CN104594370A - High-pressure combined flushing grouting method and structure in karst region - Google Patents

High-pressure combined flushing grouting method and structure in karst region Download PDF

Info

Publication number
CN104594370A
CN104594370A CN201410695167.4A CN201410695167A CN104594370A CN 104594370 A CN104594370 A CN 104594370A CN 201410695167 A CN201410695167 A CN 201410695167A CN 104594370 A CN104594370 A CN 104594370A
Authority
CN
China
Prior art keywords
grouting
karst
flushing
pressure
paste
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410695167.4A
Other languages
Chinese (zh)
Other versions
CN104594370B (en
Inventor
屈昌华
郭维祥
余波
朱代强
昝廷东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201410695167.4A priority Critical patent/CN104594370B/en
Publication of CN104594370A publication Critical patent/CN104594370A/en
Application granted granted Critical
Publication of CN104594370B publication Critical patent/CN104594370B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a karst area high-pressure combined flushing grouting method and a structure thereof, wherein when filling type karst caves or corrosion cracks are met in the grouting process, cement mortar or cement paste with the ratio of 0.5:1 is backfilled after fillers are flushed out by high-pressure water or high-pressure wind and water, and the conventional cement grouting method is adopted for grouting after the cement mortar is solidified for 24-72 hours. The high-pressure combined flushing grouting method is an economical and efficient grouting treatment technology aiming at geological defect sites such as karst caves, corrosion cracks and the like, and has the advantages of simple method (no need of adding special construction equipment and operators), remarkable flushing effect, capability of greatly improving construction efficiency, grouting quality guarantee and the like. When the grouting flushing and grouting method is adopted to perform grouting flushing and grouting in geological defect sections such as karst caves, corrosion cracks and the like in karst regions, the design requirements can be effectively and quickly met, the construction efficiency can be greatly improved, and the waste of grouting raw materials can be reduced.

Description

Karst high pressure associating douche can paste-making method and structure thereof
Technical field
The present invention relates to karst geological disposal method, be specifically related to a kind of karst high pressure associating douche can paste-making method and structure thereof.
Background technology
Karst topography refers to that the water with corrosion power carries out to solublerock the general name that corrosion etc. acts on earth's surface and the underground form formed.Water, based on corrosion, also comprises the erosion of flowing water, shallow erosion, and the mechanical erosion process such as to collapse.
In the Hydraulic and Hydro-Power Engineering impervious grouting processing procedure of karst; often can run into filling-type Karst cave or corrosion fissure, or strong corrosion district, charges mostly are clay, loam; adopt conventional flushing and grouting method often not to reach designing requirement, and affect anti-seepage effect.
By current specifications (DL/T5148-2012) requirement, grout hole (section) will carry out crack and rinse and simple and easy setting-out (maximum pressure is not more than 1MPa) before grouting, whether carries out special flushing for regulation in the Special zone such as solution cavity, tomography specification according to designing requirement.At present, in Hydraulic and Hydro-Power Engineering, designing unit carries out normal developing to the General Requirements of the Special zone such as solution cavity, tomography, charges in solution cavity can not well be gone out by this normal developing method, affect again construction speed and quality, also have to adopt the method such as " encrypting grout hole between former grout hole " to process, make engineering quantity and investment increasing degree is comparatively large, the construction period significantly extends.
In karst Hydraulic and Hydro-Power Engineering impervious grouting " construction technical requirement ", simple and easy packer permeability test is rinsed to crack and generally have clear stipulaties, mostly be normal developing, when running into the Special zone such as solution cavity, corrosion fissure, fault zone, rare special rinsing requirement, before this conventional grout, flushing does not only reach the object of flushing, can worsen on the contrary by the performance of filling with rock mass, affect grouting quality.
Therefore, for the project seepage controlling grouting treatment of casta region, in prior art, desirable technical scheme is not still had.
Summary of the invention
The object of the invention is to the problem for solving to the project seepage controlling grouting treatment of casta region in prior art, a kind of karst high pressure associating douche can paste-making method is provided.
Technical scheme of the present invention is such:
First it is a kind of karst high pressure associating douche can paste-making method, when the method runs into filling-type Karst cave or corrosion fissure in filling process, by water under high pressure or high-pressure blast, water, charges are gone out the cement paste of rear backfill cement mortar or 0.5:1, after solidifying 24h ~ 72h, take traditional cements grouting method to pour into again.The method comprises the steps:
1) find out that solution cavity grows scale, the character of charges, roof and floor hole depth or elevation by boring or geophysical prospecting method; This work general grouting pilot hole (no longer increasing drilled grout hole) is carried out.
2) according to the solution cavity developmental state found out, the grout hole in the Geological Defects locations such as reasonable Arrangement solution cavity, corrosion fissure is as flushing hole, these grout holes are after being drilled into the hole depth residing for corresponding solution cavity or corrosion fissure, utilize two conventional high-pressure grout pumps (in parallel, Stress control is at 3 ~ 6MPa, during hole depth 40m ~ 100m, maximum pressure is no more than 25MPa) or press air compressor machine (Stress control 3 ~ 4 MPa) to carry out high pressure water washing or wind and water combined flushing in combining, charges in solution cavity are gone out from boring, until when aperture backwater is peace and quiet only.
3) answer cement paste or the cement mortar of quickly stuffing 0.5:1 after having rinsed, and treat solidifying 24h ~ 72h.
4) reach cleaning bottom of hole after the solidifying time and carry out conventional strengthening grouting, until reach designing requirement.
In order to realize such method, present invention employs so a kind of grouting structure being applicable to karst: it is the Geological Defects section for the treatment of karst, this Geological Defects section is positioned at the below of basement rock, this structure is provided with at least three borings, boring is vertically goed deep in basement rock, and the bottom of boring is in Geological Defects section; In three borings, at least two is geomantic omen import, and one for rinsing outlet.Preferably, two geomantic omen imports lay respectively at the both sides rinsing outlet.
High pressure of the present invention associating douche can paste-making method is for the one economy in the Geological Defects such as solution cavity, corrosion fissure location, efficiently grouting treatment technology, have method simple (not needing to increase special construction equipment and operating personnel), developing result significantly, construction efficiency can be increased substantially, ensure the advantages such as grouting quality.The present invention is with a kind of brand-new thinking, and the Geological Defects location such as solution cavity, corrosion fissure solving karst in simple, convenient, efficient mode is rinsed and grouting problem.Adopt the Geological Defects locations such as the solution cavity of the present invention in karst, corrosion fissure to carry out grouting to rinse with when being in the milk, designing requirement can be reached effectively and rapidly, and construction efficiency can be increased substantially and reduce grouting waste of raw materials.
Accompanying drawing explanation
Fig. 1 rinses grouting structural representation of the present invention associating.
Description of reference numerals: 1-basement rock, 2-holes, and 3-Geological Defects section, the import of 4-geomantic omen, 5-rinses outlet.
Detailed description of the invention
Below in conjunction with drawings and Examples, the present invention is described in further detail.
First see Fig. 1, Fig. 1 illustrates laying structure of combining flushing grouting of the present invention, and as we can see from the figure, the present invention is to be processed is Geological Defects section 3, and this Geological Defects section 3 is arranged in basement rock 1, is building the below of engineering in advance.For each processing unit engineering, the present invention needs the boring 2 being drilled with more than three, and wherein two borings 2 are as geomantic omen import 4, and for rinsing the import that hole is wind and water, another boring 2 conduct rinses outlet 5, for rinsing the passage of emerging of thing.Geomantic omen import 4 in figure is positioned at the right and left, rinses outlet 5 and is positioned at centre.
Embodiment 1: the present invention is applied to the situation of large-scale filling-type Karst cave: this solution-cavity filling thing is mainly clay, clay burning into sand etc., and hole depth is 45m ~ 67m.In filling process, grouting pressure is difficult to reach designing requirement 3.5MPa, and porous is repeatedly answered filling and reached designing requirement not yet.After adopting the present invention's construction, reach designing requirement on inspection.
Embodiment 2: the present invention is applied to the situation that engineering curtain grouting district is in strong corrosion district: this situation solution-cavity filling thing is based on sand and yellow mud, because trial zone scope is less, single hole process is carried out when running into solution cavity, adopt layering high pressure douche from top to bottom, namely creep into solution cavity, segment length with can pore-forming for principle, then high pressure washing (Stress control is at 4 ~ 7MPa) is carried out, rinse and be in the milk (based on grout injection again after returning clear water to aperture, injection rate is large and can mix the Admixtures such as water glass in proportion after having poured into a certain amount of slurries, Reperfu-sion cement paste, at the end of cement injection-water glass slurries), wait after reaching limit standard to coagulate (treating that the solidifying time is generally 24h ~ 72h), segment length is shortened during cleaning bottom of hole, the hole depth of last time when solidifying can not be punched, and then be in the milk, so repeatedly process, until this section carries out next section of process after reaching designing requirement.After construction terminates, on inspection, above karst cave treatment position construction quality all reaches designing requirement.
Certainly, more than just embody rule example of the present invention, the technical scheme that the present invention also has other embodiment, all employings to be equal to replacement or equivalent transformation to be formed, all drops within protection domain of the presently claimed invention.

Claims (5)

1. a karst high pressure associating douche can paste-making method, it is characterized in that: when the method runs into filling-type Karst cave or corrosion fissure in filling process, by water under high pressure or high-pressure blast, water, charges are gone out the cement paste of rear backfill cement mortar or 0.5:1, after solidifying 24h ~ 72h, take traditional cements grouting method to pour into again.
2. karst according to claim 1 high pressure associating douche can paste-making method, is characterized in that the method comprises the steps:
1) find out that solution cavity grows scale, the character of charges, roof and floor hole depth or elevation by boring or geophysical prospecting method;
2) arrange that the grout hole in Geological Defects location is as flushing hole, these grout holes are after being drilled into the hole depth residing for corresponding solution cavity or corrosion fissure, utilizing in two conventional high-pressure grout pumps or associating presses air compressor machine to carry out high pressure water washing or wind and water combined flushing, charges in solution cavity are gone out from boring, until when aperture backwater is peace and quiet only;
(3) answer cement paste or the cement mortar of quickly stuffing 0.5:1 after having rinsed, and treat solidifying 24h ~ 72h;
(4) reach cleaning bottom of hole after the solidifying time and carry out conventional strengthening grouting, until reach designing requirement.
3. karst according to claim 2 high pressure associating douche can paste-making method, it is characterized in that: step 2) described in two conventional high-pressure grout pumps according to being arranged in parallel, Stress control is at 3 ~ 6MPa, and during hole depth 40m ~ 100m, maximum pressure is no more than 25MPa; Stress control 3 ~ 4 MPa of air compressor machine is pressed in described associating.
4. one kind is applicable to the grouting structure of karst, it is the Geological Defects section (3) for the treatment of karst, this Geological Defects section (3) is positioned at the below of basement rock (1), it is characterized in that: this structure is provided with at least three borings (2), boring (2) is vertically goed deep in basement rock (1), and the bottom of boring (2) is in Geological Defects section (3); In three borings (2), at least two is geomantic omen import (4), and one for rinsing outlet (5).
5. the grouting structure being applicable to karst according to claim 4, is characterized in that: two geomantic omen imports (4) lay respectively at the both sides rinsing outlet (5).
CN201410695167.4A 2014-11-27 2014-11-27 High-pressure combined flushing grouting method and structure in karst region Active CN104594370B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410695167.4A CN104594370B (en) 2014-11-27 2014-11-27 High-pressure combined flushing grouting method and structure in karst region

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410695167.4A CN104594370B (en) 2014-11-27 2014-11-27 High-pressure combined flushing grouting method and structure in karst region

Publications (2)

Publication Number Publication Date
CN104594370A true CN104594370A (en) 2015-05-06
CN104594370B CN104594370B (en) 2017-10-10

Family

ID=53120397

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410695167.4A Active CN104594370B (en) 2014-11-27 2014-11-27 High-pressure combined flushing grouting method and structure in karst region

Country Status (1)

Country Link
CN (1) CN104594370B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862725A (en) * 2016-03-31 2016-08-17 大连久鼎祥瑞特种工程技术研究院有限公司 Underground construction preliminary grouting waterproof and anti-seepage supporting technology
CN105887886A (en) * 2016-06-16 2016-08-24 中国水利水电第十工程局有限公司 Strong karst development stratum curtain grouting construction method
CN106088094A (en) * 2016-07-31 2016-11-09 中水东北勘测设计研究有限责任公司 High mountain strid Method of Arch Dam Foundation segmentation stage grouting method
CN106498965A (en) * 2016-12-05 2017-03-15 广西大学 A kind of karst area water sealing consolidation construction method
CN113152412A (en) * 2021-04-30 2021-07-23 中国葛洲坝集团第一工程有限公司 Foundation pit slope karst seepage-proofing reinforcing treatment method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509264A (en) * 2009-03-25 2009-08-19 李旺雷 One-step pore-creating, segmenting high pressure cement grout construction method
WO2013082906A1 (en) * 2011-12-07 2013-06-13 长江勘测规划设计研究有限责任公司 Rock-fill dam deformation control method
CN204266221U (en) * 2014-11-27 2015-04-15 中国电建集团贵阳勘测设计研究院有限公司 grouting structure suitable for karst region

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509264A (en) * 2009-03-25 2009-08-19 李旺雷 One-step pore-creating, segmenting high pressure cement grout construction method
WO2013082906A1 (en) * 2011-12-07 2013-06-13 长江勘测规划设计研究有限责任公司 Rock-fill dam deformation control method
CN204266221U (en) * 2014-11-27 2015-04-15 中国电建集团贵阳勘测设计研究院有限公司 grouting structure suitable for karst region

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
姜成海等: "高压帷幕灌浆在喀斯特地区抽水蓄能电站中的应用", 《水力发电》 *
屈昌华: "中梁水库防渗工程深部充填、半充填型溶洞处理方案探索", 《贵州省岩石力学与工程学会2012年学术年会论文集》 *
屈昌华等: "中梁水库喀斯特发育区组合灌浆技术探讨", 《探矿工程-岩土钻掘工程》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862725A (en) * 2016-03-31 2016-08-17 大连久鼎祥瑞特种工程技术研究院有限公司 Underground construction preliminary grouting waterproof and anti-seepage supporting technology
CN105887886A (en) * 2016-06-16 2016-08-24 中国水利水电第十工程局有限公司 Strong karst development stratum curtain grouting construction method
CN105887886B (en) * 2016-06-16 2018-02-27 中国水利水电第十一工程局有限公司 A kind of strong karsts developing area stratum Curtain Grouting Construction method
CN106088094A (en) * 2016-07-31 2016-11-09 中水东北勘测设计研究有限责任公司 High mountain strid Method of Arch Dam Foundation segmentation stage grouting method
CN106498965A (en) * 2016-12-05 2017-03-15 广西大学 A kind of karst area water sealing consolidation construction method
CN113152412A (en) * 2021-04-30 2021-07-23 中国葛洲坝集团第一工程有限公司 Foundation pit slope karst seepage-proofing reinforcing treatment method

Also Published As

Publication number Publication date
CN104594370B (en) 2017-10-10

Similar Documents

Publication Publication Date Title
CN104594370B (en) High-pressure combined flushing grouting method and structure in karst region
CN103510957B (en) A kind of combined type coal uncovering method
CN107620312A (en) High hydraulic pressure precipitation well construction and hydrostatic slip casting method for blocking in a kind of Metro station excavation
CN104612134A (en) Cast-in place pile post-grouting construction method for pouring construction
CN107747312B (en) Method for drilling and grouting construction of gravel stratum
CN109098687A (en) Single stop grouting plug retrusive sublevel grouting device and method suitable for crack rock
CN104278667A (en) Underground karst cave filling treatment method
CN105804410A (en) Sub-cabin pressure grouting method for vertical connection of prefabricated concrete structure
CN104988915B (en) A kind of prefabricated installation method of detachable steel casing and under water connection beam
CN105887886A (en) Strong karst development stratum curtain grouting construction method
CN103362117A (en) Full-section grouting method for grouting section
CN102660952A (en) Controllable clay paste slurry grouting technique
CN102002950B (en) Liquid division slip casting reinforcing method for subsurface structure construction joints
CN204266221U (en) grouting structure suitable for karst region
CN102720176B (en) Foundation strengthening treatment method
CN108756945A (en) The device and construction method administered for multilayer goaf grouting
CN104032713B (en) A kind of pressure diversion tunnel composite lining concrete anti-seepage structure and construction technology thereof
CN105604163A (en) Sewage pipeline internal plugging and external grouting construction method
CN101205766B (en) Waterproof treatment method for joint of new station and old station
CN101967964A (en) Method for prewashing multi-density double-setting long-sealing gas channeling prevention well cementing
CN204000861U (en) Bored pile casing in a kind of water
CN103979880A (en) Pipeline engineering trench backfill material cement all-in-one mixture and preparation method thereof
CN102296617A (en) Post-grouting reinforcement construction method of flexible joints of diaphragm walls
CN115142852A (en) Treatment method for deep pore water-containing stratum of vertical shaft working face
CN104594369A (en) Karst region high-pressure group hole replacement grouting method and structure thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant