CN204238264U - A kind of sole plate post-poured strip structure - Google Patents

A kind of sole plate post-poured strip structure Download PDF

Info

Publication number
CN204238264U
CN204238264U CN201420687628.9U CN201420687628U CN204238264U CN 204238264 U CN204238264 U CN 204238264U CN 201420687628 U CN201420687628 U CN 201420687628U CN 204238264 U CN204238264 U CN 204238264U
Authority
CN
China
Prior art keywords
post
concrete
plate
prefabricated
bottom plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420687628.9U
Other languages
Chinese (zh)
Inventor
彭国禄
张和国
周自红
聂强
方小毛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongda Construction Co ltd
ZHONGDA CONSTRUCTION GROUP CO Ltd
Original Assignee
ZHONGDA CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHONGDA CONSTRUCTION Co Ltd filed Critical ZHONGDA CONSTRUCTION Co Ltd
Priority to CN201420687628.9U priority Critical patent/CN204238264U/en
Application granted granted Critical
Publication of CN204238264U publication Critical patent/CN204238264U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Building Environments (AREA)

Abstract

本实用新型涉及一种基础底板后浇带结构,由基础底板、混凝土垫层、预埋螺杆、预制封闭板、板肋、防水混凝土、后浇带混凝土、遇水膨胀橡胶、底板装饰层等组成;后浇带两侧面的混凝土设置成台阶状;预制封闭板下表面的台阶上预埋螺杆;后浇带从下往上依次设有防水混凝土、后浇带混凝土、预制封闭板、底板装饰层;预制封闭板两侧设有遇水膨胀橡胶;基础底板与预制封闭板上表面设有底板装饰层。本实用新型涉及结构可以有效保护两侧伸出钢筋的腐蚀,避免杂物及施工垃圾掉入后浇带凹槽内,后浇带混凝土浇筑后可立即进行下道工序的施工,同时具有良好的防水效果。

The utility model relates to a post-pouring belt structure of a foundation bottom plate, which is composed of a foundation bottom plate, a concrete cushion, a pre-embedded screw, a prefabricated closing plate, a slab rib, waterproof concrete, a post-pouring belt concrete, water-swellable rubber, a bottom plate decoration layer, etc. ; The concrete on both sides of the post-casting belt is set in a stepped shape; the screw is embedded on the steps on the lower surface of the prefabricated closed slab; the post-casting belt is provided with waterproof concrete, post-cast concrete, prefabricated closed slab, and bottom plate decorative layer in sequence from bottom to top Water-swellable rubber is provided on both sides of the prefabricated closed plate; the base plate and the upper surface of the prefabricated closed plate are provided with a bottom plate decorative layer. The utility model relates to a structure that can effectively protect the corrosion of steel bars protruding from both sides, prevent sundries and construction waste from falling into the groove of the post-casting belt, and the construction of the next process can be carried out immediately after the concrete of the post-casting belt is poured, and at the same time it has good Waterproof effect.

Description

一种基础底板后浇带结构A post-cast strip structure for the foundation base plate

技术领域technical field

本实用新型涉及一种基础底板后浇带结构,属于建筑施工构造技术领域。The utility model relates to a post-pouring strip structure of a foundation bottom plate, which belongs to the technical field of building construction structures.

背景技术Background technique

随着高层建筑向体量大型化和结构功能多样化方向发展,超长(即超过钢筋混凝土结构伸缩缝的最大间距)结构、主楼裙房式结构或体形不规则结构不断出现,特别是对地下防水有要求的建筑物,要求结构不留变形缝,常采用施工后浇缝(即后浇带)来取代它,对长度较长、面积较大带地下室的高层板式楼宇等建筑物,以及独立的地下建筑物都根据设计规范要求设置了沉降或伸缩后浇带。随着后浇带广泛在工程中使用,后浇带的施工质量直接影响主体工程的质量。With the development of high-rise buildings in the direction of large-scale volume and diversified structural functions, super-long (that is, exceeding the maximum distance between expansion joints of reinforced concrete structures), structures of main building podiums, or structures with irregular shapes continue to appear, especially for underground buildings. For buildings with waterproof requirements, no deformation joints are required in the structure, and post-construction pouring joints (ie post-pouring belts) are often used to replace them. All underground buildings are equipped with settlement or telescopic post-casting belts according to the requirements of the design code. As the post-cast belt is widely used in projects, the construction quality of the post-cast belt directly affects the quality of the main project.

传统的基础底板后浇带结构(申请号:201120202782.9),从下至上依次包括垫层、后浇带加强层、防水层、防水保护层和混凝土结构层,其中后浇带的加强层由沿后浇带长度方向铺设的钢板形成的一体结构取代了原来的钢筋混凝土结构,减少了工程量和劳动力;垫层施工完成后,只需将钢板按设计位置放置即可,施工方便,能大大减轻劳动作业量,提高工作效率,减少施工时间。此结构形式存在以下缺点:(1)施工过程中后浇带始终处于敞开状态,施工垃圾容易进入后浇带,对后浇带结构的施工质量、强度以及耐久性产生一定的不良影响,同时后浇带中外露的钢筋容易受到腐蚀;(2)后浇带两侧面容易产生渗水通道,影响结构的使用年限。The traditional base plate post-cast belt structure (application number: 201120202782.9) consists of a cushion layer, a post-cast belt reinforcement layer, a waterproof layer, a waterproof protection layer and a concrete structure layer from bottom to top, wherein the post-cast belt reinforcement layer is formed along the rear The integrated structure formed by the steel plates laid in the length direction of the pouring belt replaces the original reinforced concrete structure, which reduces the amount of work and labor; after the cushion construction is completed, it is only necessary to place the steel plates according to the designed position, which is convenient for construction and can greatly reduce labor. Reduce workload, improve work efficiency and reduce construction time. This structural form has the following disadvantages: (1) The post-cast belt is always open during the construction process, and construction waste is easy to enter the post-cast belt, which has a certain adverse effect on the construction quality, strength and durability of the post-cast belt structure. The exposed steel bars in the pouring belt are easily corroded; (2) water seepage channels are likely to be formed on both sides of the post-casting belt, which affects the service life of the structure.

实用新型内容Utility model content

本实用新型的目的是克服现有技术中的不足,提供一种能够有效保护后浇带两侧伸出的钢筋,避免钢筋腐蚀,有效避免施工垃圾掉入后浇带并具有防水效果的结构。The purpose of the utility model is to overcome the deficiencies in the prior art and provide a waterproof structure that can effectively protect the steel bars protruding from both sides of the post-casting belt, avoid corrosion of the steel bars, effectively prevent construction waste from falling into the post-casting belt.

这种基础底板后浇带结构,包括基础底板、混凝土垫层、预埋螺杆、预制封闭板、板肋、防水混凝土、后浇带混凝土、遇水膨胀橡胶和底板装饰层;后浇带从下往上依次设有防水混凝土、后浇带混凝土、预制封闭板、底板装饰层;所述后浇带混凝土两侧面设置成台阶状;预制封闭板下表面的台阶上预埋将预制封闭板与基础底板固定的螺杆;预制封闭板两侧设有遇水膨胀橡胶;基础底板与预制封闭板上表面设有底板装饰层。This post-cast belt structure of the foundation bottom plate includes foundation bottom plate, concrete cushion, pre-embedded screw, prefabricated closed plate, slab ribs, waterproof concrete, post-cast concrete, water-swellable rubber and bottom plate decorative layer; Waterproof concrete, post-cast concrete, prefabricated closed slab, and bottom plate decoration layer are arranged in sequence on the top; the two sides of the post-cast concrete are set in a step shape; the prefabricated closed slab and the foundation The bottom plate is fixed with screws; the two sides of the prefabricated closing plate are provided with water-swellable rubber;

作为优选:所述后浇带两侧混凝土设置成台阶状,上下的横向钢筋伸出侧面,并分别和台阶另一侧的横向钢筋焊接在一起。As a preference: the concrete on both sides of the post-pouring belt is arranged in a step shape, and the upper and lower transverse reinforcements protrude from the side, and are respectively welded together with the transverse reinforcements on the other side of the step.

