CN207331739U - A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall - Google Patents
A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall Download PDFInfo
- Publication number
- CN207331739U CN207331739U CN201721198117.0U CN201721198117U CN207331739U CN 207331739 U CN207331739 U CN 207331739U CN 201721198117 U CN201721198117 U CN 201721198117U CN 207331739 U CN207331739 U CN 207331739U
- Authority
- CN
- China
- Prior art keywords
- retaining wall
- reinforced concrete
- concrete retaining
- laterally
- decompression
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000011150 reinforced concrete Substances 0.000 title claims abstract description 50
- 238000007596 consolidation process Methods 0.000 title claims abstract description 20
- 230000006837 decompression Effects 0.000 claims abstract description 47
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 46
- 230000002787 reinforcement Effects 0.000 claims abstract description 18
- 239000004567 concrete Substances 0.000 claims description 30
- 241000826860 Trapezium Species 0.000 claims description 6
- 240000002853 Nelumbo nucifera Species 0.000 claims description 3
- 235000006508 Nelumbo nucifera Nutrition 0.000 claims description 3
- 235000006510 Nelumbo pentapetala Nutrition 0.000 claims description 3
- 239000011513 prestressed concrete Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 14
- 230000008569 process Effects 0.000 abstract description 7
- 238000010276 construction Methods 0.000 description 45
- 238000009434 installation Methods 0.000 description 23
- 239000002689 soil Substances 0.000 description 20
- 239000010410 layer Substances 0.000 description 17
- 238000013461 design Methods 0.000 description 14
- 239000000463 material Substances 0.000 description 12
- 229910000831 Steel Inorganic materials 0.000 description 11
- 239000010959 steel Substances 0.000 description 11
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 8
- 239000004576 sand Substances 0.000 description 7
- 238000002360 preparation method Methods 0.000 description 6
- 238000005516 engineering process Methods 0.000 description 5
- 239000000945 filler Substances 0.000 description 5
- 238000000465 moulding Methods 0.000 description 5
- 239000000047 product Substances 0.000 description 5
- 238000012360 testing method Methods 0.000 description 4
- 238000009412 basement excavation Methods 0.000 description 3
- 238000005266 casting Methods 0.000 description 3
- 239000000428 dust Substances 0.000 description 3
- 238000012545 processing Methods 0.000 description 3
- 238000012797 qualification Methods 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 241000037237 Peliosanthes gracilipes Species 0.000 description 2
- 238000003556 assay Methods 0.000 description 2
- 239000004927 clay Substances 0.000 description 2
- 230000015271 coagulation Effects 0.000 description 2
- 238000005345 coagulation Methods 0.000 description 2
- 239000004035 construction material Substances 0.000 description 2
- 238000009826 distribution Methods 0.000 description 2
- 238000007689 inspection Methods 0.000 description 2
- 239000004033 plastic Substances 0.000 description 2
- 239000011265 semifinished product Substances 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 244000025254 Cannabis sativa Species 0.000 description 1
- 235000012766 Cannabis sativa ssp. sativa var. sativa Nutrition 0.000 description 1
- 235000012765 Cannabis sativa ssp. sativa var. spontanea Nutrition 0.000 description 1
- 235000008331 Pinus X rigitaeda Nutrition 0.000 description 1
- 235000011613 Pinus brutia Nutrition 0.000 description 1
- 241000018646 Pinus brutia Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000033228 biological regulation Effects 0.000 description 1
- 238000003490 calendering Methods 0.000 description 1
- 235000009120 camo Nutrition 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 235000005607 chanvre indien Nutrition 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 239000011248 coating agent Substances 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 238000005056 compaction Methods 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 229910001651 emery Inorganic materials 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 230000004927 fusion Effects 0.000 description 1
- 239000004746 geotextile Substances 0.000 description 1
- 239000011487 hemp Substances 0.000 description 1
- 238000007654 immersion Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
- 230000010412 perfusion Effects 0.000 description 1
- 238000005498 polishing Methods 0.000 description 1
- 239000011241 protective layer Substances 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- -1 reinforcing bar Substances 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 238000012827 research and development Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000007493 shaping process Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 238000003892 spreading Methods 0.000 description 1
- 230000007480 spreading Effects 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
- 239000002436 steel type Substances 0.000 description 1
- 239000000758 substrate Substances 0.000 description 1
- 238000012876 topography Methods 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
The utility model provides a kind of heightening and consolidation structure of in-service reinforced concrete retaining wall, structure includes in-service reinforced concrete retaining wall, mode is pasted within in-service reinforced concrete retaining wall top reinforcing riser is set, the bottom for reinforcing riser sets laterally decompression off-load tablet, and laterally decompression off-load tablet is located at in-service reinforced concrete retaining wall wall back side, laterally decompression off-load tablet lower part sets pile foundation, and the longitudinal reinforcement of pile foundation anchors into the laterally decompression off-load tablet;Reinforce between riser and laterally decompression off-load tablet to be additionally provided with and help plate.The utility model can save time and cost, while ensure the safety and stability of original side slope, and the parameters such as size and the basement process form of retaining wall can be set according to actual conditions, have broad applicability.
Description
Technical field
The utility model belongs to retaining wall heightening and consolidation technology, and in particular to a kind of in-service reinforced concrete retaining wall adds
High ruggedized construction.
Background technology
China is the country of a topography and geomorphology choppy, and substantial amounts of architectural engineering especially road and rail engineering can not
What is avoided is built in the complex grounds such as mountain area location, due to above location stratum is more complicated, geological conditions changes greatly, crag compared with
The presence of many unfavorable factors such as more, slope support engineering are particularly important.
Retaining wall is for supporting Roadbed Soil or the hillside soil body, preventing from banketing or a kind of of soil deformation unstability constructs
Thing.Retaining wall can be used to stablize embankment and cut slope, lower execavated rockmass height, reduces earthwork volume and takes up an area face
Product, shrinks roadbed slope foot, prevents current scour roadbed, prevents hillside coating glides and resistance is come down etc., and be frequently used for
The disasters such as regulation landslide, landslide.In steep slope region, rock weathering and for avoiding the cutting of a large amount of excavations and reduction slope height
Section, it is possible to create landslide, the Unfavorable Conditions on landslide, high roadbed location, current scour are serious or for a long time by the edge of water immersion
River roadbed location, is all contemplated that for protection important building, ecological environment or location of other special requirements etc. and builds retaining wall.
Therefore, retaining wall is applied very extensive in Practical Project.
As a kind of long-term structures, retaining wall can be potentially encountered wall body cracking, external drum in use, it is also possible to meet
Wall body is caused to be increased to planning and adjusting, pole respective location, which even occurs, surprisingly to cave in, and with the exploitation in hillside soil, heap
Soil, situations such as banketing cause the increase of original slope height, cause original retaining wall to be no longer applicable in, safety and stability can not
Reach requirement, threaten life and property security of the country and people.Traditional solutions are usually that original retaining wall is removed weight
Build, but the quantities of this method is big, cost is also higher, time-consuming, while also with certain danger, it is original
Easily there is unstability in side slope, therefore no matter from the point of view of engineering construction angle or people life property safety's angle, in-service reinforcing bar
The research and development of concrete retaining wall heightening and consolidation technology are very necessary.
The content of the invention
In view of the problems of the existing technology, the utility model provides a kind of increasing for in-service reinforced concrete retaining wall
Fixing structure, effectively increases the physical and mechanical property of in-service reinforced concrete retaining wall, smoothly realizes in-service armored concrete
The heightening and consolidation of retaining wall.The technical solution of the utility model is:
A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall, including in-service reinforced concrete retaining wall, it is described
Mode is pasted within in-service reinforced concrete retaining wall top reinforcing riser is set, the bottom for reinforcing riser sets laterally decompression
Off-load tablet, and the laterally decompression off-load tablet is located at the in-service reinforced concrete retaining wall wall back side, the horizontal stroke
Pile foundation is set to decompression off-load tablet lower part, the longitudinal reinforcement of the pile foundation anchors into the laterally decompression off-load tablet;Institute
State to reinforce between riser and the laterally decompression off-load tablet to be additionally provided with and help plate.
