CN109236322A - It a kind of artificial bottom plate preventing soft-rock tunnel pucking and its constructs and method for maintaining - Google Patents

It a kind of artificial bottom plate preventing soft-rock tunnel pucking and its constructs and method for maintaining Download PDF

Info

Publication number
CN109236322A
CN109236322A CN201811388338.3A CN201811388338A CN109236322A CN 109236322 A CN109236322 A CN 109236322A CN 201811388338 A CN201811388338 A CN 201811388338A CN 109236322 A CN109236322 A CN 109236322A
Authority
CN
China
Prior art keywords
floor
bottom plate
module
tunnel
floor module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811388338.3A
Other languages
Chinese (zh)
Other versions
CN109236322B (en
Inventor
南存全
王礼江
武小慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Technical University
Original Assignee
Liaoning Technical University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Technical University filed Critical Liaoning Technical University
Priority to CN201811388338.3A priority Critical patent/CN109236322B/en
Publication of CN109236322A publication Critical patent/CN109236322A/en
Application granted granted Critical
Publication of CN109236322B publication Critical patent/CN109236322B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/02Feeding the unshaped material to moulds or apparatus for producing shaped articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B15/00General arrangement or layout of plant ; Industrial outlines or plant installations
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/086Methods of making concrete lining segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/01Methods or apparatus for enlarging or restoring the cross-section of tunnels, e.g. by restoring the floor to its original level
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Chemical & Material Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Road Paving Structures (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

It a kind of artificial bottom plate preventing soft-rock tunnel pucking and its constructs and method for maintaining, artificial bottom plate concrete pad along two rows of reinforced concrete floor modules that roadway floor trend is laid on roadway floor central axes two sides by being made up of;Filling flexible waterproof sealing filler between longitudinally adjacent floor module, the drainage pipeline in module, which is longitudinally interconnected, constitutes draining secret tunnel;Hydraulic jack is installed between laterally adjacent module;U-shaped drainage groove is arranged at jack lower part;The Concrete Filled material of top covering waterproof material is filled between floor module and tunnel highwall.By prefabricated panel module, casting concrete cushion block, be laid with floor module, construct drainage channel, installation jack and lay a railway track and etc. complete artificial bottom plate and construct;Tunnel occurs to take two sides rotation maintenance mode when pucking.The artificial bottom plate, which solves bottom plate existing for soft-rock tunnel and seeps water to corrode vulnerable to tunnel, occurs that pucking, supporting construction are complicated, support material cannot reuse and the technical problems such as inconvenient maintenance.

Description

It a kind of artificial bottom plate preventing soft-rock tunnel pucking and its constructs and method for maintaining
Technical field
The present invention relates to coal mining technology field, especially a kind of artificial bottom plate and its structure for preventing soft-rock tunnel pucking It builds and method for maintaining.
Background technique
Pucking is a kind of common mine pressure phenomenon of Soft Rock Drifts At Coal.Increasingly expand as coal in China is production-scale Big and mining depth to be continuously increased, pucking disaster increases increasingly.When pucking occurs for tunnel, the sky between back and bottom plate Between highly can be different degrees of reduction, interfere normal transport, pedestrian and the ventilation in tunnel;Serious Floor Heave in Roadway will affect tunnel The overall stability of country rock causes grave danger to the safety and high efficiency of Deep Mine, directly affects Safety of Coal Mine Production It goes on smoothly.
Existing Floor Heave in Roadway administering method from mechanical mechanism, is divided into two class of method for strengthening and destressing method mostly.Method for strengthening Mainly floor strata is improved by reinforcement measures such as bottom plate anchor pole, floor grouting, closed support and concrete anti-arch Intensity, to realize the purpose of floor lift control;Destressing method, which mainly passes through the unloading pressure means such as joint-cutting, drilling, standing, to be made originally Continuous rock mass is in discrete state, shifts the high stress around tunnel to deep, and floor rock is made to be in stress reduction Area, to achieve the purpose that floor lift control.
Mining Practice for many years proves, although the above method has certain control effect to Floor Heave in Roadway, is directed to Soft-rock tunnel, the effect is unsatisfactory, and pucking metaboly occurs for soft-rock tunnel still very generally, some tunnels is caused to undergo Repeatedly overhaul.
Currently, the method for protecting support of soft-rock tunnel mostly based on fixed structure, can generally repeat benefit after the damage of supporting structures It is less;In addition supporting structure structure is complicated, supporting and overhauls arduously time-consuming, and operation labor intensity is big, causes to prop up Protect higher cost.
Soft-rock tunnel bottom plate water swelling is the principal element for leading to occur pucking.For this purpose, Soft Rock Mine enterprise is around comprehensive Conjunction, which is harnessed the river, implements a series of administering methods, as airtight waterproof, tunnel change its course waterproof and defeated row control;To there is the soft of hydraulic connection Waterproof grout injection control before pick is taken in rock gangway road.Although these method specific aims are stronger, input cost is big, long in time limit, water blockoff effect Fruit is not significant, or even can generate water blockoff failure phenomenon.In addition, the gutter position in tunnel is all disposed within greatly tunnel side at present At base angle, this is that tunnel-surrounding stress collects the position for neutralizing complexity the most the most, is easiest to deformation failure, causes gutter structure Also it destroys;Gutter is destructurized and can accelerate the further deformation failure at tunnel base angle, to form vicious circle. This technical problem fails effectively to be solved so far.
The maintenance of soft-rock tunnel pucking, what is taken at present is once carried out by tunnel overall with, needs to tear rail open, by manually borrowing Simple tool is helped, pucking is crushed, is then laid a railway track again, rock is used in shipment pucking maintenance.Entire maintenance process leans on entirely Manual work cannot achieve mechanization, and large labor intensity, maintenance speed is slow, laborious time-consuming;Meanwhile because the maintenance period needs to seal Tunnel is closed, influences to produce.
The limitation of above-mentioned soft-rock tunnel bottom plate method for protecting support and the complexity of pucking maintenance process are soft as restricting at present The bottleneck of rock Floor Heave in Roadway Prevention Technique development.In order to control serious pucking deformation, have to be used in combination a variety of at present Maintaining method increases the complexity of supporting construction;At the same time, support material consumption is more and more, and the material consumed is more It for fixed structure, cannot reuse, support cost is high.
Summary of the invention
The object of the present invention is to provide a kind of artificial bottom plates for preventing soft-rock tunnel pucking, are deposited with solving above-mentioned soft-rock tunnel Bottom plate corroded by tunnel infiltration, supporting construction is complicated, support material cannot reuse and the technologies such as pucking inconvenience maintenance Problem.
The present invention also provides this artificial bottom plate construct and method for maintaining.
The artificial bottom plate provided by the invention for preventing soft-rock tunnel pucking, by the square floor being laid on above roadway floor Module splicing composition;
The floor module is by interior interconnected longitudinal drainage pipeline, transverse drainage duct and the vertical drainage pipeline of setting The rectangular block of armored concrete is constituted, wherein the upper end of vertical drainage pipeline and the V-arrangement sink for being laid on floor module upper surface In metal screen connect;The both lateral sides of floor module have backplate made of channel steel, there is hanging ring above backplate, wherein side There is hemispherical groove on backplate lateral surface;
Floor module is along the central axes two sides that the trend of roadway floor is in that two rows are symmetrically distributed in roadway floor, floor module Bottom surface by the concrete pad that corresponds to floor module connecting part and be placed in along roadway floor longitudinal central axis line in roadway floor Support pad;Hydraulic jack is installed by the hemispherical groove on the backplate lateral surface between laterally adjacent floor module, it is hydraulic The lower part of jack has by the two rows of floor modules for being symmetrically distributed in roadway floor central axes two sides and indulges along roadway floor The U-shaped drainage groove that the concrete pad in roadway floor is constituted is placed in central axes;It is filled between longitudinally adjacent floor module Flexible water airtight and watertight padding, the longitudinal drainage pipeline in floor module is in flexible water airtight and watertight padding by compressible communicating pipe Front and back connection, constitutes the draining secret tunnel of tunnel infiltration;Flexible waterproof material is covered with top between floor module and tunnel highwall Concrete Filled material filling.