作为优选:所述预制封闭板采用预制钢筋混凝土板或钢板,预制封闭板上预留螺杆贯穿孔,预制封闭板下表面设有板肋,预制封闭板顶部与基础底板的上表面处于同一水平面。As a preference: the prefabricated closed slab is made of prefabricated reinforced concrete slab or steel plate, screw holes are reserved on the prefabricated closed slab, the lower surface of the prefabricated closed slab is provided with plate ribs, and the top of the prefabricated closed slab is at the same level as the upper surface of the base plate.

作为优选:所述后浇带混凝土与基础底板采用同一标号的混凝土。As a preference: the post-cast strip concrete and the base plate adopt the same grade of concrete.

本实用新型具有以下的特点和有益效果:The utility model has the following characteristics and beneficial effects:

1、本实用新型涉及的基础底板后浇带结构能够有效保护后浇带两侧伸出的横向钢筋,避免钢筋腐蚀。1. The post-cast strip structure of the foundation floor involved in the utility model can effectively protect the transverse steel bars protruding from both sides of the post-cast strip to avoid corrosion of the steel bars.

2、预制封闭板板的设置可以保持后浇带内部的清洁,避免杂物以及施工垃圾进入后浇带凹槽内,从而提高结构的施工质量及耐久性,同时,后浇带混凝土浇筑完毕后,可立即进行下道工序的施工,有效缩短了施工工期。2. The setting of prefabricated closed slabs can keep the interior of the post-casting belt clean, and prevent debris and construction waste from entering the groove of the post-casting belt, thereby improving the construction quality and durability of the structure. At the same time, after the concrete pouring of the post-casting belt is completed , The construction of the next process can be carried out immediately, which effectively shortens the construction period.

3、预制钢筋混凝土盖板四周以及与螺杆固定连接处设置遇水膨胀橡胶,可以有效提高结构的防水效果。3. Water-swellable rubber is installed around the prefabricated reinforced concrete cover plate and at the fixed connection with the screw, which can effectively improve the waterproof effect of the structure.

4、后浇带底部设置防水混凝土,可以增强后浇带结构的防水效果,避免基础底部的地下水对基础产生不良影响。4. Waterproof concrete is set at the bottom of the post-casting belt, which can enhance the waterproof effect of the post-casting belt structure and avoid the adverse effects of groundwater at the bottom of the foundation on the foundation.

综上所述,采用本基础底板后浇带结构可有效保护后浇带中外露的底板上下主筋,同时避免了杂物以及施工垃圾进入后浇带,起到提高后浇带结构的施工质量、强度以及耐久性的作用,同时具有很好的防水性能。To sum up, the post-pouring belt structure of the base plate can effectively protect the exposed main ribs of the bottom plate in the post-casting belt, and at the same time prevent debris and construction waste from entering the post-casting belt, which can improve the construction quality of the post-casting belt structure. The role of strength and durability, while having a good waterproof performance.

附图说明Description of drawings

图1是本实用新型一种基础底板后浇带防水混凝土浇筑前结构示意图;Fig. 1 is a schematic diagram of the structure before pouring waterproof concrete of a foundation base plate of the present invention;

图2是本实用新型一种基础底板后浇带结构示意图。Fig. 2 is a structural schematic diagram of a base plate post-casting belt of the utility model.

附图标记说明:基础底板1;混凝土垫层2;预埋螺杆3;紧固螺帽4;横向钢筋5;纵向钢筋6;预制封闭板7;焊接接头8;遇水膨胀橡胶9;防水混凝土10;后浇带混凝土11;底板装饰层12;板肋13;后浇带凹槽14。Explanation of reference signs: base plate 1; concrete cushion 2; embedded screw 3; fastening nut 4; transverse reinforcement 5; longitudinal reinforcement 6; prefabricated closed plate 7; welded joint 8; water-swellable rubber 9; 10; post-pouring concrete 11; floor decoration layer 12; plate rib 13; post-pouring groove 14.

具体实施方式Detailed ways

下面结合附图和实施例对本实用新型做进一步描述。虽然本实用新型将结合较佳实施例进行描述,但应知道,并不表示本实用新型限制在所述实施例中。相反,本实用新型将涵盖可包含在有附后权利要求书限定的本实用新型的范围内的替换物、改进型和等同物。Below in conjunction with accompanying drawing and embodiment the utility model is described further. Although the utility model will be described in conjunction with preferred embodiments, it should be understood that it does not mean that the utility model is limited to the embodiments. On the contrary, the invention is to cover alternatives, modifications and equivalents, which may be included within the scope of the invention as defined by the appended claims.

混凝土的制作过程、运输与浇筑方式等本实施例中不在累述,重点阐述本实用新型涉及结构的实施方式。The production process, transportation and pouring methods of concrete, etc. will not be described repeatedly in this embodiment, and the embodiment of the structure related to the present utility model will be explained emphatically.

图1是本实用新型一种基础底板后浇带防水混凝土浇筑前结构示意图;图2是本实用新型一种基础底板后浇带结构示意图,参照图1、图2所示的一种基础底板后浇带结构主要包括:基础底板1、混凝土垫层2、预埋螺杆3、预制封闭板7、遇水膨胀橡胶9、防水混凝土10、后浇带混凝土11、底板装饰层12、板肋13。基础底板1厚度为650mm,混凝土垫层2厚度为200,后浇带凹槽14的三个台阶的宽度分别为100mm,15mm,20mm。Fig. 1 is a schematic diagram of the structure of the post-pouring belt of the foundation floor of the present invention before pouring waterproof concrete; Fig. 2 is a schematic diagram of the structure of the post-casting strip of the foundation floor of the present invention, referring to the post-casting of a foundation floor shown in Fig. 1 and Fig. 2 The cast belt structure mainly includes: foundation base plate 1, concrete cushion 2, pre-embedded screw rod 3, prefabricated closed plate 7, water-swellable rubber 9, waterproof concrete 10, post-cast concrete 11, base plate decorative layer 12, plate rib 13. The thickness of the base plate 1 is 650 mm, the thickness of the concrete cushion 2 is 200 mm, and the widths of the three steps with grooves 14 after casting are 100 mm, 15 mm, and 20 mm respectively.

后浇带从下往上依次设有防水混凝土10、后浇带混凝土11、预制封闭板7、底板装饰层12。防水混凝土10的强度等级为C30,石子最大粒径为5~31.5mm,掺合6%~8%的YEA-H复合型膨胀剂。The post-cast belt is provided with waterproof concrete 10, post-cast concrete 11, prefabricated closing plate 7, and bottom plate decoration layer 12 sequentially from bottom to top. The strength grade of the waterproof concrete 10 is C30, the maximum particle size of the stone is 5-31.5mm, and 6%-8% of YEA-H composite expansion agent is mixed.

后浇带混凝土10与基础底板1采用42.5号普通硅酸盐水泥,混凝土强度等级为C30。预制封闭板7采用钢板,厚度为20mm,宽度为400mm,预制封闭板7上表面与基础底板1的上表面处于同一水平面上。板肋13采用钢板,板肋13厚10mm,宽20mm,每隔50mm设置一个。The post-cast strip concrete 10 and the base plate 1 are made of No. 42.5 ordinary Portland cement, and the concrete strength grade is C30. The prefabricated closing plate 7 is made of a steel plate with a thickness of 20 mm and a width of 400 mm. The upper surface of the prefabricated closing plate 7 is on the same level as the upper surface of the foundation base plate 1 . The plate rib 13 adopts a steel plate, and the plate rib 13 is 10mm thick and 20mm wide, and one is set every 50mm.

施工过程如下:施工时首先对混凝土垫层2进行浇筑,达到强度要求后对基础底板1进行施工,浇筑后浇带两侧的基础底板1时,在台阶上预埋螺杆3;待基础底板1的混凝土初凝后,在其上铺盖一层预制封闭板7,并固定在预埋螺杆3上,预制封闭板7采用带有板肋13的钢板;对后浇带凹槽14内进行施工时,移开预制封闭板7,焊接后浇带中的横向钢筋5;向后浇带底部内浇筑防水混凝土10,防水混凝土10上部浇筑后浇带混凝土11,后浇带混凝土11和两侧基础底板1采用同一标号混凝土;待混凝土初凝后,可立即铺设预制封闭板7,并通过预埋螺杆3与基础底板1固定连接,其中预制封闭板7两侧以及预埋螺杆3固定连接处涂抹遇水膨胀橡胶9。The construction process is as follows: during construction, the concrete cushion 2 is poured first, and the foundation floor 1 is constructed after the strength requirements are met. After the initial setting of the concrete, lay a layer of prefabricated closing plate 7 on it, and fix it on the pre-embedded screw 3. The prefabricated closing plate 7 adopts a steel plate with plate ribs 13; , remove the prefabricated closing plate 7, weld the transverse reinforcement 5 in the post-casting belt; pour waterproof concrete 10 in the bottom of the back-casting belt, pour the post-casting concrete 11 on the upper part of the waterproof concrete 10, post-casting the concrete 11 and the base plates on both sides 1 Use the same grade of concrete; after the initial setting of the concrete, the prefabricated closing plate 7 can be laid immediately, and fixedly connected with the foundation base plate 1 through the embedded screw 3, wherein the two sides of the prefabricated closing plate 7 and the fixed connection of the pre-embedded screw 3 are painted with Water-swellable rubber9.

Claims (4)

1.一种基础底板后浇带结构,其特征在于:包括基础底板(1)、混凝土垫层(2)、预埋螺杆(3)、预制封闭板(7)、板肋(13)、防水混凝土(10)、后浇带混凝土(11)、遇水膨胀橡胶(9)和底板装饰层(12);后浇带从下往上依次设有防水混凝土(10)、后浇带混凝土(11)、预制封闭板(7)、底板装饰层(12);所述后浇带混凝土(11)两侧面设置成台阶状;预制封闭板(7)下表面的台阶上预埋将预制封闭板(7)与基础底板(1)固定的螺杆(3);预制封闭板(7)两侧设有遇水膨胀橡胶(9);基础底板(1)与预制封闭板(7)上表面设有底板装饰层(12)。1. a post-pouring belt structure of foundation base plate, is characterized in that: comprise base base plate (1), concrete pad (2), pre-embedded screw rod (3), prefabricated closed plate (7), slab rib (13), waterproof Concrete (10), post-cast concrete (11), water-swellable rubber (9) and bottom plate decoration layer (12); the post-cast belt is provided with waterproof concrete (10), post-cast concrete (11) from bottom to top ), a prefabricated closing plate (7), a base plate decorative layer (12); the two sides of the post-cast concrete (11) are set in a step shape; the prefabricated closing plate ( 7) The screw (3) fixed to the base plate (1); water-swellable rubber (9) is provided on both sides of the prefabricated closing plate (7); the base plate (1) and the upper surface of the prefabricated closing plate (7) are provided with a bottom plate Decorative layer (12). 2.根据权利要求1所述的基础底板后浇带结构,其特征在于:所述后浇带两侧混凝土设置成台阶状,上下的横向钢筋伸出侧面,并分别和台阶另一侧的横向钢筋焊接在一起。2. foundation bottom plate post-pouring belt structure according to claim 1, is characterized in that: described post-pouring belt both sides concrete is set to step shape, and the horizontal steel bar up and down stretches out side, and respectively with the transverse direction of step other side The bars are welded together. 3.根据权利要求1所述的基础底板后浇带结构,其特征在于:所述预制封闭板(7)采用预制钢筋混凝土板或钢板,预制封闭板(7)上预留螺杆贯穿孔,预制封闭板(7)下表面设有板肋(13),预制封闭板(7)顶部与基础底板(1)的上表面处于同一水平面。3. foundation bottom plate post-cast belt structure according to claim 1, it is characterized in that: described prefabricated closing plate (7) adopts prefabricated reinforced concrete slab or steel plate, reserves screw through hole on the prefabricated closing plate (7), prefabricated The lower surface of the closing plate (7) is provided with plate ribs (13), and the top of the prefabricated closing plate (7) is at the same level as the upper surface of the base plate (1). 4.根据权利要求1所述的基础底板后浇带结构,其特征在于:所述后浇带混凝土(11)与基础底板(1)采用同一标号的混凝土。4. foundation bottom plate post-cast belt structure according to claim 1, is characterized in that: described post-cast belt concrete (11) and foundation bottom plate (1) adopt the concrete of same label.
CN201420687628.9U 2014-11-17 2014-11-17 A kind of sole plate post-poured strip structure Expired - Lifetime CN204238264U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420687628.9U CN204238264U (en) 2014-11-17 2014-11-17 A kind of sole plate post-poured strip structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420687628.9U CN204238264U (en) 2014-11-17 2014-11-17 A kind of sole plate post-poured strip structure

Publications (1)

Publication Number Publication Date
CN204238264U true CN204238264U (en) 2015-04-01

Family

ID=52767777

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420687628.9U Expired - Lifetime CN204238264U (en) 2014-11-17 2014-11-17 A kind of sole plate post-poured strip structure

Country Status (1)

Country Link
CN (1) CN204238264U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040742A (en) * 2015-07-21 2015-11-11 成都聚智工业设计有限公司 Waterproof post-cast strip structure
CN109736847A (en) * 2019-02-14 2019-05-10 中铁十一局集团有限公司 One-time pouring concrete inverted arch and construction method thereof
CN113047460A (en) * 2021-03-29 2021-06-29 中信国安建工集团有限公司 Post-cast strip structure and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040742A (en) * 2015-07-21 2015-11-11 成都聚智工业设计有限公司 Waterproof post-cast strip structure
CN109736847A (en) * 2019-02-14 2019-05-10 中铁十一局集团有限公司 One-time pouring concrete inverted arch and construction method thereof
CN113047460A (en) * 2021-03-29 2021-06-29 中信国安建工集团有限公司 Post-cast strip structure and construction method
CN113047460B (en) * 2021-03-29 2023-02-03 中信国安建工集团有限公司 Post-cast strip structure and construction method

Similar Documents

Publication Publication Date Title
CN109853367B (en) Ultra-high-performance concrete combined permanent formwork and application
CN107882240B (en) Recycled block concrete prefabricated laminated slab and manufacturing process thereof
CN104947719A (en) Basement roof post-cast strip hanging support formwork structure and post-cast strip construction method thereof
CN104790436B (en) Basement in high rise building top board pouring after settlement advance water stop construction method
CN112144674A (en) Precast concrete reversed ridge and construction method thereof
CN102251540A (en) Construction installation method for fast-easy setback grid of bottom plate construction joint
CN210086032U (en) An ultra-high performance concrete combined permanent formwork
CN104060781A (en) Cast-in-situ cranked slab stair without seams at stair sections and construction method
CN107859223A (en) A kind of novel precast floor slab and the casting method of monoblock floor is built up by it
CN105780976A (en) Compound concrete shear wall structure and concrete pouring method thereof
CN204238264U (en) A kind of sole plate post-poured strip structure
CN105604344A (en) A method for strengthening the interior wall with cracks
CN101451380B (en) Processing method of prefabricating common concrete outer plate recycled concrete core shear wall
CN204690801U (en) Formwork erecting structure is hung in basement roof ater-casting
CN110965778B (en) Cast-in-situ plate water stop type reserved hole telescopic shaping die
CN204662742U (en) The movable surface construction structure of a kind of pitched roof
CN203905331U (en) Cast-in-place plate-type staircase with seamless steps
CN204326100U (en) The Preserved node of covered back-digging side wall bar splice
CN203603462U (en) Post-cast strip beam plate formwork supporting structure
CN103046670B (en) Prefabricated recycled concrete shear wall with energy dissipation connector and fabrication method
CN104294962A (en) Method for manufacturing pre-placed recycled aggregate grouted concrete energy-saving and heat-preservation building block and wall system
CN211735536U (en) Off-wall ditch structure and station hall structure layer
CN203891470U (en) Fastening bolt for shear wall formwork
CN202148608U (en) Fast-easy closing-up net construction installation structure of bottom board construction seam
CN207672389U (en) Roadbed concrete curb cast-in-place mould

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 330095 No. 92 Lake Road, Shangrao, Jiangxi

Patentee after: ZHONGDA CONSTRUCTION Co.,Ltd.

Address before: 330095 No. 92 Lake Road, Shangrao, Jiangxi

Patentee before: Zhongda Construction Group Co.,Ltd.

Address after: 330095 No. 92 Lake Road, Shangrao, Jiangxi

Patentee after: Zhongda Construction Group Co.,Ltd.

Address before: 330095 No. 92 Lake Road, Shangrao, Jiangxi

Patentee before: ZHONGDA CONSTRUCTION Co.,Ltd.

CX01 Expiry of patent term

Granted publication date: 20150401

CX01 Expiry of patent term