CN202492854U - Foundation platform structures of deepwater bare rock and karstic piles - Google Patents
Foundation platform structures of deepwater bare rock and karstic piles Download PDFInfo
- Publication number
- CN202492854U CN202492854U CN2012201048593U CN201220104859U CN202492854U CN 202492854 U CN202492854 U CN 202492854U CN 2012201048593 U CN2012201048593 U CN 2012201048593U CN 201220104859 U CN201220104859 U CN 201220104859U CN 202492854 U CN202492854 U CN 202492854U
- Authority
- CN
- China
- Prior art keywords
- steel
- pile foundation
- steel casing
- steel pipe
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000011435 rock Substances 0.000 title claims abstract description 30
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 100
- 239000010959 steel Substances 0.000 claims abstract description 100
- 239000004567 concrete Substances 0.000 claims abstract description 27
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 28
- 229910052742 iron Inorganic materials 0.000 claims description 14
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 11
- 235000015170 shellfish Nutrition 0.000 claims description 6
- 238000010276 construction Methods 0.000 abstract description 13
- 238000000034 method Methods 0.000 abstract description 6
- 238000009434 installation Methods 0.000 abstract description 5
- 238000005553 drilling Methods 0.000 description 6
- 230000007797 corrosion Effects 0.000 description 4
- 238000005260 corrosion Methods 0.000 description 4
- 230000010412 perfusion Effects 0.000 description 4
- 231100000241 scar Toxicity 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 239000012530 fluid Substances 0.000 description 2
- -1 Xie Yan Substances 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000003628 erosive effect Effects 0.000 description 1
- 238000005429 filling process Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 239000011395 ready-mix concrete Substances 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 239000003351 stiffener Substances 0.000 description 1
- 239000002344 surface layer Substances 0.000 description 1
Images
Landscapes
- Revetment (AREA)
Abstract
Description
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2012201048593U CN202492854U (en) | 2012-03-19 | 2012-03-19 | Foundation platform structures of deepwater bare rock and karstic piles |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2012201048593U CN202492854U (en) | 2012-03-19 | 2012-03-19 | Foundation platform structures of deepwater bare rock and karstic piles |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN202492854U true CN202492854U (en) | 2012-10-17 |
Family
ID=46999089
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2012201048593U Expired - Fee Related CN202492854U (en) | 2012-03-19 | 2012-03-19 | Foundation platform structures of deepwater bare rock and karstic piles |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN202492854U (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102619206A (en) * | 2012-04-06 | 2012-08-01 | 中铁二十二局集团第三工程有限公司 | Foundation platform structure of bare rock and karst pile in deep water |
| CN102979090A (en) * | 2012-12-13 | 2013-03-20 | 中铁上海工程局第二工程有限公司 | Construction method for fixing steel casing on covering-free steep bare rock in deepwater and rapid stream |
| CN103233432A (en) * | 2013-04-26 | 2013-08-07 | 济南城建集团有限公司 | Bailey beam reverse lifting support system and construction method thereof |
| CN105569064A (en) * | 2015-12-10 | 2016-05-11 | 中铁大桥局集团有限公司 | Arrangement type sunk well foundation construction method applicable to deepwater bare rock |
| CN109914399A (en) * | 2019-03-21 | 2019-06-21 | 杭州公路工程监理咨询有限公司 | A kind of pile base construction method of environmental protection |
| CN110485305A (en) * | 2019-08-27 | 2019-11-22 | 中铁大桥局集团有限公司 | Steel pile casting Anti-fall platform and its construction method for water Bridge foundation construction |
| CN116289652A (en) * | 2023-04-04 | 2023-06-23 | 中船第九设计研究院工程有限公司 | Pile type bridge approach repairing structure and method |
-
2012
- 2012-03-19 CN CN2012201048593U patent/CN202492854U/en not_active Expired - Fee Related
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102619206A (en) * | 2012-04-06 | 2012-08-01 | 中铁二十二局集团第三工程有限公司 | Foundation platform structure of bare rock and karst pile in deep water |
| CN102979090A (en) * | 2012-12-13 | 2013-03-20 | 中铁上海工程局第二工程有限公司 | Construction method for fixing steel casing on covering-free steep bare rock in deepwater and rapid stream |