The above-mentioned artificial bottom plate for preventing soft-rock tunnel pucking construct and method for maintaining, comprising the following steps:
Step 1, prefabricated panel module
In the backplate both upper ends thereof welding hanging ring processed, and hemispherical is processed on the wherein lateral surface of one piece of backplate Groove;Then the steel mesh being connected with backplate is bound between two backplates;Plastics control will be used while assembling reinforcement net At interconnected longitudinal drainage pipeline, transverse drainage duct and vertical drainage pipe element bind in steel mesh;Then Using end template and the cope plate casting concrete with v-depression, the nozzle of vertical drainage pipeline is corresponded on concrete top V-arrangement sink is poured out, and makes vertical drainage pipeline tapping in the slot bottom of V-arrangement sink;Form removal after concrete curing, V-arrangement metal screen is placed in V-arrangement sink respectively, floor module is made;
Step 2, the casting concrete cushion block in roadway floor
Roadway floor compacting is smoothed, and makes roadway floor laterally with its high center in central axes center both sides is low and water 2~3 ° of angle states of Heisei;The punishment that connects longitudinally being laid in roadway floor along the central axes of roadway floor and floor module The groove for not digging out deep 0.4m, width 0.5m pours strong concrete in the trench, constitutes the coagulation for being used for support pad floor module Native cushion block;
Step 3 is laid with floor module
Using on the prefabricated floor module of step 1 hanging ring and monorail crane along roadway floor trend be laid with from front to back it is prefabricated Floor module, when laying will be such that the of laterally opposite two side backplates of floor module take in step 2 along roadway floor axis In thread concrete pad, take floor module longitudinal direction both ends in step 2 along the joint that floor module is longitudinally laid with In manufactured concrete pad;
Step 4 constructs drainage channel
The longitudinal drainage pipeline being connected to compressible communicating pipe in longitudinally adjacent floor module first made of flexible material, Draining secret tunnel is constituted, the gap of longitudinally adjacent floor module is then filled with flexible water airtight and watertight padding;By two rows of bottom plate moulds Block and the bottom surface and two sides that the U-lag constituted between the concrete pad in roadway floor is placed in along roadway floor longitudinal central axis line Spray foam glue on face, and waterproof cloth is bonded, the U-shaped drainage groove penetrated through before and after roadway floor central axes is made;
The Concrete Filled material that covering waterproof material in top is filled between floor module and tunnel highwall, makes tunnel seep water Cannot from the highwall of tunnel under seep;
Step 5, installation hydraulic jack
The fixed hemispherical groove on backplate lateral surface matches respectively on the upper top surface of hydraulic jack and bottom surface Hemispherical bumps are respectively placed in the hemispherical groove on the backplate of opposed bottom module side by the hemispherical bumps of conjunction, are completed The installation of hydraulic jack;
Step 6 after completing hydraulic jack installation, is overlapped on the upper of opposed bottom module side backplate plate with metal cover board Portion avoids solid sundries from falling between opposed bottom module, damage hydraulic jack and blocking U-shaped drainage groove;
Step 7 is laid a railway track on mounted artificial bottom plate, and artificial bottom plate can formally come into operation;
The maintenance of step 8, artificial bottom plate bottom
Artificial bottom plate bottom is using after a certain period of time, and with gradually heaving for roadway floor, artificial bottom plate can be by original both sides State high, that center is low gradually becomes the high inverse state in the low center in both sides, and the development of this state influences mine car to a certain extent Artificial bottom plate need to be repaired when normally travel, rotation maintenance mode at left and right sides of artificial bottom plate is taken in maintenance, and side is repaired, The other side can use as usual, and operation order includes: the track removed on artificial bottom plate side;Remove metal cover board;Remove liquid Press jack;The floor module of side is sling one by one using monorail crane and is momentarily placed on the artificial bottom plate in opposite side;Then to the side Heaving for roadway floor is modified, the original state for keeping the low both sides of its rehabilitation center high;After terminating side finishing, single track is utilized It hangs the artificial floor module that will be removed to sling one by one, be replaced on the roadway floor trimmed by original position, with communicating pipe weight New connection longitudinal drainage pipeline, refills axial clearance with flexible water airtight and watertight padding;With mixing for top covering waterproof material Solidifying soil filler material refills the gap of floor module side backplate Yu tunnel highwall;Then on the artificial bottom plate in the side completed Again it lays a railway track, comes into operation;After the maintenance for completing artificial bottom plate side, the artificial bottom plate in the other side is repaired in the same way;Manually After bottom plate two sides are repaired, U-shaped drainage groove is constructed again;Hydraulic jack is reinstalled into of laterally opposite bottom plate mould Between block;Cover metal cover board;Whole maintenance works of artificial bottom plate, which are accused, to be completed.
The steel mesh being connected with backplate is bound described in above-mentioned steps 1 between two backplates to constitute by the following method Trussed reinforcing bar network: the both ends of transverse steel are respectively welded at the lower edges position on the inside of two backplates, on transverse steel Longitudinal reinforcement and longitudinal reinforcement net cover (every three transverse steels bind one group of longitudinal reinforcement net cover) are bound, by transverse steel, is indulged Trussed reinforcing bar network is constituted to reinforcing bar and reinforcing bar net cover.
