CN104947649A - Control method for open caisson back soil deformation caused by pipe-jacking construction - Google Patents

Control method for open caisson back soil deformation caused by pipe-jacking construction Download PDF

Info

Publication number
CN104947649A
CN104947649A CN201410113955.8A CN201410113955A CN104947649A CN 104947649 A CN104947649 A CN 104947649A CN 201410113955 A CN201410113955 A CN 201410113955A CN 104947649 A CN104947649 A CN 104947649A
Authority
CN
China
Prior art keywords
jacking
open caisson
soil body
pipe
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410113955.8A
Other languages
Chinese (zh)
Inventor
樊亚文
郑世宝
孙阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiaotong University
Original Assignee
Shanghai Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiaotong University filed Critical Shanghai Jiaotong University
Priority to CN201410113955.8A priority Critical patent/CN104947649A/en
Publication of CN104947649A publication Critical patent/CN104947649A/en
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention provides a control method for open caisson back soil deformation caused by pipe-jacking construction and belongs to the technical field of construction. The control method for open caisson back soil deformation caused by pipe-jacking construction comprises the steps that firstly, well point dewatering is executed on the periphery of an open caisson, the underground water level is lowered to be below the bottom face of the open caisson, and therefore the friction force between the wall and the bottom face of the open caisson and a soil layer is increased; anchorage of the bottom of the open caisson in the soil layer is reinforced, the overall rigidness of the open caisson is brought into play, and the space deformation harmony of the open caisson under the action of jacking force is improved; a jacking sequence is determined, and two parallel jacking pipes are used for simultaneous jacking; simplified three-dimensional finite element models of the open caisson and the back soil of the open caisson are established, and the most unfavorable combination value [Vi, Vj] of the jacking force of the two parallel jacking pipes is determined through a stability analysis method and used as the jacking force pre-control parameter of jacking construction; in jacking construction, a small duct advanced slip casting technology is adopted, a thixotropic fluid sleeve with good performance is formed between the outer walls of the jacking pipes and the soil layer, the functions of reducing friction and lowering resistance are achieved, and therefore the disturbance influence of the jacking force on the back soil is reduced; finally, according to the preset jacking sequence of the parallel jacking pipes, a monitoring scheme is made in a targeted mode, monitoring point arrangement and monitoring are conducted before jacking construction is conducted, a test instrument is installed in the back soil, information is fed back in time, and therefore construction parameters can be adjusted.

Description

The back soil body deformation of open caisson control method that jacking construction causes
Technical field
What the present invention relates to is a kind of method of underground structrue engineering technical field, specifically the back soil body deformation of open caisson control method that causes of a kind of jacking construction.
Background technology
Pipe-jacking technology is when not excavating earth surface, utilizes hydraulic jack from upper pipe working well jacking section by section in underground by push-bench and tube coupling to be laid, until the non-excavating underground pipe line cable laying operation technique of push pipe received well.Pipe-jacking technology due to its superiority more and more universal, the field of application is also more and more wider.Be applied in recent years in the construction of many pipelines such as running water pipe, gas pipe, power cable, communication cable and generating plant circulation-water cooling system.In pipe-jacking project, open caisson has a wide range of applications as active well.It is in pipeline jack-in process, the top power moved in circles is passed to the soil body after wall by rear parados.If top power is excessive, and when open caisson back soil body stability is inadequate, larger distortion may appear in the soil body, makes the backhaul of jack part consume on soil deformation, lowers efficiency; Back soil can be caused time serious to destroy, make jacking failure.In addition, larger soil deformation also will cause the damage of road surface and building around open caisson, causes a series of environment disease.Therefore, strict control back soil body deformation of open caisson that jacking construction causes to guarantee pipe-jacking project safety with carry out smoothly very important.
Through retrieving existing technical literature, Yan Shaojun and Zhang Aihua is in " coal field geology and exploration " (in February, 2006,34th volume the 1st phase, 37th to the 40th page) in " pipe-jacking project back stressed with distortion three dimensional analysis " (article the number: 1001-1986 (2006) 01-0037-04) of delivering with certain pipe-jacking project for background, the supporting capacity of employing Rankine theory of passive pressure of soil to the back soil body is analyzed.By changing the modulus of elasticity parameter of the back soil body, getting different modulus respectively adopts Drucker-Prager model to calculate, obtain corresponding body of wall maximum horizontal displacement value, and reach a conclusion: the modulus of elasticity improving the soil body, can effectively reduce the horizontal movement value of back body of wall.The document is only carried out quantitative computational analysis to the bearing capacity of the open caisson back soil body and displacement according to theoretical, does not provide the correlation technique measure of restriction back land movement, does not namely consider the actual conditions of the loading-off-load repeatedly of push pipe.
Summary of the invention
The present invention is directed to prior art above shortcomings, the back soil body deformation of open caisson control method that a kind of jacking construction causes is proposed, solve in pipe-jacking project the deformation controlling problem considering the open caisson back soil body that top power repeated action causes, ensure that carrying out smoothly and reducing the impact on surrounding enviroment to greatest extent of pipe-jacking project.
The present invention is achieved by the following technical solutions, the present invention includes:
1) well-points dewatering is implemented, by groundwater table is reduced to below open caisson bottom surface, to increase the friction of open caisson wall and bottom surface and soil layer at open caisson periphery.
Described well-points dewatering, the construction characteristic according to the hydrogeological conditions in place, engineering design requirements and well sinking chooses dewatering mode.
The well depth of described dewatering well is H=H 1+ H 2+ H 3+ H 4+ ir 0, wherein: H is dewatering well well depth, H 1for caisson cutting edge is to surface distance, H 2for the requirement degree of depth at the bottom of precipitation water level distance open caisson, H 3for the active length of precipitation strainer, H 4for sediment tube length, i is hydraulic gradient, r 0for open caisson Equivalent Calculation radius.
Described dewatering well is chosen apart from the distance of open caisson wall by the place situation of open caisson periphery, is preferably 4m ~ 8m.
2) strengthen the anchoring bottom open caisson in soil layer, by playing open caisson integral rigidity, realizing the raising of the geometric distortion harmony of open caisson under the power effect of top, specifically comprising the following steps:
2.1) with giant, groove reserved inside the borehole wall above sword pin is rinsed well, whole for surface concrete dabbing is exposed stone, be convenient to the combination of New-old concrete, reserved steel bar and baseplate reinforcing bar adopt and are welded to connect, the length of welding point jointing is more than or equal to 35d, and d is the larger diameter of Reinforcement.
2.2) castinplace pile of concrete drill hole is set bottom open caisson, to resist the slippage that top power may cause.
