CN202831000U - 固定式塔吊整体迁移机构 - Google Patents

固定式塔吊整体迁移机构 Download PDF

Info

Publication number
CN202831000U
CN202831000U CN 201220394543 CN201220394543U CN202831000U CN 202831000 U CN202831000 U CN 202831000U CN 201220394543 CN201220394543 CN 201220394543 CN 201220394543 U CN201220394543 U CN 201220394543U CN 202831000 U CN202831000 U CN 202831000U
Authority
CN
China
Prior art keywords
tower crane
jack
steel plate
moving
slideway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220394543
Other languages
English (en)
Inventor
梁宝芳
王宝龙
王辉
董慧荣
张大鹏
王茂威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum Jilin Chemical Engineering and Construction Co Ltd
Original Assignee
China Petroleum Jilin Chemical Engineering and Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum Jilin Chemical Engineering and Construction Co Ltd filed Critical China Petroleum Jilin Chemical Engineering and Construction Co Ltd
Priority to CN 201220394543 priority Critical patent/CN202831000U/zh
Application granted granted Critical
Publication of CN202831000U publication Critical patent/CN202831000U/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

一种固定式塔吊整体迁移机构,其特征在于:包括托换梁、竖向千斤顶、水平千斤顶、道木、钢板滑道,托换梁作滑道基础,滑道基础上面设置由两层钢板之间夹有滚轴构成的钢板滑道,钢板滑道上面设有竖向千斤顶,水平千斤顶通过道木靠在一侧,用于移动塔吊。本实用新型在整个塔吊迁移的过程中,塔吊都能正常工作,不影响正常施工,能大大缩短因迁移引起的工期;在实施过程中不需要大型的水平和垂直运输机械,不需要另作基础,成本低廉,仅是常规方法成本的10%左右;在实施中绝大部分是地面作业,不存在高空作业,能大大降低安全风险。

Description

固定式塔吊整体迁移机构
技术领域
本实用新型涉及建筑运输机械,尤其是涉及一种固定式塔吊托换整体迁移机构。
现有技术
固定式塔吊是目前建筑业使用最多的垂直运输机械,由于各种原因需要将正在作业的塔吊短距离迁移到新位置的事时有发生。目前常用的方法就是新建一个基础,再将固定式塔吊拆卸后到新地点重新组立。这种方法比较传统,工艺成熟容易掌握。但产生的成本高,另外由于需要拆卸吊车,重新做基础,需要较长时间,影响工期。
实用新型内容
本实用新型的目的是提供一种固定式塔吊托换整体迁移机构,以节省工期,降低建造成本,降低安全风险。
为实现上述目的,本实用新型提供一种固定式塔吊整体迁移机构,其特征在于:包括托换梁、竖向千斤顶、水平千斤顶、道木、钢板滑道,托换梁作滑道基础,滑道基础上面设置由两层钢板之间夹有滚轴构成的钢板滑道,钢板滑道上面设有竖向千斤顶,水平千斤顶通过道木靠在一侧,用于移动塔吊。
本实用新型使用时,将原塔吊基础、新塔吊基础位置和滑道基础及行进路线的土挖出,然后将本机构布置上,将要移动的塔吊布置在竖向千斤顶上面,侧面通过水平千斤顶顶住,采用两条临时托换梁做滑道基础,辅助两条滚动式滑道,使固定式塔吊平稳的从原位置迁移到新位置后,找正、注浆后回填土,完成全部迁移过程。在整个塔吊迁移的过程中,塔吊都能正常工作,不影响正常施工,能大大缩短因迁移引起的工期;在实施过程中不需要大型的水平和垂直运输机械,不需要另作基础,成本低廉,仅是常规方法成本的10%左右;在实施中绝大部分是地面作业,不存在高空作业,能大大降低安全风险。
附图说明
附图是本实用新型施工示意图。
具体实施方式
参照附图,原塔吊基础1,托换梁2作滑道基础、竖向千斤顶3、水平千斤顶4、钢板5、滚轴6,滑道基础上面设置由两层钢板之间夹有滚轴构成的钢板滑道,钢板滑道上面设有竖向千斤顶,水平千斤顶通过道木7靠在基础一侧,用于移动塔吊。
具体施工步骤如下:
1、首先确定迁移后的位置,然后将原基础位置、新基础位置和滑道基础(托换梁)及行进路线的土挖出。
 2、施工滑道基础(托换梁),并在滑道基础上面依次安装好钢板、滚轴、钢板组合的钢板滑道;
3、将竖向千斤顶布置好,并开始对基础同步加荷,当满负荷后,开始布置道木及水平千斤顶,并使水平千斤顶受力;
    4、给水平千斤顶对基础加荷,随着塔吊的平稳前移,不断地倒换滑道钢板和滚轴和道木,直到将基础滑到新基础位置;
5、塔吊到达新基础后,用经纬仪观测塔吊的垂直度,并用竖向千斤顶调整,达到要求后,用短型钢替换竖向千斤顶,把竖向千斤顶撤出;
6、用细石混凝土或灌浆料将基础底部灌满,然后回填土。  

Claims (1)

1.一种固定式塔吊整体迁移机构,其特征在于:包括托换梁、竖向千斤顶、水平千斤顶、道木、钢板滑道,托换梁作滑道基础,滑道基础上面设置由两层钢板之间夹有滚轴构成的钢板滑道,钢板滑道上面设有竖向千斤顶,水平千斤顶通过道木靠在一侧,用于移动塔吊。
CN 201220394543 2012-08-10 2012-08-10 固定式塔吊整体迁移机构 Expired - Lifetime CN202831000U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220394543 CN202831000U (zh) 2012-08-10 2012-08-10 固定式塔吊整体迁移机构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220394543 CN202831000U (zh) 2012-08-10 2012-08-10 固定式塔吊整体迁移机构

Publications (1)

Publication Number Publication Date
CN202831000U true CN202831000U (zh) 2013-03-27

Family

ID=47942745

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220394543 Expired - Lifetime CN202831000U (zh) 2012-08-10 2012-08-10 固定式塔吊整体迁移机构

Country Status (1)

Country Link
CN (1) CN202831000U (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102795554A (zh) * 2012-08-10 2012-11-28 中油吉林化建工程有限公司 固定式塔吊整体迁移机构及迁移方法
CN103628417A (zh) * 2013-12-19 2014-03-12 中铁六局集团有限公司 支架法安装钢管拱拱节段坐标调整装置
CN106638663A (zh) * 2016-11-25 2017-05-10 天地科技股份有限公司 一种沉陷区高压输电铁塔基础加固及整体纠倾平移方法
CN106930336A (zh) * 2017-03-31 2017-07-07 上海宝冶集团南京建筑有限公司 一种建筑独立基础位移纠偏方法
CN112431190A (zh) * 2020-12-10 2021-03-02 施秀华 一种输电铁塔纠偏系统

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102795554A (zh) * 2012-08-10 2012-11-28 中油吉林化建工程有限公司 固定式塔吊整体迁移机构及迁移方法
CN103628417A (zh) * 2013-12-19 2014-03-12 中铁六局集团有限公司 支架法安装钢管拱拱节段坐标调整装置
CN103628417B (zh) * 2013-12-19 2015-11-18 中国铁路总公司 支架法安装钢管拱拱节段坐标调整装置
CN106638663A (zh) * 2016-11-25 2017-05-10 天地科技股份有限公司 一种沉陷区高压输电铁塔基础加固及整体纠倾平移方法
CN106638663B (zh) * 2016-11-25 2018-11-20 天地科技股份有限公司 一种沉陷区高压输电铁塔基础加固及整体纠倾平移方法
CN106930336A (zh) * 2017-03-31 2017-07-07 上海宝冶集团南京建筑有限公司 一种建筑独立基础位移纠偏方法
CN112431190A (zh) * 2020-12-10 2021-03-02 施秀华 一种输电铁塔纠偏系统

Similar Documents

Publication Publication Date Title
CN202831000U (zh) 固定式塔吊整体迁移机构
CN105000503A (zh) 堆取料机回转体整体顶升回转轴承滑移更换的施工方法
CN107031790A (zh) 三维调整仪合拢大型总组段工艺方法
CN201635410U (zh) 承受吊装施工荷载的混凝土结构临时加固装置
CN204715366U (zh) 一种大面积深基坑分区顺逆工况下的支撑体系
CN103541300B (zh) 基于平推法实施的铁路混凝土连续梁的施工方法
CN202000644U (zh) 移动式承重支架平台
CN206426071U (zh) 一种隧道盾构管片存放装置
CN202108003U (zh) 大吨位预应力混凝土连续箱梁桥顶推施工的预制支承系统
CN204002876U (zh) 一种用于隧洞施工的钢台车
CN106241234A (zh) 一种用于预制综合管廊的自行式运输拼装车
CN203498743U (zh) 一种基于平推法实施的铁路混凝土连续梁
CN203978442U (zh) 一种公铁合建水下隧道
CN203795435U (zh) 一种对撑加固结构
RU51099U1 (ru) Передвижная буровая установка
CN204040058U (zh) 组合式塔吊基础结构
CN204080820U (zh) 一种混凝土结构基坑换撑装置
CN102500997B (zh) 安装快锻机下横梁的方法
CN204080821U (zh) 一种钢结构基坑换撑装置
CN103362123A (zh) 倒y形灌注桩及其施工方法
CN202298674U (zh) 压力分散型抗浮锚杆施工质量监测装置
CN202400545U (zh) 管廊大型管道安装快捷运输装置
CN204439062U (zh) 高填方土体分层沉降观测装置
CN204572017U (zh) 地铁三层架施工格构柱
CN107288354B (zh) 一种龙门吊整体移位的施工方法

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130327