CN102561406A - Construction method for controlling back soil body deformation of open caisson - Google Patents

Construction method for controlling back soil body deformation of open caisson Download PDF

Info

Publication number
CN102561406A
CN102561406A CN2011104220740A CN201110422074A CN102561406A CN 102561406 A CN102561406 A CN 102561406A CN 2011104220740 A CN2011104220740 A CN 2011104220740A CN 201110422074 A CN201110422074 A CN 201110422074A CN 102561406 A CN102561406 A CN 102561406A
Authority
CN
China
Prior art keywords
jacking
caisson
soil
construction
open caisson
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011104220740A
Other languages
Chinese (zh)
Inventor
孙阳
徐正良
沈水龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Co ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Co ltd filed Critical Shanghai Urban Construction Design Research Institute Co ltd
Priority to CN2011104220740A priority Critical patent/CN102561406A/en
Publication of CN102561406A publication Critical patent/CN102561406A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

本发明公开了一种控制沉井后背土体变形的施工方法,包括步骤一,将地下水位降低至沉井的底面以下;步骤二,提高沉井的整体刚度;步骤三,交替安排多个平行顶管的顶进顺序;步骤四,建立沉井及其后背土体的简化三维有限元模型并根据后背土体的最大允许变形限值,确定顶进施工时的顶力预控参数;步骤五,在顶进施工中采用注浆工艺使顶管的外壁与土层之间形成具有减摩降阻作用的触变泥浆套;步骤六,根据平行顶管的顶进顺序,顶管施工前在后背土体中安装测试仪器进行测点布置,施工中根据测点反馈的测试信息调整施工参数。本发明解决了大直径平行顶管施工工程中考虑顶力反复作用引起的沉井后背土体的变形控制问题,具有易于实施、费用低的有益效果。

The invention discloses a construction method for controlling soil deformation at the back of a caisson, which comprises step 1, lowering the groundwater level below the bottom surface of the caisson; step 2, increasing the overall rigidity of the caisson; and step 3, arranging multiple caissons alternately The jacking sequence of parallel pipe jacking; step 4, establish a simplified 3D finite element model of the caisson and its back soil and determine the jacking force pre-control parameters during jacking construction according to the maximum allowable deformation limit of the back soil ; Step five, use grouting process in the jacking construction to form a thixotropic mud sleeve with the effect of reducing friction and drag between the outer wall of the pipe jacking and the soil layer; Step six, according to the jacking sequence of parallel pipe jacking, pipe jacking Before construction, install testing instruments in the back soil to arrange measuring points, and adjust construction parameters according to the test information fed back from the measuring points during construction. The invention solves the deformation control problem of the soil at the back of the caisson due to the repeated action of the jacking force in the large-diameter parallel pipe jacking construction project, and has the beneficial effects of easy implementation and low cost.

Description

控制沉井后背土体变形的施工方法The Construction Method of Controlling the Deformation of the Soil at the Back of the Caisson

技术领域 technical field

本发明涉及地下建筑工程技术领域,尤其涉及一种控制大直径平行顶管施工引起的沉井后背土体变形的施工方法。The invention relates to the technical field of underground construction engineering, in particular to a construction method for controlling soil deformation at the back of a caisson caused by large-diameter parallel pipe jacking construction.

背景技术 Background technique

顶管技术是在不开挖地表的情况下,利用液压油缸从顶管工作井中将顶管机和待铺设的管节在地下逐节顶进直到顶管接收井的一种非开挖地下管道敷设施工工艺。沉井用作工作井在顶管工程中有着广泛的应用。The pipe jacking technology is a non-excavation underground pipeline that uses hydraulic cylinders to push the pipe jacking machine and the pipe joints to be laid underground one by one from the pipe jacking working well to the pipe jacking receiving well without excavating the surface. laying construction process. Caissons are widely used as working wells in pipe jacking engineering.

在管道顶进过程中,顶管机循环往复的顶力通过后背墙反作用到后背墙后的后背土体上。当顶力过大同时沉井的后背土体不够稳定时,后背土体可能会出现较大的变形,使顶管机的一部分工作回程消耗在后背土体的变形上,降低了顶管机的工作效率。后背土体的严重变形还可能造成后背土被破坏,使顶进施工失败。另一方面,后背土体的较大变形也将导致沉井周围路面或建筑物的损坏,从而引发一系列环境灾害。因此,严格控制顶管施工引起的沉井后背土体变形对确保顶管工程安全与顺利进行十分重要。During the pipeline jacking process, the reciprocating jacking force of the pipe jacking machine reacts to the back soil behind the back wall through the back wall. When the jacking force is too large and the soil at the back of the caisson is not stable enough, the soil at the back may be greatly deformed, so that part of the working return of the pipe jacking machine is consumed on the deformation of the soil at the back, reducing the The working efficiency of the pipe machine. Severe deformation of the back soil may also cause the back soil to be destroyed, making the jacking construction fail. On the other hand, the large deformation of the back soil will also cause damage to the roads or buildings around the caisson, thus triggering a series of environmental disasters. Therefore, it is very important to strictly control the soil deformation at the back of the caisson caused by pipe jacking construction to ensure the safety and smooth progress of the pipe jacking project.