The compressible communicating pipe of longitudinal drainage pipeline is rubber in the longitudinally adjacent floor module of connection described in above-mentioned steps 4 Pipe;The flexible water airtight and watertight padding in the longitudinally adjacent floor module gap of filling is foamed glue;It is described in floor module and lane The Concrete Filled material for the top covering waterproof material filled between road highwall, the waterproof material of upper part covering are foamed glue, The Concrete Filled material of lower part is made of flyash, sandstone and cement mixing.
The present invention compared with the existing technology possessed by the utility model has the advantages that
1, the artificial bottom plate of the present invention is both the support unit of roadway floor and the carrying road surface of vehicle and pedestrian, is based on It can effectively prevent soft-rock tunnel that pucking occurs the following effect of roadway floor: 1. pass through draining secret tunnel and the edge in floor module The U-shaped drainage groove penetrated through before and after central shaft can all collect the infiltration in tunnel and discharge in time, and percolation-proof effect is good, Corrode roadway floor vulnerable to water body;It, can be uniform to roadway floor 2. floor module is symmetrically assembled in the surface of roadway floor Apply pressure, roadway floor is compacted, the deformation force of roadway floor is resisted;It closes, makes 3. roadway floor is isolated by artificial bottom plate Roadway floor is not by extraneous physics and and chemical depletion.
2, it is filled between artificial floor module longitudinal direction using flexible waterproof material, by hydraulic jack top support between transverse direction, Artificial bottom plate can be made using early stage to there are vertical and horizontal to allow to press characteristic, the high stress of roadway surrounding rock is avoided to destroy artificial bottom plate Structure.
3, when artificial base plate paving, jack can give artificial bottom plate setting load, and jack can be given during roadway deformation The constant power of artificial bottom plate, makes artificial bottom plate and jack that arch supporting construction, supporting intensity and rigidity and tunnel bottom be collectively formed Plate country rock is adapted, and comprehensive support action can be played to roadway floor.
4, artificial bottom plate takes modular construction, and the roadway floor later period can realize artificial bottom plate or so two once pucking occurs Side wheel changes use and maintenance, does not interfere with each other tunnel use with maintenance, reduces to the influence degree normally produced;It can make to tie up simultaneously Realization mechanization is repaired, mitigates maintenance labor intensity, improves maintenance work efficiency.
5, the floor module of artificial bottom plate is made of the strong concrete of internal truss frame structure, and intensity is high, is had higher Resistance to compression tension and bending resistance, the contraction distortion of roadway floor middle and later periods can be resisted without damaging, can after tunnel is discarded Dismounting recycles and reuses, and advantageously reduces enterprise's production cost.
6, the reduction of supporting construction complexity is made by artificial bottom plate, the support material of consumption is reduced, and advantageously reduces branch Shield expense.
Detailed description of the invention
Fig. 1 is the schematic diagram of artificial bottom plate of the invention (along the transverse center cross-sectional view of floor module);
Fig. 2 is the schematic three dimensional views of Fig. 1 indsole plate module;
Fig. 3 is the transverse cross-sectional view of Fig. 2 floor module (without steel mesh);
Fig. 4 is the connection schematic diagram of laterally adjacent floor module;
Fig. 5 is the connection schematic diagram of longitudinally adjacent floor module;
Fig. 6 is the truss structure schematic diagram in Fig. 2 floor module;
Fig. 7 is transverse direction in Fig. 2 floor module, longitudinal reinforcement web frame schematic diagram;
Fig. 8 is the longitudinal reinforcement net cover coil structures schematic diagram in Fig. 2 floor module;
Fig. 9 is the drain pipeline structure schematic diagram in Fig. 2 floor module;
Figure 10 is status diagram when pucking occurs for tunnel;
Figure 11 is artificial bottom plate maintenance with reference to figure.
Symbol description in figure: 1- floor module, 2- longitudinal drainage pipeline, 3- transverse drainage duct, 4-V type sink, 5- are perpendicular To drainage pipeline, the top 6- covers the Concrete Filled material of waterproof material, 7- backplate, 8- monorail crane, 9- hanging ring, 10- communicating pipe, 11- flexible water airtight and watertight padding, 12- roadway floor, 13- (in V-arrangement sink) metal screen, 14-U shape drainage groove, 15- are mixed Solidifying soil cushion block, 16- metal cover board, 17- hydraulic jack, 18- transverse steel, 19- longitudinal reinforcement, 20- longitudinal reinforcement net cover, 21 Hemispherical groove.
Specific embodiment
Below in conjunction with drawings and examples, the present invention will be further described.
The present embodiment is that be laid on certain mine baseplate width be the artificial bottom plate in the soft-rock tunnel of 4200m.
As shown in Figure 1, artificial bottom plate is made of the splicing of square floor module 1 being laid on above roadway floor 12.
As shown in Figures 2 and 3, the floor module sets interconnected longitudinal drainage pipeline 2, transverse drainage duct by interior 3 and the armored concrete block of vertical drainage pipeline 5 constitute, wherein the upper end of vertical drainage pipeline and be laid on floor module Metal screen 13 in surface V-arrangement sink 4 connects;The both lateral sides of floor module have backplate 7 made of channel steel, have above backplate Hanging ring 9 wherein has the hemispherical groove 21 abutted against for hydraulic jack on the backplate lateral surface of side.
The size of the floor module are as follows: longitudinal (moving towards along tunnel) length 3000mm, transverse width 1800mm are thick up and down Spend 400mm.
In conjunction with Fig. 1, Fig. 4 and Fig. 5, floor module is symmetrically distributed in roadway floor along the trend of roadway floor in two rows Axis two sides, the bottom surface of floor module is by correspond to that floor module connecting part is placed in roadway floor concrete pad 15 Pad;Hydraulic jack 17 is installed by the hemispherical groove on the backplate lateral surface between laterally adjacent floor module, it is hydraulic The U-shaped drainage groove 14 that setting is moved towards along roadway floor central axes is arranged at the lower part of jack;It is filled out between longitudinally adjacent floor module Flexible water airtight and watertight padding 11 is filled, the longitudinal drainage pipeline in floor module is in flexible water airtight and watertight padding by compressible connection It is connected to before and after pipe 10, constitutes the draining secret tunnel of tunnel infiltration;Flexible water is covered with top between floor module and tunnel highwall The Concrete Filled material 6 of material is filled.
In conjunction with Fig. 6, Fig. 7, Fig. 8 and Fig. 9, when prefabricated panel module, make backplate with the channel steel processed, on backplate top two End installation hanging ring, and hemispherical groove is processed on one piece of backplate lateral surface wherein;Then by the both ends of transverse steel 18 It is respectively welded at the lower edges position surveyed in two backplates, longitudinal reinforcement 19 and longitudinal reinforcement net cover 20 are bound on transverse steel (every three transverse steels bind one group of longitudinal reinforcement net cover), constitutes purlin by transverse steel, longitudinal reinforcement and longitudinal reinforcement net cover Posture steel mesh;The longitudinal drainage pipeline being interconnected made of plastic tube, cross will be used shown in Fig. 9 while assembling reinforcement net To drainage pipeline and the binding of vertical drainage pipe element in steel mesh;Then end template and the upper mold with v-depression are utilized Plate casting concrete pours out V-arrangement sink in the nozzle that concrete top corresponds to vertical drainage pipeline, and makes vertical drainage pipeline Nozzle it is exposed on the bottom surface of V-arrangement sink;Form removal after end concrete curing places V-arrangement gold respectively in V-arrangement sink Belong to strainer, floor module is made.
When being laid with floor module, first roadway floor compacting is smoothed, and makes roadway floor laterally centered on its central axes The high center in both sides is low and level is at 2~3 ° of angle states (as shown in Figure 1);Along the central axes of roadway floor in roadway floor The groove for digging out deep 0.4m, width 0.5m respectively with the joint that floor module is longitudinally laid with, pours high-intensitive coagulation in the trench Soil constitutes the concrete pad for being used for support pad floor module.Then the hanging ring and single track of floor module backplate both upper ends thereof are utilized 8 are hung, is laid with prefabricated floor module from front to back along roadway floor trend, when laying will make floor module of laterally opposite two The backplate of side is taken in the concrete pad made of the roadway floor central axes in step 2, and floor module longitudinal direction both ends are taken In concrete pad, make between longitudinally adjacent floor module made of the joint that floor module is longitudinally laid in step 2 Form the gap 150mm;400mm spacing is formed between laterally adjacent floor module, is formed between floor module and tunnel highwall wide Spend the gap of 100mm.
When constructing drainage channel, the longitudinal drainage pipe that is connected to the communicating pipe made of rubber in longitudinally adjacent floor module Road (all or part of connection, the present embodiment are only connected to two longitudinal drainage pipelines positioned at side), constitutes draining secret tunnel, then The gap of longitudinally adjacent floor module is filled with the flexible water airtight and watertight padding that foamed glue is constituted;By longitudinal two rows of floor modules Spray foam glue in the groove that the backplate of two opposite sides and the concrete pad made of the roadway floor central axes are formed, And waterproof cloth is bonded, the U-shaped drainage groove penetrated through before and after roadway floor central axes is made;Between floor module and tunnel highwall Foamed glue, the under-filled Concrete Filled material being made of flyash, sandstone and cement of thickness 100mm is filled in gap middle and upper part, makes Tunnel infiltration cannot from the highwall of tunnel under seep.
When hydraulic jack is installed, on the upper top surface of hydraulic jack and bottom surface respectively it is fixed on backplate lateral surface The hemispherical bumps that match of hemispherical groove, half hemispherical bumps are respectively placed on the backplate of opposed bottom module side In spherical groove.
After completing hydraulic jack installation, the top of opposed bottom module side backplate plate is overlapped on metal cover board 16, Solid sundries are avoided to fall between opposed bottom module, damage hydraulic jack and blocking U-shaped drainage groove.
After the completion of artificial base plate paving, lay a railway track on mounted artificial bottom plate, artificial bottom plate can formally come into operation.
As shown in Figure 10, artificial bottom plate bottom uses after a certain period of time, with gradually heaving for roadway floor, artificial bottom plate meeting The high inverse state in the low center in both sides is gradually become by the low state in the high center in original both sides.This state develops shadow to a certain extent Artificial bottom plate need to be repaired when ringing to mine car normally travel.
As shown in figure 11, artificial bottom plate two sides rotation maintenance mode is taken in maintenance, i.e. side is repaired, and the other side can make as usual With operation order includes: the track removed on artificial bottom plate side;Remove metal cover board 16;Remove hydraulic jack;It utilizes Monorail crane slings the floor module of side one by one to be momentarily placed on the artificial bottom plate in opposite side;Then to the side, roadway floor is heaved It is modified, the original state for keeping the low both sides of its rehabilitation center high;It is artificial by what is removed using monorail crane after terminating side finishing Floor module is sling one by one, is replaced on the roadway floor trimmed by original position, is connected to longitudinal drainage with rubber communicating pipe Pipeline refills gap between floor module longitudinal direction with foamed glue;Bottom is refilled with the concrete of top covering foamed glue The gap of plate module side backplate and tunnel highwall;Then it lays a railway track, comes into operation again on the artificial bottom plate in the side completed;It is complete After repairing at side, the artificial bottom plate in the other side is repaired in the same way;After the artificial bottom plate maintenance in two sides, construct again artificial U-shaped drainage groove between bottom plate two sides;Hydraulic jack is reinstalled between of laterally opposite floor module;Cover metal Cover board;Complete whole maintenance works of artificial bottom plate.

Claims (4)

1. a kind of artificial bottom plate for preventing soft-rock tunnel pucking, which is characterized in that the artificial bottom plate is by being laid on roadway floor (12) square floor module (1) above splices composition;
The floor module sets interconnected longitudinal drainage pipeline (2), transverse drainage duct (3) and vertical drainage pipeline by interior (5) the rectangular block of armored concrete is constituted, wherein the upper end of vertical drainage pipeline and the V-arrangement for being laid on floor module upper surface Metal screen (13) in sink (4) connects;The both lateral sides of floor module have backplate made of channel steel (7), have above backplate Hanging ring (9) wherein has hemispherical groove (21) on the backplate lateral surface of side;
Floor module is along the central axes two sides that the trend of roadway floor is in that two rows are symmetrically distributed in roadway floor, the bottom of floor module Face is by the concrete pad (15) that corresponds to floor module connecting part and be placed in roadway floor along roadway floor longitudinal central axis line Support pad;Hydraulic jack (17) are installed by the hemispherical groove on the backplate lateral surface between laterally adjacent floor module, The lower part of hydraulic jack has by the two rows of floor modules for being symmetrically distributed in roadway floor central axes two sides and along tunnel bottom Plate longitudinal central axis line is placed in the U-shaped drainage groove (14) of the composition of the concrete pad in roadway floor;Longitudinally adjacent floor module Between filling flexible waterproof sealing filler (11), longitudinal drainage pipeline in floor module is in flexible water airtight and watertight padding by can Connection before and after the communicating pipe (10) of compression, constitutes the draining secret tunnel of tunnel infiltration;Top is used between floor module and tunnel highwall Cover Concrete Filled material (6) filling of flexible waterproof material.
2. prevented described in claim 1 the artificial bottom plate of soft-rock tunnel pucking construct and method for maintaining, feature include following Step:
Step 1, prefabricated panel module
In the backplate both upper ends thereof welding hanging ring processed, and it is recessed on the wherein lateral surface of one piece of backplate to process hemispherical Slot;Then the steel mesh being connected with backplate is bound between two backplates;It will be made of plastic tube while assembling reinforcement net Interconnected longitudinal drainage pipeline, transverse drainage duct and vertical drainage pipe element bind in steel mesh;Then sharp With end template and the cope plate casting concrete with v-depression, poured in the nozzle that concrete top corresponds to vertical drainage pipeline V-arrangement sink is built out, and makes vertical drainage pipeline tapping in the slot bottom of V-arrangement sink;Form removal after concrete curing, in V V-arrangement metal screen is placed in shape sink respectively, floor module is made;
Step 2, the casting concrete cushion block in roadway floor
Roadway floor compacting is smoothed, and keeps roadway floor laterally low with its high center in central axes center both sides and horizontal at 2 ~3 ° of angle states;It is dug out respectively in roadway floor along the joint that the central axes of roadway floor and floor module are longitudinally laid with The groove of deep 0.4m, width 0.5m pour strong concrete in the trench, constitute the concrete mats for being used for support pad floor module Block;
Step 3 is laid with floor module
Using on the prefabricated floor module of step 1 hanging ring and monorail crane (8) along roadway floor trend be laid with from front to back it is prefabricated Floor module, when laying will be such that the of laterally opposite two side backplates of floor module take in step 2 along roadway floor axis In thread concrete pad, take floor module longitudinal direction both ends in step 2 along the joint that floor module is longitudinally laid with In manufactured concrete pad;
Step 4 constructs drainage channel
The longitudinal drainage pipeline being connected to compressible communicating pipe in longitudinally adjacent floor module first made of flexible material is constituted Secret tunnel is drained, the gap of longitudinally adjacent floor module is then filled with flexible water airtight and watertight padding;By two rows of floor modules and Along the bottom surface and two sides that roadway floor longitudinal central axis line is placed in the U-lag constituted between the concrete pad in roadway floor Spray foam glue, and waterproof cloth is bonded, the U-shaped drainage groove penetrated through before and after roadway floor central axes is made;
The Concrete Filled material that covering waterproof material in top is filled between floor module and tunnel highwall makes tunnel infiltration cannot It is seeped under from the highwall of tunnel;
Step 5, installation hydraulic jack
It is fixed respectively on the upper top surface of hydraulic jack and bottom surface to be matched with the hemispherical groove on backplate lateral surface Hemispherical bumps are respectively placed in the hemispherical groove on the backplate of opposed bottom module side by hemispherical bumps, are completed hydraulic The installation of jack;
Step 6 after completing hydraulic jack installation, is overlapped on the upper of opposed bottom module side backplate plate with metal cover board (16) Portion avoids solid sundries from falling between opposed bottom module, damage hydraulic jack and blocking U-shaped drainage groove;
Step 7 is laid a railway track on mounted artificial bottom plate, and artificial bottom plate can formally come into operation;
The maintenance of step 8, artificial bottom plate bottom
Artificial bottom plate bottom is using after a certain period of time, with gradually heaving for roadway floor, artificial bottom plate can it is high by original both sides, in The low state of the heart gradually becomes the high inverse state in the low center in both sides, and the development of this state influences the normal row of mine car to a certain extent Artificial bottom plate need to be repaired when sailing, rotation maintenance mode at left and right sides of artificial bottom plate, side maintenance, the other side are taken in maintenance It can use as usual, operation order includes: the track removed on artificial bottom plate side;Remove metal cover board;Remove hydraulic jack Top;The floor module of side is sling one by one using monorail crane and is momentarily placed on the artificial bottom plate in opposite side;Then to the side tunnel bottom Heaving for plate is modified, the original state for keeping the low both sides of its rehabilitation center high;After terminating side finishing, it will be torn open using monorail crane Under artificial floor module sling one by one, be replaced on the roadway floor trimmed by original position, reconnected with communicating pipe Longitudinal drainage pipeline refills axial clearance with flexible water airtight and watertight padding;It is filled out with the concrete of top covering waterproof material Charge refills the gap of floor module side backplate Yu tunnel highwall;Then it is spread again on the artificial bottom plate in the side completed Rail comes into operation;After the maintenance for completing artificial bottom plate side, the artificial bottom plate in the other side is repaired in the same way;Artificial bottom plate two After side is repaired, U-shaped drainage groove is constructed again;By hydraulic jack reinstall to of laterally opposite floor module it Between;Cover metal cover board;Whole maintenance works of artificial bottom plate, which are accused, to be completed.
3. prevent according to claim 2 the artificial bottom plate of soft-rock tunnel pucking construct and method for maintaining, which is characterized in that Binding the steel mesh being connected with backplate described in step 1 between two backplates is the truss-like reinforcing bar constituted by the following method Net: being respectively welded at the lower edges position on the inside of two backplates for the both ends of transverse steel (18), binds on transverse steel vertical To reinforcing bar (19) and longitudinal reinforcement net cover (20), trussed reinforcing bar network is constituted by transverse steel, longitudinal reinforcement and reinforcing bar net cover.
4. according to claim 2 for prevent soft-rock tunnel pucking artificial bottom plate construct and method for maintaining, feature It is, the compressible communicating pipe of longitudinal drainage pipeline is rubber tube in the longitudinally adjacent floor module of connection described in step 4;It is described The flexible water airtight and watertight padding for filling longitudinally adjacent floor module gap is foamed glue;It is described floor module and tunnel highwall it Between the Concrete Filled material of top covering waterproof material filled, the waterproof material of upper part covering is foamed glue, lower part it is mixed Solidifying soil filler material is made of flyash, sandstone and cement mixing.
CN201811388338.3A 2018-11-21 2018-11-21 Artificial bottom plate for preventing soft rock roadway floor heave and construction and maintenance method thereof Active CN109236322B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811388338.3A CN109236322B (en) 2018-11-21 2018-11-21 Artificial bottom plate for preventing soft rock roadway floor heave and construction and maintenance method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811388338.3A CN109236322B (en) 2018-11-21 2018-11-21 Artificial bottom plate for preventing soft rock roadway floor heave and construction and maintenance method thereof

Publications (2)

Publication Number Publication Date
CN109236322A true CN109236322A (en) 2019-01-18
CN109236322B CN109236322B (en) 2020-03-06

Family

ID=65076156

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811388338.3A Active CN109236322B (en) 2018-11-21 2018-11-21 Artificial bottom plate for preventing soft rock roadway floor heave and construction and maintenance method thereof

Country Status (1)

Country Link
CN (1) CN109236322B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110529142A (en) * 2019-07-30 2019-12-03 太原理工大学 Deep tunnel pucking control device and method based on intelligent hydraulic bag
CN111894624A (en) * 2020-06-02 2020-11-06 神华包神铁路集团有限责任公司 Tunnel and bottom structure for preventing pucking disease
CN114017554A (en) * 2021-11-10 2022-02-08 北京城乡建设集团有限责任公司 Pipe orifice butt joint method and device for concrete pipeline
CN114776373A (en) * 2022-06-20 2022-07-22 长春黄金研究院有限公司 Artificial false bottom for thin-vein stope and manufacturing method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1293354A1 (en) * 1985-10-30 1987-02-28 Карагандинский политехнический институт Method of preventing bulging of soil species
JPH07259490A (en) * 1994-03-23 1995-10-09 Ishikawajima Constr Materials Co Ltd Walk floor laying method for tunnel
CN103388481A (en) * 2013-08-05 2013-11-13 中国矿业大学 Combined prefabricated slab for governing floor heave and method for governing floor heave
CN105201535A (en) * 2015-10-22 2015-12-30 山东科技大学 Resisting force dodging device for controlling floor heave, and construction method for device
CN106014443A (en) * 2016-05-10 2016-10-12 山东科技大学 Method for preventing roadway floor heaving and wall sliding of gob-side entry retaining

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1293354A1 (en) * 1985-10-30 1987-02-28 Карагандинский политехнический институт Method of preventing bulging of soil species
JPH07259490A (en) * 1994-03-23 1995-10-09 Ishikawajima Constr Materials Co Ltd Walk floor laying method for tunnel
CN103388481A (en) * 2013-08-05 2013-11-13 中国矿业大学 Combined prefabricated slab for governing floor heave and method for governing floor heave
CN105201535A (en) * 2015-10-22 2015-12-30 山东科技大学 Resisting force dodging device for controlling floor heave, and construction method for device
CN106014443A (en) * 2016-05-10 2016-10-12 山东科技大学 Method for preventing roadway floor heaving and wall sliding of gob-side entry retaining

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110529142A (en) * 2019-07-30 2019-12-03 太原理工大学 Deep tunnel pucking control device and method based on intelligent hydraulic bag
CN111894624A (en) * 2020-06-02 2020-11-06 神华包神铁路集团有限责任公司 Tunnel and bottom structure for preventing pucking disease
CN111894624B (en) * 2020-06-02 2022-04-01 神华包神铁路集团有限责任公司 Tunnel and bottom structure for preventing pucking disease
CN114017554A (en) * 2021-11-10 2022-02-08 北京城乡建设集团有限责任公司 Pipe orifice butt joint method and device for concrete pipeline
CN114776373A (en) * 2022-06-20 2022-07-22 长春黄金研究院有限公司 Artificial false bottom for thin-vein stope and manufacturing method
CN114776373B (en) * 2022-06-20 2022-10-11 长春黄金研究院有限公司 Artificial false bottom for thin-vein stope and manufacturing method

Also Published As

Publication number Publication date
CN109236322B (en) 2020-03-06

Similar Documents

Publication Publication Date Title
CN101838968B (en) Double track bridge construction process crossing existing railway operational lines
CN109236322A (en) It a kind of artificial bottom plate preventing soft-rock tunnel pucking and its constructs and method for maintaining
CN108951425A (en) Cast-in-situ prestressed concrete continuous box girder primary concreting molding construction method
CN101906768B (en) Panel construction method of concrete faced rock-fill dam
CN207987983U (en) A kind of waterproof construction being used for underground engineering main body construction seam and post-cast strip
CN208136927U (en) A kind of soil cutting side slope supporting construction
CN201746840U (en) Foundation pit support system equipped with a plurality of inclined rear anchors capable of recycling
CN208280965U (en) Coal mine deep well tunnel smooth surface concrete spraying support structure
CN110158389A (en) A kind of light soil road structure and its construction method
CN110863498A (en) Deep foundation pit combined supporting construction method next to subway station
CN208899527U (en) A kind of supporting and the integrated system of Pipe rack
CN204753604U (en) A excavation supporting system for expanding soil district
CN113073680B (en) Slag disposal site retaining wall structure of plateau high-cold area and construction method thereof
CN107100649B (en) Construction process for inclined shaft concrete pouring
CN104863382A (en) Roof panel reinforcing method
CN112012762B (en) Construction method of double-layer secondary lining multi-arch tunnel structure
CN212272234U (en) High-strength combined template for open groove section of large-section inclined shaft
CN112709143A (en) Cast-in-place inclined leg rigid frame bridge disc buckle type full-space support and template construction method
CN110820756A (en) Shield well and vertical shaft deep foundation pit excavation safety construction method
CN214366158U (en) Coal mine underground cement blanket type air bridge
CN107401142B (en) Bank revetment heightening construction method is refuted in active service
CN109930610A (en) Constrained environment foundation pit adds the construction method of steel pipe mixing diagonal brace using concrete
CN115030731A (en) Pilot tunnel construction method in cross tunnel engineering
CN110904866B (en) Concrete bridge deck pavement replacement and repair structure and construction method
CN211421139U (en) Shield constructs well crown beam bearing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant