CN111335640A - Construction method for preventing guide wall from sputtering floating slurry - Google Patents

Construction method for preventing guide wall from sputtering floating slurry Download PDF

Info

Publication number
CN111335640A
CN111335640A CN202010195446.XA CN202010195446A CN111335640A CN 111335640 A CN111335640 A CN 111335640A CN 202010195446 A CN202010195446 A CN 202010195446A CN 111335640 A CN111335640 A CN 111335640A
Authority
CN
China
Prior art keywords
guide wall
thin paper
plastic thin
concrete
adhesive tape
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010195446.XA
Other languages
Chinese (zh)
Inventor
贺英峰
解鹏飞
吴纯旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN202010195446.XA priority Critical patent/CN111335640A/en
Publication of CN111335640A publication Critical patent/CN111335640A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Abstract

The invention discloses a construction method for preventing a guide wall from sputtering laitance, and belongs to the technical field of building construction. The method comprises the following steps: the method comprises the following steps: after a concrete construction joint is formed, a double-faced adhesive tape is pasted along the edge of the construction joint before formwork erection; step two: sticking a layer of plastic thin paper on the double-faced adhesive tape to enable the screw on the lower guide wall to penetrate through the plastic thin paper; step three: when a formwork is erected, the formwork deviates 250-300 mm towards the lower guide wall and is continuously reinforced by using a screw of the lower guide wall; step four: and after the concrete pouring is finished, taking down the plastic thin paper. According to the invention, the double faced adhesive tape is pasted on the edge of the concrete construction joint, and the plastic thin paper layer is pasted on the double faced adhesive tape, so that the plastic thin paper can be vertically downward to support the formwork, and the laitance can be splashed onto the plastic thin paper when the concrete is poured.

Description

Construction method for preventing guide wall from sputtering floating slurry
Technical Field
The invention relates to the technical field of building construction, in particular to a construction method for preventing a guide wall from sputtering laitance.
Background
The floating slurry is a layer of slurry floating on the surface of concrete after the concrete is cast and molded, generally, particles deposited on the surface along with water secretion in the concrete with large water cement and poor working performance consist of hydrated and condensed cement and fine particles in sand, contain a large amount of water, and a porous loose layer is left after the water is evaporated. The surface of the concrete is easy to cause sand and crack, the strength and the impermeability of the concrete are affected, when the concrete needs to be continuously poured or jointed, the concrete needs to be removed to strengthen the adhesion between the newly poured concrete and the previously poured concrete, and the lower guide wall needs to avoid slurry leakage and slurry sputtering so as not to affect the engineering quality.
Disclosure of Invention
1. Technical problem to be solved by the invention
The construction method can effectively avoid the laitance generated by pouring the concrete while not influencing the attaching degree of the template and reduce the labor cost generated by later cleaning.
2. Technical scheme
In order to achieve the purpose, the technical scheme provided by the invention is as follows:
the invention relates to a construction method for preventing a guide wall from sputtering floating slurry, which comprises the following steps:
the method comprises the following steps: after a concrete construction joint is formed, a double-faced adhesive tape is pasted along the edge of the construction joint before formwork erection;
step two: sticking a layer of plastic thin paper on the double-faced adhesive tape to enable the screw on the lower guide wall to penetrate through the plastic thin paper;
step three: when a formwork is erected, the formwork deviates 250-300 mm towards the lower guide wall and is continuously reinforced by using a screw of the lower guide wall;
step four: and after the concrete pouring is finished, taking down the plastic thin paper.
3. Advantageous effects
Compared with the prior art, the technical scheme provided by the invention has the following beneficial effects:
according to the invention, the double faced adhesive tape is pasted on the edge of the concrete construction joint, and the plastic thin paper layer is pasted on the double faced adhesive tape, so that the plastic thin paper can be vertically downward to support the formwork, and the laitance can be splashed onto the plastic thin paper when the concrete is poured.
Drawings
FIG. 1 is a plan view of a double-sided adhesive tape application location of the present invention;
FIG. 2 is a perspective view of a double-sided adhesive tape applying position of the present invention;
FIG. 3 is a plan view of a plastic tissue application location of the present invention;
FIG. 4 is a perspective view of a plastic tissue application site of the present invention;
FIG. 5 is a plan view of the screw mounting position of the present invention;
FIG. 6 is a perspective view of the screw mounting location of the present invention;
fig. 7 is a partial sectional view of the screw installation of the present invention.
Detailed Description
The invention is further described with reference to the following figures and examples:
example 1
As can be seen from fig. 1-2, the construction method for preventing the guide wall from sputtering floating slurry of the embodiment includes the steps of:
the method comprises the following steps: as can be seen from fig. 1-2, the position a in the figure is the installation position of the double faced adhesive tape, after the concrete construction joint is formed, the double faced adhesive tape is pasted along the edge of the construction joint before the formwork is erected;
step two: 3-4, the position B is the plastic tissue installation position, and a layer of plastic tissue is adhered to the double-faced adhesive tape, so that the screw on the lower guide wall passes through the plastic tissue;
step three: as can be seen from fig. 5-7, the position C in the figure is the screw installation position, and when the formwork is supported, the formwork deviates 250 mm-300 mm from the lower guide wall and is continuously reinforced by using the screws of the lower guide wall;
step four: and after the concrete pouring is finished, taking down the plastic thin paper.
The concrete construction joints are kept at positions where the structure is less stressed and convenient to construct, and when the horizontal construction joints are arranged in layers, the positions and the interval time of the horizontal construction joints are determined according to the temperature crack control requirement in the concrete pouring process, the concrete supply capacity, the construction of the steel bar engineering, the installation of embedded pipes and other factors except that the horizontal construction joints meet the design requirement.
According to the invention, the double faced adhesive tape is pasted on the edge of the concrete construction joint, and the plastic thin paper layer is pasted on the double faced adhesive tape, so that the plastic thin paper can be vertically downward to support the formwork, and the laitance can be splashed onto the plastic thin paper when the concrete is poured.
The present invention and its embodiments have been described above schematically, without limitation, and what is shown in the drawings is only one of the embodiments of the present invention, and the actual structure is not limited thereto. Therefore, if the person skilled in the art receives the teaching, without departing from the spirit of the invention, the person skilled in the art shall not inventively design the similar structural modes and embodiments to the technical solution, but shall fall within the scope of the invention.

Claims (1)

1. A construction method for avoiding guide wall sputtering laitance is characterized in that: the method comprises the following steps:
the method comprises the following steps: after a concrete construction joint is formed, a double-faced adhesive tape is pasted along the edge of the construction joint before formwork erection;
step two: sticking a layer of plastic thin paper on the double-faced adhesive tape to enable the screw on the lower guide wall to penetrate through the plastic thin paper;
step three: when a formwork is erected, the formwork deviates 250-300 mm towards the lower guide wall and is continuously reinforced by using a screw of the lower guide wall;
step four: and after the concrete pouring is finished, taking down the plastic thin paper.
CN202010195446.XA 2020-03-19 2020-03-19 Construction method for preventing guide wall from sputtering floating slurry Pending CN111335640A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010195446.XA CN111335640A (en) 2020-03-19 2020-03-19 Construction method for preventing guide wall from sputtering floating slurry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010195446.XA CN111335640A (en) 2020-03-19 2020-03-19 Construction method for preventing guide wall from sputtering floating slurry

Publications (1)

Publication Number Publication Date
CN111335640A true CN111335640A (en) 2020-06-26

Family

ID=71182515

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010195446.XA Pending CN111335640A (en) 2020-03-19 2020-03-19 Construction method for preventing guide wall from sputtering floating slurry

Country Status (1)

Country Link
CN (1) CN111335640A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859260A (en) * 2017-10-31 2018-03-30 浙江品宏涂装有限公司 A kind of wall surface spraying technique
CN108532631A (en) * 2018-05-28 2018-09-14 中国十七冶集团有限公司 Formwork reinforcement structure and construction method at a kind of underground pipe gallery horizontal construction joint
CN109137885A (en) * 2018-10-16 2019-01-04 中铁二十二局集团轨道工程有限公司 A kind of construction method of underground continuous wall
CN110512656A (en) * 2019-07-12 2019-11-29 中冶天工集团有限公司 A kind of waterproofing node method at outer wall of underground structure formwork erection and construction joint

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859260A (en) * 2017-10-31 2018-03-30 浙江品宏涂装有限公司 A kind of wall surface spraying technique
CN108532631A (en) * 2018-05-28 2018-09-14 中国十七冶集团有限公司 Formwork reinforcement structure and construction method at a kind of underground pipe gallery horizontal construction joint
CN109137885A (en) * 2018-10-16 2019-01-04 中铁二十二局集团轨道工程有限公司 A kind of construction method of underground continuous wall
CN110512656A (en) * 2019-07-12 2019-11-29 中冶天工集团有限公司 A kind of waterproofing node method at outer wall of underground structure formwork erection and construction joint

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杜福祥等: "成都来福士广场浅色饰面清水混凝土结构成品保护技术", 《施工技术》 *

Similar Documents

Publication Publication Date Title
CN110607809B (en) Waterproof construction method for basement of building engineering
CN207499403U (en) A kind of FS composite thermal-insulating exterior formworks system
CN106436893A (en) Fully-prefabricated structure and construction method thereof
CN101831985A (en) Precast concrete wallboard and preparation method thereof
CN104032771B (en) Attractive joint anti-crack construction method set up by a kind of underground structure
CN101818541A (en) Precast composite wallboard with door/window holes and manufacturing method thereof
CN206220238U (en) Fully-prefabricated assembled structure
CN112252462A (en) Construction method of concrete roof layer waterproof structure
CN110056097A (en) A kind of fiberglass gridding ultra-high performance concrete heat preservation decoration integrative assembling type outer wall plate
CN209397803U (en) A kind of removable steel bar girder laminated floor slab of UHPC ultra-high performance concrete
CN207685961U (en) Spliced gutter based on bellows
CN113529982A (en) Deformation joint waterproof construction method
CN111335640A (en) Construction method for preventing guide wall from sputtering floating slurry
CN204326522U (en) Insulation protection integrated non-dismantling formwork
CN112112295A (en) Reinforcing construction method for post-cast strip of post-sealed outer wall
CN103572786A (en) Pile head joint waterproof processing device and construction method thereof
CN110629801A (en) Construction method using vertical mold as base surface of pre-paved anti-sticking self-adhesive waterproof roll
CN109518769A (en) A kind of method and structure using PVC waterstop joint installation sewer pipe
CN211229512U (en) Formwork and formwork base body for pouring clear water concrete column
CN218990501U (en) Bathroom water stop ridge structure
CN219808506U (en) Waterproof structure of prefabricated side fascia horizontal joint of assembled building
CN219952281U (en) Water stop ridge with anti-leakage reinforced structure
CN220504284U (en) Prevent support template roof exempts from of fracture
CN215889364U (en) Accurate positioning device for beam and plate reserved vertical hole of construction building
CN109441060A (en) Tolerant noise-insulating warm-keeping composite pad

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200626