经过对现有的技术文献检索,严绍军和张爱华在《煤田地质与勘探》(2006年2月,第34卷第1期,第37至第40页)上发表的“顶管工程后背受力与变形三维分析”(文章编号:1001-1986(2006)01-0037-04)中以某顶管工程为背景,采用朗肯被动土压力理论对后背土体的承载能力进行了分析。通过改变后背土体的弹性模量参数,分别取不同模量采用德鲁克-普拉格模型进行计算,得到相应的墙体最大水平位移值,并得出结论:提高土体的弹性模量能有效地降低后背墙体的水平位移值。但是,该文献仅仅对沉井后背土体的承载力以及位移依据理论进行了定量的计算分析,并没有给出控制后背土体位移的相关技术措施。同时,在这篇文章的结论中作者也指出了其所用方法的局限性,即没有考虑顶管的反复加荷-卸荷的实际情况。After retrieving the existing technical literature, Yan Shaojun and Zhang Aihua published in "Coalfield Geology and Exploration" (February 2006, Vol. Three-dimensional analysis of deformation and deformation" (article number: 1001-1986 (2006) 01-0037-04) takes a pipe jacking project as the background, and uses Rankine's passive earth pressure theory to analyze the bearing capacity of the back soil. By changing the elastic modulus parameters of the back soil, taking different moduli and using the Drucker-Prager model to calculate, the corresponding maximum horizontal displacement value of the wall is obtained, and a conclusion is drawn: to improve the elastic modulus of the soil The amount can effectively reduce the horizontal displacement value of the back wall. However, this document only quantitatively calculates and analyzes the bearing capacity and displacement of the soil at the back of the caisson based on theory, and does not provide relevant technical measures to control the displacement of the soil at the back. At the same time, in the conclusion of this article, the author also pointed out the limitations of the method used, that is, the actual situation of repeated loading-unloading of pipe jacking was not considered.

因此,本领域的技术人员致力于开发一种控制沉井后背土体变形的施工方法,以解决复杂加载尤其是循环或变化重复载荷作用下沉井后背土体的变形控制问题。Therefore, those skilled in the art are devoting themselves to developing a construction method for controlling the deformation of the soil behind the caisson, so as to solve the problem of controlling the deformation of the soil behind the caisson under complex loading, especially under the action of cyclic or changing repeated loads.

发明内容 Contents of the invention

有鉴于现有技术的上述缺陷,本发明所要解决的技术问题是提供一种解决复杂加载尤其是循环或变化重复载荷作用下沉井后背土体的变形控制问题的控制沉井后背土体变形的施工方法。In view of the above-mentioned defects in the prior art, the technical problem to be solved by the present invention is to provide a control method for controlling the deformation of the caisson back soil under complex loading, especially under the action of cyclic or changing repeated loads. Deformed construction methods.

为实现上述目的,本发明提供了一种控制沉井后背土体变形的施工方法,包括以下步骤:步骤一,在沉井周边实施井点降水,将地下水位降低至所述沉井的底面以下;步骤二,加强所述沉井的底部在土层中的锚固提高所述沉井的整体刚度;步骤三,交替安排多个平行顶管的顶进顺序;步骤四,建立所述沉井及其后背土体的简化三维有限元模型,并根据所述后背土体的最大允许变形限值确定顶进施工时的顶力预控参数;步骤五,在顶进施工中采用注浆工艺使所述顶管的外壁与土层之间形成具有减摩降阻作用的触变泥浆套;步骤六,根据步骤三所述平行顶管的顶进顺序,顶管施工前在所述后背土体中安装测试仪器进行测点布置,顶管施工中根据所述测点反馈的测试信息调整施工参数。In order to achieve the above object, the present invention provides a construction method for controlling soil deformation at the back of the caisson, comprising the following steps: step 1, implement dewatering at the well point around the caisson, and lower the groundwater level to the bottom surface of the caisson Following; Step 2, strengthening the anchoring of the bottom of the caisson in the soil layer to improve the overall rigidity of the caisson; Step 3, alternately arranging the jacking sequence of a plurality of parallel pipe jacking; Step 4, establishing the caisson and the simplified three-dimensional finite element model of the back soil, and determine the jacking force pre-control parameters during the jacking construction according to the maximum allowable deformation limit of the back soil; step five, use grouting in the jacking construction The process makes the outer wall of the pipe jacking and the soil layer form a thixotropic mud sleeve with the effect of reducing friction and resistance; step 6, according to the jacking sequence of the parallel pipe jacking described in step 3, before the pipe jacking construction, after the pipe jacking Install testing instruments in the back soil to arrange measuring points, and adjust construction parameters according to the test information fed back from the measuring points during pipe jacking construction.

进一步地,步骤二中,用高压水枪将刃脚上方井壁内侧的预留凹槽冲洗干净,将表面混凝土全部凿毛并露出石子,并将预留钢筋与底板钢筋焊接。Further, in step 2, use a high-pressure water gun to clean the reserved groove on the inner side of the well wall above the blade foot, chisel all the concrete on the surface and expose the stones, and weld the reserved steel bars to the bottom plate steel bars.

进一步地,步骤二中,在所述沉井的底部设置混凝土钻孔灌注桩以抵抗顶力引起的反作用力;所述灌注桩与所述沉井的底部采用倒梯形桩帽连接;所述灌注桩的桩顶钢筋锚入所述沉井的底板,所述灌注桩在所述沉井的底部各区格中沿着垂直于顶管顶进方向均匀分布。Further, in step 2, a concrete bored cast-in-place pile is set at the bottom of the caisson to resist the reaction force caused by the top force; the poured pile is connected to the bottom of the caisson by an inverted trapezoidal pile cap; the pouring The pile top steel bars of the piles are anchored into the bottom plate of the caisson, and the cast-in-place piles are evenly distributed in each cell at the bottom of the caisson along the direction perpendicular to the jacking pipe jacking direction.

进一步地,步骤三中,两根所述平行顶管同时顶进所引起的沉井后背墙上的两个顶力的差值不超过20%。Further, in step three, the difference between the two jacking forces on the back wall of the caisson caused by simultaneous jacking of the two parallel jacking pipes does not exceed 20%.

进一步地,步骤四中,采用安定性分析法确定顶进施工时的所述顶力预控参数。Further, in Step 4, the stability analysis method is used to determine the jacking force pre-control parameters during jacking construction.

进一步地,步骤五中,在机头尾部环向均匀布置多个压浆孔,所述机头后面的三节管节上都设置压浆孔,再往后每三节里有一节管节上设置压浆孔,管节压浆孔均呈斜向45°正交环向交叉布置。Further, in step 5, a plurality of grouting holes are evenly arranged in the circumferential direction of the tail of the machine head, and the grouting holes are all set on the three pipe joints behind the machine head, and then set on a pipe joint in every three joints. The grouting holes and the pipe joint grouting holes are arranged in an oblique 45° orthogonal circular crossing.

进一步地,步骤五中,采用由膨润土、粉末化学浆糊、纯碱和水构成的泥浆润滑减摩剂。Further, in the fifth step, the friction reducer is lubricated with mud composed of bentonite, powdered chemical paste, soda ash and water.

进一步地,步骤六中,根据顶进顺序及所述后背土体的场地条件,在所述后背土体贴近所述后背墙处埋设侧斜管和土压力传感器,在地表测试端采用围砌砖墙的方式与周围隔离。Further, in step 6, according to the jacking sequence and the site conditions of the back soil, a lateral slope pipe and an earth pressure sensor are buried near the back wall at the back soil, and the surface test end adopts The way of surrounding brick wall is isolated from the surrounding.

进一步地,步骤六中,在所述后背土体固结后进行测试以验证测点的可用性;在所述平行顶管顶进施工之前进行同样的测试步骤。在所述后背土体需要加固时,采用在所述后背墙后一定范围内进行垂直旋喷桩加固。Further, in step six, a test is performed after the back soil is consolidated to verify the availability of the measuring point; the same test step is performed before the parallel pipe jacking construction. When the back soil needs to be reinforced, vertical jet grouting piles are used for reinforcement within a certain range behind the back wall.

本发明的有益效果是:The beneficial effects of the present invention are:

本发明的控制沉井后背土体变形的施工方法,通过上述步骤,解决了大直径平行顶管施工工程中考虑顶力反复作用引起的沉井后背土体的变形控制问题,使得沉井后背土体的变形可以有效地控制在设计要求范围内,保证了顶管工程的顺利进行以及最大限度地降低了沉井后背土体变形对周边环境的负面影响。本发明的施工方法弥补了已有施工工艺的不足和缺陷,具有易于实施、费用低等有益效果。The construction method for controlling the deformation of the soil at the back of the caisson of the present invention, through the above steps, solves the problem of controlling the deformation of the soil at the back of the caisson due to the repeated action of the jacking force in the large-diameter parallel pipe jacking construction project, making the caisson The deformation of the soil at the back of the caisson can be effectively controlled within the scope of the design requirements, ensuring the smooth progress of the pipe jacking project and minimizing the negative impact of the deformation of the soil at the back of the caisson on the surrounding environment. The construction method of the invention makes up for the deficiencies and defects of the existing construction technology, and has beneficial effects such as easy implementation and low cost.

以下将结合附图对本发明的构思、具体结构及产生的技术效果作进一步说明,以充分地了解本发明的目的、特征和效果。The idea, specific structure and technical effects of the present invention will be further described below in conjunction with the accompanying drawings, so as to fully understand the purpose, features and effects of the present invention.

附图说明 Description of drawings

图1是本发明的一实施例中的平面状态示意图。Fig. 1 is a schematic plan view of an embodiment of the present invention.

图2是图1的剖面状态示意图。FIG. 2 is a schematic diagram of the cross-sectional state of FIG. 1 .

图3是沉井底部混凝土灌注桩的结构示意图。Fig. 3 is a structural schematic diagram of the concrete pouring pile at the bottom of the caisson.

图4是三维简化模型的示意图。Fig. 4 is a schematic diagram of a three-dimensional simplified model.

图5是后背土体中监测点平面位置示意图。Fig. 5 is a schematic diagram of the plane positions of the monitoring points in the back soil.

具体实施方式 Detailed ways

如图1、图2所示,本发明的一种控制沉井后背土体变形的施工方法,应用于以下工程,主涵管穿越河道,长450米,采用4条顶管1(每节钢筋混凝土预制顶管规格为:内直径3500毫米,长2.5米,分别以1#、2#、3#、4#区别),每条顶管由180节预制管组成,具有大截面、长距离的特点。As shown in Fig. 1 and Fig. 2, a kind of construction method of controlling the deformation of caisson back soil of the present invention is applied to the following projects, the main culvert crosses the river course, and the length is 450 meters, adopting 4 jacking pipes 1 (each section of steel bar The specifications of concrete prefabricated pipe jacking are: inner diameter 3500 mm, length 2.5 meters, respectively 1#, 2#, 3#, 4#), each jacking pipe is composed of 180 prefabricated pipes, with large cross-section and long distance features.

各条顶管1之间的中心距为9.5米,管底、管顶高程分别为-17.65米和-13.45米。南侧工作井21和北侧接收井22均为沉井结构,平面尺寸37米×22.5米,刃脚底高程均为-21.0米。顶管1由南侧工作井21出发,顶进到北侧接受井22结束。箭头A所示为顶进方向。The center distance between the jacking pipes 1 is 9.5 meters, and the elevations of the pipe bottom and pipe top are respectively -17.65 meters and -13.45 meters. The working well 21 on the south side and the receiving well 22 on the north side are both caisson structures, with a planar size of 37 meters x 22.5 meters, and the elevation of the blade foot is -21.0 meters. The pipe jacking 1 starts from the working well 21 on the south side and ends at the receiving well 22 on the north side. Arrow A shows the jacking direction.

参见图3、图4所示,本发明的施工方法主要包括以下步骤:Referring to Fig. 3, shown in Fig. 4, construction method of the present invention mainly comprises the following steps:

步骤一,在沉井4(工作井)周边实施井点降水,将地下水位降低至沉井4的底面以下。Step 1, implement well point dewatering around the caisson 4 (working well), and lower the groundwater level below the bottom surface of the caisson 4.

降水方法根据场地的水文地质条件、工程设计要求及沉井下沉的施工特点选取,降水井井深:The method of precipitation is selected according to the hydrogeological conditions of the site, engineering design requirements and construction characteristics of caisson sinking. The depth of the precipitation well is:

H=H1+H2+H3+H4+ir0 H=H 1 +H 2 +H 3 +H 4 +ir 0

上式中:H为降水井井深;H1为沉井刃脚至地表距离;H2为降水水位距离沉井底的要求深度;H3为降水过滤器的工作长度;H4为沉淀管长度;i为水力坡度;r0为沉井等效计算半径。In the above formula: H is the depth of the precipitation well; H 1 is the distance from the edge of the caisson to the surface; H 2 is the required depth from the precipitation water level to the bottom of the caisson; H 3 is the working length of the precipitation filter; H 4 is the length of the sedimentation tube ; i is the hydraulic gradient; r 0 is the equivalent calculation radius of caisson.

降水井距沉井壁的距离按沉井周边的场地情况在4米~8米之间取值。The distance between the precipitation well and the caisson wall is set between 4m and 8m according to the site conditions around the caisson.

本实施例中,依据施工场地的详细地质勘探数据,结合工程设计要求及沉井下沉的施工特点,采用桥式滤水钢管井降水,H1取25米;H2取1米;H3取2米;H4取2米;i取1/5;r0取17.5米,适当考虑富余量,H按35米取值。降水井布置在沉井外围,距离沉井外壁7米。In this embodiment, according to the detailed geological exploration data of the construction site, combined with the engineering design requirements and the construction characteristics of caisson sinking, a bridge-type water filter steel pipe well is used for dewatering. H1 takes 25 meters; H2 takes 1 meter; H3 takes 2 meters; H 4 is taken as 2 meters; i is taken as 1/5; r 0 is taken as 17.5 meters, and the surplus amount is properly considered, and H is taken as 35 meters. The precipitation well is arranged on the periphery of the caisson, 7 meters away from the outer wall of the caisson.

步骤一的作用是增大沉井壁及底面与土层的摩擦,同时便于步骤二实施。The function of the first step is to increase the friction between the caisson wall and the bottom surface and the soil layer, and facilitate the implementation of the second step.

步骤二,加强沉井4的底部在土层43中的锚固提高沉井4的整体刚度。Step 2, strengthening the anchoring of the bottom of the caisson 4 in the soil layer 43 to improve the overall rigidity of the caisson 4 .

步骤二中,用高压水枪将刃脚上方沉井侧壁42内侧的预留凹槽44冲洗干净,将表面混凝土全部凿毛并露出石子,并将预留钢筋与沉井底板41的钢筋焊接,焊接接头连接区段的长度不小于35d,d为纵向受力钢筋的较大直径。In step 2, the reserved groove 44 on the inner side of the caisson side wall 42 above the blade foot is rinsed clean with a high-pressure water gun, all the surface concrete is chiseled and the stones are exposed, and the reserved steel bar is welded to the steel bar of the caisson bottom plate 41, The length of the welded joint connection section is not less than 35d, where d is the larger diameter of the longitudinally stressed reinforcement.

在沉井4的底部设置混凝土钻孔灌注桩45以抵抗顶力引起的反作用力。灌注桩45与沉井底板41采用倒梯形桩帽连接。灌注桩45的桩顶钢筋锚入沉井底板41,灌注桩45在沉井4的底部各区格中沿着垂直于顶管顶进方向均匀分布。Concrete bored piles 45 are set at the bottom of the caisson 4 to resist the reaction force caused by the jacking force. The cast-in-place pile 45 is connected with the caisson bottom plate 41 by an inverted trapezoidal pile cap. The pile top steel bars of the cast-in-place piles 45 are anchored into the caisson bottom plate 41, and the cast-in-place piles 45 are evenly distributed in each cell at the bottom of the caisson 4 along the direction perpendicular to the pipe jacking direction.

本实例中当沉井4下沉到设计标高后,在对四周预留凹槽44进行冲洗及表面凿毛处理后,凹槽44中的预留钢筋与沉井底板41的新铺钢筋采用焊接连接,焊接接头相互错开,d=28毫米,焊接接头连接区段的长度取为1000毫米。In this example, after the caisson 4 is sunk to the design elevation, after the grooves 44 reserved around are washed and the surface roughened, the reserved steel bars in the grooves 44 and the newly laid steel bars of the caisson bottom plate 41 are welded Connection, the welded joints are staggered from each other, d=28 mm, and the length of the welded joint connection section is taken as 1000 mm.

另外,综合沉井底部场地条件,选取灌注桩45直径D=0.8米,由《建筑桩基技术规范》(JGJ94-2008)中5.7.2条确定,共需16根桩长I=8米的混凝土灌注桩,在每个区格中沿着垂直于顶管顶进方向各设置2根,灌注桩与沉井底部采用倒梯形桩帽连接,桩顶钢筋锚入沉井底板。In addition, considering the site conditions at the bottom of the caisson, the cast-in-place pile 45 with a diameter of D=0.8 meters is selected, which is determined by Article 5.7.2 of the "Technical Specifications for Building Pile Foundations" (JGJ94-2008), and a total of 16 piles with a length of I=8 meters are required. Concrete cast-in-place piles are installed in each cell along the direction perpendicular to the jacking pipe jacking direction. The cast-in-place piles are connected to the bottom of the caisson by inverted trapezoidal pile caps, and the steel bars on the top of the piles are anchored into the bottom plate of the caisson.

步骤二的作用是提高沉井4在顶力作用下的空间变形协调性。The function of the second step is to improve the spatial deformation coordination of the caisson 4 under the action of the jacking force.

步骤三,交替安排四个平行顶管1的顶进顺序。根据机械设备、场地条件及经济性要求选择合理的顶进顺序,分散后背墙5作用力,同时充分利用沉井4的整体刚度。Step 3, alternately arrange the jacking sequence of the four parallel jacking pipes 1 . Select a reasonable jacking sequence according to mechanical equipment, site conditions and economical requirements to disperse the force of the back wall 5 and make full use of the overall stiffness of the caisson 4 at the same time.

本实例中,有四根相互平行的顶管1(分别编号1#、2#、3#、4#)需顶进,考虑到设备的限制及经济性,按照二根顶管一组的原则分阶段顶进。为减小顶管之间的相互影响,不使后背墙5的作用力过于集中,每组顶管同时顶进。顶进时,密切观察两边油缸读数,将两根顶管顶进引起的沉井后背墙上的顶力Vi、Vj的差值控制在20%以内。In this example, there are four parallel jacking pipes 1 (respectively numbered 1#, 2#, 3#, 4#) that need to be jacked. Considering the limitation of equipment and economy, according to the principle of two jacking pipes in one group Jacking in stages. In order to reduce the mutual influence between the jacking pipes and prevent the force of the back wall 5 from being too concentrated, each group of jacking pipes is jacked up at the same time. When jacking, closely observe the readings of the oil cylinders on both sides, and control the difference between the jacking forces Vi and Vj on the back wall of the caisson caused by the jacking of the two pipes within 20%.

步骤四,根据工程计算精度要求,建立沉井4及其后背土体3的简化三维有限元模型,并根据后背土体3的最大允许变形限值,采用安定性分析法确定顶进施工时的顶力预控参数。Step 4: Establish a simplified three-dimensional finite element model of the caisson 4 and its back soil 3 according to the engineering calculation accuracy requirements, and use the stability analysis method to determine the jacking construction according to the maximum allowable deformation limit of the back soil 3 The pre-control parameters of the jacking force.

根据步骤六中后背土体3的最大允许变形限值,采用安定性分析方法取多组顶力组合值施加在模型上,进行循环加、卸载,最终确定两平行顶管顶力的最不利组合值[Vi,Vj],以此作为顶进施工时的顶力预控参数。According to the maximum allowable deformation limit of the back soil body 3 in step 6, the stability analysis method is used to take multiple sets of jacking force combination values to be applied to the model, and to carry out cyclic loading and unloading, and finally determine the most unfavorable jacking force of two parallel pipe jacking The combined value [Vi, Vj] is used as the jacking force pre-control parameter during jacking construction.

本实施例中获得的Vi=10290kN,Vj=9650kN,具体步骤为:Vi=10290kN obtained in this embodiment, Vj=9650kN, the specific steps are:

1、有限元模型的建模范围:本工程实例中,垂直于顶管顶进方向宽度B=37米,顶管反力作用面的边长d=4.2米,顶管反力作用面与沉井顶部之间的距离s=12.2米。因此,沉井4的后背土体3的长度L=35米,高度h=18米。1. The modeling range of the finite element model: in this project example, the width B=37 meters perpendicular to the pipe jacking direction, the side length of the pipe jacking reaction surface d=4.2 meters, the pipe jacking reaction surface and the sinking The distance s=12.2 meters between the tops of the wells. Therefore, the length L of the back soil body 3 of the caisson 4 is 35 meters, and the height h is 18 meters.

2、模型边界条件:在后背墙5的底边z=-1米处和两侧面z=-1米处施加切向均布力,分别模拟沉井底板41与土体摩擦力、沉井侧壁42与土体摩擦力;在z向z=0处4个顶管反力作用面上按照步骤三的顶进顺序按照每2根顶管一组施加反力,其余部分不约束。两个侧面x=-18.5米和x=+18.5米处,除了z=-1米部分,限制其x方向位移;底面y=0处,除了z=-1米部分,限制其y方向的位移;背面z=-20米处,限制其z方向位移;地表y=+18米处为自由面。2. Boundary conditions of the model: Apply tangential uniform force at the bottom edge z=-1 meter of the back wall 5 and the two sides z=-1 meter, respectively simulate the friction force between the caisson bottom plate 41 and the soil, and the caisson Frictional force between the side wall 42 and the soil body; on the 4 pipe jacking reaction force acting surfaces at z=0 in the z direction, the reaction force is applied for each group of 2 pipe jackings according to the jacking sequence of step 3, and the remaining parts are not constrained. At the two sides x=-18.5 meters and x=+18.5 meters, except for the z=-1 meter part, the displacement in the x direction is restricted; at the bottom y=0, except for the z=-1 meter part, the displacement in the y direction is restricted ; The position at z=-20 meters on the back is to limit its displacement in the z direction; the position at y=+18 meters on the surface is a free surface.

3、后背土体3与后背墙5均用三维六面体实体单元模拟,土体本构关系采用考虑弹塑性应变的莫尔库伦等面积圆模型,后背墙5按弹性体考虑,不考虑其塑性变形。在后背墙5与后背土体3之间设置接触面单元模刚体-柔体的面面接触特性,土与混凝土之间的摩擦系数取0.3。3. Both the back soil body 3 and the back wall 5 are simulated by three-dimensional hexahedron solid elements, and the constitutive relationship of the soil body adopts the Mohr-Coulomb equal-area circle model considering elastic-plastic strain, and the back wall 5 is considered as an elastic body, without considering its plastic deformation. Between the back wall 5 and the back soil 3, the surface-to-surface contact characteristics of the rigid body-flexible body of the contact surface unit form are set, and the friction coefficient between the soil and the concrete is taken as 0.3.

步骤五,在顶进施工中采用高效的注浆工艺使顶管1的外壁与土层之间形成具有减摩降阻作用的触变泥浆套,从而减小顶力对后背土体3的扰动影响,保证触变泥浆的注浆效果。Step 5: In the jacking construction, a high-efficiency grouting process is used to form a thixotropic mud sleeve with the effect of reducing friction and drag between the outer wall of the jacking pipe 1 and the soil layer, thereby reducing the impact of the jacking force on the back soil 3 Disturbance effect ensures the grouting effect of thixotropic mud.

在进出洞口设置防水效果较好的止水装置,管接口密封性能保持良好,确保浆液不从进出洞口渗漏。从出洞口开始压浆,避免顶管进入土体后被握裹。A water-stop device with good waterproof effect is installed at the entrance and exit hole, and the sealing performance of the pipe joint is kept good to ensure that the slurry does not leak from the entrance and exit hole. Start grouting from the exit of the hole to prevent the jacking pipe from being gripped after entering the soil.

具体如,在进出洞口处制作宽度为25厘米的一圈止水法兰,另在洞口内制作一圈止水钢套环与之相连。在打开洞门,机头进洞时开始压浆。在机头尾部环向均匀布置多个压浆孔(如四个),机头后面的三节管节上都设置压浆孔,再往后每三节里有一节管节上设置压浆孔,管节压浆孔均呈斜向45°正交环向交叉布置。在整个顶管中每间隔2个管子设1个补浆断面,每个断面共4个注浆孔,利用机头尾部的压浆孔进行同步注浆,利用管节上的压浆孔进行补浆,补浆按顺序依次进行。Specifically, make a circle of water-stop flange with a width of 25 cm at the entrance and exit of the hole, and make a circle of water-stop steel collar in the hole to connect with it. When the hole door is opened and the machine head enters the hole, grouting starts. A plurality of grouting holes (such as four) are evenly arranged in the circumferential direction of the tail of the machine head. The three pipe joints behind the machine head are all equipped with grouting holes, and then every three joints are provided with grouting holes. The grouting holes of the pipe joints are arranged in an oblique 45° orthogonal circular crossing arrangement. In the entire pipe jacking, a grouting section is set every 2 pipes, and each section has 4 grouting holes. The grouting holes at the tail of the machine head are used for synchronous grouting, and the grouting holes on the pipe joints are used for grouting. Slurry and slurry replenishment are carried out in sequence.

同时,还可以采用由膨润土、粉末化学浆糊、纯碱和水构成的泥浆润滑减摩剂。具体可以为,膨润土、CMC(粉末化学浆糊)、纯碱和水的重量比为:16%、0.2%、0.6%、84%,拌和好的触变泥浆静置24小时后再进行灌注。At the same time, a mud lubrication friction reducer composed of bentonite, powder chemical paste, soda ash and water can also be used. Specifically, the weight ratios of bentonite, CMC (powder chemical paste), soda ash and water are: 16%, 0.2%, 0.6%, 84%, and the mixed thixotropic mud is allowed to stand for 24 hours before pouring.

步骤六,根据后背土体3的场地条件,及步骤三平行顶管1的顶进顺序,在顶管施工前进行测点布置和监测,在后背土体3贴近后背墙5处埋设侧斜管和土压力传感器,以反馈测试信息从而调整施工参数,在地表测试端采用围砌砖墙的方式与周围隔离,避免遭到其它施工工序的破坏和干扰。Step 6: According to the site conditions of the back soil body 3 and the jacking sequence of the parallel pipe jacking 1 in step 3, arrange and monitor the measuring points before the pipe jacking construction, and bury the back soil body 3 close to the back wall 5 The side slope pipe and the earth pressure sensor can adjust the construction parameters by feeding back the test information. The surface test end is isolated from the surrounding area by building a brick wall to avoid damage and interference from other construction processes.

具体地,参见图5所示,在沉井4的结构封底结束后,即进行测试仪器的埋设,测斜管和土压力传感器均采用钻孔回填的方法埋设。在距离后背墙5的1米处的1#、3#顶进反力之间各设置一个土压测点S1和位移测点C1。在距离后背墙5的1米处的2#、4#顶进反力之间各设置一个土压测点S2和位移测点C-2,测点S1、C1、S2、C2埋深均为距后背土体3的地表10米。裸露在地表的测试端用空心砖围砌0.5米×0.5米的围护保护测点。Specifically, as shown in FIG. 5 , after the structural bottom sealing of the caisson 4 is completed, the test instrument is buried, and the inclinometer pipe and the earth pressure sensor are buried by backfilling the borehole. Set an earth pressure measuring point S1 and a displacement measuring point C1 between the 1# and 3# jacking reaction forces at a distance of 1 meter from the back wall 5. Set a soil pressure measuring point S2 and a displacement measuring point C-2 between the 2# and 4# jacking reaction forces 1 meter away from the back wall 5, and the buried depths of the measuring points S1, C1, S2, and C2 are equal. It is 10 meters away from the surface of the soil body 3 on the back. The test end exposed on the surface is surrounded by hollow bricks with a 0.5m x 0.5m enclosure to protect the measuring point.

待测点处土体固结7天后,对其进行试测,测点S1、C1、S2、C2的读数均较为稳定,连续3次的数值差均不超过均值的10%。约40天后,顶管开始顶进施工,在此之前进行同样的步骤测试初始值,把此时测得的3次数据的平均值作为整个顶进过程的初始值。After 7 days of soil consolidation at the point to be measured, the test was carried out. The readings of the points S1, C1, S2, and C2 were relatively stable, and the difference between the three consecutive values did not exceed 10% of the average value. About 40 days later, the pipe jacking construction began. Before that, the same steps were carried out to test the initial value, and the average value of the three data measured at this time was used as the initial value of the entire jacking process.

正常顶进时,各阶段的测试频率一天2次,当顶力读数偏大或地表出现异常情况时,根据需要适当提高测试频率。土体位移值均在-30毫米~+30毫米范围内,且土压实测值无异常,最大值未超出120kPa,不需要采取额外的土体加固措施。During normal jacking, the test frequency of each stage is twice a day. When the jacking force reading is too large or there is an abnormal situation on the ground surface, the test frequency should be appropriately increased as needed. The soil displacement values are all within the range of -30 mm to +30 mm, and the measured soil pressure values are normal, with the maximum value not exceeding 120kPa, and no additional soil reinforcement measures are required.

在后背土体3需要加固时,采用在后背墙5后B/2范围内进行垂直旋喷桩加固。When the back soil body 3 needs to be reinforced, vertical jet grouting piles are used for reinforcement within the B/2 range behind the back wall 5 .

本发明紧密结合施工过程采取相应控制措施,需额外增加的工序少,可节省工期、降低费用,是顶管工程中合理控制沉井后背土体变形的一种简单实用的方法。The present invention is closely combined with the construction process to take corresponding control measures, requires few additional procedures, can save construction time and reduce costs, and is a simple and practical method for reasonably controlling the deformation of the soil at the back of caissons in pipe jacking projects.

以上详细描述了本发明的较佳具体实施例。应当理解,本领域的普通技术人员无需创造性劳动就可以根据本发明的构思作出诸多修改和变化。因此,凡本技术领域中技术人员依本发明的构思在现有技术的基础上通过逻辑分析、推理或者有限的实验可以得到的技术方案,皆应在由权利要求书所确定的保护范围内。The preferred specific embodiments of the present invention have been described in detail above. It should be understood that those skilled in the art can make many modifications and changes according to the concept of the present invention without creative efforts. Therefore, all technical solutions that can be obtained by those skilled in the art based on the concept of the present invention through logical analysis, reasoning or limited experiments on the basis of the prior art shall be within the scope of protection defined by the claims.

Claims (10)

1. job practices of controlling open caisson back soil deformation may further comprise the steps:
Step 1 is implemented well-points dewatering at the open caisson periphery, groundwater table is reduced to below the bottom surface of said open caisson;
Step 2 is strengthened the integral rigidity of the said open caisson of the bottom anchoring in soil layer raising of said open caisson;
Step 3, the jacking order of alternately arranging a plurality of parallel push pipes;
Step 4 is set up the simplification three-dimensional finite element model of the said open caisson and the back soil body thereof, and the top power when allowing the distortion limit value to confirm jacking construction according to the maximum of the said back soil body is controlled parameter in advance;
Step 5 adopts grouting process to make in jacking construction and forms between outer wall and the soil layer of said push pipe to have the thixotropic slurry cover that the resistance effect falls in antifriction;
Step 6, according to the jacking of the said parallel push pipe of step 3 order, before the jacking construction in the said back soil body installation testing instrument carry out measuring point and arrange, in the jacking construction according to the detecting information adjustment construction parameter of said measuring point feedback.
2. job practices as claimed in claim 1 wherein, in the step 2, is rinsed the inboard reservation groove of the sword pin top borehole wall well with giant, and surperficial concrete is all cut a hole hair and exposed stone, and with reserved steel bar and the welding of base plate reinforcing bar.
3. job practices as claimed in claim 1 wherein, in the step 2, is provided with the reaction force that concrete drilling bored concrete pile causes with opposing top power in the bottom of said open caisson; Said castinplace pile adopts down trapezoidal pile cover to be connected with the bottom of said open caisson; The stake top reinforcing bar of said castinplace pile anchors into the base plate of said open caisson, and said castinplace pile is respectively distinguished in the bottom of said open caisson in the lattice along evenly distributing perpendicular to push pipe jacking direction.
4. job practices as claimed in claim 1, wherein, in the step 3, the difference of two top power behind two caused open caissons of said parallel push pipe jacking simultaneously on the parados is no more than 20%.
5. job practices as claimed in claim 1, wherein, in the step 4, the said top power when adopting the shakedown analysis method to confirm jacking construction is controlled parameter in advance.
6. job practices as claimed in claim 1; Wherein, In the step 5, evenly arrange a plurality of mud jacking hole, on the three-joint pipe joint of said head back the mud jacking hole is set all at head afterbody hoop; Have on the pipe joint joint in per backward again three joints the mud jacking hole is set, tube coupling mud jacking hole all is oblique 45 ° of orthogonal loops to arranged crosswise.
7. job practices as claimed in claim 1 wherein, in the step 5, adopts the mud lubrication anti-friction agent that is made up of swell soil, powder chemistry paste, soda ash and water.
8. job practices as claimed in claim 1; Wherein, in the step 6, according to the site condition of the jacking order and the said back soil body; Press close to parados place, said back at the said back soil body and bury skew back pipe and soil pressure sensor underground, test lead adopts the mode of brick work brick wall and isolates on every side on the face of land.
9. job practices as claimed in claim 8 wherein, in the step 6, is tested the availability with the checking measuring point behind said back soil solidifying; Before said parallel push pipe jacking construction, carry out same testing procedure.
10. job practices as claimed in claim 9 wherein, in the step 6, when the said back soil body needs reinforcement, is employed in and carries out vertical rotary churning pile in the certain limit behind the parados of said back and reinforce.
CN2011104220740A 2011-12-15 2011-12-15 Construction method for controlling back soil body deformation of open caisson Pending CN102561406A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011104220740A CN102561406A (en) 2011-12-15 2011-12-15 Construction method for controlling back soil body deformation of open caisson

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011104220740A CN102561406A (en) 2011-12-15 2011-12-15 Construction method for controlling back soil body deformation of open caisson

Publications (1)

Publication Number Publication Date
CN102561406A true CN102561406A (en) 2012-07-11

Family

ID=46407885

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011104220740A Pending CN102561406A (en) 2011-12-15 2011-12-15 Construction method for controlling back soil body deformation of open caisson

Country Status (1)

Country Link
CN (1) CN102561406A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104278665A (en) * 2014-09-28 2015-01-14 河海大学 Underwater burying device and method for steel open caisson side wall and blade foot soil piezometer
CN105302953A (en) * 2015-10-21 2016-02-03 河海大学 Three-dimensional finite element verification method of multilayer railroad bed structure shakedown analysis
CN105354370A (en) * 2015-10-21 2016-02-24 河海大学 Three-dimensional finite element calculation method for shakedown analysis of multi-layer railway roadbed structure
CN108999202A (en) * 2018-08-23 2018-12-14 中铁六局集团广州工程有限公司 Prevent the super heavy method and device of open caisson
CN109372532A (en) * 2018-12-25 2019-02-22 中建四局第六建筑工程有限公司 Jacking construction engineering method under multiplexed address environment
CN113464720A (en) * 2021-08-17 2021-10-01 中铁五局集团第一工程有限责任公司 Slurry balance pipe jacking construction method
CN113790308A (en) * 2021-08-27 2021-12-14 深圳大学 Volume intelligent regulation and control air bag pile capable of reducing influence of back soil in pipe jacking construction and regulation and control method
WO2023092966A1 (en) * 2022-04-13 2023-06-01 中交第一航务工程局有限公司 Caisson structure, and construction method and use therefor

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0536486A1 (en) * 1991-10-08 1993-04-14 Seiko Kogyo Kabushiki Kaisha Foundation having cylindrical shell and construction method therefor
JP2004137685A (en) * 2002-10-15 2004-05-13 East Japan Railway Co Caisson laying method and supporting method using permanent foundation pile
CN101148890A (en) * 2007-11-08 2008-03-26 中交武汉港湾工程设计研究院有限公司 Bridge caisson composite pile foundation and reverse construction method thereof
CN101270581A (en) * 2008-05-09 2008-09-24 天津市市政工程设计研究院 Anchor pile caisson foundation and its construction technology

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0536486A1 (en) * 1991-10-08 1993-04-14 Seiko Kogyo Kabushiki Kaisha Foundation having cylindrical shell and construction method therefor
JP2004137685A (en) * 2002-10-15 2004-05-13 East Japan Railway Co Caisson laying method and supporting method using permanent foundation pile
CN101148890A (en) * 2007-11-08 2008-03-26 中交武汉港湾工程设计研究院有限公司 Bridge caisson composite pile foundation and reverse construction method thereof
CN101270581A (en) * 2008-05-09 2008-09-24 天津市市政工程设计研究院 Anchor pile caisson foundation and its construction technology

Non-Patent Citations (7)

* Cited by examiner, † Cited by third party
Title
夏明耀等: "《地下工程设计施工手册》", 31 July 1999, 中国建筑工业出版社 *
孙阳: "结构安定性数值分析方法及其工程应用研究", 《中国博士学位论文全文数据库工程科技II辑》 *
朱丽娟: "大直径、长距离顶管在仙蠡桥工程中的应用", 《人民长江》 *
梁交心等: "软弱土层中的大型沉井施工技术探究", 《建筑施工》 *
赵文胜: "顶管工作坑钢筋混凝土沉井", 《山西建筑》 *
陈镇松: "顶管工程操作井的钢筋混凝土沉井施工法", 《中国市政工程》 *
龚宏华: "顶进框架桥沉井后背墙设计与施工", 《铁道建筑》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104278665A (en) * 2014-09-28 2015-01-14 河海大学 Underwater burying device and method for steel open caisson side wall and blade foot soil piezometer
CN104278665B (en) * 2014-09-28 2016-01-06 河海大学 Steel open caisson sidewall and sword pin earth pressure gauge embedded device and method for embedding thereof under water
CN105302953A (en) * 2015-10-21 2016-02-03 河海大学 Three-dimensional finite element verification method of multilayer railroad bed structure shakedown analysis
CN105354370A (en) * 2015-10-21 2016-02-24 河海大学 Three-dimensional finite element calculation method for shakedown analysis of multi-layer railway roadbed structure
CN105302953B (en) * 2015-10-21 2017-12-15 河海大学 A kind of three-dimensional finite element verification method of multilayer railway bed Shakedown of Structures analysis
CN105354370B (en) * 2015-10-21 2017-12-19 河海大学 A kind of dimensional Finite Element method of multilayer railway bed Shakedown of Structures analysis
CN108999202A (en) * 2018-08-23 2018-12-14 中铁六局集团广州工程有限公司 Prevent the super heavy method and device of open caisson
CN109372532A (en) * 2018-12-25 2019-02-22 中建四局第六建筑工程有限公司 Jacking construction engineering method under multiplexed address environment
CN113464720A (en) * 2021-08-17 2021-10-01 中铁五局集团第一工程有限责任公司 Slurry balance pipe jacking construction method
CN113790308A (en) * 2021-08-27 2021-12-14 深圳大学 Volume intelligent regulation and control air bag pile capable of reducing influence of back soil in pipe jacking construction and regulation and control method
CN113790308B (en) * 2021-08-27 2023-05-05 深圳大学 Volume intelligent regulation and control air bag pile capable of reducing influence of back soil in pipe jacking construction and regulation and control method
WO2023092966A1 (en) * 2022-04-13 2023-06-01 中交第一航务工程局有限公司 Caisson structure, and construction method and use therefor

Similar Documents

Publication Publication Date Title
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN102953341B (en) A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock
CN102561406A (en) Construction method for controlling back soil body deformation of open caisson
CN103437341B (en) On cover effective forming construction method thereof of diaphragm wall in the micro-famp of sand
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN102535477B (en) Safety construction method for cutting off anchor cables of support of excavating foundation pit
CN110080237A (en) It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure
CN104947649A (en) Control method for open caisson back soil deformation caused by pipe-jacking construction
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN107724383B (en) Rotary digging cast-in-place pile construction method
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN105386474B (en) Method for determining the impact of water-stop curtain leakage on the surrounding environment above the excavation surface of foundation pit
CN102561330A (en) Integrated construction method for artificial dug pile and steel pipe concrete column
CN103015429A (en) Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN102134853A (en) CT sealed steel pipe pile foundation pit water stop supporting device and construction method thereof
CN106758759B (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN112227401A (en) Method for constructing bearing platform by filling stones in underwater stone abrupt slope area
CN103397634A (en) Anchoring construction method for fastener steel tube pile cofferdam
CN101701460A (en) The Construction Method of Controlling Surrounding Surface Subsidence During Foundation Pit Construction
CN108166532A (en) A kind of groutable underground continuous wall connector and its construction method
CN210263062U (en) Anti construction structures that floats of shallow earthing subway tunnel foundation ditch earthwork excavation in pit bottom
CN201943077U (en) Waterproof curtain of CT-type fore shaft steel pipe pile
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN206477240U (en) A kind of trestle pile foundation for deep water drift net riverbed
CN205224019U (en) Stake of reinforcing bar fiber cement soil

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120711