| CN103233432A (en) * | 2013-04-26 | 2013-08-07 | 济南城建集团有限公司 | Bailey beam reverse lifting support system and construction method thereof |
| CN103233432B (en) * | 2013-04-26 | 2015-02-18 | 济南城建集团有限公司 | Bailey beam reverse lifting support system and construction method thereof |
| CN105569064A (en) * | 2015-12-10 | 2016-05-11 | 中铁大桥局集团有限公司 | Arrangement type sunk well foundation construction method applicable to deepwater bare rock |
| CN109914399A (en) * | 2019-03-21 | 2019-06-21 | 杭州公路工程监理咨询有限公司 | A kind of pile base construction method of environmental protection |
| CN109914399B (en) * | 2019-03-21 | 2021-06-01 | 杭州公路工程监理咨询有限公司 | Environment-friendly pile foundation construction method |
| CN110485305A (en) * | 2019-08-27 | 2019-11-22 | 中铁大桥局集团有限公司 | Steel pile casting Anti-fall platform and its construction method for water Bridge foundation construction |
| CN116289652A (en) * | 2023-04-04 | 2023-06-23 | 中船第九设计研究院工程有限公司 | Pile type bridge approach repairing structure and method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102619206A (en) | Foundation platform structure of bare rock and karst pile in deep water | |
| CN101666081B (en) | Abrupt slope bare rock drilling platform and technology in huge reservoir | |
| CN205776347U (en) | Novel cover for subway station digs against making structural system | |
| CN103255771B (en) | Method for excavating super-deep foundation pit engineering piles in graded mode and graded composite supporting of supporting piles | |
| CN106930319A (en) | A kind of high slope framed revetment and its construction method | |
| CN102953341A (en) | Overhead trestle structure built on non-covering steep bare rocks in deep rapids | |
| CN206308569U (en) | It is a kind of to reinforce the road structure for punishing the solution cavity that underlies | |
| CN104790410B (en) | A kind of Support of Foundation Pit Excavation method that is applicable to shallow water mud river course | |
| CN107761708A (en) | The processing method that big thickness Collapsible Loess District Subway station groundwork is reinforced | |
| CN103195076A (en) | Method for constructing silt deep foundation pit tower crane foundation | |
| CN106087997A (en) | A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method | |
| CN107489164A (en) | The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall | |
| CN112227401A (en) | Method for constructing bearing platform by filling stones in underwater stone abrupt slope area | |
| CN108625368A (en) | A kind of Deep Thick Soft Ground Area Rigid Long-Short-Pile Composite Foundation construction method | |
| CN108755698B (en) | Construction method for steep slope loose accumulation body large inclined rock surface foundation | |
| CN109137885A (en) | A kind of construction method of underground continuous wall | |
| CN102561406A (en) | Construction method for controlling back soil body deformation of open caisson | |
| CN107489106B (en) | A kind of construction method of rock river bed water cap | |
| CN201502056U (en) | Bare rock drilling platform for steep slope of deep reservoir area | |
| CN113174991B (en) | Pile periphery stratum collapse grouting reinforcement method for ocean deepwater inclined piles | |
| CN114045839A (en) | A kind of semi-excavated and semi-suspended low-pile bearing platform supporting structure and construction method of bridge in steep ridge section near water | |
| CN207331739U (en) | A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall | |
| CN205502063U (en) | Combined type retaining structure | |
| CN111350106A (en) | A kind of railway track temporary support structure and construction method thereof | |
| CN106087996B (en) | Manual digging pile construction method based on self leveling backpressure device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| ASS | Succession or assignment of patent right |
Owner name: CHINA RAILWAY 22TH BUREAU GROUP CO., LTD. Effective date: 20130123 |
|
| C41 | Transfer of patent application or patent right or utility model | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20130123 Address after: TA Pu Siming East Road Xiamen city Fujian province 361000 No. 166 22 floor Patentee after: The No.3 Engineering., Ltd. of China Railway 22th Bureau Group Patentee after: China Railway 22nd Construction Bureau Co., Ltd. Address before: TA Pu Siming East Road Xiamen city Fujian province 361000 No. 166 22 floor Patentee before: The No.3 Engineering., Ltd. of China Railway 22th Bureau Group |
|
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20121017 Termination date: 20210319 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |