CN111851588A - A pipe jacking well structure and its construction method - Google Patents

A pipe jacking well structure and its construction method Download PDF

Info

Publication number
CN111851588A
CN111851588A CN202010675595.6A CN202010675595A CN111851588A CN 111851588 A CN111851588 A CN 111851588A CN 202010675595 A CN202010675595 A CN 202010675595A CN 111851588 A CN111851588 A CN 111851588A
Authority
CN
China
Prior art keywords
steel sheet
pipe jacking
purlins
sheet pile
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010675595.6A
Other languages
Chinese (zh)
Inventor
胡传鹏
张世浪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Original Assignee
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd filed Critical China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority to CN202010675595.6A priority Critical patent/CN111851588A/en
Publication of CN111851588A publication Critical patent/CN111851588A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

本发明公开了一种顶管井结构及其施工方法,包括多个用于竖直可拆插设在土内的钢板桩,多个所述钢板桩围合成中空的施工空间;所述施工空间内的钢板桩内侧固定设有至少一层围檩结构;所述围檩结构包括多个固定设于所述钢板桩内侧面的围檩,多个所述围檩依次固定且首尾连接,各所述围檩的底部均设有支撑件,相邻的围檩之间连接有角撑;所述钢板桩的下部设有沉井本体。本发明的顶管井结构及其施工方法既能发挥钢板桩施工方便、效率高的特点,同时也能发挥钢筋混凝土沉井刚度大、侧壁承载力高、整体性好以及安全性高等优点,能最大化的兼顾效率、经济以及安全,从而达到有效的缩短施工工期,降低工程造价的目的。

Figure 202010675595

The invention discloses a pipe jacking well structure and a construction method thereof, comprising a plurality of steel sheet piles that are vertically and detachably inserted into the soil, and the plurality of the steel sheet piles are enclosed to form a hollow construction space; The inner side of the steel sheet pile is fixed with at least one layer of surrounding purlin structure; the surrounding purlin structure includes a plurality of surrounding purlins fixed on the inner side of the steel sheet pile, a plurality of the surrounding purlins are fixed in sequence and connected end to end, each The bottoms of the purlins are all provided with support pieces, and gussets are connected between adjacent purlins; the lower part of the steel sheet pile is provided with a caisson body. The pipe jacking shaft structure and the construction method of the invention can not only take advantage of the advantages of convenient construction and high efficiency of steel sheet piles, but also take advantage of the advantages of high rigidity of reinforced concrete caisson, high side wall bearing capacity, good integrity and high safety. Maximize efficiency, economy and safety, so as to effectively shorten the construction period and reduce the project cost.

Figure 202010675595

Description

一种顶管井结构及其施工方法A pipe jacking well structure and its construction method

技术领域technical field

本发明涉及地下建筑结构及市政工程领域,特别是涉及一种顶管井结构及其施工方法。The invention relates to the field of underground building structures and municipal engineering, in particular to a pipe jacking well structure and a construction method thereof.

背景技术Background technique

由于环境治理投入的不足,加上生态环境系统较为脆弱,环境污染问题较突出。尤其在水环境领域,管网系统不完善,生活污水直接排放等现象仍旧普遍,水生态受损严重,环境隐患多。在管网工程的具体实施过程中,管道的施工方法应根据管道所处土层性质、管径、地下水位、附近地下和地上建筑物等因素,经技术、经济综合比较后确定。当具备开挖条件时,可采用明沟开挖形式敷设管道或采用支护开挖;当管道埋深较大且开挖工作面受限或由于土质情况而无法放坡时,可采用顶管或牵引等暗挖方式施工。Due to the lack of investment in environmental governance and the fragile ecological environment system, the problem of environmental pollution is more prominent. Especially in the field of water environment, the pipe network system is not perfect, the direct discharge of domestic sewage is still common, the water ecology is seriously damaged, and there are many environmental hazards. In the specific implementation process of the pipeline network project, the construction method of the pipeline should be determined after comprehensive comparison of technology and economy according to the characteristics of the soil layer where the pipeline is located, the diameter of the pipeline, the groundwater level, nearby underground and above-ground buildings and other factors. When the excavation conditions are met, the pipeline can be laid in the form of open trench excavation or the support excavation can be used; when the pipeline is buried deep and the excavation face is limited or cannot be graded due to soil conditions, pipe jacking or excavation can be used. Traction and other underground excavation methods for construction.

现有技术中为改善水环境用的管网,一般针对老城区现有污水管网进行改造。改造过程中,由于污水管网的管道除了部分主干管,大部分支管都深入到社区之中,如果选择在社区开挖,将会对附近居民的生活造成较大影响,同时由于社区道路狭窄,路两侧都是年代久远的民房,明挖施工存在较大的风险,因此暗挖工法在这些工程中是主要的管道施工工法。In the prior art, in order to improve the water environment, the pipe network is generally transformed for the existing sewage pipe network in the old city. During the renovation process, except for some main pipes, most of the branch pipes of the sewage pipe network are deep into the community. If you choose to excavate in the community, it will have a great impact on the lives of nearby residents. At the same time, due to the narrow roads in the community, There are old houses on both sides of the road, and open-cut construction has greater risks. Therefore, the open-cut construction method is the main pipeline construction method in these projects.

根据实际工程经验反馈,采用牵引方式施工的管道,管道在土层中呈现波浪起伏的状况,时间一长容易产生淤积从而影响排水效果,很多地区在选择暗挖工法时,优先选用顶管工法。顶管井结构一般利用沉井法或逆做法施工。其中沉井法施工时施工人员可以在井外作业,作业过程较安全,挖土量少对邻近建筑物的影响比较小,而逆作法需要开挖后现浇钢筋混凝土,施工前应进行降排水作业,施工工期长,对于地下水位较高、土质较差且周围环境较复杂的区域,故一般选用沉井工法施工顶管井。According to the feedback of actual engineering experience, the pipeline constructed by traction method will show undulations in the soil layer, which is easy to accumulate over time and affect the drainage effect. In many areas, when choosing the underground excavation method, the pipe jacking method is preferred. The pipe jacking well structure is generally constructed by the caisson method or the reverse method. Among them, the construction personnel can work outside the well during the construction of the caisson method, the operation process is relatively safe, and the impact of less soil excavation on the adjacent buildings is relatively small, while the reverse method requires in-situ reinforced concrete after excavation, and drainage should be carried out before construction. For the areas with high groundwater level, poor soil quality and complex surrounding environment, the caisson construction method is generally used to construct the pipe jacking well.

现有技术中的沉井施工工法,沉井下沉速度慢、沉井下沉过程中会导致周围土体下拉变形,局部地方还会产生流土涌砂,对周围邻近建构筑的基础稳定性会产生较大影响。此外,钢筋混凝土沉井以及其他相关的配套支护结构都不具有复用性,作为临时支护使用的费用高、浪费大。另一方面,在有些工程上也会采用钢板桩支护直接兼做顶管井,钢板桩支护有施工效率高的优势,但是钢板桩刚度小,作为顶管始发井时,如果顶力过大,钢板桩可能会产生较大变形,变形过大会导致上部钢支撑脱落,存在较大的施工风险。In the caisson construction method in the prior art, the sinking speed of the caisson is slow, the surrounding soil body will be pulled down and deformed during the sinking process of the caisson, and flow soil and sand will also be generated in some places, which will affect the foundation stability of the surrounding adjacent buildings. greater impact. In addition, the reinforced concrete caisson and other related supporting structures are not reusable, and the cost and waste of temporary support are high. On the other hand, in some projects, steel sheet pile support is also used directly as a pipe jacking well. Steel sheet pile support has the advantage of high construction efficiency, but the stiffness of steel sheet piles is small. When used as the starting well for pipe jacking, if the jacking force exceeds If the steel sheet pile is too large, the steel sheet pile may be deformed greatly. If the deformation is too large, the upper steel support will fall off, and there will be a greater construction risk.

综上,需要一种既能发挥钢板桩施工方便、效率高的特点,同时也能发挥钢筋混凝土沉井刚度大、侧壁承载力高、整体性好以及安全性高等优点的施工方法,同时,所使用临时支护能够多次的重复使用,最大化的兼顾效率、经济以及安全,从而达到有效的缩短施工工期,降低工程造价的目的。In conclusion, there is a need for a construction method that can not only take advantage of the convenience and high efficiency of steel sheet pile construction, but also take advantage of the advantages of high stiffness of reinforced concrete caisson, high sidewall bearing capacity, good integrity and high safety. The temporary support used can be reused many times to maximize efficiency, economy and safety, so as to effectively shorten the construction period and reduce the project cost.

发明内容SUMMARY OF THE INVENTION

为解决上述问题,本发明的目的是提供一种顶管井结构,该顶管井结构既能发挥钢板桩施工方便、效率高的特点,同时也能发挥钢筋混凝土沉井刚度大、侧壁承载力高、整体性好以及安全性高等优点,同时能够重复使用,最大化的兼顾效率、经济以及安全,从而达到有效的缩短施工工期,降低工程造价的目的;本发明的另外一个目的在于提供一种顶管井结构的施工方法。In order to solve the above-mentioned problems, the purpose of the present invention is to provide a pipe jacking well structure, which can not only play the characteristics of convenient construction and high efficiency of steel sheet piles, but also play a role in the high rigidity of the reinforced concrete caisson and the high bearing capacity of the side walls. It has the advantages of good integrity and high safety, and can be reused at the same time, maximizing efficiency, economy and safety, so as to effectively shorten the construction period and reduce the project cost; another purpose of the present invention is to provide a top Construction method of tube well structure.

为了实现上述目的,本发明提供一种顶管井结构,包括多个用于竖直可拆插设在土内的钢板桩,多个所述钢板桩围合成中空的施工空间;In order to achieve the above object, the present invention provides a pipe jacking well structure, comprising a plurality of steel sheet piles for vertical and detachable insertion in the soil, and the plurality of the steel sheet piles encloses a hollow construction space;

所述施工空间内的钢板桩内侧固定设有至少一层围檩结构;At least one layer of purlin structure is fixed on the inner side of the steel sheet pile in the construction space;

所述围檩结构包括多个固定设于所述钢板桩内侧面的围檩,多个所述围檩依次固定且首尾连接,各所述围檩的底部均设有支撑件,相邻的围檩之间连接有角撑;The purlin structure includes a plurality of purlins fixed on the inner side of the steel sheet pile, the plurality of purlins are fixed in sequence and connected end to end, the bottom of each purlin is provided with a support member, and the adjacent purlins are provided with support members. There are corner braces connected between the purlins;

所述钢板桩的下部设有沉井本体。The lower part of the steel sheet pile is provided with a caisson body.

作为优选方案,所述围檩设有四个,四个所述围檩围合成方形;As a preferred solution, the purlin is provided with four, and the four purlins are formed into a square shape;

所述围檩为工字钢。The purlin is I-beam.

作为优选方案,所述支撑件为钢牛腿;As a preferred solution, the support is a steel corbel;

所述钢牛腿包括水平布置且与所述围檩的底部固定连接的支撑板,所述支撑板的底部竖直固定设有三角形的肋板;The steel corbel includes a support plate arranged horizontally and fixedly connected with the bottom of the purlin, and the bottom of the support plate is vertically fixed with a triangular rib;

所述支撑板与所述肋板呈T型布置。The support plate and the rib are arranged in a T-shape.

作为优选方案,所述沉井本体与所述钢板桩的内壁之间填充有中粗砂。As a preferred solution, medium-coarse sand is filled between the caisson body and the inner wall of the steel sheet pile.

作为优选方案,所述沉井本体的底部设有沉井底板,所述沉井底板的底部设有封底混凝土;As a preferred solution, the bottom of the caisson body is provided with a caisson bottom plate, and the bottom of the caisson bottom plate is provided with bottom sealing concrete;

所述沉井本体上设有顶管后座墙。The caisson body is provided with a pipe jacking rear seat wall.

一种顶管井结构的施工方法,包括以下步骤:A construction method for a pipe jacking well structure, comprising the following steps:

S1,将多个经过防锈处理的钢板桩沉桩,多个所述钢板桩围合成施工空间;S1, a plurality of rust-proof treated steel sheet piles are piled, and a plurality of the steel sheet piles are enclosed into a construction space;

S2,移除所述施工空间的第一深度的土方,在所述钢板桩上设置围檩结构;S2, remove the earthwork of the first depth of the construction space, and set a purlin structure on the steel sheet pile;

首先设置支撑件,所述支撑件的上部设置多个呈环状布置的围檩;其次,相邻所述围檩上固定设置角撑;First, a support is provided, and a plurality of purlins arranged in a ring shape are arranged on the upper part of the support; secondly, a gusset is fixedly arranged on the adjacent said purlin;

S3,继续向下移除所述施工空间的第二深度的土方,设置围檩结构;S3, continue to remove the earthwork of the second depth of the construction space downward, and set the purlin structure;

S4,继续向下移除所述施工空间的第三深度的土方,依次设置多节沉井;S4, continue to remove the earthwork of the third depth of the construction space downward, and set multi-section caisson in turn;

S5,待全部井壁施工完成且基坑已经开挖至设计标高后,浇筑封底混凝土,去除积水后在所述封底混凝土上设置沉井底板。S5, after the construction of all the well walls is completed and the foundation pit has been excavated to the design elevation, the bottom sealing concrete is poured, and the caisson floor is set on the bottom sealing concrete after removing the accumulated water.

S6,顶管作业后,回填基坑并逐层拆除钢围檩、角撑和钢板桩。S6, after the pipe jacking operation, backfill the foundation pit and remove the steel purlins, gussets and steel sheet piles layer by layer.

作为优选方案,所述步骤1中,所述钢板桩沉桩前,应按设计图纸要求在现场放线定位,并设置导架,锁口内应填防水材料;As a preferred solution, in the step 1, before the steel sheet pile is piled, it should be positioned on the site according to the requirements of the design drawings, and a guide frame should be set up, and the lock opening should be filled with waterproof material;

所述钢板桩沉桩的垂直度偏差不应大于1/100。The verticality deviation of the steel sheet piles should not be greater than 1/100.

作为优选方案,所述第一深度为1米,所述第二深度为4米,所述第三深度为3米。As a preferred solution, the first depth is 1 meter, the second depth is 4 meters, and the third depth is 3 meters.

作为优选方案,所述步骤S4中,所述沉井本体的浇筑步骤为:准备刃脚的承垫;绑扎沉井钢筋并封装模板;模板封装后浇筑混凝土,待混凝土强度达到设计强度的75%后,可下沉沉井本体。As a preferred solution, in the step S4, the pouring steps of the caisson body are: preparing the bearing pad of the edge foot; binding the steel bars of the caisson and encapsulating the formwork; pouring concrete after the formwork is encapsulated, and waiting for the concrete strength to reach 75% of the design strength Afterwards, the caisson body can be sunk.

作为优选方案,沉井本体下沉方法采用挤土下沉,挖土均匀、对称,确保沉井平衡、均匀和稳定下沉;As a preferred solution, the subsidence method of the caisson body adopts the method of extruding the soil and excavating the soil evenly and symmetrically, so as to ensure the balanced, uniform and stable subsidence of the caisson;

下沉前,在沉井本体的井壁与钢板桩墙之间设置随沉井同步下沉的中粗砂。Before sinking, medium-coarse sand, which sinks synchronously with the caisson, is set between the shaft wall of the caisson body and the steel sheet pile wall.

与现有技术相比,本发明的有益效果在于:Compared with the prior art, the beneficial effects of the present invention are:

本发明的顶管井结构将钢板桩作为支护用于沉井施工方法中,采用多个竖直插设在土内的钢板桩围合成中空的施工空间,在施工空间内的钢板桩内侧固定设有至少一层围檩结构;围檩结构包括多个固定设于钢板桩内侧面的围檩,多个围檩依次固定且首尾连接,各围檩的底部均设有支撑件,相邻的围檩之间连接有角撑;钢板桩的下部设有沉井本体。在沉井施工完成后可依次的拆除钢围檩、角撑和钢板桩,对钢板桩回收再利用。采用钢板桩作为沉井支护,利用钢板桩施工方便快捷的特点,在顶管井基坑的上部5m到6m的范围内形成支护,然后利用沉井刚度大的特点,在基坑下部的4m到5m的范围内形成支护结构用于顶管井结构作业,从而尽可能的发挥钢板桩和沉井施工各自的优势,形成优势互补。The pipe jacking well structure of the present invention uses steel sheet piles as support in the caisson construction method, adopts a plurality of steel sheet piles vertically inserted in the soil to form a hollow construction space, and is fixedly arranged on the inner side of the steel sheet piles in the construction space. There is at least one layer of purlin structure; the purlin structure includes a plurality of purlins fixed on the inner side of the steel sheet pile, the plurality of purlins are fixed in sequence and connected end to end, the bottom of each purlin is provided with a support, and the adjacent purlins are A gusset is connected between the purlins; the lower part of the steel sheet pile is provided with a caisson body. After the construction of the caisson is completed, the steel purlins, gussets and steel sheet piles can be removed in sequence, and the steel sheet piles can be recycled and reused. Steel sheet piles are used as caisson support, and the steel sheet piles are convenient and quick in construction to form support within the upper 5m to 6m range of the foundation pit of the pipe jacking well. A support structure is formed within a range of 5m for the pipe jacking well structure operation, so as to maximize the respective advantages of steel sheet piles and caisson construction and form complementary advantages.

本发明的顶管井结构的施工方法既能发挥钢板桩施工方便、效率高的特点,同时也能发挥钢筋混凝土沉井刚度大、侧壁承载力高、整体性好以及安全性高等优点,钢板桩以及围檩结构能够回收再利用,以最大化的兼顾效率、经济以及安全,从而达到有效的缩短施工工期,降低工程造价的目的。The construction method of the pipe jacking shaft structure of the present invention can not only take advantage of the characteristics of convenient construction and high efficiency of steel sheet piles, but also take advantage of the advantages of high rigidity of reinforced concrete caisson, high side wall bearing capacity, good integrity and high safety. And the purlin structure can be recycled and reused to maximize efficiency, economy and safety, so as to effectively shorten the construction period and reduce the project cost.

附图说明Description of drawings

图1为本发明实施例中顶管井结构的结构示意图;1 is a schematic structural diagram of a pipe jacking well structure in an embodiment of the present invention;

图2为图1的俯视图;Fig. 2 is the top view of Fig. 1;

图3为围檩结构的结构示意图。Figure 3 is a schematic structural diagram of the purlin structure.

图中,1、钢板桩;2、钢牛腿;21、支撑板;22、肋板;3、钢围檩;4、钢角撑;5、沉井本体;6、中粗砂;7、封底混凝土;8、沉井底板;9、顶管后座墙。In the figure, 1, steel sheet pile; 2, steel corbel; 21, support plate; 22, rib; 3, steel purlin; 4, steel angle brace; 5, caisson body; 6, medium and coarse sand; 7, Back cover concrete; 8. caisson floor; 9. pipe jacking rear seat wall.

具体实施方式Detailed ways

下面结合附图和实施例,对本发明的具体实施方式作进一步详细描述。以下实施例用于说明本发明,但不用来限制本发明的范围。The specific embodiments of the present invention will be described in further detail below with reference to the accompanying drawings and embodiments. The following examples are intended to illustrate the present invention, but not to limit the scope of the present invention.

在本发明的描述中,需要理解的是,术语“上”、“下”、“左”、“右”、“顶”、“底”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。应当理解的是,本发明中采用术语“第一”、“第二”等来描述各种信息,但这些信息不应限于这些术语,这些术语仅用来将同一类型的信息彼此区分开。例如,在不脱离本发明范围的情况下,“第一”信息也可以被称为“第二”信息,类似的,“第二”信息也可以被称为“第一”信息。In the description of the present invention, it should be understood that the orientations or positional relationships indicated by the terms "upper", "lower", "left", "right", "top", "bottom", etc. are based on those shown in the accompanying drawings The orientation or positional relationship is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the indicated device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the present invention. It should be understood that the terms "first", "second", etc. are used in the present invention to describe various information, but these information should not be limited to these terms, which are only used to distinguish the same type of information from each other. For example, "first" information may also be referred to as "second" information, and similarly, "second" information may also be referred to as "first" information, without departing from the scope of the present invention.

本发明的顶管井结构的优选实施例,如图1所示,包括多个用于竖直可拆插设在土内的钢板桩1,多个钢板桩1围合成中空的施工空间;钢板桩1具体为平直状的杆状结构,其截面可以为方形或者半圆形等,在施工空间内的钢板桩1内侧固定设有至少一层围檩结构;围檩结构用于支撑和维护钢板桩1。The preferred embodiment of the pipe jacking well structure of the present invention, as shown in FIG. 1 , includes a plurality of steel sheet piles 1 for vertical and detachable insertion in the soil, and the plurality of steel sheet piles 1 encloses a hollow construction space; the steel sheet piles 1 Specifically, it is a straight rod-shaped structure, and its cross section can be square or semi-circular. At least one layer of purlin structure is fixed inside the steel sheet pile 1 in the construction space; the purlin structure is used to support and maintain the steel plate. Pile 1.

具体的,围檩结构包括多个固定设于钢板桩1内侧面的围檩3,多个围檩3依次固定且首尾连接,各个的围檩3与钢板桩1均为焊接固定,各围檩3的底部均设有支撑件,支撑件同时与钢板桩1和围檩固定连接,同时支撑件为钢铁材质,支撑件与钢板桩1和钢围檩焊接固定连接。相邻的围檩3之间连接有角撑4,以进一步的提高围檩结构的支撑强度;在钢板桩1的下部设有沉井本体5。Specifically, the surrounding purlin structure includes a plurality of surrounding purlins 3 fixed on the inner side of the steel sheet pile 1, the plurality of surrounding purlins 3 are fixed in sequence and connected end to end, each surrounding purlin 3 and the steel sheet pile 1 are welded and fixed, and each surrounding purlin The bottom of 3 is provided with support pieces, which are fixedly connected with the steel sheet pile 1 and the purlin at the same time, and the support piece is made of steel, and the support piece is fixedly connected with the steel sheet pile 1 and the steel purlin by welding. Angle braces 4 are connected between adjacent purlins 3 to further improve the supporting strength of the purlin structure;

本发明的顶管井结构在沉井施工完成后可依次的拆除围檩3、角撑4和钢板桩1,对钢板桩1回收再利用。采用钢板桩1作为沉井支护,利用钢板桩1施工方便快捷的特点,在顶管井基坑的上部5m到6m的范围内形成支护,然后利用沉井刚度大的特点,在基坑下部的4m到5m的范围内形成支护结构用于顶管井结构作业,从而尽可能的发挥钢板桩1和沉井施工各自的优势,形成优势互补。In the pipe jacking well structure of the present invention, the purlins 3, the angle braces 4 and the steel sheet piles 1 can be removed in sequence after the caisson construction is completed, and the steel sheet piles 1 can be recycled and reused. The steel sheet pile 1 is used as the support for the caisson, and the steel sheet pile 1 is used for convenient and fast construction to form support within the upper 5m to 6m range of the foundation pit of the pipe jacking well, and then take advantage of the high stiffness of the caisson. The supporting structure is formed within the range of 4m to 5m for the pipe jacking structure operation, so as to maximize the respective advantages of the steel sheet pile 1 and the caisson construction and form complementary advantages.

本发明的顶管井结构既能发挥钢板桩1施工方便、效率高的特点,同时也能发挥钢筋混凝土沉井本体刚度大、侧壁承载力高、整体性好以及安全性高等优点,钢板桩1以及围檩3结构能够回收再利用,以最大化的兼顾效率、经济以及安全,从而达到有效的缩短施工工期,降低工程造价的目的。The pipe jacking shaft structure of the present invention can not only take advantage of the characteristics of convenient construction and high efficiency of the steel sheet pile 1, but also take advantage of the advantages of high rigidity of the reinforced concrete caisson body, high side wall bearing capacity, good integrity and high safety. And the purlin 3 structure can be recycled and reused to maximize efficiency, economy and safety, so as to effectively shorten the construction period and reduce the project cost.

其中,本申请的实施例中,围檩3设有四个,围檩3具体为工字钢,四个围檩3围合成方形状,角撑4为板状结构,角撑4也为四个,分别倾斜设在围檩结构的四个角上,用于连接相邻的两个围檩3。Wherein, in the embodiment of the present application, there are four surrounding purlins 3, the surrounding purlins 3 are specifically I-beams, the four surrounding purlins 3 are enclosed in a square shape, the gusset 4 is a plate-like structure, and the gusset 4 is also four They are respectively inclined and arranged on the four corners of the purlin structure, and are used to connect two adjacent purlins 3 .

进一步的,支撑件2为钢牛腿,具体的,钢牛腿包括水平布置且与围檩3的底部固定连接的支撑板21,支撑板21与围檩4的底部可以焊接固定或者通过螺栓等紧固件固定连接,支撑板21的底部竖直固定设有三角形的肋板22,支撑板21与肋板22呈T型布置。肋板22用于支撑支撑板21,提高支撑板21的固定作用。Further, the support 2 is a steel corbel. Specifically, the steel corbel includes a supporting plate 21 that is arranged horizontally and is fixedly connected to the bottom of the purlin 3. The supporting plate 21 and the bottom of the purlin 4 can be fixed by welding or by bolts, etc. The fasteners are fixedly connected, the bottom of the support plate 21 is vertically fixed with a triangular rib plate 22, and the support plate 21 and the rib plate 22 are arranged in a T-shape. The rib plate 22 is used to support the support plate 21 to improve the fixing effect of the support plate 21 .

其中,沉井本体5与钢板桩1的内壁之间填充有中粗砂,中粗砂跟随沉井本体5同步下沉,便于沉井本体5的施工。The medium-coarse sand is filled between the caisson body 5 and the inner wall of the steel sheet pile 1 , and the medium-coarse sand sinks synchronously with the caisson body 5 to facilitate the construction of the caisson body 5 .

其中,本申请的沉井本体5的底部设有沉井底板8,沉井底板8的底部设有封底混凝土7;沉井本体5上设有顶管后座墙9。Wherein, the bottom of the caisson body 5 of the present application is provided with a caisson bottom plate 8, and the bottom of the caisson bottom plate 8 is provided with a bottom sealing concrete 7;

具体施工时,第一节沉井本体5下沉完成后,按同样的步骤施工下一节沉井本体5。待全部沉井本体5施工完成且基坑已经开挖至设计标高后,及时浇筑封底混凝土7,封底混凝土7可根据沉井的施工工法选择降水封底或者水下封底。封底混凝土7浇筑完成后,抽干沉井坑内积水,施工沉井底板8,完成顶管井的开挖工作。沉井底板8施工完成后,施工顶管后座墙9以及安装顶管设备并进行管道顶进作业,顶管作业完工后,根据需要施工相应的检查井,回填基坑并逐层拆除钢围檩、角撑等水平支撑结构。基坑按要求回填完成后回收钢板桩1,桩位的洞采用中砂或注浆填实。During the specific construction, after the sinking of the first section of the caisson body 5 is completed, the next section of the caisson body 5 is constructed according to the same steps. After the construction of all the caisson bodies 5 is completed and the foundation pit has been excavated to the design elevation, the bottom sealing concrete 7 is poured in time. The bottom sealing concrete 7 can be selected according to the construction method of the caisson. After the bottom sealing concrete 7 is poured, the accumulated water in the caisson pit is drained, the caisson bottom plate 8 is constructed, and the excavation of the pipe jacking well is completed. After the construction of the caisson floor 8 is completed, the rear seat wall 9 of the pipe jacking is constructed, the pipe jacking equipment is installed and the pipe jacking operation is carried out. Purlins, gussets and other horizontal support structures. After the foundation pit is backfilled as required, the steel sheet pile 1 shall be recovered, and the hole in the pile position shall be filled with medium sand or grouting.

本发明的顶管井结构的施工方法的实施例,包括以下步骤:The embodiment of the construction method of the pipe jacking well structure of the present invention comprises the following steps:

S1,将多个经过防锈处理的钢板桩1沉桩,多个所述钢板桩1围合成施工空间。S1 , driving a plurality of rust-proof treated steel sheet piles 1 to form a construction space.

施工钢板桩1前,应按设计图纸要求在现场放线定位,确保钢板桩1所围和的施工空间能满足后续沉井本体5施工的要求,钢板桩1沉桩前先进行防锈处理,具体可涂环氧煤沥青漆保护。锁口内应填防水材料。钢板桩1沉桩前应设置导架,以保证平面尺寸的准确。沉桩时垂直度偏差不应大于1/100,同时应保证锁口紧密。Before the construction of the steel sheet pile 1, the line should be set out on the site according to the requirements of the design drawings to ensure that the construction space enclosed by the steel sheet pile 1 can meet the requirements of the subsequent construction of the caisson body 5. Specific can be coated with epoxy coal tar paint protection. The lock should be filled with waterproof material. A guide frame should be set before the steel sheet pile 1 is driven to ensure the accuracy of the plane size. The verticality deviation should not be greater than 1/100 when driving the pile, and the lock should be tight.

S2,移除施工空间的第一深度的土方,在钢板桩1上设置围檩结构;S2, remove the earthwork of the first depth in the construction space, and set a purlin structure on the steel sheet pile 1;

首先设置支撑件21,支撑件21的上部设置多个呈环状布置的围檩3;其次,相邻围檩3上固定设置角撑4。First, a support member 21 is provided, and a plurality of purlins 3 arranged in a ring shape are arranged on the upper part of the support member 21 ;

钢板桩1施工完毕后进行土方开挖,开挖到约1米深时,施工第一道围檩结构。施工围檩3前先施工钢牛腿,钢牛腿包括支撑板21和肋板22,支撑板21和肋板22呈丁字形焊接固定,如图3所示,支撑板21和肋板22均需要与钢板桩1相焊接,焊缝质量等级为三级,须进行外观检查验收后方可进行下一步施工。在第一道围檩3及角撑4等水平支撑结构施工完成后继续向下开挖,开挖到约4米深时,施工第二个围檩结构,第二个围檩结构与第一个围檩结构的施工方法相同。After the construction of the steel sheet pile 1 is completed, earthwork excavation shall be carried out. When the excavation reaches a depth of about 1 meter, the first surrounding purlin structure shall be constructed. Before constructing the purlin 3, construct the steel corbel first. The steel corbel includes a support plate 21 and a rib plate 22. The support plate 21 and the rib plate 22 are welded and fixed in a T-shape. As shown in FIG. 3, the support plate 21 and the rib plate 22 are both It needs to be welded with the steel sheet pile 1, and the quality level of the welding seam is level 3. The next step of construction can be carried out after the appearance inspection and acceptance. After the construction of the horizontal supporting structures such as the first purlin 3 and the angle brace 4 is completed, continue to excavate downward. When the excavation reaches a depth of about 4 meters, construct the second purlin structure, which is the same as the first purlin structure. The construction method of each purlin structure is the same.

S3,继续向下移除施工空间的第三深度的土方,依次设置多节沉井本体5。沉井本体5施工可根据具体的地质情况合理选择采用排水下沉或不排水下沉。当沉井本体5的下沉深度范围内有地下水且土层中存在粉土或粉细砂层或沉井附近存在已有建筑物或构筑物,建议采用不排水下沉。S3, continue to remove the earthwork of the third depth in the construction space downward, and set the multi-section caisson body 5 in sequence. The construction of the caisson body 5 can reasonably choose to use drainage or undrained subsidence according to the specific geological conditions. When there is groundwater within the subsidence depth of the caisson body 5 and there is silt or silty sand layer in the soil layer, or there are existing buildings or structures near the caisson, it is recommended to use undrained subsidence.

具体的,第一节井壁本体5包含刃脚共约2.5m高,准备好刃脚的承垫设施后,绑扎沉井钢筋并封装模板。模板封装好后浇筑混凝土,等到本节沉井本体5浇筑的混凝土强度达到设计强度的75%后,开始下沉沉井本体5。沉井本体5下沉时宜采用挤土下沉,不得随意掏空刃脚,挖土应均匀、对称,采取有效措施保持沉井本体平衡、均匀和稳定下沉。沉井本体5下沉前应在沉井井壁与钢板桩1墙之间采用中粗砂6进行填充,中粗砂6跟随井壁5同步下沉。第一节沉井本体5下沉完成后,按照同样的方法施工下一节沉井本体5。Specifically, the first section of the shaft wall body 5 includes a total of about 2.5 m in height of the blade feet. After the cushion facilities for the blade feet are prepared, the caisson steel bars are bound and the formwork is packaged. After the formwork is packaged, concrete is poured, and the sinking of the caisson body 5 is started after the concrete strength of the caisson body 5 in this section reaches 75% of the design strength. When the caisson body 5 sinks, it is advisable to use extruding soil to sink, and the cutting edge should not be hollowed out at will. The excavation should be uniform and symmetrical, and effective measures should be taken to maintain the balance, uniform and stable sinking of the caisson body. Before the caisson body 5 sinks, medium-coarse sand 6 should be used to fill the space between the caisson shaft wall and the wall of the steel sheet pile 1 , and the medium-coarse sand 6 sinks synchronously with the well wall 5 . After the sinking of the first section of the caisson body 5 is completed, the next section of the caisson body 5 is constructed according to the same method.

S4,待全部井壁施工完成且基坑已经开挖至设计标高后,浇筑封底混凝土7,封底混凝土7可根据沉井本体5的施工方法选择降水封底或者水下封底,然后去除积水,在封底混凝土7上设置沉井底板8。最后,施工顶管后座墙9以及安装顶管设备并进行管道顶进作业。S4, after the construction of all the well walls is completed and the foundation pit has been excavated to the design elevation, pour the bottom sealing concrete 7, and the bottom sealing concrete 7 can be selected according to the construction method of the caisson body 5. A caisson floor 8 is arranged on the back cover concrete 7 . Finally, construct the pipe jacking rear seat wall 9 and install the pipe jacking equipment and carry out the pipe jacking operation.

S5,顶管作业后,回填基坑并逐层拆除围檩3、角撑4和钢板桩1。S5, after the pipe jacking operation, backfill the foundation pit and remove the purlins 3, the angle braces 4 and the steel sheet piles 1 layer by layer.

顶管作业完工后,根据需要施工相应的检查井,回填基坑并逐层拆除钢围檩3及角撑4等水平支撑结构。基坑按要求回填完成后方可回收钢板桩11,钢板桩11的桩位的洞采用中砂或注浆填实。After the pipe jacking operation is completed, the corresponding inspection wells shall be constructed according to the needs, the foundation pit shall be backfilled, and the horizontal supporting structures such as steel purlins 3 and angle braces 4 shall be removed layer by layer. After the foundation pit is backfilled as required, the steel sheet piles 11 can be recovered, and the holes in the pile positions of the steel sheet piles 11 are filled with medium sand or grouting.

本发明的顶管井结构的施工方法既能发挥钢板桩1施工方便、效率高的特点,同时也能发挥钢筋混凝土沉井本体刚度大、侧壁承载力高、整体性好以及安全性高等优点,钢板桩1以及围檩结构能够回收再利用,以最大化的兼顾效率、经济以及安全,从而达到有效的缩短施工工期,降低工程造价的目的。The construction method of the pipe jacking shaft structure of the present invention can not only take advantage of the advantages of convenient construction and high efficiency of the steel sheet pile 1, but also take advantage of the advantages of high rigidity of the reinforced concrete caisson body, high side wall bearing capacity, good integrity and high safety. The steel sheet pile 1 and the surrounding purlin structure can be recycled and reused to maximize efficiency, economy and safety, so as to effectively shorten the construction period and reduce the project cost.

以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明技术原理的前提下,还可以做出若干改进和替换,这些改进和替换也应视为本发明的保护范围。The above are only the preferred embodiments of the present invention. It should be pointed out that for those skilled in the art, without departing from the technical principle of the present invention, several improvements and replacements can be made. These improvements and replacements It should also be regarded as the protection scope of the present invention.

Claims (10)

1. A pipe jacking well structure is characterized by comprising a plurality of steel plate piles which are vertically and detachably inserted in soil, wherein a hollow construction space is defined by the steel plate piles;
at least one layer of enclosing purlin structure is fixedly arranged on the inner side of the steel sheet pile in the construction space;
the enclosing purlin structure comprises a plurality of enclosing purlins fixedly arranged on the inner side surfaces of the steel sheet piles, the plurality of enclosing purlins are sequentially fixed and connected end to end, the bottom of each enclosing purlin is provided with a support piece, and a corner brace is connected between every two adjacent enclosing purlins;
and the lower part of the steel sheet pile is provided with an open caisson body.
2. The pipe jacking well structure of claim 1, wherein the purlins are four, and four purlins enclose a square;
the enclosing purlin is made of I-shaped steel.
3. The pipe jacking well structure of claim 2, wherein said support member is a steel corbel;
the steel bracket comprises a supporting plate which is horizontally arranged and fixedly connected with the bottom of the enclosing purlin, and a triangular rib plate is vertically and fixedly arranged at the bottom of the supporting plate;
The supporting plate and the rib plate are arranged in a T shape.
4. The push bench structure of claim 1, wherein medium grit is filled between said caisson body and the inner wall of said steel sheet pile.
5. The push bench structure of claim 1, wherein a bottom plate of the open caisson is arranged at the bottom of the open caisson body, and bottom sealing concrete is arranged at the bottom of the open caisson plate;
and a jacking pipe rear seat wall is arranged on the open caisson body.
6. A pipe jacking well structure construction method according to any one of claims 1 to 5, comprising the steps of:
s1, piling a plurality of steel sheet piles subjected to rust prevention treatment, wherein the plurality of steel sheet piles enclose a construction space;
s2, removing earthwork of the first depth of the construction space, and arranging a surrounding purlin structure on the steel sheet pile;
firstly, arranging a support piece, wherein the upper part of the support piece is provided with a plurality of annularly arranged purlins; secondly, angle braces are fixedly arranged on the adjacent surrounding purlins;
s3, continuously removing earthwork of a second depth of the construction space downwards, and setting a surrounding purlin structure;
s4, continuously removing earthwork at a third depth of the construction space downwards, and sequentially arranging a plurality of sections of open caisson;
S5, after all well wall constructions are completed and the foundation pit is excavated to the designed elevation, pouring bottom sealing concrete, and setting a sunk well bottom plate on the bottom sealing concrete after removing accumulated water.
And S6, backfilling the foundation pit and removing the steel surrounding purlin, the angle brace and the steel sheet pile layer by layer after pipe jacking operation.
7. The pipe jacking well structure construction method according to claim 6, wherein in the step 1, before the steel sheet pile is sunk, the steel sheet pile is positioned by paying off on site according to the design drawing requirements, a guide frame is arranged, and waterproof materials are filled in the locking opening;
the verticality deviation of the steel plate pile sinking is not more than 1/100.
8. The pipe jacking well structure construction method according to claim 6, wherein the first depth is 1 m, the second depth is 4 m, and the third depth is 3 m.
9. The pipe jacking well structure construction method according to claim 6, wherein in the step S4, the step of pouring the caisson body is as follows: preparing a bearing pad of the blade foot; binding open caisson reinforcing steel bars and packaging a template; and pouring concrete after the template is packaged, and sinking the open caisson body after the strength of the concrete reaches 75% of the design strength.
10. The pipe jacking well structure construction method according to claim 9, wherein the sinking method of the sinking well body adopts soil squeezing sinking, the soil digging is uniform and symmetrical, and the balanced, uniform and stable sinking of the sinking well is ensured;
Before sinking, medium coarse sand which sinks synchronously along with the open caisson is arranged between the well wall of the open caisson body and the steel sheet pile wall.
CN202010675595.6A 2020-07-14 2020-07-14 A pipe jacking well structure and its construction method Pending CN111851588A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010675595.6A CN111851588A (en) 2020-07-14 2020-07-14 A pipe jacking well structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010675595.6A CN111851588A (en) 2020-07-14 2020-07-14 A pipe jacking well structure and its construction method

Publications (1)

Publication Number Publication Date
CN111851588A true CN111851588A (en) 2020-10-30

Family

ID=72983863

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010675595.6A Pending CN111851588A (en) 2020-07-14 2020-07-14 A pipe jacking well structure and its construction method

Country Status (1)

Country Link
CN (1) CN111851588A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113089689A (en) * 2021-04-25 2021-07-09 江苏天启建设有限公司 Working well with support system and construction method thereof
CN113186942A (en) * 2021-05-11 2021-07-30 中建八局第一建设有限公司 Pipe jacking well enclosure structure and excavation construction method
CN115233703A (en) * 2022-08-12 2022-10-25 中国五冶集团有限公司 Detachable pipe jacking working well support and construction process thereof
CN115492126A (en) * 2022-10-26 2022-12-20 中国电建集团西北勘测设计研究院有限公司 Steel sheet pile and vertical shaft combined foundation pit supporting structure and method
CN116043921A (en) * 2023-03-13 2023-05-02 中交上海航道局有限公司 Construction method for steel-concrete combined structure retaining wall of water supply and drainage top pipe well

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204199297U (en) * 2014-09-12 2015-03-11 中国建筑第八工程局有限公司 Bracing members axle force compensating device
CN204959771U (en) * 2015-09-25 2016-01-13 江苏东合南岩土科技股份有限公司 Prestressing force H shaped steel bearing structure
CN105714833A (en) * 2016-03-01 2016-06-29 江苏东合南岩土科技股份有限公司 Construction method of steel plate pile open caisson support
CN106013052A (en) * 2016-05-23 2016-10-12 江苏东合南岩土科技股份有限公司 Steel sheet pile and open caisson combined underground garage and construction method thereof
CN207619987U (en) * 2017-08-22 2018-07-17 浙江绩丰岩土技术股份有限公司 A kind of prefabricated foundation pit enclosure structure of environment-friendly type underground garage
CN212294747U (en) * 2020-07-14 2021-01-05 中国能源建设集团广东省电力设计研究院有限公司 Pipe jacking well structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204199297U (en) * 2014-09-12 2015-03-11 中国建筑第八工程局有限公司 Bracing members axle force compensating device
CN204959771U (en) * 2015-09-25 2016-01-13 江苏东合南岩土科技股份有限公司 Prestressing force H shaped steel bearing structure
CN105714833A (en) * 2016-03-01 2016-06-29 江苏东合南岩土科技股份有限公司 Construction method of steel plate pile open caisson support
CN106013052A (en) * 2016-05-23 2016-10-12 江苏东合南岩土科技股份有限公司 Steel sheet pile and open caisson combined underground garage and construction method thereof
CN207619987U (en) * 2017-08-22 2018-07-17 浙江绩丰岩土技术股份有限公司 A kind of prefabricated foundation pit enclosure structure of environment-friendly type underground garage
CN212294747U (en) * 2020-07-14 2021-01-05 中国能源建设集团广东省电力设计研究院有限公司 Pipe jacking well structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
段良策等: "沉井设计与施工", 31 May 2006, 第249-250页第一节, pages: 249 - 250 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113089689A (en) * 2021-04-25 2021-07-09 江苏天启建设有限公司 Working well with support system and construction method thereof
CN113186942A (en) * 2021-05-11 2021-07-30 中建八局第一建设有限公司 Pipe jacking well enclosure structure and excavation construction method
CN115233703A (en) * 2022-08-12 2022-10-25 中国五冶集团有限公司 Detachable pipe jacking working well support and construction process thereof
CN115233703B (en) * 2022-08-12 2024-10-18 中国五冶集团有限公司 Detachable pipe jacking working well support and construction process thereof
CN115492126A (en) * 2022-10-26 2022-12-20 中国电建集团西北勘测设计研究院有限公司 Steel sheet pile and vertical shaft combined foundation pit supporting structure and method
CN115492126B (en) * 2022-10-26 2024-07-05 中国电建集团西北勘测设计研究院有限公司 Foundation pit supporting structure and method for combining steel sheet piles and vertical shafts
CN116043921A (en) * 2023-03-13 2023-05-02 中交上海航道局有限公司 Construction method for steel-concrete combined structure retaining wall of water supply and drainage top pipe well
CN116043921B (en) * 2023-03-13 2024-07-16 中交上海航道局有限公司 Construction method for steel-concrete combined structure retaining wall of water supply and drainage top pipe well

Similar Documents

Publication Publication Date Title
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN111851588A (en) A pipe jacking well structure and its construction method
CN100572686C (en) The construction technology of hole support system in the hole
CN101538833B (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN101215834A (en) Construction Method of Outrigger Type Diaphragm Wall
CN105756091B (en) A Construction Method of Subway Station Foundation Pit Controlling the Deformation of Adjacent Buildings
CN203475440U (en) SMW stiffened wall inclined-supporting combined space enclosing structure for foundation pit
CN108678751B (en) Assembly type construction method of shield cutter head manhole by jacking and excavating firstly
CN212294747U (en) Pipe jacking well structure
JP2024037138A (en) Method for constructing large-span station by two-wing open type semi-covered excavation and semi-reverse construction
CN105332382B (en) Adjacent river foundation ditch builds island cofferdam clay water stop construction method
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN112064751A (en) Deep groove construction method for drainage pipeline
CN111236241A (en) Reinforcement and excavation method of subway foundation pit in soft and water-rich stratum based on half-cover excavation method
CN105926642B (en) A kind of Urban Underground pipe gallery pattern foundation pit supporting structure and underground structure external mold integral structure and construction method
CN110565686A (en) Construction method for penetrating river channel under pipe gallery
CN114232602A (en) Underground continuous pile construction process
CN118814811A (en) Circular deep foundation pit support method
CN113216215A (en) Deep groove support reverse construction method in complex environment
CN209941754U (en) High-voltage power pipe culvert in-situ protection structure
CN111549789A (en) Reinforcing structure for foundation pit support and construction method thereof
CN111236265A (en) A kind of foundation pit support system of one-side waterfront bridge and its construction method
CN207176702U (en) Suitable for the underwater support table construction foundation pit supporting construction under the conditions of Unfavorable geology
CN207469303U (en) A kind of removable assembled template peace tears operating system open

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination