CN202347842U - Hydraulic climbing template device of high-rise building - Google Patents

Hydraulic climbing template device of high-rise building Download PDF

Info

Publication number
CN202347842U
CN202347842U CN2011205230444U CN201120523044U CN202347842U CN 202347842 U CN202347842 U CN 202347842U CN 2011205230444 U CN2011205230444 U CN 2011205230444U CN 201120523044 U CN201120523044 U CN 201120523044U CN 202347842 U CN202347842 U CN 202347842U
Authority
CN
China
Prior art keywords
guide rail
climbing
hydraulic
frame
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011205230444U
Other languages
Chinese (zh)
Inventor
朱海生
朱海根
沈雪锋
张建清
沈建中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU INDUSTRIAL PARK XINGSHENG CONSTRUCTION Co Ltd
Original Assignee
SUZHOU INDUSTRIAL PARK XINGSHENG CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU INDUSTRIAL PARK XINGSHENG CONSTRUCTION Co Ltd filed Critical SUZHOU INDUSTRIAL PARK XINGSHENG CONSTRUCTION Co Ltd
Priority to CN2011205230444U priority Critical patent/CN202347842U/en
Application granted granted Critical
Publication of CN202347842U publication Critical patent/CN202347842U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a hydraulic climbing template device of a high-rise building. The hydraulic climbing template device comprises a guide rail connected with and attached to a wall, a moving beam connected with the guide rail, a template device connected above the moving beam, and a hydraulic-drive lifting device and a construction platform which are connected below the moving beam, wherein the guide rail is connected with the concreting wall at intervals by a wall attaching device, and step plates are uniformly distributed on the guide rail; the upper end and the lower end of a hydraulic drive cylinder are respectively connected with an upper climbing frame and a lower climbing frame, and concave chutes are formed on the inner side surfaces of the upper and lower climbing frames and are connected with the guide rail in a sliding way; and a pin roll is arranged between two side walls of frame bodies of the climbing frames and penetrates through a pin hole at the center of a stress block and a rotating handle, the front surface of the stress block is a trapezoid folding surface with a flat middle part and two oblique sides, the two oblique side surfaces of the stress block are intersected with the upper and lower stress surfaces of the stress block to form right angles, the stress block and the rotating handle are fixedly connected with each other by a small pin roll, and a pressure spring is connected between the rotating handle and the outer side of the frame body. The hydraulic climbing template device has the advantages of saving manpower and material resources and shortening construction period.

Description

A kind of highrise building hydraulic climbing shuttering device
Technical field
The utility model relates to a kind of high-building construction and uses the template field, and the template that can climb along concrete wall surface relates in particular to a kind of highrise building hydraulic climbing shuttering device.
Background technology
At present, climbing template device is a kind of template to be attached in the building structure, the device that successively promotes along with structure construction; Be adapted to highrise building or the building operations of towering structure cast-in-situ steel reinforced concrete vertical structure, traditional climbing template device has hydraulic slip-form device, electronic climbing frame device, common climbing apparatus and turning-over, and common climbing apparatus needs the hanging device next work plane that just can climb; The climbing frame guide rail that can only climb again can not jumping formwork, complex structure; Long construction period, Surface Quality of Concrete is bad, and safety, operability are undesirable; The template consumption is more, and efficient is lower, and cost is higher; Traditional sliding form apparatus can not be asked disconnected construction, and concrete surface is coarse, and operating personnel will possess higher professional knowledge.
The utility model content
The purpose of the utility model provides the hydraulically powered climbing template device of a kind of highrise building safe, reliable, that efficient is high; Solve the highrise building hydraulic climbing shuttering; It can be along the concreting metope next work plane that climbs; And solve traditional climbing frame can only climb guide rail, can not jumping formwork problem; Also solve traditional climbing template device complex structure simultaneously, long construction period, safety, operability is undesirable, the template consumption is more, efficient is lower and the cost problem of higher.
The technical scheme that the utility model adopts is:
A kind of highrise building hydraulic climbing shuttering device; Comprise the hydraulic-driven lifting appliance and the operation platform that connect below the guide rail that attached wall connects, the moving beam that is connected with guide rail, the plate device of moving beam top connection, the mobile crossbeam; It is characterized in that: guide rail whenever is connected with the concreting metope by wall-attaching equipment at a distance from one section, is evenly distributed with step plate on the guide rail; The hydraulic driving oil cylinder upper and lower end is connected with the upper and lower frame that climbs respectively, and the support body medial surface of the upper and lower frame that climbs has the spill chute that is slidingly connected with guide rail; Climbing has bearing pin between the support body side frames wall of frame; Bearing pin passes the pin-and-hole and the turning handle at force block center; The front of force block is middle flat, the oblique trapezoidal folding face in both sides; Two inclined-planes intersect with last stress surface and lower stress face respectively and are the right angle, and force block is fixedly connected through small clevis pin with head with turning handle, are connected stage clip between outside turning handle and its support body.
Mould pulls that device comprises template truss, template that is connected with template truss and the adjustable support that is connected with moving beam.
Operation platform comprises main upright support, regulates diagonal brace and cat ladder, also connects operation platform down below this operation platform.
The stage clip outside is with compression spring sleeve.
The utility model is compared the beneficial effect that is had with tradition construction jumping formwork:
The utility model passes through fluid pressure drive device along the attached wall guide rail, from a concreting metope; The operation platform, folding template truss, the one or many that utilize fluid pressure drive device to use climbing template device, operation platform, assembling reinforcement rise to next working face; When the Structural Engineering concrete reaches form removal intensity and after the demoulding, mould is pulled and do not landed, rely on plant equipment and supporter with template and the climbing apparatus one deck that upwards climbs; Locate fastening, circulation construction repeatedly.
The utility model is rationally formed one to plate device, template truss and operation platform, fluid pressure drive device, electric control gear, wall-attaching equipment and climbing device; Reasonable combination accomplishes that the template of each circulation is climbed, the up-down of template truss, operation platform; Compare with the tradition construction, its advantage is: save human and material resources, reduction of erection time.
The utility model connects upper and lower two framves that climb at the hydraulic driving oil cylinder two ends, the force block that climbs in the frame has last stress surface and lower stress face, not only can jumping formwork; The guide rail that also can climb has characteristics simple to operate, security of operation, has realized that climbing apparatus and plate device climb synchronously; The template consumption is few; Short construction period, Surface Quality of Concrete is good, and its safety, operability obviously improve.
The utility model has overcome common jumping formwork needs just can the climb trouble of next working face of hanging device, and time saving and energy saving, cost is low, has solved the climbing frame guide rail that can only climb, deficiency that can not jumping formwork.
Description of drawings
Fig. 1 is a kind of highrise building hydraulic climbing shuttering of the utility model device, structural representation;
Fig. 2 is a kind of highrise building hydraulic climbing shuttering of the utility model device, the side structure sketch map;
Fig. 3 is a kind of highrise building hydraulic climbing shuttering of the utility model device, the structural representation of hydraulic-driven lifting appliance during jumping formwork;
Fig. 4 is a kind of highrise building hydraulic climbing shuttering of the utility model device, the structural representation of hydraulic-driven lifting appliance when climbing guide rail;
Fig. 5 is a kind of highrise building hydraulic climbing shuttering of the utility model device, the force block structure chart during jumping formwork;
Fig. 6 is a kind of highrise building hydraulic climbing shuttering of the utility model device, the force block structure chart when climbing guide rail;
Fig. 7 is a kind of highrise building hydraulic climbing shuttering of the utility model device, the front view of the frame that climbs down;
Fig. 8 is a kind of highrise building hydraulic climbing shuttering of the utility model device, the upward view of the frame that climbs down.
Among the figure:
1, template, 2, the concreting metope, 3, wall-attaching equipment, 4, guide rail, 5, hydraulic driving oil cylinder, 6, the frame that climbs down; 7, step plate, 8, on the frame that climbs, 9, operation platform down, 10, cat ladder, 11, regulate diagonal brace, 12, main upright support; 13, moving beam, 14, adjustable support, 15, template truss, 61, force-bearing piece, 611, spigot surface, 612, go up stress surface; 613, lower stress face, 614, big pin-and-hole, 615, little pin-and-hole, 62, bearing pin, 63, support body, 64, compression spring sleeve; 65, stage clip, 66, hook, 67, turning handle, 68, chute, 69, connecting hole.
The specific embodiment
A kind of highrise building hydraulic climbing shuttering of the utility model device, the specific embodiment is:
See Fig. 1, Fig. 2; A kind of highrise building hydraulic climbing shuttering device; Comprise guide rail 4, the moving beam 13 that is connected with guide rail that attached wall connects, move the hydraulic-driven lifting appliance and the operation platform that connect below the plate device, moving beam of connection above the crossbeam; Guide rail 4 whenever is connected with concreting metope 2 by wall-attaching equipment 3 at a distance from one section, is evenly distributed with step plate 7 on the guide rail; Plate device comprises template truss 15, the template 1 that is connected with template truss 15, the adjustable support 14 that is connected with moving beam 13; Operation platform comprises main upright support 12, regulates diagonal brace 11, cat ladder 10, also connects operation platform 9 down below this operation platform.
See Fig. 3-8; The upper and lower side of hydraulic driving oil cylinder 5 respectively with on climb frame 8, the frame 6 that climbs is connected down; Support body 63 medial surfaces of the upper and lower frame that climbs have the spill chute 68 that is slidingly connected with guide rail 4; Climbing has bearing pin 62 between the support body side frames wall of frame, and bearing pin passes the big pin-and-hole 614 and turning handle 67 at force block center, and force block passes little pin-and-hole 615 with turning handle with small clevis pin with head and is fixedly connected; Be connected stage clip 65 between the hook 66 in turning handle 67 and the support body outside, stage clip 65 outsides also can be with compression spring sleeve 64.
See Fig. 5; Fig. 6; The spigot surface 611 of force block 61 is middle flat, the oblique trapezoidal folding face in both sides; Two inclined-planes are that trapezoidal two waists intersect with last stress surface 612 and lower stress face 613 respectively and are that right angle, force block center have and are used to connect the climb big pin-and-hole 614 and the little pin-and-hole 615 that is used to be connected turning handle of frame support body.
See Fig. 7, Fig. 8; Climb down have between the support body 63 side frames walls of frame one be used to connect force block and turning handle bearing pin 62; Support body 63 medial surfaces have one to be used for the spill chute 68 that is slidingly connected with guide rail; The support body outside have one be used to connect stage clip hook 66, support body top have one be used to connect hydraulic driving oil cylinder connecting hole 69.
The detailed process of the utility model is:
The first step, formwork, fluid concrete;
In second step, wall-attaching equipment, attached wall guide rail and template truss are installed;
The 3rd step, matched moulds, fluid concrete;
In the 4th step, move back mould, the lifting guide rail;
In the 5th step, fixed guide is pulled with the fluid pressure drive device mould that climbs;
The 6th step, matched moulds, fluid concrete;
The 7th step, wall-attaching equipment is installed, lift rail, the mould that climbs is pulled;
The 8th step, the cleaning template, matched moulds, vibrated concrete, a circulation finishes.
The detailed process of jumping formwork is:
See Fig. 3,5, turning handle 67 rotates around bearing pin, and the force block 61 lower stress faces 613 in the frame 6 that climbs down are pressed in above the step plate 7 of guide rail, by stage clip thrust are provided, and hydraulic driving oil cylinder 5 upwards stretches out, and the jacking moving beam climbs thereby drive template; Put in place and climb that force block is pressed in above the step plate 7 of guide rail in the frame 8 on the back, the template height that rises, hydraulic driving oil cylinder 5 shrinks; Frame 6 climbs under promoting; Make it accomplish an operation cycle above the step plate to last one, so circulation is climbed up to template and is put in place.
The detailed process of guide rail of climbing is:
See Fig. 4,6, turning handle 67 upwards rotates around bearing pin, and the last stress surface 612 of the force block 61 in the frame that climbs is supported on below the step plate 7 of guide rail; By stage clip thrust is provided, on the frame 8 that climbs motionless, hydraulic driving oil cylinder 5 stretches up and down, contractile motion; Drive guide rail 4 and promote, after putting in place, on climb force block supporting guide in the frame; Accomplish an operation cycle, so circulation is climbed up to guide rail and is put in place.

Claims (4)

1. highrise building hydraulic climbing shuttering device; Comprise the hydraulic-driven lifting appliance and the operation platform that connect below the guide rail that attached wall connects, the moving beam that is connected with guide rail, the plate device of moving beam top connection, the mobile crossbeam; It is characterized in that: guide rail whenever is connected with the concreting metope by wall-attaching equipment at a distance from one section, is evenly distributed with step plate on the guide rail; The hydraulic driving oil cylinder upper and lower end is connected with the upper and lower frame that climbs respectively, and the support body medial surface of the upper and lower frame that climbs has the spill chute that is slidingly connected with guide rail; Climbing has bearing pin between the support body side frames wall of frame; Bearing pin passes the pin-and-hole and the turning handle at force block center; The front of force block is middle flat, the oblique trapezoidal folding face in both sides; Two inclined-planes intersect with last stress surface and lower stress face respectively and are the right angle, and force block is fixedly connected through small clevis pin with head with turning handle, are connected stage clip between outside turning handle and its support body.
2. a kind of highrise building hydraulic climbing shuttering device according to claim 1 is characterized in that: mould pulls that device comprises template truss, template that is connected with template truss and the adjustable support that is connected with moving beam.
3. a kind of highrise building hydraulic climbing shuttering device according to claim 1 is characterized in that: operation platform comprises main upright support, regulates diagonal brace and cat ladder, also connects operation platform down below this operation platform.
4. a kind of highrise building hydraulic climbing shuttering device according to claim 1 is characterized in that: the stage clip outside is with compression spring sleeve.
CN2011205230444U 2011-12-15 2011-12-15 Hydraulic climbing template device of high-rise building Expired - Fee Related CN202347842U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011205230444U CN202347842U (en) 2011-12-15 2011-12-15 Hydraulic climbing template device of high-rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011205230444U CN202347842U (en) 2011-12-15 2011-12-15 Hydraulic climbing template device of high-rise building

