CN109137885A - A kind of construction method of underground continuous wall - Google Patents

A kind of construction method of underground continuous wall Download PDF

Info

Publication number
CN109137885A
CN109137885A CN201811200962.6A CN201811200962A CN109137885A CN 109137885 A CN109137885 A CN 109137885A CN 201811200962 A CN201811200962 A CN 201811200962A CN 109137885 A CN109137885 A CN 109137885A
Authority
CN
China
Prior art keywords
construction
wall
continuous wall
underground
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811200962.6A
Other languages
Chinese (zh)
Inventor
兰峰涛
刘继鹏
庞前凤
张峰辉
刘崇
徐小燕
赵小兵
吕朝臣
何洪涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 22nd Bureau Group Co Ltd
China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd.
Original Assignee
China Railway 22nd Bureau Group Co Ltd
China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 22nd Bureau Group Co Ltd, China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd. filed Critical China Railway 22nd Bureau Group Co Ltd
Priority to CN201811200962.6A priority Critical patent/CN109137885A/en
Publication of CN109137885A publication Critical patent/CN109137885A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints

Abstract

The invention discloses a kind of construction method of underground continuous wall, including 1), surveying setting-out;2), construction of guide wall;3), slurrying and adjustment;4), continuous wall trench underground is constructed;5), connector, installation of embedded parts;6), underwater concreting;7), slot connector cutting is constructed;8), waste pulp, wastewater treatment;9), quality testing.Construction of diaphragm wall structure of the invention and construction method are that a large amount of construction experiences are combined on the basis of standard, can shorten construction period, save construction cost, and the construction requirement that entirely appropriate construction site environment is complicated or construction site environment is special.

