CN204023410U - Winter deck paving heat preservation construction device - Google Patents
Winter deck paving heat preservation construction device Download PDFInfo
- Publication number
- CN204023410U CN204023410U CN201420333559.1U CN201420333559U CN204023410U CN 204023410 U CN204023410 U CN 204023410U CN 201420333559 U CN201420333559 U CN 201420333559U CN 204023410 U CN204023410 U CN 204023410U
- Authority
- CN
- China
- Prior art keywords
- support system
- construction
- insulating support
- roof insulating
- heat preservation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 41
- 238000004321 preservation Methods 0.000 title claims abstract description 17
- 238000009413 insulation Methods 0.000 claims abstract description 20
- 238000004078 waterproofing Methods 0.000 claims abstract description 7
- 238000005452 bending Methods 0.000 claims abstract description 5
- 239000004746 geotextile Substances 0.000 claims abstract description 5
- 239000004567 concrete Substances 0.000 abstract description 15
- 238000010438 heat treatment Methods 0.000 abstract description 5
- 238000003466 welding Methods 0.000 abstract description 5
- 230000000694 effects Effects 0.000 abstract description 2
- 230000003020 moisturizing effect Effects 0.000 abstract description 2
- 229910000831 Steel Inorganic materials 0.000 description 4
- 230000001680 brushing effect Effects 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 238000009434 installation Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 3
- 239000004709 Chlorinated polyethylene Substances 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 239000000428 dust Substances 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 239000003973 paint Substances 0.000 description 2
- 239000002985 plastic film Substances 0.000 description 2
- 229920002635 polyurethane Polymers 0.000 description 2
- 239000004814 polyurethane Substances 0.000 description 2
- 238000012545 processing Methods 0.000 description 2
- 238000007789 sealing Methods 0.000 description 2
- 238000003915 air pollution Methods 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 239000003245 coal Substances 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- PCHJSUWPFVWCPO-UHFFFAOYSA-N gold Chemical compound [Au] PCHJSUWPFVWCPO-UHFFFAOYSA-N 0.000 description 1
- 239000010931 gold Substances 0.000 description 1
- 229910052737 gold Inorganic materials 0.000 description 1
- 230000013011 mating Effects 0.000 description 1
- 239000012528 membrane Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 238000012946 outsourcing Methods 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 229920003023 plastic Polymers 0.000 description 1
- 231100000572 poisoning Toxicity 0.000 description 1
- 230000000607 poisoning effect Effects 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 239000000779 smoke Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Landscapes
- Road Paving Structures (AREA)
Abstract
The utility model relates to field of bridge construction, be specially one deck paving heat preservation construction device in winter, solve existing construction and adopt stove insulation, there is complex operation, contaminated environment, the problems such as homogeneous heating degree is bad, comprise by column, longeron, truss crossbeam and cross binding, the roof insulating support system that vertical supporting forms, two sides of roof insulating support system, two end faces and end face are coated with geotextiles insulation layer from inside to outside successively, Polypropylence Sheet insulation layer and tarpaulin waterproofing course, warm-air drier is installed in roof insulating support system inner side, the low bending in high two ends in the middle of all truss beam weldings become, road wheel is installed in roof insulating support system below, make temperature of shed reach code requirement, can reach the effect that bridge deck concrete in construction adds gentle moisturizing, attemperator need to be able to be moved according to construction, can have enough to meet the need use, peace is torn open conveniently, there is cost low, convenient construction, improve the advantages such as work efficiency.
Description
Technical field
The utility model relates to field of bridge construction, is specially one deck paving heat preservation construction device in winter.
Background technology
In bridge construction, the concrete of deck paving is because area is large and thin thickness, especially winter construction and health have certain difficulty, concrete is ability setting and harden under certain temperature condition in addition, carry out bridge deck concrete construction winter and can make concrete endure cold, and cannot make concrete coagulation, the contained moisture freezes such as soil, concrete, mortar, the easy embrittlement of constructional materials, brings many difficulties to building operations.Traditional cold weather concrete insulation protection adopts stove heat preservation construction, and the problem of its existence has: in (1) construction and need continuous coal in insulating process, complex operation, impact construction; (2) insulation stove produces volume of smoke, and construction environment is stuff, and easily poisoning, air pollution is serious; (3) near insulation stove local temperature higher, and away from local temperature lower, the uniformity of heating is bad, cause concrete construction quality be difficult to ensure.
Summary of the invention
The utility model adopts stove insulation in order to solve Deck Concrete Pavement construction in existing winter, has the problems such as complex operation, contaminated environment, homogeneous heating degree be bad, provide a kind of winter deck paving heat preservation construction device.
The utility model is to adopt following technical scheme to realize: winter deck paving heat preservation construction device, comprise by column, longeron, interval and be connected in the roof insulating support system that two truss crossbeams between longeron and some cross binding, vertical supporting form, two sides of roof insulating support system, two end faces and end face are coated with geotextiles insulation layer, Polypropylence Sheet insulation layer and tarpaulin waterproofing course from inside to outside successively, and inner side, roof insulating support system one end is provided with warm-air drier.
Described all truss beam weldings become the low bending in middle high two ends, at utmost increase the interior construction space of roof insulating in the situation that taking into account ceiling draining.
Described roof insulating support system below is installed and is laid on the road wheel that the guide rail on bridge floor cooperatively interacts, and like this, the construction speed that whole heat preservation construction device can be laid with bridge floor arbitrarily moves along track, easy to operate, time saving and energy saving.
Adopt structure design of the present utility model, adopt warm-air drier to heat environment in bridge floor and canopy, make temperature of shed reach code requirement, can reach the effect that bridge deck concrete in construction adds gentle moisturizing, in addition, insulation is made system bottom road wheel is installed, thereby attemperator need to be able to be moved according to construction, can have enough to meet the need use, peace is torn open conveniently, has the advantages such as cost is low, convenient construction, raising work efficiency.Adopting heat preservation construction device described in the utility model to carry out winter Surfacing Construction is a kind of novel construction method, compare former stove heating and thermal insulation, control insulation temperature of shed that can be more stable, and in roof insulating, be to heat more uniformly, can effectively ensure the concrete quality of deck paving.
Brief description of the drawings
Fig. 1 is the floor map of the utility model insulation support system;
Fig. 2 is facade structures schematic diagram of the present utility model;
In figure: 1-column; 2-longeron; 3-truss crossbeam; 4-geotextiles insulation layer; 5-Polypropylence Sheet insulation layer; 6-tarpaulin waterproofing course; 7-warm-air drier; 8-road wheel.
Detailed description of the invention
Winter deck paving heat preservation construction device, as shown in Figure 1, 2, comprise by column 1, longeron 2, interval and be connected in the roof insulating support system that two truss crossbeams 3 between longeron and some cross binding, vertical supporting form, two sides of roof insulating support system, two end faces and end face are coated with geotextiles insulation layer 4, Polypropylence Sheet insulation layer 5 and tarpaulin waterproofing course 6 from inside to outside successively, and inner side, roof insulating support system one end is provided with warm-air drier 7.The low bending in high two ends in the middle of all truss crossbeams 3 are welded into.Roof insulating support system below is installed and is laid on the road wheel 8 that the guide rail on bridge floor cooperatively interacts.
When concrete making, warm-air drier employing section gold warm air curtain, product type: D-30, air quantity: 2500m3/h, wind speed: 2-3m/s, power of motor: 250W, heating power: 30KW.Roof insulating adopts diameter ф 50, ф 20 steel pipe weldings to be connected into support system, and outsourcing trilaminate material, is respectively building cloth, plastic sheeting and water-proof tarpaulin, roof insulating 4 root posts adopt ф 50 steel pipes, and 4 road wheels are installed under steel pipe, to promote when mobile roof insulating.Other columns and horizontal vertical supporting adopt ф 20 steel pipes, every a truss crossbeam of 3 meters of designs, truss crossbeam is also formed by ф 20 steel-pipe weldings, the low bending in high both sides in the middle of truss beam welding becomes, the maximum interior construction space that increases in the situation that taking into account ceiling draining.
Warm-air drier heat preservation construction step:
(1) beam face cleaning
To bridge deck dabbing, with artificial floating bits and the drifting dust removed, then clean bridge floor with giant.
Before mating formation, beam face is checked, bridge floor should be smooth, coarse, dry, clean and tidy, must not have dust, foreign material or greasy dirt, and deck transverse slope should meet the requirements.Undesirable processing, is polished or is studied for a second time courses one has flunked thin projections or pit.
(2) mobile heat preservation construction device of the present utility model
Mobile heat preservation construction device, to the beam face of having cleared up, is then installed warm-air drier, when installation, will carry out earth leakage protective measure.After warm-air drier Installation and Debugging, open warm-air drier, keep temperature of shed 10 DEG C of left and right.
(3) Surfacing Construction
Waterproof Layer Spreading of Bridge Surface adopts Chlorinated polyethylene plastic sheets for waterproofing, and topping adopts C40 microlith fibrous concrete.
When construction on the beam face of having cleared up evenly brushing one deck polyurethane water-proof paint as cementing agent, brushing thickness is not less than 1.5mm, then the surperficial paving Chlorinated polyethylene plastic sheets for waterproofing brushing in painting, installation of membrane is from one end, and bridge floor laterally sequentially carries out paving from low to high.Waterproof roll edge and beam body seam crossing adopt polyurethane water-proof paint to carry out edge sealing processing, and edge sealing width is not less than 100mm, and brushing thickness is not less than 2mm.
(4) insulated curing
Maintenance adopts watering maintenance, and insulation temperature of shed ensures that first day is surveyed once every about 4 hours 10 DEG C of left and right, after the initial set of topping concrete, surveys once every 8 hours.After three days, heat preservation construction device is removed, and adopts engineering cotton-wadded quilt covering curing 14 days.
Claims (3)
- One kind winter deck paving heat preservation construction device, it is characterized in that comprising by column (1), longeron (2), interval and be connected in the roof insulating support system that two truss crossbeams (3) between longeron and some cross binding, vertical supporting form, two sides of roof insulating support system, two end faces and end face are coated with geotextiles insulation layer (4), Polypropylence Sheet insulation layer (5) and tarpaulin waterproofing course (6) from inside to outside successively, and inner side, roof insulating support system one end is provided with warm-air drier (7).
- According to claim 1 winter deck paving heat preservation construction device, it is characterized in that all truss crossbeams (3) be welded in the middle of high two ends low bendings.
- According to described in claim 1 or 2 winter deck paving heat preservation construction device, it is characterized in that roof insulating support system below installs and be laid on the road wheel (8) that the guide rail on bridge floor cooperatively interacts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420333559.1U CN204023410U (en) | 2014-06-23 | 2014-06-23 | Winter deck paving heat preservation construction device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420333559.1U CN204023410U (en) | 2014-06-23 | 2014-06-23 | Winter deck paving heat preservation construction device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204023410U true CN204023410U (en) | 2014-12-17 |
Family
ID=52063298
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420333559.1U Expired - Fee Related CN204023410U (en) | 2014-06-23 | 2014-06-23 | Winter deck paving heat preservation construction device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204023410U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106120795A (en) * | 2016-06-23 | 2016-11-16 | 中国十九冶集团有限公司 | Concrete placings mark temperature operational method |
CN106592430A (en) * | 2016-11-14 | 2017-04-26 | 中建三局基础设施工程有限公司 | Cast-in-place winter construction method for hanging basket cantilever |
CN108316660A (en) * | 2018-04-27 | 2018-07-24 | 中冶建工集团有限公司 | Piping lane winter construction Windproof thermal insulation shed |
CN108457301A (en) * | 2018-03-09 | 2018-08-28 | 中交路桥建设有限公司 | Improve the heat preserving method and system of extremely frigid zones shield duct piece processing temperature |
CN108457199A (en) * | 2018-06-11 | 2018-08-28 | 中铁二局第工程有限公司 | A kind of mobile awning of beam portion construction and its construction method |
-
2014
- 2014-06-23 CN CN201420333559.1U patent/CN204023410U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106120795A (en) * | 2016-06-23 | 2016-11-16 | 中国十九冶集团有限公司 | Concrete placings mark temperature operational method |
CN106592430A (en) * | 2016-11-14 | 2017-04-26 | 中建三局基础设施工程有限公司 | Cast-in-place winter construction method for hanging basket cantilever |
CN108457301A (en) * | 2018-03-09 | 2018-08-28 | 中交路桥建设有限公司 | Improve the heat preserving method and system of extremely frigid zones shield duct piece processing temperature |
CN108316660A (en) * | 2018-04-27 | 2018-07-24 | 中冶建工集团有限公司 | Piping lane winter construction Windproof thermal insulation shed |
CN108457199A (en) * | 2018-06-11 | 2018-08-28 | 中铁二局第工程有限公司 | A kind of mobile awning of beam portion construction and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204023410U (en) | Winter deck paving heat preservation construction device | |
CN106436777B (en) | A kind of subway station skin-type waterproof construction and its construction method | |
CN203583525U (en) | Waterproof structure for movement joints of peat soft soil stratum subway station | |
CN203583526U (en) | Waterproof structure of peat soft soil stratum subway station | |
CN203546762U (en) | Triple waterproof advance water stop structure for post-cast strip | |
CN102747750A (en) | Construction method for post-pouring settlement belt protective measures of basement top plates | |
CN106836663B (en) | The construction method of water-proof insulating roof | |
CN201695411U (en) | Waterproof system of bottom board and wall surface of basement | |
CN108179669A (en) | Frozen earth roadbed thermal protection struc ture body and its cooling means | |
CN109236322A (en) | It a kind of artificial bottom plate preventing soft-rock tunnel pucking and its constructs and method for maintaining | |
CN109707114A (en) | Tile roofing antiskid construction technology engineering method | |
CN204662742U (en) | The movable surface construction structure of a kind of pitched roof | |
CN202689047U (en) | Waterproof structure applied to construction joint in fabricated tube section of immersed tube | |
CN206616711U (en) | A kind of waterproof construction at subway station main body and accessory interface | |
CN203383520U (en) | Deep foundation pit canopy | |
CN205804785U (en) | Self waterproofing environment-friendly type overhead heat insulation Rotating fields | |
CN105089290A (en) | Method for repairing roof | |
CN204238264U (en) | A kind of sole plate post-poured strip structure | |
CN103628506B (en) | Construction method for waterproof positions of foundation platform and pile head | |
CN206448603U (en) | A kind of concrete flue movement joint | |
CN205224451U (en) | Roofing parapet flashing protective layer structure | |
CN204547227U (en) | Carry the waterproof thermal-insulated composite sheet material of self-adhesion of welding edge | |
CN205116573U (en) | Waterproof polyurethane roof boarding keeps warm | |
CN204266404U (en) | A kind of outer-wall crack-resisting anti-leakage structure | |
CN104196178B (en) | Hollow double structure layer water-proof roofing and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20141217 |