Publications (1)

Publication Number Publication Date
CN202347842U true CN202347842U (en) 2012-07-25

Family

ID=46536854

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011205230444U Expired - Fee Related CN202347842U (en) 2011-12-15 2011-12-15 Hydraulic climbing template device of high-rise building

Country Status (1)

Country Link
CN (1) CN202347842U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103015706A (en) * 2012-11-08 2013-04-03 广西建工集团第五建筑工程有限责任公司 System for lifting elevator shaft mold and construction method for cast-in-place wall of elevator shaft
CN104695693A (en) * 2015-03-02 2015-06-10 赵金海 Hydraulic climbing type outer wall scaffold
CN105401529A (en) * 2015-12-18 2016-03-16 辽宁科技学院 Full-automatic bridge pier template lifting and locating device and method
CN106677524A (en) * 2017-01-17 2017-05-17 上海建工建集团有限公司 Force transfer device
CN108661310A (en) * 2018-06-07 2018-10-16 中建局集团建设发展有限公司 A kind of the interior wall climbing apparatus and its construction method of shear wall
CN110725533A (en) * 2019-10-14 2020-01-24 中交武汉港湾工程设计研究院有限公司 Novel climbing mechanism

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103015706A (en) * 2012-11-08 2013-04-03 广西建工集团第五建筑工程有限责任公司 System for lifting elevator shaft mold and construction method for cast-in-place wall of elevator shaft
CN103015706B (en) * 2012-11-08 2015-04-22 广西建工集团第五建筑工程有限责任公司 System for lifting elevator shaft mold and construction method for cast-in-place wall of elevator shaft
CN104695693A (en) * 2015-03-02 2015-06-10 赵金海 Hydraulic climbing type outer wall scaffold
CN105401529A (en) * 2015-12-18 2016-03-16 辽宁科技学院 Full-automatic bridge pier template lifting and locating device and method
CN105401529B (en) * 2015-12-18 2018-03-13 辽宁科技学院 A kind of full-automatic bridge abutment moulding plate lifting positioner device
CN106677524A (en) * 2017-01-17 2017-05-17 上海建工建集团有限公司 Force transfer device
CN108661310A (en) * 2018-06-07 2018-10-16 中建局集团建设发展有限公司 A kind of the interior wall climbing apparatus and its construction method of shear wall
CN108661310B (en) * 2018-06-07 2023-12-01 中建一局集团建设发展有限公司 Inner wall climbing formwork device of shear wall and construction method thereof
CN110725533A (en) * 2019-10-14 2020-01-24 中交武汉港湾工程设计研究院有限公司 Novel climbing mechanism

Similar Documents

Publication Publication Date Title
CN202347842U (en) Hydraulic climbing template device of high-rise building
CN100387796C (en) Automatic hydraulic climbing shuttering
CN201826525U (en) Climbing shuttering system device for buildings
CN202000646U (en) Self-lifting construction platform integrating vertical transportation device and mould frame
WO2013120419A1 (en) Hydraulic lifting self-climbing template system
CN100365237C (en) Autolifting type variable-shape diassembllable integrated lifting steel plateform system and construction method thereof
CN201962944U (en) Hydraulic climbing formwork for building construction
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN202627493U (en) Combined template for constructing elevator shaft
CN201703943U (en) Hydraulic climbing stair
CN107419746A (en) A kind of mobile formwork system and its construction method
CN202850484U (en) Safety mechanism for building construction climbing template
CN210002868U (en) hydraulic creeping formwork system
CN202248860U (en) Hydraulic climbing formwork system
CN205704617U (en) Precast beam hydraulic pressure opening template
CN202899608U (en) Climbing device of building construction hydraulic pressure template
CN112482317A (en) Door slot second-stage concrete self-climbing slip form pouring system and construction method
CN202689498U (en) Liftable scaffold for simple and easy building outer wall
CN203755173U (en) Formwork device used for hydraulic climbing of bridge high pier
CN203867198U (en) Slip equipment for high-rise steel structure transfer layer truss
CN212897492U (en) Climbing frame model
CN204609261U (en) Movable up-down builds scaffold by laying bricks or stones
CN211714541U (en) Special handling frame for installing shear wall template in elevator shaft
CN206800201U (en) The compound Hanging basket on front support of single cable plane
CN106065709B (en) Prefabricated concrete beam operating platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120725

Termination date: 20131215