Description

A kind of construction method of underground continuous wall
Technical field
The present invention relates to technical field of building construction, and in particular to a kind of construction method of underground continuous wall.
Background technique
In construction, the construction of diaphram wall, diaphram wall have in especially municipal matching operation project The feature that rigidity is big, globality is strong, impervious and good durability, acts not only as building enclosure, plays retaining soil and water Effect, is also used as load-carrying members;Suitable for Various Complex foundation condition, land occupation is few when practice of construction, and effect is high, the duration It is short, reliable in quality, high financial profit.The advantages of due to diaphram wall above series of, so that diaphram wall is further extensive Apply to water content abundant, underground exterior-protected structure of bad ground and require bearing capacity big foundation engineering in.
In the prior art, although diaphragm wall is widely applied in construction work, more and more units in charge of construction are only Be the construction of diaphragm wall is carried out according to standard (national standard or professional standard), and it is complex for construction site environment, can not Fully according to the engineering that standard executes, it will increase the difficulty of construction of construction personnel, increase construction cost.
Summary of the invention
The object of the present invention is to provide a kind of saving construction period, ensure that the preferable diaphram wall of construction in later period quality is applied Work method.
To achieve the goals above, the invention provides the following technical scheme:
A kind of construction method of underground continuous wall disclosed by the invention, comprising the following steps:
1), surveying setting-out;
2), construction of guide wall, the construction of guide wall specifically include surveying and locating, channel excavation, mode supporting steel rod binding, pour and be injected back into It fills out and conserves;
3), slurrying and adjustment;
4), continuous wall trench underground is constructed, and the continuous wall trench underground construction includes trenching construction, the displacement of clear bottom and brush Wall construction, grooving examination, fabrication of reinforcing cage installation;
5), connector, installation of embedded parts;
6), underwater concreting;
7), slot connector cutting is constructed;
8), waste pulp, wastewater treatment;
9), quality testing.
Further, in the step 1) surveying setting-out be according to the cross-post of construction process requirement record and each stake site, Review measurement is carried out, after review is errorless, fills in pile extension record;
According to design ground-connecting-wall center point coordinate data, with total station by axis point coordinate and X, Y direction pilot measurement to applying Work scene, and it is made into permanent pile anchoring;
On the basis of permanent pile anchoring, each slot section line of demarcation is navigated to using steel ruler according to unit groove section division principle and leads wall On bed course, the construction axis location point of ground-connecting-wall is accurately measured, by the accurate location measuring of each slot section to leading on wall bed course, is reported Management review uses after review is errorless, in this, as the benchmark of construction of guide wall and position detection.
Further, the construction of guide wall measurement of the step 2) uses polygonometric method;
Channel excavation in the step 2) uses 0.4m3Backacter excavates, and manually repairs slope, leads wall depth by design For 2200mm, when digging 200mm above to designed elevation, using artificial clear bottom, cell wall is repaired;
Mode supporting steel rod binding top surface in the step 2) pours 100mm C15 plain concrete cushion layer, and 1.2m wide leads wall steel Muscle, template are bound according to construction requirement, are installed, and pad reinforcing bar protection block in the lower section of slot bottom longitudinal reinforcement, wherein longitudinal The overlap joint of reinforcing bar takes binding form, and binding length is 500mm, and side wall formwork uses combined steel formwork, and lateral, longitudinal back cord is equal 100 × 100mm flitch is selected, and adds 2 cross-braces every 2.0m.
Further, added in the step 4) using 2 hydraulic clamshell chute forming machines continuous under 4 Double-wheel milling construction grounds Wall;
Wherein, hydraulic grab grooving more than rock stratum is used;
When rock strength is higher, using diameter 1m, after the top fuller of weight 14t is hammered, then using Double-wheel milling progress Enter rock drilling, self-control plane set-hammer carries out cell wall finishing, and chute forming machine carries out clear bottom.
Further, in the pre-buried concrete breast beam in diaphram wall excavation face side and anti-floating capping beam in the step 5) Connector, waist rail be 16 × 100mm of Φ connector, capping beam be 22 × 200mm of Φ connector.
Further, concreting uses two to pour frame in the step 6), and two conduits are poured simultaneously, first Envelope uses 1.6m3Small hopper, 8~12m3Concrete waggon directly toward continuous placing in hopper.
Further, it is arranged one by pulper, cyclone, reciprocating sieve and slurry tank in every construction point in the step 8) The mud disposal system of composition.
In the above-mentioned technical solutions, a kind of construction method of underground continuous wall provided by the invention, has the advantages that
Construction of diaphragm wall structure of the invention and construction method are that a large amount of construction experiences, energy are combined on the basis of standard Enough shorten construction period, save construction cost, and entirely appropriate construction site environment is complicated or construction site environment is special Construction requirement.
Detailed description of the invention
