adopt polyurethane water-proof paint to carry out edge sealing processing, and edge sealing width is not less than 100mm, and brushing thickness is not less than 2mm.
(4) insulated curing
Maintenance adopts watering maintenance, and insulation temperature of shed ensures that first day is surveyed once every about 4 hours 10 DEG C of left and right, after the initial set of topping concrete, surveys once every 8 hours.After three days, heat preservation construction device is removed, and adopts engineering cotton-wadded quilt covering curing 14 days.

Claims (3)

  1. One kind winter deck paving heat preservation construction device, it is characterized in that comprising by column (1), longeron (2), interval and be connected in the roof insulating support system that two truss crossbeams (3) between longeron and some cross binding, vertical supporting form, two sides of roof insulating support system, two end faces and end face are coated with geotextiles insulation layer (4), Polypropylence Sheet insulation layer (5) and tarpaulin waterproofing course (6) from inside to outside successively, and inner side, roof insulating support system one end is provided with warm-air drier (7).
  2. According to claim 1 winter deck paving heat preservation construction device, it is characterized in that all truss crossbeams (3) be welded in the middle of high two ends low bendings.
  3. According to described in claim 1 or 2 winter deck paving heat preservation construction device, it is characterized in that roof insulating support system below installs and be laid on the road wheel (8) that the guide rail on bridge floor cooperatively interacts.
CN201420333559.1U 2014-06-23 2014-06-23 Winter deck paving heat preservation construction device Active CN204023410U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420333559.1U CN204023410U (en) 2014-06-23 2014-06-23 Winter deck paving heat preservation construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420333559.1U CN204023410U (en) 2014-06-23 2014-06-23 Winter deck paving heat preservation construction device

Publications (1)

Publication Number Publication Date
CN204023410U true CN204023410U (en) 2014-12-17

Family

ID=52063298

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420333559.1U Active CN204023410U (en) 2014-06-23 2014-06-23 Winter deck paving heat preservation construction device

Country Status (1)

Country Link
CN (1) CN204023410U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120795A (en) * 2016-06-23 2016-11-16 中国十九冶集团有限公司 Concrete placings mark temperature operational method
CN106592430A (en) * 2016-11-14 2017-04-26 中建三局基础设施工程有限公司 Cast-in-place winter construction method for hanging basket cantilever
CN108316660A (en) * 2018-04-27 2018-07-24 中冶建工集团有限公司 Piping lane winter construction Windproof thermal insulation shed
CN108457199A (en) * 2018-06-11 2018-08-28 中铁二局第工程有限公司 A kind of mobile awning of beam portion construction and its construction method
CN108457301A (en) * 2018-03-09 2018-08-28 中交路桥建设有限公司 Improve the heat preserving method and system of extremely frigid zones shield duct piece processing temperature

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120795A (en) * 2016-06-23 2016-11-16 中国十九冶集团有限公司 Concrete placings mark temperature operational method
CN106592430A (en) * 2016-11-14 2017-04-26 中建三局基础设施工程有限公司 Cast-in-place winter construction method for hanging basket cantilever
CN108457301A (en) * 2018-03-09 2018-08-28 中交路桥建设有限公司 Improve the heat preserving method and system of extremely frigid zones shield duct piece processing temperature
CN108316660A (en) * 2018-04-27 2018-07-24 中冶建工集团有限公司 Piping lane winter construction Windproof thermal insulation shed
CN108457199A (en) * 2018-06-11 2018-08-28 中铁二局第工程有限公司 A kind of mobile awning of beam portion construction and its construction method

Similar Documents

Publication Publication Date Title
CN204023410U (en) Winter deck paving heat preservation construction device
CN106436777B (en) A kind of subway station skin-type waterproof construction and its construction method
CN203546762U (en) Triple waterproof advance water stop structure for post-cast strip
CN204492025U (en) The waterproof construction of the contour deformation joint of roofing
CN106836663B (en) The construction method of water-proof insulating roof
CN201695411U (en) Waterproof system of bottom board and wall surface of basement
CN108179669A (en) Frozen earth roadbed thermal protection struc ture body and its cooling means
CN109236322A (en) It a kind of artificial bottom plate preventing soft-rock tunnel pucking and its constructs and method for maintaining
CN109707114A (en) Tile roofing antiskid construction technology engineering method
CN114876117A (en) Multi-gradient planting roof structure and construction method thereof
CN204662742U (en) The movable surface construction structure of a kind of pitched roof
CN202689047U (en) Waterproof structure applied to construction joint in fabricated tube section of immersed tube
CN206616711U (en) A kind of waterproof construction at subway station main body and accessory interface
CN203383520U (en) Deep foundation pit canopy
CN205804785U (en) Self waterproofing environment-friendly type overhead heat insulation Rotating fields
CN105089290A (en) Method for repairing roof
CN204238264U (en) A kind of sole plate post-poured strip structure
CN206448603U (en) A kind of concrete flue movement joint
CN205224451U (en) Roofing parapet flashing protective layer structure
CN204547227U (en) Carry the waterproof thermal-insulated composite sheet material of self-adhesion of welding edge
CN205116573U (en) Waterproof polyurethane roof boarding keeps warm
CN204266404U (en) A kind of outer-wall crack-resisting anti-leakage structure
CN104196178B (en) Hollow double structure layer water-proof roofing and construction method thereof
CN204401651U (en) Abnormity resistance to compression longitudinal prestressing pin-connected panel underground pipe gallery
CN203808327U (en) Novel double T plates with brims

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant