CN204000861U - Bored pile casing in a kind of water - Google Patents

Bored pile casing in a kind of water Download PDF

Info

Publication number
CN204000861U
CN204000861U CN201420456592.3U CN201420456592U CN204000861U CN 204000861 U CN204000861 U CN 204000861U CN 201420456592 U CN201420456592 U CN 201420456592U CN 204000861 U CN204000861 U CN 204000861U
Authority
CN
China
Prior art keywords
casing
pile
little
water
bored pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420456592.3U
Other languages
Chinese (zh)
Inventor
李西洪
华立辉
李俊
柯霞
范清华
张宏魏
曹文军
高立峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG TIANYI TRANSPORTATION CONSTRUCTION Co Ltd
Original Assignee
ZHEJIANG TIANYI TRANSPORTATION CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG TIANYI TRANSPORTATION CONSTRUCTION Co Ltd filed Critical ZHEJIANG TIANYI TRANSPORTATION CONSTRUCTION Co Ltd
Priority to CN201420456592.3U priority Critical patent/CN204000861U/en
Application granted granted Critical
Publication of CN204000861U publication Critical patent/CN204000861U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses bored pile casing in a kind of water, in this water, bored pile comprises large casing and little casing with casing, described little casing is positioned at large casing inside and both are in the same center line, between described large casing and little casing, be provided with backfill clay, the length of described little casing is greater than the length of large casing.In this water, the large little casing of casing embedded set in casing for bored pile, successively extracts little casing and large casing after pile, has realized the recycling of casing, has saved construction cost; Two casing construction parties have been avoided the quality accident such as mud loss, collapse hole bury drills, have reduced pile risk, have improved pile quality.In water, bored pile double pile casing construction economy benefit is obvious, and constructing operation is convenient, and pile quality is high.

Description

Bored pile casing in a kind of water
Technical field
The utility model relates to bored pile casing in a kind of water.
Background technology
In water, bored pile construction mainly adopts full casing method at present, and casing can not be recycled, and causes bored pile construction cost in water to increase, and profundal zone bored pile cost increases particularly evident.
Summary of the invention
The technical problems to be solved in the utility model is to provide bored pile casing in a kind of water that can reclaim from construction environment.
For solving the problems of the technologies described above, the utility model adopts following technical scheme: in this water, bored pile comprises large casing and little casing with casing, described little casing is positioned at large casing inside and both are in the same center line, between described large casing and little casing, be provided with backfill clay, the length of described little casing is greater than the length of large casing.
The utility model adopts after technique scheme: the large little casing of casing embedded set in casing for bored pile in this water, after pile, successively extract little casing and large casing, and realize the recycling of casing, save construction cost; Two casing construction parties have been avoided the quality accident such as mud loss, collapse hole bury drills, have reduced pile risk, have improved pile quality.In water, bored pile double pile casing construction economy benefit is obvious, and constructing operation is convenient, and pile quality is high.
Brief description of the drawings
Below in conjunction with the drawings and specific embodiments, the utility model is further described in detail.
Fig. 1 is use schematic diagram of the present utility model.
Detailed description of the invention
As shown in Figure 1, in this water, bored pile comprises large casing 1 and little casing 2 with casing, described little casing is positioned at large casing inside and both are in the same center line, and between described large casing and little casing, is provided with backfill clay 3, and the length of described little casing is greater than the length of large casing.
When use, first in water, set up working platform, utilize leading truck that large casing is transferred to riverbed and adopted vibrating hammer vibration hammering to make large casing sink to certain buried depth, the water in large casing is taken out to backfill clay compacting in large casing.Then little casing sinks to by vibrating hammer hammering, and little casing must pass the back fill course in large casing, and than more than the super dark 0.5m of large casing, little casing exceeds large casing 0.5m, in order to mud circulation.After soil layer in the middle of little casing is cleaned out; under the protection of little casing, can complete smoothly pore-forming, underwater concreting; due to rich and influential family by and little casing between backfill clay, before concrete initial set, little casing can be pulled out, and there will not be the quality problems such as collapse hole, necking down.Concrete completes setting and harden in large casing and backfill clay, wait pile strength reach design strength 75% after, owing to there being the isolation of backfill, large casing also can be pulled out smoothly.

Claims (1)

1. bored pile casing in a water, it is characterized in that: in described water, bored pile casing comprises large casing and little casing, described little casing is positioned at large casing inside and both are in the same center line, between described large casing and little casing, be provided with backfill clay, the length of described little casing is greater than the length of large casing.
CN201420456592.3U 2014-08-13 2014-08-13 Bored pile casing in a kind of water Expired - Fee Related CN204000861U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420456592.3U CN204000861U (en) 2014-08-13 2014-08-13 Bored pile casing in a kind of water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420456592.3U CN204000861U (en) 2014-08-13 2014-08-13 Bored pile casing in a kind of water

Publications (1)

Publication Number Publication Date
CN204000861U true CN204000861U (en) 2014-12-10

Family

ID=52040886

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420456592.3U Expired - Fee Related CN204000861U (en) 2014-08-13 2014-08-13 Bored pile casing in a kind of water

Country Status (1)

Country Link
CN (1) CN204000861U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105672255A (en) * 2016-02-22 2016-06-15 深圳市工勘岩土集团有限公司 Double pile casing construction method for controlling perpendicularity
CN113445488A (en) * 2021-07-16 2021-09-28 中铁六局集团有限公司 Method for treating underground pipeline or karst cave
CN114135753A (en) * 2021-11-23 2022-03-04 华立辉 Communication equipment support with prevent falling effect

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105672255A (en) * 2016-02-22 2016-06-15 深圳市工勘岩土集团有限公司 Double pile casing construction method for controlling perpendicularity
CN105672255B (en) * 2016-02-22 2018-07-27 深圳市工勘岩土集团有限公司 Control the construction method for double pile casings of verticality
CN113445488A (en) * 2021-07-16 2021-09-28 中铁六局集团有限公司 Method for treating underground pipeline or karst cave
CN114135753A (en) * 2021-11-23 2022-03-04 华立辉 Communication equipment support with prevent falling effect

Similar Documents

Publication Publication Date Title
CN105908862B (en) A kind of production method of masonry shell in 3D printing reinforced masonry shear wall
CN104514219A (en) Underwater drilled pile foundation construction system capable of recycling steel casing and construction method thereof
CN204000965U (en) The discontinuous vibration isolation empty well structure that subtracts of a kind of railway
CN104480934A (en) Underwater drilled pile foundation construction system capable of recycling outer steel casing and construction method thereof
CN204000861U (en) Bored pile casing in a kind of water
CN106149683A (en) A kind of cast-in-place pile construction method using double casing to pass through deep metalling
CN102425173A (en) Deep foundation pit earthwork digging method
CN104563147B (en) Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
CN205475201U (en) A device for constructing steel plate concrete ground is wall even
CN104563126B (en) Construction method for bored pile by rotary drilling rig
CN204002832U (en) A kind of shield tunnel portal structure
CN104164873A (en) Prestressed pipe pile and construction method thereof
CN203174595U (en) Recyclable steel casing
CN104594370A (en) High-pressure combined flushing grouting method and structure in karst region
CN106978817A (en) A kind of Novel retaining wall based process pattern and a kind of Novel retaining wall
CN103741690B (en) A kind of soil plug compensates pile tube and extracts construction method and soil plug used compensation pile tube pile pulling device thereof
CN102865083A (en) Working well free shield arrival engineering method and structure of existing basement structure
CN204941551U (en) A kind of subway station of Curve Pipe Jacking supporting and protection structure enlarging shield-tunneling construction
WO2017133373A1 (en) Small-diameter pile cluster used for pile foundation, and method for construction thereof
CN204326068U (en) Underwater drilling pile foundation construction system with recyclable outer steel casing
CN204326069U (en) Underwater drilling pile foundation construction system with recyclable steel casing
CN204326061U (en) A kind of pile tube be drawn out easily
CN205116201U (en) Open caisson construction equipment
CN204266221U (en) grouting structure suitable for karst region
CN204000846U (en) Floral tube slip casting uplift pile

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141210

Termination date: 20150813

EXPY Termination of patent right or utility model