In order to illustrate the technical solutions in the embodiments of the present application or in the prior art more clearly, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only one recorded in the present invention A little embodiments are also possible to obtain other drawings based on these drawings for those of ordinary skill in the art.
Fig. 1 is a kind of construction flow chart of construction method of underground continuous wall provided in an embodiment of the present invention;
Fig. 2 is a kind of construction of guide wall process flow chart of construction method of underground continuous wall provided in an embodiment of the present invention;
Fig. 3 is a kind of mud system process flow chart of construction method of underground continuous wall provided in an embodiment of the present invention;
Fig. 4 is a kind of mud configuration method figure of construction method of underground continuous wall provided in an embodiment of the present invention;
Fig. 5 is a kind of impact drill construction flow chart of construction method of underground continuous wall provided in an embodiment of the present invention.
Specific embodiment
In order to make those skilled in the art more fully understand technical solution of the present invention, below in conjunction with attached drawing to this hair It is bright to be further detailed.
As shown in Figures 1 to 5, a kind of construction method of underground continuous wall provided in an embodiment of the present invention, comprising the following steps:
1), surveying setting-out;
2), construction of guide wall, construction of guide wall specifically include surveying and locating, channel excavation, mode supporting steel rod binding, casting backfill and Maintenance;
3), slurrying and adjustment;
4), continuous wall trench underground is constructed, and continuous wall trench underground construction includes that trenching construction, the displacement of clear bottom and brush wall are applied Work, grooving examination, fabrication of reinforcing cage installation;
5), connector, installation of embedded parts;
6), underwater concreting;
7), slot connector cutting is constructed;
8), waste pulp, wastewater treatment;
9), quality testing.
Preferably, surveying setting-out is according to the cross-post of construction process requirement record and each stake position in step 1) in the present embodiment Point carries out review measurement, after review is errorless, fills in pile extension record;
According to design ground-connecting-wall center point coordinate data, with total station by axis point coordinate and X, Y direction pilot measurement to applying Work scene, and it is made into permanent pile anchoring;
On the basis of permanent pile anchoring, each slot section line of demarcation is navigated to using steel ruler according to unit groove section division principle and leads wall On bed course, the construction axis location point of ground-connecting-wall is accurately measured, by the accurate location measuring of each slot section to leading on wall bed course, is reported Management review uses after review is errorless, in this, as the benchmark of construction of guide wall and position detection.
Preferably, the construction of guide wall measurement of step 2) uses polygonometric method in the present embodiment;
Channel excavation in step 2) uses 0.4m3Backacter excavates, and manually repairs slope, leading wall depth by design is 2200mm when digging 200mm above to designed elevation, using artificial clear bottom, repairs cell wall;
Mode supporting steel rod binding top surface in step 2) pours 100mm C15 plain concrete cushion layer, and 1.2m wide leads wall reinforcing bar, mould Plate is bound according to construction requirement, is installed, and pads reinforcing bar protection block in the lower section of slot bottom longitudinal reinforcement, wherein longitudinal reinforcement Overlap joint take binding form, binding length is 500mm, and side wall formwork uses combined steel formwork, and laterally, longitudinal back cord selects 100 × 100mm flitch, and 2 cross-braces are added every 2.0m.
Preferably, added in step 4) using 2 hydraulic clamshell chute forming machines in the present embodiment and connected under 4 Double-wheel milling construction grounds Continuous wall;
Wherein, hydraulic grab grooving more than rock stratum is used;
When rock strength is higher, using diameter 1m, after the top fuller of weight 14t is hammered, then using Double-wheel milling progress Enter rock drilling, self-control plane set-hammer carries out cell wall finishing, and chute forming machine carries out clear bottom.
Preferably, in the present embodiment in step 5) in the pre-buried concrete breast beam in diaphram wall excavation face side and anti-floating pressure The connector of top beam, waist rail are Φ 16x100mm connector, and capping beam is Φ 22x200mm connector.Due to connector and pre-buried Muscle status requirement precision is high, during fabrication of reinforcing cage, according to hangs muscle position, measures and leads wall elevation at hangs muscle, determine to hang Muscle length controls built-in fitting position in this, as basic point.One of horizontal bar is welded after muscle of plugging into, it is horizontal so as to fixed muscle of plugging into It is connected between muscle and main reinforcement by short muscle.The horizontal bar of steel reinforcement cage and the intermediate fixation horizontal bar added are by anti-floating Liang Po at connector Degree setting, to ensure the pre-buried precision of connector and embedded ribs.
Ground-connecting-wall built-in fitting is mainly sound detecting pipe, inclinometer pipe, concrete and bracing members embedded bar, steel plate etc., built-in fitting Answer position according to the requirements of the drawings, order of magnitude model to carry out pre-buried, bracing members pre-embedded steel slab and steel reinforcement cage weld together and under It is put into position.The position accuracy of pre-embedded steel slab influences bracing members construction and foundation pit is stablized.According to the construction elevation of steel reinforcement cage and often The construction elevation of layer bracing members, to determine the fixation absolute altitude for connecing pre-embedded steel slab on ground wall steel reinforcement cage, by surveyor in steel reinforcement cage On make apparent mark, and the reinforcing bar of steel reinforcement cage is adjusted to be coupled with steel plate dowel, to guarantee the position of built-in fitting It sets correct.
After connector and built-in fitting are fixed correctly on steel reinforcement cage, the heavy cage work of steel reinforcement cage can be carried out, steel reinforcement cage is heavy The control of cage absolute altitude is very crucial process.Therefore apparent mark must be set on steel reinforcement cage, it is controlled by level Absolute altitude is sunk to, its verticality is controlled by theodolite, while lifting machinery must remove steel wire by ability pine after steel reinforcement cage is stable in place Rope, to guarantee the final absolute altitude of steel reinforcement cage.
Preferably, concreting uses two to pour frame in step 6) in the present embodiment, and two conduits are poured simultaneously It builds, head envelope uses 1.6m3Small hopper, 8~12m3Concrete waggon directly toward continuous placing in hopper.First batch of concreting is just Chang Hou should be poured successively, and plummet probing concrete surface height is applied in casting process, calculate conduit lower end Transducers Embedded in Concrete Depth, and make a record, the promotion and dismounting of accurate instruction conduit.Until the depth of conduit lower end Transducers Embedded in Concrete reaches 4m When, conduit is promoted, then is continuing to pour.The mud overflowed in wellhole should be drained at appropriate place in casting process Reason prevents pollution environment.
When pouring concrete, notch should set cover board, and not allowing concrete to fall into slot in principle deteriorates mud property.It should be protected in pouring Two tremie placings while property is demonstrate,proved, to guarantee the uniform rising of concrete surface, highest part is not more than than the height difference of lowermost portion 30cm.Conduit buried depth under concrete surface cannot be less than 2 meters, also be not greater than 6 meters, and concreting will accomplish without any letup, must not It interrupts, the supply delay time is not greater than 30 minutes, and ensures the concrete surface rate of climb not less than 3m/h.Depth of tremie is maintained at 2 ~6m when concrete is poured, measures concrete face height at any time, and the quantity that verification concrete face and conduit remove is forbidden to pull out sky, concrete end hole mark Height is 50cm or more higher than designed elevation.
Specification production is strictly pressed in the resistance to compression of concrete, impervious test block.Unit in charge of construction is made by each unit groove section concrete One group of compression strength test.
Preferably, it is arranged one by pulper, cyclone, reciprocating sieve and mud in every construction point in step 8) in the present embodiment Starch the mud disposal system of tank composition.It is made of at the setting of every construction point one pulper, cyclone, reciprocating sieve and slurry tank Mud disposal system, preparation, storage, conveying, circulation, separation of mud etc. are completed by mud disposal system.In addition, at the scene It builds and deposits heatable adobe sleeping platform and mud-settling pit and cesspool etc., guarantee that mud does not land, to reduce the pollution to environment.On inspection cannot The poor mud that regenerated mud and concrete placings displace after sedimentation basin, cyclone, reciprocating sieve separating treatment, with tank car will, Solidfied material is transported to designated place and discards, and constructs sewage after precipitating and reaching discharge standard, is discharged into sewer pipe.
The quality testing of diaphram wall should be met the following requirements:
(1) concrete underground continuous wall detects wall structural intergrity using sound wave transmission method, and detection slot number of segment is no less than Total slot number 20% under the conditions of, and 3 slot sections must not be less than.The pre-buried ultrasonic wave duct number of each detection wall section should not be less than 4, It is arranged in the four side midpoints in wall section.
(2) cell wall measuring for verticality should be carried out, amount detection must not be less than 20% of total slot number of segment under the conditions of, and many In 10 width;When diaphram wall is as main body underground structure component, cell wall measuring for verticality should be carried out to each slot section.
(3) slot bottom sediment thickness detection should be carried out;When diaphram wall is as main body underground structure component, reply is each Slot section carries out the detection of slot bottom sediment thickness.
(4) it when the wall determined according to sound wave transmission method is off quality, should be verified using core drilling method.
(5) when diaphram wall is as main body underground structure component, quality testing should still meet the requirement of related specifications.
In the above-mentioned technical solutions, a kind of construction method of underground continuous wall provided by the invention, has the advantages that
Construction of diaphragm wall structure of the invention and construction method are that a large amount of construction experiences, energy are combined on the basis of standard Enough shorten construction period, save construction cost, and entirely appropriate construction site environment is complicated or construction site environment is special Construction requirement.
It is above that certain exemplary embodiments of the invention are only described by way of explanation, undoubtedly, for ability The those of ordinary skill in domain without departing from the spirit and scope of the present invention can be with a variety of different modes to institute The embodiment of description is modified.Therefore, above-mentioned attached drawing and description are regarded as illustrative in nature, and should not be construed as to the present invention The limitation of claims.

Claims (7)

1. a kind of construction method of underground continuous wall, which comprises the following steps:
1), surveying setting-out;
2), construction of guide wall, the construction of guide wall specifically include surveying and locating, channel excavation, mode supporting steel rod binding, casting backfill and Maintenance;
3), slurrying and adjustment;
4), continuous wall trench underground is constructed, and the continuous wall trench underground construction includes that trenching construction, the displacement of clear bottom and brush wall are applied Work, grooving examination, fabrication of reinforcing cage installation;
5), connector, installation of embedded parts;
6), underwater concreting;
7), slot connector cutting is constructed;
8), waste pulp, wastewater treatment;
9), quality testing.
2. a kind of construction method of underground continuous wall according to claim 1, which is characterized in that measurement is put in the step 1) Line is to carry out review measurement according to the cross-post of construction process requirement record and each stake site, after review is errorless, fills in pile extension note Record;
It is with total station that axis point coordinate and X, Y direction pilot measurement is existing to construction according to design ground-connecting-wall center point coordinate data , and it is made into permanent pile anchoring;
On the basis of permanent pile anchoring, each slot section line of demarcation is navigated to using steel ruler according to unit groove section division principle and leads wall bed course On, the construction axis location point of ground-connecting-wall is accurately measured, by the accurate location measuring of each slot section to leading on wall bed course, reports management Review uses after review is errorless, in this, as the benchmark of construction of guide wall and position detection.
3. a kind of construction method of underground continuous wall according to claim 1, which is characterized in that the wall of leading of the step 2) is applied Work measurement uses polygonometric method;
Channel excavation in the step 2) uses 0.4m3Backacter excavates, and manually repairs slope, leading wall depth by design is 2200mm when digging 200mm above to designed elevation, using artificial clear bottom, repairs cell wall;
Mode supporting steel rod binding top surface in the step 2) pours 100mm C15 plain concrete cushion layer, and 1.2m wide leads wall reinforcing bar, mould Plate is bound according to construction requirement, is installed, and pads reinforcing bar protection block in the lower section of slot bottom longitudinal reinforcement, wherein longitudinal reinforcement Overlap joint take binding form, binding length is 500mm, and side wall formwork uses combined steel formwork, and laterally, longitudinal back cord selects 100 × 100mm flitch, and 2 cross-braces are added every 2.0m.
4. a kind of construction method of underground continuous wall according to claim 1, which is characterized in that use 2 in the step 4) Platform hydraulic clamshell chute forming machine adds 4 Double-wheel milling construction diaphram walls;
Wherein, hydraulic grab grooving more than rock stratum is used;
When rock strength is higher, using diameter 1m, after the top fuller of weight 14t is hammered, then Double-wheel milling is used to carry out into rock Drilling, self-control plane set-hammer carry out cell wall finishing, and chute forming machine carries out clear bottom.
5. a kind of construction method of underground continuous wall according to claim 1, which is characterized in that in underground in the step 5) The connector of diaphragm wall excavation face side pre-buried concrete breast beam and anti-floating capping beam, waist rail are Φ 16x100mm connector, pressure Top beam is Φ 22x200mm connector.
6. a kind of construction method of underground continuous wall according to claim 1, which is characterized in that concrete in the step 6) It pours and pours frame using two, two conduits are poured simultaneously, and head envelope uses 1.6m3Small hopper, 8~12m3Concrete waggon Directly toward continuous placing in hopper.
7. a kind of construction method of underground continuous wall according to claim 1, which is characterized in that applied in the step 8) often A mud disposal system being made of pulper, cyclone, reciprocating sieve and slurry tank is arranged in work point.
CN201811200962.6A 2018-10-16 2018-10-16 A kind of construction method of underground continuous wall Pending CN109137885A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811200962.6A CN109137885A (en) 2018-10-16 2018-10-16 A kind of construction method of underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811200962.6A CN109137885A (en) 2018-10-16 2018-10-16 A kind of construction method of underground continuous wall

Publications (1)

Publication Number Publication Date
CN109137885A true CN109137885A (en) 2019-01-04

Family

ID=64811909

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811200962.6A Pending CN109137885A (en) 2018-10-16 2018-10-16 A kind of construction method of underground continuous wall

Country Status (1)

Country Link
CN (1) CN109137885A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110387874A (en) * 2019-07-30 2019-10-29 杭州江润科技有限公司 Diaphram wall and construction method
CN110409458A (en) * 2019-07-22 2019-11-05 武汉一冶建筑安装工程有限责任公司 Ultra-deep abnormal shape diaphram wall enters rock construction method
CN111335640A (en) * 2020-03-19 2020-06-26 中国十七冶集团有限公司 Construction method for preventing guide wall from sputtering floating slurry
CN111519679A (en) * 2020-05-21 2020-08-11 中铁二十二局集团轨道工程有限公司 Rapid grooving construction method for micro-weathering rock of diaphragm wall
CN114960619A (en) * 2022-06-16 2022-08-30 中国五冶集团有限公司 Underground continuous wall guide wall cover plate limiting device and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691294A (en) * 2012-05-15 2012-09-26 安宜建设集团有限公司 Construction method of underground continuous wall
CN104120712A (en) * 2013-04-28 2014-10-29 杨哲 Construction method for underground diaphragm wall
CN105178288A (en) * 2015-07-31 2015-12-23 中铁隧道集团有限公司 Construction method of underground continuous wall below viaduct

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691294A (en) * 2012-05-15 2012-09-26 安宜建设集团有限公司 Construction method of underground continuous wall
CN104120712A (en) * 2013-04-28 2014-10-29 杨哲 Construction method for underground diaphragm wall
CN105178288A (en) * 2015-07-31 2015-12-23 中铁隧道集团有限公司 Construction method of underground continuous wall below viaduct

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
中国建材工业出版社: "《建筑业10项新技术(2017版)》", 30 September 2018, 中国建材工业出版社 *
候永生等: "《桥梁施工技术问答》", 31 January 2014 *
黄钟焕: "《建筑工程施工监理便携手册(第2版)》", 31 March 2014, 中国建材工业出版社 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110409458A (en) * 2019-07-22 2019-11-05 武汉一冶建筑安装工程有限责任公司 Ultra-deep abnormal shape diaphram wall enters rock construction method
CN110387874A (en) * 2019-07-30 2019-10-29 杭州江润科技有限公司 Diaphram wall and construction method
CN111335640A (en) * 2020-03-19 2020-06-26 中国十七冶集团有限公司 Construction method for preventing guide wall from sputtering floating slurry
CN111519679A (en) * 2020-05-21 2020-08-11 中铁二十二局集团轨道工程有限公司 Rapid grooving construction method for micro-weathering rock of diaphragm wall
CN114960619A (en) * 2022-06-16 2022-08-30 中国五冶集团有限公司 Underground continuous wall guide wall cover plate limiting device and construction method

Similar Documents

Publication Publication Date Title
CN109137885A (en) A kind of construction method of underground continuous wall
CN104532813B (en) A kind of aquatic building operation platform and erection method, using method
CN100497841C (en) Supporting leg type underground continuous wall construction method
CN106381866A (en) Construction method of ultra-deep underground diaphragm wall in water-rich soft-soil area
CN102425160A (en) Method for constructing engineering pile by combining rotary drilling rig with manual pile base chambering
CN100473790C (en) Tower crane foundation for construction and manufacturing method thereof
CN104846829A (en) Shield-reserved penetration composite type foundation pit support wall and construction method thereof
CN110344423A (en) A kind of drop shaft sinking forms the construction method of water level for local deep foundation pit under high water level
CN110185844A (en) Shallow earthing pipe-jacking with large diameter construction method
CN105275381A (en) Drilling construction method for water-rich cobble stratum by utilizing impact drill
CN102430277B (en) Coarse grid sunk well for physically processing waste water and construction method thereof
CN109505229A (en) Highway high gradient slope stress equilibrium and vibration damping are taken precautions against natural calamities high bridge pier structure and construction method
CN104947649A (en) Control method for open caisson back soil deformation caused by pipe-jacking construction
CN102268871A (en) Construction method of turnover platform for underwater pile foundation of bridge
CN107489164A (en) The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall
CN106812153A (en) Beam and slab type construction elevator foundation construction engineering method in a kind of backfill
CN110644363A (en) Construction method of underwater main tower of cross-river cable-stayed bridge of high-speed railway
CN111350104A (en) Construction method of high-speed railway excavation roadbed in deep artificial spoil area
CN112695763A (en) Deep sludge stratum foundation pit excavation method
CN207331739U (en) A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall
CN204174625U (en) The superimposed cantilever foundation pit supporting construction of a kind of piling wall
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN109457705A (en) A kind of Open Cut Method construction method
CN104895054A (en) Construction method of fiber rib concrete uplift pile
CN117107749A (en) Construction method of large-diameter punched bored pile under influence of sea water seepage in sea-filling land-building area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190104