It is further, described that to help plate be triangular structure, its two short sides respectively with the reinforcing riser and the transverse direction
Depressurize the connection of off-load tablet.
Further, the laterally decompression off-load tablet is equipped with wedge-shaped connector, the wedge close to the reinforcing riser side
Shape connection body section is chamfer trapezium structure, and the straight waist of the chamfer trapezium structure and upper bottom edge connect described in-service respectively
Reinforced concrete retaining wall and the laterally decompression off-load tablet, the wedge shape connector reinforce riser, the transverse direction by described
Off-load tablet is depressurized to be rigidly connected with the in-service reinforced concrete retaining wall.
Further, the reinforcing riser, the laterally decompression off-load tablet and the wedge-shaped connector rigid connection shape
It is integral, further to reinforce integral wall body.
Further, the pile foundation uses bored concrete pile or prestressed-concrete pile form.
A kind of heightening and consolidation method of in-service reinforced concrete retaining wall, comprises the following steps:
(1) preparation of construction:Banketed according to the foundation of in-service reinforced concrete retaining wall, structure type, the wall back of the body closely knit
Degree and bearing capacity, obtain construction parameter, and carry out the preparation of place, construction material and mechanical equipment;
(2) construction foundation pile:Pile foundation is set according to construction parameter;
(3) foundation trench excavates:After pile foundation test qualification, the foundation trench that the in-service reinforced concrete retaining wall wall back of the body bankets is carried out
Excavate, abolish pile crown, remove surflaes, work surface is provided for laterally decompression off-load tablet cushion construction;
(4) off-load tablet is laterally depressurized in construction:The reinforcing bar of off-load tablet, pouring molding and and pile foundation are laterally depressurized in installation
It is connected firmly;
(5) construction reinforcement riser and plate is helped:The reinforcing bar for reinforcing riser is installed according to interior patch mode and the reinforcing bar of plate is helped in installation,
Pouring molding;
(6) back of the body backfill of riser wall is reinforced:Riser wall body to be reinforced, help plate and the laterally strong concrete of decompression off-load tablet
After degree reaches the 75% of design strength, carried on the back using the in-service reinforced concrete retaining wall wall of filler back-filling in layers.
Further, soil thickness≤300mm that individual layer backfills in the step (6), backfill compacting factor >=0.94.
Compared with prior art, the characteristics of the utility model and beneficial effect is:
The utility model sets in-service reinforced concrete retaining wall wall back of the body pile foundation can be by newly-built reinforcing riser and its wall
Carry on the back the vertical force banketed to be transferred to below substrate, add antiskid and the overall stability of retaining wall totality;Laterally decompression is set
Off-load tablet can increase the load assignment area for reinforcing that riser and its wall back of the body banket, while reduce a part and act on in-service gear
The soil lateral pressure of cob wall, adds the anti-overturning and stability for reinforcing riser;Reinforce riser and original retaining wall structure
Interior patch connection mode further increases the rigidity of overall retaining wall, lifts the height and stable degree of in-service retaining wall, also avoids
Remove time-consuming caused by rebuilding;In addition, the utility model can be cost-effective.The processing mode rebuild is removed with tradition
Compare, the in-service reinforced concrete retaining wall heightening and consolidation scheme of the utility model can save time and cost, and ensure at the same time
The safety and stability of original side slope, can set the parameters such as size and the basement process form of retaining wall according to actual conditions,
With broad applicability.
Brief description of the drawings
Fig. 1 is the diagrammatic cross-section of the heightening and consolidation structure of the in-service reinforced concrete retaining wall of the utility model;
Fig. 2 is the heightening and consolidation side that in-service reinforced concrete retaining wall is carried out using the heightening and consolidation structure of the utility model
The process flow chart of method;
In figure:1st, pile foundation, 2, in-service reinforced concrete retaining wall, 3, horizontal decompression off-load tablet, 4, wedge-shaped connector,
5th, riser is reinforced, 6, help plate.
Embodiment
The utility model is described in further details with specific embodiment below in conjunction with the accompanying drawings, described is to this practicality
New explanation rather than restriction.
As shown in Figure 1, the utility model provides a kind of heightening and consolidation structure of in-service reinforced concrete retaining wall, it is included in
Reinforced concrete retaining wall 2 is used as a servant, patch mode sets reinforcing riser 5 within the top of in-service reinforced concrete retaining wall 2, reinforces vertical
The bottom of plate 5 sets laterally decompression off-load tablet 3, and laterally depressurizes off-load tablet 3 and be located at in-service reinforced concrete retaining wall 2
Above the wall back of the body bankets, laterally depressurize 3 lower part of off-load tablet and pile foundation 1 is set, the longitudinal reinforcement of pile foundation 1 is anchored into laterally to depressurize and unloaded
Lotus tablet 3, pile foundation use bored concrete pile or prestressed-concrete pile form.Laterally decompression off-load tablet 3 is close to reinforcing riser 5
Side is equipped with wedge-shaped connector 4, and wedge-shaped 4 section of connector is chamfer trapezium structure, the straight waist of the chamfer trapezium structure and upper
Base is connected to labour reinforced concrete retaining wall 2 and laterally decompression off-load tablet 3, wedge-shaped connector 4 will reinforce riser 5,
Laterally decompression off-load tablet 3 is rigidly connected with in-service reinforced concrete retaining wall 2.And reinforce riser 5, laterally decompression off-load is put down
Plate 3 and the wedge-shaped rigid connection of connector 4 form entirety, further to reinforce integral wall body.Reinforce riser 5 and laterally decompression off-load
It is additionally provided between tablet 3 and helps plate 6, it is triangular structure to help plate 6, its two short sides are unloaded with reinforcing riser 5 and laterally depressurizing respectively
Lotus tablet 3 connects.
A kind of heightening and consolidation method of in-service reinforced concrete retaining wall, is the heightening and consolidation knot using the utility model
Structure, its process flow chart is as shown in Fig. 2, comprise the following steps:
(1) preparation of construction:Banketed according to the foundation of in-service reinforced concrete retaining wall, structure type, the wall back of the body closely knit
Degree and bearing capacity, obtain construction parameter, and carry out the preparation of place, construction material and mechanical equipment;
(2) construction foundation pile:Pile foundation is set according to construction parameter;
(3) foundation trench excavates:After pile foundation test qualification, the foundation trench that the in-service reinforced concrete retaining wall wall back of the body bankets is carried out
Excavate, remove surflaes, work surface is provided for laterally decompression off-load tablet construction;
(4) off-load tablet is laterally depressurized in construction:The reinforcing bar of off-load tablet, pouring molding and and pile foundation are laterally depressurized in installation
It is connected firmly;
(5) wedge shape of constructing connector:The reinforcing bar of the in-service wedge-shaped connector of reinforced concrete retaining wall installation, pouring molding,
The effect of wedge-shaped connector is in-service reinforced concrete retaining wall is connected with reinforcing patch mode within riser;
(6) construction reinforcement riser and plate is helped:Installation reinforces riser and helps the reinforcing bar of plate, pouring molding;
(7) back of the body backfill of riser wall is reinforced:Riser wall body to be reinforced, help plate and the laterally strong concrete of decompression off-load tablet
After degree reaches the 75% of design strength, carried on the back using the in-service reinforced concrete retaining wall wall of filler back-filling in layers, wherein individual layer backfills
Soil thickness≤300mm, backfill compacting factor >=0.94.
Embodiment 1
Anshan, liaoning Province location mountainous region side slope original height 6.0m, length about 300m, stratum is from top to bottom:0.5~3.0m
Thick silty clay, 1.0~3.8m thickness dauks, 1.0~3.8m thickness completely decomposed Sandy Silts, are thickness below completely decomposed mud stone
Severely-weathered Sandy Silt more than 5m, original in-service reinforced concrete retaining wall are cantilevered reinforced concrete retaining wall, side slope
Bearing capacity f after wall back of the body plain fill compactingak=100~~120Kpa, retaining wall has been run for many years, due to Develop by stages, according to
Existing planning causes the highly desirable increase 4.0m of original retaining wall.
Retaining wall increases that measure is as follows, and specific configuration is with reference to figure 1:The former retaining walls back of the body sets manually digging hole filling pile basis
1, the long 8.5m of stake, stake footpath 800mm;Laterally 3 high 500mm, width 4000mm of decompression off-load tablet;Reinforce riser 5 and original earth-retaining
Wall 2 is connected using interior patch method;Reinforce riser 5 high 4000mm, thickness 600mm;Help the thickness of plate 6 400mm, horizontal spacing 4000mm.
If rebuilding new barricade after original retaining wall 2 is removed, it is necessary to devote a tremendous amount of time and expense, lose more than gain,
And not necessarily can guarantee that the safety and stabilization of original side slope in demolishing process, use the heightening and consolidation structure of the utility model can be with
Successfully solve the problems, such as this.
Specific construction flow is followed the steps below with reference to figure 2:
1st, preparation of construction
1.1 technique preparation
A. be familiar with and understand the foundation of original reinforced concrete retaining wall, structure type, the wall back of the body banket compactness and
Bearing capacity;
B. by geology, hydrological data, environmental requirement, with reference to field condition, surveying and locating makes excavation scope, determines to excavate
Mode, depth;
C. it is familiar with the requirement of reinforcement fabrication installation specification, calculates number of steel bars, draws steel bar meter installation drawing;
D. template stress is checked according to construction drawing and engineering structure form, load;
1.2 Farm Planning
Scene need to accomplish " three supplies and one leveling ", after excavation of foundation pit, according to foundation pit surrounding landform, carry out ground prevent, drainage works.
1.3 materials prepare
A. consumable material:Concrete, reinforcing bar, plastic row according to needed for retaining wall construction is selected in design and related construction requirement
The materials such as water sheet material, and former material inspection is carried out by design and related standard samples, through examining qualified former material to be sent to by stages and in groups
Construction site;
B. circulation material:According to the construction method of use, the material such as reasonable selection template, steel pipe, the lumps of wood;
1.4 mechanical equipments prepare
Get out the mechanical equipment needed for retaining wall construction;
2nd, construction foundation pile
In-service reinforced concrete retaining wall wall back of the body pile foundation is basic using manually digging hole filling pile, accurate before pile foundation construction
Pile foundation position is really measured, makes steel reinforcement cage, after steel reinforcement cage is placed correctly, concrete perfusion, and in the construction process
Pay attention to finished product protection;
3rd, foundation trench excavates
After pile foundation concrete strength reaches testing conditions, carry out what the in-service reinforced concrete retaining wall wall back of the body banketed
Foundation trench excavates, and removes surflaes, carries out pile body integrity and bearing capacity of pile foundation detection, is interior patch method junction and laterally decompression off-load
Tablet cushion construction provides work surface;
4th, off-load tablet bed course is laterally depressurized in construction:After pile measurement qualification, the C15 element coagulations of 0.1m~0.2m thickness are poured
Soil padding, work surface is provided for laterally decompression off-load tablet construction;
5th, off-load tablet is laterally depressurized in construction
5.1 steel bar meter
Using HRB335 and HRB400 two types reinforcing bars, processed after former material is qualified after testing in strict accordance with drawing,
The oil stain of rebar surface, paint dirt, iron rust are all first removed clean, connector by whether reinforcing bar former material, or the finished product of machine-shaping
Overlap joint welding can be used, fusion length and quality will meet design and code requirement;
5.2 reinforcement installation
Semi-finished product reinforcing bar is transported to construction site installation after the assay was approved, by steel bar meter field;
Surveying setting-out carries out reinforcement installation after determining laterally decompression off-load panel size, is required according to design drawing, per single
The bar one-time binding of the horizontal decompression off-load tablet of first section, installation forming, reinforcing bar, which binds the quantity of point, spacing etc., to be met
Design requirement;
Process and reinforcing bar is installed, carry out disposably binding, installation forming, pile foundation reinforcing bar is anchored into transverse direction by design requirement
Off-load tablet is depressurized, and is reserved and is reinforced riser and help the connection reinforcing bar of plate, makes laterally to depressurize off-load tablet with reinforcing riser
And help plate to be connected firmly, quantity, the spacing of reinforcing bar binding point will meet design requirement;
5.3 model sheetinstallat
The O. gracilipes for the horizontal decompression off-load tablet made according to survey crew's setting-out, installation form, template can use
Steel type gang form, before model sheetinstallat, by the polishing of the contact surface of template and concrete, cleans out and brushes the water-soluble demoulding
Agent;
5.4 concreting
Before concreting, go through bar types, quantity and protective layer situation, template position deviation, cross dimensions,
Surface smoothness, absolute altitude and support conditions etc., and concrete performance is tested, after meeting the requirements, you can carry out coagulation
Soil pours;
Walling bottom plate is poured, points three layers pour, and during layer-by-layer distribution, pour the second layer after having poured one layer again, paving thickness is not
Preferably greater than 40cm;Concreting is carried out continuously, and must not be interrupted, and when pause interval for some reason, its intermittent time should be less than front layer
The presetting period of concrete;, should be by pouring interrupt processing when more than the intermittent time is allowed, while indwelling construction joint is answered, construct
The plane of seam should be with the axis perpendicular of structure;
After concreting, finishing in time, smooth out concrete exposed surface, takes secondary calendaring technology;
5.5 form removable
When laterally decompression off-load tablet concrete strength reaches more than 2.5MPa, and its surface and corner angle not because of dismounting and by
Damage, concrete temperature are in cooldown period, and between component core concrete and surface concrete, surface concrete and environment
When temperature difference is no more than 20 DEG C, you can remove the template of laterally decompression off-load tablet;
5.6 subsiding cracks are constructed
Subsiding crack position can set 2cm thickness cystosepiments, wait base concrete pour after the completion of, subsiding crack filling before first will stitch
Cystosepiment removes the pitch hemp cut clean, tunneling boring filling has been soaked, when filling to accomplish slit width uniformly, seam body it is vertical, circumferential direction
Perforation, filling are closely knit, bright and clean without cavity, appearance;
6th, wedge shape of constructing connector
In order to make reinforcing riser be connected with pasting mode within original retaining wall, the wedge-shaped connector of installation is processed by design requirement
Reinforcing bar, installation form and on request casting concrete, Specific construction flow applies with step 5 laterally decompression off-load tablet construction
To focus on finished product protection during work;
7th, construction reinforcement riser and plate is helped
7.1 construction joint dabbings
When laterally decompression off-load tablet and wedge-shaped connector concrete strength reach more than 2.5MPa, reinforce riser and
The construction of plate is helped, first manually cuts laterally decompression off-load tablet and the cement bonded sand reinforced riser, help plate joint part concrete surface
Slurry and the weak layer of pine, are rinsed well after dabbing with water, big fresh concrete area is not less than the gross area 75% are exposed after dabbing;
7.2 reinforcement installation
A. steel bar meter
Steel bar meter requirement is the same as 5.1 steel bar meters;
B. reinforcement installation
Semi-finished product reinforcing bar is transported to construction site installation after the assay was approved, by steel bar meter field, first welds spreading riser and helps
Plate stud, then the horizontal reinforcement installed and reinforce riser, help plate, finally install pull hook muscle.
Surveying setting-out determines to reinforce riser, help plate O. gracilipes after carry out reinforcement installation, required according to design drawing, per single
The reinforcing riser of first section, help the reinforcing bar of plate to carry out disposably binding, installation forming, and reinforcing bar binds the quantity of point, spacing etc. and to accord with
Close design requirement;
7.3 model sheetinstallat
Reinforcement installation binding finishes, it is qualified by inspection after, start installation and reinforce riser and help template die plate, reinforce riser and help
Plate graded casting concrete, needs to pay special attention to the verticality of template, flatness and faulting of slab ends control in construction;
7.4 concreting
Before concreting, template position deviation, cross dimensions, surface smoothness, absolute altitude and bracing reinforcement should be checked
Situation etc., can carry out pouring for concrete after passed examination;
For height of the discharge port away from concreting face no more than 1m, layer-by-layer distribution, has poured one layer during casting concrete
Pour the second layer again afterwards, paving thickness is not preferably greater than 30cm;
Concreting should be carried out continuously, and must not be interrupted, and when pause interval for some reason, its intermittent time should be less than front layer and mix
Coagulate the presetting period of soil;, should be by pouring interrupt processing when more than the intermittent time is allowed, while answer indwelling construction joint, construction joint
Plane should be with the axis perpendicular of structure;
It after concreting, should in time repair, smooth out concrete exposed surface;
7.5 stent, form removable
With the related request of 5.5 form removables;
7.6 spilled water holes are installed
When installation reinforces riser, helps template die plate, while spilled water hole is installed, spilled water hole is installed in strict accordance with design drawing lateral
Model requires to carry out, and sluicing pitch of holes can be set by 2m~3m, in installation process it is noted that setting and the spilled water hole slope of rubble anti-filter
The angle of degree;
7.7 wall body subsiding cracks are constructed
With the related request of 5.6 subsiding cracks construction;
8th, the back of the body backfill construction of riser wall is reinforced
Riser wall body to be reinforced, help plate and laterally the concrete strength of decompression off-load tablet reaches the 75% of design strength
After carry out fill construction, filler using B groups filler (well gather materials, including dysgeogenous magma stone, the erratic boulder of disproportionately graded
Soil, land pebble, gravelly soil, circle gravel soil, dust soil, gravelly sand, coarse sand, middle sand, fine grained soil content 15%~30% erratic boulder it is native,
Land pebble, gravelly soil, circle gravel soil, dust soil and fine sand, glutinous sand, emery dust soil, sand clay) or its above rank filler, sluicing
Hole water inlet is wrapped up using permeable geotextiles, installs 5cm thickness plastic draining sheet materials in time, then carries out wall by reinforcing riser height
Placement in layers is constructed afterwards, individual layer filled slope≤300mm, and mechanically or manually compaction in layers, backfill compacting system are utilized after filling
Number >=0.94, it is noted that finished product protection during filling.
Although the embodiment of the utility model has been shown and described above, it is to be understood that above-described embodiment is
Exemplary, it is impossible to the limitation to the utility model is interpreted as, those of ordinary skill in the art are in the scope of the utility model
It is interior above-described embodiment to be changed, changed, replaced and modification.
Claims (5)
1. a kind of heightening and consolidation structure of in-service reinforced concrete retaining wall, it is characterised in that kept off including in-service armored concrete
Cob wall, patch mode sets reinforcing riser within the in-service reinforced concrete retaining wall top, and the bottom for reinforcing riser is set
Laterally decompression off-load tablet is put, and the laterally decompression off-load tablet is located at the in-service reinforced concrete retaining wall wall back
Side, the laterally decompression off-load tablet lower part set pile foundation, and the longitudinal reinforcement of the pile foundation anchors into the laterally decompression and unloads
Lotus tablet;It is additionally provided between the reinforcing riser and the laterally decompression off-load tablet and helps plate.
A kind of 2. heightening and consolidation structure of in-service reinforced concrete retaining wall according to claim 1, it is characterised in that institute
It is triangular structure to state and help plate, its two short sides are connected with the reinforcing riser and the laterally decompression off-load tablet respectively.
A kind of 3. heightening and consolidation structure of in-service reinforced concrete retaining wall according to claim 2, it is characterised in that institute
State laterally decompression off-load tablet and be equipped with wedge-shaped connector close to the reinforcing riser side, the wedge shape connection body section is chamfer
Trapezium structure, the straight waist of the chamfer trapezium structure and upper bottom edge connect the in-service reinforced concrete retaining wall and institute respectively
State laterally decompression off-load tablet, it is described wedge shape connector by it is described reinforcing riser, it is described laterally decompression off-load tablet with it is described
Use as a servant reinforced concrete retaining wall rigid connection.
A kind of 4. heightening and consolidation structure of in-service reinforced concrete retaining wall according to claim 3, it is characterised in that institute
State reinforcing riser, the laterally decompression off-load tablet and the wedge-shaped connector to be rigidly connected to form entirety, further to reinforce
Integral wall body.
5. a kind of in-service reinforced concrete retaining wall according to Claims 1 to 4 any one claim is increased
Fixing structure, it is characterised in that the pile foundation uses bored concrete pile or prestressed-concrete pile form.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721198117.0U CN207331739U (en) | 2017-09-19 | 2017-09-19 | A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721198117.0U CN207331739U (en) | 2017-09-19 | 2017-09-19 | A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207331739U true CN207331739U (en) | 2018-05-08 |
Family
ID=62369018
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721198117.0U Active CN207331739U (en) | 2017-09-19 | 2017-09-19 | A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207331739U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107489164A (en) * | 2017-09-19 | 2017-12-19 | 中冶沈勘工程技术有限公司 | The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall |
CN109958101A (en) * | 2019-04-23 | 2019-07-02 | 上海勘测设计研究院有限公司 | Reinforcement of retaining wall for heightening and consolidation original retaining wall |
CN111945484A (en) * | 2020-08-06 | 2020-11-17 | 兰州交通大学 | An existing-new side-by-side pile-board wall supporting structure and construction method |
CN114482149A (en) * | 2022-01-25 | 2022-05-13 | 张文元 | Municipal construction foundation pile foundation construction method |
-
2017
- 2017-09-19 CN CN201721198117.0U patent/CN207331739U/en active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107489164A (en) * | 2017-09-19 | 2017-12-19 | 中冶沈勘工程技术有限公司 | The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall |
CN109958101A (en) * | 2019-04-23 | 2019-07-02 | 上海勘测设计研究院有限公司 | Reinforcement of retaining wall for heightening and consolidation original retaining wall |
CN111945484A (en) * | 2020-08-06 | 2020-11-17 | 兰州交通大学 | An existing-new side-by-side pile-board wall supporting structure and construction method |
CN114482149A (en) * | 2022-01-25 | 2022-05-13 | 张文元 | Municipal construction foundation pile foundation construction method |
CN114482149B (en) * | 2022-01-25 | 2024-06-04 | 广东玄城建设工程有限公司 | Municipal construction foundation pile foundation construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106930319A (en) | A kind of high slope framed revetment and its construction method | |
CN107489164A (en) | The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall | |
CN107447778A (en) | The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall | |
CN113445521B (en) | High side slope construction method for filling | |
CN106958256A (en) | A kind of placement layer by layer, the open caisson construction technique repeatedly sunk | |
CN106088127A (en) | Open caisson construction method | |
CN207331739U (en) | A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall | |
CN109914161B (en) | Construction method of high-speed railway filling roadbed in soft soil area | |
CN207331740U (en) | A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall | |
CN108316339A (en) | A kind of construction method of water penetration geology large size arch bridge base | |
CN102430277B (en) | Coarse grid sunk well for physically processing waste water and construction method thereof | |
CN107724401A (en) | The construction method of bridge pier foundation ditch | |
CN111350104A (en) | Construction method of high-speed railway excavation roadbed in deep artificial spoil area | |
CN112695763A (en) | Deep sludge stratum foundation pit excavation method | |
CN102235007B (en) | Method for supporting deep foundation with upper nail-lower pile combination | |
CN109706952A (en) | Large-scale well-sinking construction method | |
CN201339186Y (en) | Soft rock concrete replacement pile composite foundation | |
CN206736957U (en) | A kind of high slope framed revetment | |
CN105484270B (en) | Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit | |
Wehr et al. | Deep vibro techniques | |
CN112227126A (en) | Highway foundation reinforcing structure in soft soil area and construction method and supervision method thereof | |
CN113684785B (en) | Construction process of pile foundation wharf | |
CN111335912A (en) | Large-pipe-diameter mechanical pipe jacking construction process for soft soil foundation in collapsible loess area | |
CN111042144A (en) | Excavation method for foundation pit of underground beam under condition of continuous flow of riverway in cold region | |
CN110080266A (en) | Method for improving bearing capacity of pile foundation under construction by replacing and filling soil between piles |