Described castinplace pile, its diameter D is chosen by the site condition bottom open caisson, and quantity and the long l of stake are according to " technical code for building pile foundation " JGJ94-2008) in 5.7.2 bar determine.
Described castinplace pile is connected with adopting inverted trapezoidal pile cover bottom open caisson, and stake top reinforcing bar anchors into open caisson base plate, and castinplace pile is uniformly distributed along perpendicular to push pipe jacking direction in each district lattice bottom open caisson.
3) determine jacking order, adopt the jacking simultaneously of two parallel pipe jackings.
Described jacking order is according to plant equipment, site condition and cost-effectiveness requirement choose reasonable.
Top power V after open caisson while described caused by jacking on parados iwith V jdifference be no more than 20%.
4) set up the simplification three-dimensional finite element model of open caisson and the back soil body thereof, adopt analysis method for stability determining step 3) in the most dangerous combination value [V of two parallel pipe jacking top power i, V j], in this, as top power pre-control parameter during jacking construction, specifically comprise the following steps:
4.1) the modeling scope of FEM (finite element) model: get B perpendicular to push pipe jacking direction width, the length L of the open caisson back soil body is greater than 2d+2s, height h gets the distance of open caisson bottom surface to back soil body earth's surface, wherein: B is the width of open caisson, d is the length of side of jacking counterforce acting surface, and s is the distance between jacking counterforce acting surface to open caisson top.
4.2) computation model fringe conditions is as follows: apply tangential even distributed force at z=-t place, rear parados base and z=-t place, two sides, simulate open caisson bottom surface and soil body frictional force, open caisson sidewall and soil body frictional force respectively; Z on 4, z=0 place jacking counterforce acting surface according to step 3) jacking order apply counter-force respectively, remainder does not retrain; Two side x=-L/2 and x=+L/2 place, except z=-t part, limit its x direction displacement; Y=0 place, bottom surface, except z=-t part, limits the displacement in its y direction; Z=-L place, the back side, limits its z direction displacement; Y=h place, earth's surface is the scope of freedom.
4.3) soil body-shield machine system adopts the More's coulomb homalographic circle model considering elastic-plastic strain, and rear parados is pressed elastic body and considered, arranges the plane-plane contact characteristic of Contact surface element mould rigid body-beformable body between rear parados and the soil body.
5) in jacking construction, adopt small-lead-tube advanced slip-casting technique, make the thixotropic slurry cover forming superperformance between push pipe outer wall and soil layer, play the effect of antifriction, thus reduce top power to the disturbing influence of the back soil body, concrete steps comprise:
5.1) arrange at inlet and outlet cave there is the antipriming of waterproof effect, and from going out hole mud jacking; Make interface tube sealing performance keep good, and guaranteeing that slurries are not bonded after avoiding pipe to enter the soil body while inlet and outlet cave seepage.
5.2) be evenly arranged 4 mud jacking holes at head afterbody hoop, uniform mud jacking hole on the three-joint pipe joint after head, and in units of every three joints, select a wherein pipe joint joint upper layout mud jacking hole.
Be that oblique 45 ° of orthogonal loops are to arranged crosswise between described mud jacking hole.
5.3) the mud lubrication anti-friction agent containing swell soil, CMC (Carboxymethyl Cellulose, carboxymethyl cellulose), sodium carbonate and water is adopted to put on pipeline section sidewall and soil body contact site by injected hole.
6) by step 3) the jacking order of the parallel pipe jacking determined, formulate monitoring scheme targetedly, before jacking construction, carry out point layout and monitoring, installation testing instrument in the back soil body, timely feedback information, to adjust construction parameter, specifically comprises:
6.1) according to site condition and the step 3 of the back soil body) jacking determined order, after the back soil body is pressed close to, parados place buries skew back pipe and soil pressure sensor underground in suitable place, earth's surface test lead adopts the mode of brick work brick wall and surrounding to isolate, and avoids destruction and the interference of suffering other working procedure.
6.2) tester sinks to design elevation at open caisson, carries out after back cover terminates, and at least starts jacking construction 7 days apart from push pipe.Process to be installed all terminated soil solidifying after at least 7 days, and carry out examination and survey with the availability verifying measuring point, require stable reading, the numerical difference of continuous 3 times is no more than 10% of average.Before jacking, same step test initial value will be carried out, using the initial value of the average of 3 secondary data now recorded as whole jack-in process at push pipe.
6.3) monitoring frequency one day 2 times, when the power of top reading is bigger than normal or abnormal conditions appear in earth's surface, suitably improves test frequency as required.Land movement should control in-30mm ~+30mm scope, using these data as judging that the back soil body is the need of the foundation of carrying out reinforcing; If desired, then after rear parados, vertical rotary churning pile reinforcing is carried out within the scope of B/2.
Technique effect
Compared with prior art, The present invention gives the stronger technical measures of multinomial specific aim, solve major diameter parallel pipe jacking to construct the back soil body deformation of open caisson control problem caused, the distortion of the open caisson back soil body is made effectively to control within the scope of designing requirement, for effective performance of pushing up power in pipe-jacking project has supplied an important technology to ensure, compensate for deficiency and the defect of existing technique.The inventive method is simple, easy to implement, expense is low, is applicable to similar operating mode, has suitable reference value in similar engineering field.
Accompanying drawing explanation
Fig. 1 is engineering plan of the present invention.
Fig. 2 is engineering sectional drawing of the present invention.
Fig. 3 is open caisson lower concrete castinplace pile schematic diagram of the present invention.
Fig. 4 is three-dimensional finite element model scale diagrams of the present invention.
Fig. 5 is three-dimensional finite element model stress and strain model schematic diagram of the present invention.
Fig. 6 is back soil monitoring point layout schematic diagram of the present invention.
Fig. 7 is back land movement of the present invention actual measurement maximum value schematic diagram.
Detailed description of the invention
Elaborate to embodiments of the invention below, the present embodiment is implemented under premised on technical solution of the present invention, give detailed embodiment and concrete operating process, but protection scope of the present invention is not limited to following embodiment.
Embodiment 1
Certain north is prolonged and is sent Hydraulic Projects to need newly-builtly to contain with passing through certain river, and Fig. 1 is engineering plan, and Fig. 2 is engineering sectional drawing.The long 450m of main culvert pipe, adopts 4 push pipes often to save reinforced concrete prefabricated push pipe specification to be: interior diameter 3500mm, long 2.5m), every bar push pipe is made up of 180 joint prefabricated pipe, has the feature of heavy in section, long distance.Center to center distance 9.5m between each bar push pipe, at the bottom of pipe, pipe crest level is respectively-17.65m and-13.45m.Southern side active well and north side received well are caisson structure, planar dimension 37m × 22.5m, and sword sole elevation is-21.0m.Push pipe is by the active well of southern side, and jacking accepts well to north side and terminates.
1) according to the detailed geology survey data of construction plant, the construction characteristic of incorporation engineering designing requirement and well sinking, this programme design adopts bridge-type drainage steel tube well precipitation, H 1get 25m; H 2get 1m; H 3get 2m; H 4get 2m; I gets 1/5; r 0get 17.5m, with due regard to surplus capacity, H presses 35m value.Dewatering well is arranged in open caisson periphery, distance open caisson outer wall 7m.
2) anchoring in soil layer bottom following measures reinforcement open caisson is adopted:
1. when well sinking is to design elevation, to rinse and after surperficial dabbing process, the new paving reinforcing bar of the reserved steel bar in groove and open caisson base plate adopts and is welded to connect, and welding point staggers mutually reserving groove to surrounding, d=28mm, the length of welding point jointing is taken as 1000mm.
2. settling bottom site condition chooses castinplace pile diameter D=0.8m, by " technical code for building pile foundation " JGJ94-2008) in 5.7.2 bar determine the cast-in-place concrete pile of the long l=8m of common need 16 pile, 2 are respectively arranged along perpendicular to push pipe jacking direction in each district lattice, castinplace pile is connected with adopting inverted trapezoidal pile cover bottom open caisson, inverted trapezoidal pile cover size conforms Fig. 3 requirement, stake top reinforcing bar anchors into open caisson base plate.
3) there are 4 pipelines be parallel to each other to need jacking in this case history, consider restriction and the economy of equipment, according to the principle jacking stage by stage of 2 push pipes one group.For reducing influencing each other between push pipe, not making the active force of the back soil body too concentrated, often organizing push pipe jacking simultaneously.During jacking, close observation both sides oil cylinder reading, the top power V after the open caisson that two push pipe jackings are caused on parados i, V jdifference control within 20%.
4) according to engineering calculation required precision, Fig. 4 and Fig. 5 sets forth simplification three-dimensional finite element model size and the stress and strain model schematic diagram of open caisson and the back soil body thereof, adopting analysis method for stability to get many group tops power combined value is applied on model, carry out circulation Load-unload, finally determine that the most dangerous combination value of two parallel pipe jacking top power is for [V i=10290kN, V j=9650kN], in this, as top power pre-control parameter when often organizing push pipe jacking construction, specifically comprise the following steps:
1. the modeling scope of FEM (finite element) model: in this case history, perpendicular to push pipe jacking direction width B=37m, the length of side d=4.2m of jacking counterforce acting surface, the distance s=12.2m between jacking counterforce acting surface and open caisson top.Therefore, the length L=35m of the open caisson back soil body, height h=18m.
2. model boundary condition: apply tangential even distributed force at z=-1m place, rear parados base and z=-1m place, two sides, simulate open caisson bottom surface and soil body frictional force, open caisson sidewall and soil body frictional force respectively; Z on 4, z=0 place jacking counterforce acting surface according to step 3) jacking order apply counter-force according to every 2 push pipes one group, remainder does not retrain; Two side x=-18.5m and x=+18.5m place, except z=-1m part, limit its x direction displacement; Y=0 place, bottom surface, except z=-1m part, limits the displacement in its y direction; Z=-20m place, the back side, limits its z direction displacement; Y=+18m place, earth's surface is the scope of freedom.
3. the soil body and rear parados are all simulated with three-dimensional hexahedron solid element, and soil body-shield machine system adopts the More's coulomb homalographic circle model considering elastic-plastic strain; Rear parados is pressed elastic body and is considered, does not consider its plastic strain.Between rear parados and the soil body, arrange the plane-plane contact characteristic of Contact surface element mould rigid body-beformable body, the friction factor between soil and concrete gets 0.3.
5) in this engineering jack-in process, following several measures are taked to ensure the slip casting effect of thixotropic slurry:
1. make the circle water flange that width is 25cm at inlet and outlet cave place, in hole, separately make a circle water-stopping steel collar be attached thereto.Open portal, when head enters hole, start mud jacking.
2. be provided with 4 synchronous grouting holes at development machine afterbody, be evenly arranged in 90 degree mutually at hoop.In whole pipeline, establish 1 to mend slurry section at interval of 2 pipes, each section totally 4 injected holes, all in Oblique 45 Degree orthogonal loop to arranged crosswise, utilize the mud jacking hole of head afterbody to carry out synchronous grouting, utilize the mud jacking hole on tube coupling to carry out benefit slurry, mend slurry and carry out successively in order.
3. according to geology exploration data, there is the stratum of part containing conglomerate stone in this engineering ground, has obvious adverse effect to jacking resistance.Swell soil, CMC powder chemistry paste), the weight ratio of soda ash and water is: 16%, 0.2%, 0.6%, 84%, the thixotropic slurry mixed and stirred leaves standstill and pours into after 24 hours again.
6) the measuring point layout plan of the open caisson back soil body is given in Fig. 6:
1. a soil pressure measuring point S-1 and displacement measuring points C-1 is respectively set between 1#, 3# jacking counter-force apart from rear parados 1m place; Between 2#, 4# jacking counter-force apart from rear parados 1m place, respectively arrange a soil pressure measuring point S-2 and displacement C-2, measuring point S-1, C-1, S-2, C-2 buried depth is apart from back soil body earth's surface 10m.Exposed test lead hollow brick brick work 0.5m × 0.5m on earth's surface goes along with sb. to guard him protection measurements.
2. after caisson structure back cover terminates, namely carry out burying underground of tester, inclinometer pipe and soil pressure sensor all adopt the method for boring backfill to bury underground.Tested point place soil solidifying is after 7 days, and carry out examination to it and survey, the reading of measuring point S-1, C-1, S-2, C-2 is all comparatively stable, and the numerical difference of continuous 3 times is all no more than 10% of average.After about 40 days, push pipe starts jacking construction, tests out initial value before this, gets the continuous statistical average recorded for 3 times.
3. during normal jacking, the monitoring frequency in each stage one day 2 times, the maximum monitor value at the data in Fig. 7 are measuring point in the jack-in process different depth place in each stage, shift value is all in-30mm ~+30mm scope, and soil pressure measured value is without exception, maximum value does not exceed 120kPa, does not need to take extra soil stabilization measure.
The soil deformation maximum value monitoring result provided in Fig. 7 shows that the maximum peak excursion of the open caisson back soil body in jack-in process is no more than 22mm, advantageously demonstrates the validity and reliability of the inventive method.The present invention's work progress of combining closely takes corresponding control measure, and need the extra operation increased few, can save duration, reduction expense, be a kind of simple and practical method of conservative control back soil body deformation of open caisson in pipe-jacking project.

Claims (10)

1. the back soil body deformation of open caisson control method that causes of jacking construction, is characterized in that, comprise the following steps:
1) well-points dewatering is implemented, by groundwater table is reduced to below open caisson bottom surface, to increase the friction of open caisson wall and bottom surface and soil layer at open caisson periphery;
2) strengthening the anchoring bottom open caisson in soil layer, by playing open caisson integral rigidity, realizing the raising of the geometric distortion harmony of open caisson under the power effect of top;
3) determine jacking order, adopt the jacking simultaneously of two parallel pipe jackings;
4) set up the simplification three-dimensional finite element model of open caisson and the back soil body thereof, adopt analysis method for stability determining step 3) in the most dangerous combination value [V of two parallel pipe jacking top power i, V j], in this, as top power pre-control parameter during jacking construction;
5) in jacking construction, adopt small-lead-tube advanced slip-casting technique, make the thixotropic slurry cover forming superperformance between push pipe outer wall and soil layer, play the effect of antifriction, thus reduce top power to the disturbing influence of the back soil body;
6) by step 3) the jacking order of the parallel pipe jacking determined, formulate monitoring scheme targetedly, before jacking construction, carry out point layout and monitoring, installation testing instrument in the back soil body, timely feedback information is to adjust construction parameter.
2. method according to claim 1, is characterized in that, described well-points dewatering, and the construction characteristic according to the hydrogeological conditions in place, engineering design requirements and well sinking chooses dewatering mode.
3. method according to claim 1, is characterized in that, the well depth of described dewatering well is H=H 1+ H 2+ H 3+ H 4+ ir 0, wherein: H is dewatering well well depth, H 1for caisson cutting edge is to surface distance, H 2for the requirement degree of depth at the bottom of precipitation water level distance open caisson, H 3for the active length of precipitation strainer, H 4for sediment tube length, i is hydraulic gradient, r 0for open caisson Equivalent Calculation radius.
4. method according to claim 3, is characterized in that, described dewatering well is 4m ~ 8m apart from the distance of open caisson wall.
5. method according to claim 1, is characterized in that, described step 2 specifically comprises:
2.1) with giant, groove reserved inside the borehole wall above sword pin is rinsed well, whole for surface concrete dabbing is exposed stone, be convenient to the combination of New-old concrete, reserved steel bar and baseplate reinforcing bar adopt and are welded to connect, the length of welding point jointing is more than or equal to 35d, and d is the larger diameter of Reinforcement;
2.2) castinplace pile of concrete drill hole is set bottom open caisson, to resist the slippage that top power may cause.
6. method according to claim 5, is characterized in that, described castinplace pile is connected with adopting inverted trapezoidal pile cover bottom open caisson, and stake top reinforcing bar anchors into open caisson base plate, and castinplace pile is uniformly distributed along perpendicular to push pipe jacking direction in each district lattice bottom open caisson.
7. method according to claim 1, is characterized in that, the top power V after the open caisson while described caused by jacking on parados iwith V jdifference be no more than 20%.
8. method according to claim 1, is characterized in that, described step 4 specifically comprises:
4.1) the modeling scope of FEM (finite element) model: get B perpendicular to push pipe jacking direction width, the length L of the open caisson back soil body is greater than 2d+2s, height h gets the distance of open caisson bottom surface to back soil body earth's surface, wherein: B is the width of open caisson, d is the length of side of jacking counterforce acting surface, and s is the distance between jacking counterforce acting surface to open caisson top;
4.2) computation model fringe conditions is as follows: apply tangential even distributed force at z=-t place, rear parados base and z=-t place, two sides, simulate open caisson bottom surface and soil body frictional force, open caisson sidewall and soil body frictional force respectively; Z on 4, z=0 place jacking counterforce acting surface according to step 3) jacking order apply counter-force respectively, remainder does not retrain; Two side x=-L/2 and x=+L/2 place, except z=-t part, limit its x direction displacement; Y=0 place, bottom surface, except z=-t part, limits the displacement in its y direction; Z=-L place, the back side, limits its z direction displacement; Y=h place, earth's surface is the scope of freedom;
4.3) soil body-shield machine system adopts the More's coulomb homalographic circle model considering elastic-plastic strain, and rear parados is pressed elastic body and considered, arranges the plane-plane contact characteristic of Contact surface element mould rigid body-beformable body between rear parados and the soil body.
9. method according to claim 1, is characterized in that, described step 5 specifically comprises:
5.1) arrange at inlet and outlet cave there is the antipriming of waterproof effect, and from going out hole mud jacking; Make interface tube sealing performance keep good, and guaranteeing that slurries are not bonded after avoiding pipe to enter the soil body while inlet and outlet cave seepage;
5.2) be evenly arranged 4 mud jacking holes at head afterbody hoop, uniform mud jacking hole on the three-joint pipe joint after head, and in units of every three joints, select a wherein pipe joint joint upper layout mud jacking hole;
5.3) the mud lubrication anti-friction agent containing swell soil, CMC, sodium carbonate and water is adopted to put on pipeline section sidewall and soil body contact site by injected hole.
10. method according to claim 1, is characterized in that, described step 6 specifically comprises:
6.1) according to site condition and the step 3 of the back soil body) jacking determined order, after the back soil body is pressed close to, parados place buries skew back pipe and soil pressure sensor underground in suitable place, earth's surface test lead adopts the mode of brick work brick wall and surrounding to isolate, and avoids destruction and the interference of suffering other working procedure;
6.2) tester sinks to design elevation at open caisson, carries out after back cover terminates, and at least starts jacking construction 7 days apart from push pipe; Process to be installed all terminated soil solidifying after at least 7 days, and carry out examination and survey with the availability verifying measuring point, require stable reading, the numerical difference of continuous 3 times is no more than 10% of average; Before jacking, same step test initial value will be carried out, using the initial value of the average of 3 secondary data now recorded as whole jack-in process at push pipe;
6.3) monitoring frequency one day 2 times, when the power of top reading is bigger than normal or abnormal conditions appear in earth's surface, suitably improves test frequency as required; Land movement should control in-30mm ~+30mm scope, using these data as judging that the back soil body is the need of the foundation of carrying out reinforcing; If desired, then after rear parados, vertical rotary churning pile reinforcing is carried out within the scope of B/2.
CN201410113955.8A 2014-03-25 2014-03-25 Control method for open caisson back soil deformation caused by pipe-jacking construction Pending CN104947649A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410113955.8A CN104947649A (en) 2014-03-25 2014-03-25 Control method for open caisson back soil deformation caused by pipe-jacking construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410113955.8A CN104947649A (en) 2014-03-25 2014-03-25 Control method for open caisson back soil deformation caused by pipe-jacking construction

Publications (1)

Publication Number Publication Date
CN104947649A true CN104947649A (en) 2015-09-30

Family

ID=54162671

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410113955.8A Pending CN104947649A (en) 2014-03-25 2014-03-25 Control method for open caisson back soil deformation caused by pipe-jacking construction

Country Status (1)

Country Link
CN (1) CN104947649A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105570534A (en) * 2016-02-22 2016-05-11 中国水利水电第十一工程局有限公司 Shallow-burial-depth pipe-jacking equipment capable of controlling ground structural deformation and construction method
CN105650345A (en) * 2016-03-14 2016-06-08 中国葛洲坝集团基础工程有限公司 Construction method and detection device for top pipe outer wall thixotropic slurry lubricating sleeve formation in loose covering layer
CN108951815A (en) * 2018-08-07 2018-12-07 中国十七冶集团有限公司 One kind being suitable for deformation monitoring and control method when road rain Sewage Pipe-Jacking Construction
CN109098725A (en) * 2018-08-25 2018-12-28 许明 A kind of rectangular shield machine with the native device of anti-back
CN109695262A (en) * 2019-01-20 2019-04-30 西南交通大学 A kind of prominent heavy experimental rig of simulation open caisson generation founding
CN112307551A (en) * 2020-11-09 2021-02-02 山西四建集团有限公司 Construction method for large-diameter long-distance mechanical pipe jacking counter force structure
CN113309524A (en) * 2021-03-19 2021-08-27 中铁四局集团有限公司 Method for controlling influence of rectangular pipe jacking tunneling in shallow soil-covered stratum on surrounding environment
CN114562276A (en) * 2022-02-28 2022-05-31 重庆大学 Rock jacking pipe construction method for reducing resistance by using underground water buoyancy
CN115046055A (en) * 2022-06-21 2022-09-13 北京住总集团有限责任公司 Pipe jacking settlement control system and method
WO2023092966A1 (en) * 2022-04-13 2023-06-01 中交第一航务工程局有限公司 Caisson structure, and construction method and use therefor

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105570534B (en) * 2016-02-22 2019-07-12 中国水利水电第十一工程局有限公司 Shallow overburden push pipe controls the equipment and construction method of ground structure deformation
CN105570534A (en) * 2016-02-22 2016-05-11 中国水利水电第十一工程局有限公司 Shallow-burial-depth pipe-jacking equipment capable of controlling ground structural deformation and construction method
CN105650345A (en) * 2016-03-14 2016-06-08 中国葛洲坝集团基础工程有限公司 Construction method and detection device for top pipe outer wall thixotropic slurry lubricating sleeve formation in loose covering layer
CN108951815A (en) * 2018-08-07 2018-12-07 中国十七冶集团有限公司 One kind being suitable for deformation monitoring and control method when road rain Sewage Pipe-Jacking Construction
CN109098725A (en) * 2018-08-25 2018-12-28 许明 A kind of rectangular shield machine with the native device of anti-back
CN109098725B (en) * 2018-08-25 2020-05-19 浙江中铁工程装备有限公司 Rectangular shield constructs machine with prevent back of body native device
CN109695262A (en) * 2019-01-20 2019-04-30 西南交通大学 A kind of prominent heavy experimental rig of simulation open caisson generation founding
CN112307551B (en) * 2020-11-09 2022-10-04 山西四建集团有限公司 Construction method for large-diameter long-distance mechanical pipe jacking counter force structure
CN112307551A (en) * 2020-11-09 2021-02-02 山西四建集团有限公司 Construction method for large-diameter long-distance mechanical pipe jacking counter force structure
CN113309524A (en) * 2021-03-19 2021-08-27 中铁四局集团有限公司 Method for controlling influence of rectangular pipe jacking tunneling in shallow soil-covered stratum on surrounding environment
CN113309524B (en) * 2021-03-19 2023-09-12 中铁四局集团有限公司 Control method for influence of rectangular pipe jacking tunneling of shallow earth stratum on surrounding environment
CN114562276A (en) * 2022-02-28 2022-05-31 重庆大学 Rock jacking pipe construction method for reducing resistance by using underground water buoyancy
CN114562276B (en) * 2022-02-28 2023-03-14 重庆大学 Rock jacking pipe construction method for reducing resistance by using underground water buoyancy
WO2023092966A1 (en) * 2022-04-13 2023-06-01 中交第一航务工程局有限公司 Caisson structure, and construction method and use therefor
CN115046055A (en) * 2022-06-21 2022-09-13 北京住总集团有限责任公司 Pipe jacking settlement control system and method
CN115046055B (en) * 2022-06-21 2024-05-28 北京住总集团有限责任公司 Push pipe settlement control system and method

Similar Documents

Publication Publication Date Title
CN104947649A (en) Control method for open caisson back soil deformation caused by pipe-jacking construction
CN104196034B (en) A kind of utilize steel sheet pile as the foundation ditch construction method in supporting cofferdam
CN103510551B (en) A kind of bridge deepwater foundation three-dimensional force model stress model test platform
CN102953341B (en) A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock
CN101818505B (en) Soil pressure testing method for a cutting edge of caisson
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN106381866A (en) Construction method of ultra-deep underground diaphragm wall in water-rich soft-soil area
CN102392458B (en) Piling beam cofferdam construction method used for bare rock foundation construction in water
CN102561406A (en) Construction method for controlling back soil body deformation of open caisson
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN102635113A (en) Construction method for hydraulic vibrating sinking pipe cast-in-place piles
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN102619206A (en) Foundation platform structure of bare rock and karst pile in deep water
CN103015429A (en) Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN205748469U (en) Many Information Field monitoring systems of a kind of reservoir landslide
CN113186903A (en) Combined pile structure and construction method for treating insufficient bearing capacity of deep foundation pit construction pile by adopting combined pile structure
CN109137885A (en) A kind of construction method of underground continuous wall
CN112227401A (en) Method for constructing bearing platform by filling stones in underwater stone abrupt slope area
CN202492854U (en) Foundation platform structures of deepwater bare rock and karstic piles
CN106149673A (en) Soak heavy-tamping method in advance in collapsible loess deep
CN203049443U (en) High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer
CN110245426B (en) Finite element refined simulation method for pipe gallery structure pipe jacking construction
CN106498957A (en) Steel sheet pile cofferdam construction platform and integral construction method
CN106758759B (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN103806444A (en) Soft soil layer rotary excavating pile construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150930

WD01 Invention patent application deemed withdrawn after publication