CN202627493U - Combined template for constructing elevator shaft - Google Patents

Combined template for constructing elevator shaft Download PDF

Info

Publication number
CN202627493U
CN202627493U CN 201220278460 CN201220278460U CN202627493U CN 202627493 U CN202627493 U CN 202627493U CN 201220278460 CN201220278460 CN 201220278460 CN 201220278460 U CN201220278460 U CN 201220278460U CN 202627493 U CN202627493 U CN 202627493U
Authority
CN
China
Prior art keywords
formwork
elevator shaft
main
combined
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220278460
Other languages
Chinese (zh)
Inventor
彭旭
宋功业
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jianzhu Institute
Original Assignee
Jiangsu Jianzhu Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Jianzhu Institute filed Critical Jiangsu Jianzhu Institute
Priority to CN 201220278460 priority Critical patent/CN202627493U/en
Application granted granted Critical
Publication of CN202627493U publication Critical patent/CN202627493U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model relates to a combined template for constructing an elevator shaft, which belongs to the field of building templates. The combined template comprises four symmetrical main templates, lengthening templates which are connected to the two ends of the main templates, internal corner templates which are connected with the lengthening templates, a lifting frame, four symmetrical lengthening rods which are connected with the lifting frame, and main template supports which are arranged on the lengthening rods and are used for supporting the main templates. When the combined template operates, the main templates can be unfolded by placing the lifting frame and the lengthening rods at a horizontal position, and the size of the inner barrel of the elevator shaft, which is required by designing, can be realized by adjusting the lengths of the lengthening rods; and the lengthening templates are connected with the main templates and the internal corner templates through fasteners respectively. The combined template has the advantages that the template of the elevator shaft is convenient to assemble and disassemble, easy to operate, convenient to construct quickly, economic and practical, can be repeatedly used and has a remarkable economic benefit.

Description

The gang form that is used for construction of lift well
Technical field
The utility model relates to a kind of gang form that is used for construction of lift well, belongs to the construction formwork field.Be mainly used in the inner side template formwork construction of building construction of lift well.
Background technology
In the construction of elevator shaft template, adopt wooden form or combined steel template mostly, it is more loaded down with trivial details to construct; Holding time is long, needs material working tool a lot, and workman's amount of labour is big; Transport of materials stack and inconvenience, and material consumption is also bigger; Not economical rationality, and when construction safety of workers also be difficult to ensure, also can influence the duration sometimes.
Summary of the invention
For addressing the above problem, the utility model provides a kind of gang form that is used for construction of lift well.
The utility model is realized with following technical scheme: a kind of gang form that is used for construction of lift well; It comprises four symmetries master module, be connected the master module two ends the lengthening template, with the internal corner formwork that is connected of lengthening template, the extension bar of four symmetries that also comprise upending frame, are connected, be installed in the master module support that is used to support master module on the extension bar with upending frame; Described master module is made up of steel frame and the panel that is installed on the steel frame, steel frame is stupefied by last horizontal stroke, the limit perpendicular stupefied, in erect the horizontal stupefied rectangular frame of forming under stupefied, the crosspiece; It is triangle that described master module supports, stupefied with last horizontal stroke, the down horizontal stupefied integral body that is welded into, and last horizontal stroke is stupefied, horizontal angle between stupefied is 30 ° down--and 45 °; Master module supports with extension bar hinged; Described extension bar is a turnbuckle, and master module supports, all adopt between the upending frame and be articulated and connected; Described upending frame by cross up and down, be fixed on the suspension ring at cross top and be fixed on about between the cross center pillar form.
Its structural principle and method for using are: utilize rod member to be articulated and connected and rotate principle easily, the distance that can regulate template and metope is directly lifted by crane the last layer working face with tower crane.During operation, as long as the cross and the extension bar of upending frame placed the purpose that just can reach supporting template on the horizontal plane.When needing adjustment elevator shaft inner core to touch size, as long as the turnbuckle of adjustment extension bar just can achieve the goal.There is internal corner formwork at the inner corner trim position, when template size during greater than 1.8 meters, increases the lengthening template and can regulate size.
During form removal, as long as unclamp internal corner formwork version and lengthening template, with tower crane upending frame is sling, template and elevator shaft inner core concrete will be thrown off.
The beneficial effect of the utility model is: make things convenient for the installation and removal of elevator shaft template, and simple to operate, be convenient to rapid construction, economical and practical, and can be repeatedly used remarkable in economical benefits.
Description of drawings
Below in conjunction with accompanying drawing and embodiment the structure of the utility model is further described.
Fig. 1 is that the elevator shaft die worker makes view;
Fig. 2 is the master module structural representation;
Fig. 3 upending frame structural representation.
Among the figure: the 1-master module; 1.1-panel; 1.2-last horizontal stroke is stupefied; 1.3-the limit is perpendicular stupefied; 1.4-in perpendicular stupefied; 1.5-crosspiece; 1.6-following horizontal stroke is stupefied; The 2-master module supports; 3 extension bars; The 4-upending frame; 4.1-suspension ring; 4.2-cross; 4.3-center pillar; The 3-extension bar; The 5-template that extends; The 6-internal corner formwork.
The specific embodiment
As shown in Figure 1, the gang form that is used for construction of lift well is made up of master module 1, master module support 2, extension bar 3, upending frame 4, lengthening template 5, internal corner formwork 6.Adopt fastener to connect between master module 1, lengthening template 5, the internal corner formwork 6.Master module 1 is made up of panel 1.1 and steel frame.Lengthening template 5 is measures of the lengthening template taked for the size that meets design requirement, and the lengthening template adopts combined steel formwork, and length is 3 meters.Width is respectively 100 millimeters, 150 millimeters, 200 millimeters, 300 millimeters several kinds, can be one during use, also can be polylith.Internal corner formwork 6 adopts the internal corner formwork of combined steel formwork, and width is 150 millimeters, and length is 3 meters.
As shown in Figure 2, steel frame is stupefied 1.2 by last horizontal stroke, the limit perpendicular stupefied 1.3, in perpendicular stupefied 1.4,1.5 times horizontal strokes of crosspiece stupefied 1.6 forms, master module is grown 3 meters, and is wide 1.5 meters.Panel 1.1 is processed by 1-1.5 millimeters thick steel plate, adopts between panel 1.1 and the steel frame to be welded to connect, or connects with self-tapping screw or rivet; Last horizontal stroke stupefied 1.2 with horizontal stupefied 1.6 be to process down with the square steel pipe of 1,5 meter of the length of side 30 millimeters long, and the limit perpendicular stupefied 1.3, in adopt between perpendicular stupefied 1.4 and be welded to connect, and can adopt between the template and be welded to connect, or with self-tapping screw or rivet connection; The perpendicular stupefied 1.3 steel plate bars by the 3-6 millimeters thick in limit are made, and long 3 meters of steel plate bar is wide 40 millimeters, and in the middle of 100 millimeters places apart from both ends and at interval 250-300 millimeter place is useful on the circular hole that is connected usefulness with fastener, 12 millimeters of diameters.In perpendicular stupefied 1.4 be to process with the square steel pipe of 1.5 meters of the length of side 30 millimeters long, and last horizontal stroke is stupefied 1.2, adopt between the horizontal stroke stupefied 1.6 down and be welded to connect.Crosspiece 1.5, spacing 500-600 millimeter, and the limit perpendicular stupefied 1.3, in adopts between perpendicular stupefied 1.4 and is welded to connect, when conflict with stupefied upper fastener connecting hole position, limit in the stupefied position of horizontal stroke, adjust the position of crosspiece.It is 30 millimeters the square steel pipe triangular support that is made by the length of side that master module supports 2, is welded into integral body with last horizontal stroke stupefied 1.2, down horizontal stupefied 1.6, and last horizontal stroke is stupefied 1.2, the angle between horizontal stupefied 1.6 is between 30 °-45 ° down; Between master module support 2 and the extension bar is hinged.
As shown in Figure 3, extension bar 3 is processed by turnbuckle, and master module supports 2, all adopt between the upending frame 4 and be articulated and connected.Upending frame 4 is made up of suspension ring 4.1, cross 4.2, center pillar 4.3; Suspension ring 4.1 are welded into annulus by the reinforcing bar of 30 millimeters of diameters, and internal radius is not less than 200 millimeters; Cross is welded by two long 300 millimeters No. 6 channel-section steels, and top cross 4.2 top center and suspension ring (4.1) are welded to connect; Be welded with the center pillar 4.3 that No. 6 channel-section steels are processed up and down between the cross 4.2.
During work, place horizontal level master module 1 to strut upending frame 4 and extension bar 3, the length of regulating extension bar 3 just can realize the interior cylinder size of elevator shaft of designing requirement.During the tube template formwork, also need internal corner formworks 6 to be installed in the elevator shaft,, between internal corner formwork 6 and master module, be provided with lengthening template 5 because cylinder size is had nothing in common with each other in the elevator shaft at four jiaos.Lengthening template 5 and master module 1, internal corner formwork 6 connect with fastener respectively.
Concrete curing is after the enough intensity during form removal; Earlier internal corner formwork 6 and lengthening template 5 fasteners are unclamped; With lifting appliance suspension ring 4.1 being sling, all is hinged because extension bar 3 supports 2 with upending frame 4 and master module, during lifting; Master module 1 will leave concrete surface, and template is moved on just can be as required.

Claims (8)

1.一种用于电梯井施工的组合模板,它包括四个对称的主模板(1)、连接在主模板两端的加长模板(5)、与加长模板(5)连接的阴角模板(6),还包括起吊架(4)、与起吊架(4)连接的四个对称的加长杆(3)、安装在加长杆(3)上用于支撑主模板(1)的主模板支撑(2);所述的主模板(1)、加长模板(5)、阴角模板(6)之间采用扣件连接;所述的主模板(1)由钢框架和安装在钢框架上的面板(1.1)组成,钢框架是由上横楞(1.2)、边竖楞(1.3)、中竖楞(1.4)、横档(1.5)下横楞(1.6)组成的矩形框架;所述的主模板支撑(2)是三角形支撑,与上横楞(1.2)、下横楞(1.6)焊接成整体,与上横楞(1.2)、下横楞(1.6)之间的夹角为30°--45°;主模板支撑(2)与加长杆(3)铰接;所述的加长杆(3)由花篮螺丝制成,与主模板支撑(2)、起吊架(4)之间均采用铰接连接;所述的起吊架(4)由上下十字架(4.2)、固定在上十字架(4.2)顶部的吊环(4.1)和固定在上下十字架(4.2)之间中柱(4.3)组成。 1. A combined formwork for elevator shaft construction, which includes four symmetrical main formworks (1), extended formwork (5) connected to both ends of the main formwork, internal corner formwork (6) connected to the extended formwork (5) ), also includes the lifting frame (4), four symmetrical extension rods (3) connected with the lifting frame (4), the main formwork support (2) installed on the extension rods (3) for supporting the main formwork (1) ); the main formwork (1), the extension formwork (5), and the inner corner formwork (6) are connected by fasteners; the main formwork (1) is composed of a steel frame and a panel installed on the steel frame ( 1.1), the steel frame is a rectangular frame composed of upper horizontal flute (1.2), side vertical flute (1.3), middle vertical flute (1.4), crosspiece (1.5) and lower horizontal flute (1.6); the main template The support (2) is a triangular support, which is welded together with the upper horizontal corrugated (1.2) and the lower horizontal corrugated (1.6), and the included angle with the upper horizontal corrugated (1.2) and the lower horizontal corrugated (1.6) is 30°-- 45°; the main formwork support (2) is hinged with the extension rod (3); the extension rod (3) is made of turnbuckle screws, and is hingedly connected with the main formwork support (2) and the lifting frame (4) The lifting frame (4) is composed of the upper and lower crosses (4.2), the suspension ring (4.1) fixed on the top of the upper cross (4.2) and the middle column (4.3) fixed between the upper and lower crosses (4.2). 2.根据权利要求1所述的用于电梯井施工的组合模板,其特征在于:所述的面板(1.1)由1-1.5毫米厚钢板制成,面板(1.1)与钢框架之间采用焊接连接,或用自攻螺丝或铆钉连接。 2. The combined formwork for elevator shaft construction according to claim 1, characterized in that: the panel (1.1) is made of 1-1.5 mm thick steel plate, and the panel (1.1) is welded to the steel frame Connect, or connect with self-tapping screws or rivets. 3.根据权利要求1所述的用于电梯井施工的组合模板,其特征在于:所述的上横楞(1.2)与下横楞(1.6)是用边长30毫米长1,5米的方钢管制成,与边竖楞(1,3)、中竖楞(1.4)之间采用焊接连接,与模板之间采用焊接连接、或用自攻螺丝或铆钉连接。 3. The combined template for elevator shaft construction according to claim 1, characterized in that: the upper horizontal corrugation (1.2) and the lower horizontal corrugation (1.6) are 1.5 meters long with a side length of 30 mm It is made of square steel pipe, and is connected with side vertical flute (1,3) and middle vertical flute (1.4) by welding, and connected with the formwork by welding, or by self-tapping screws or rivets. 4.根据权利要求1所述的用于电梯井施工的组合模板,其特征在于:所述的边竖楞(1.3)由3-6毫米厚的钢板条制作而成,钢板条长3米,宽40毫米,在距两端部100毫米处中间以及间隔250-300毫米处有用于扣件与连接用的圆孔。 4. The combined formwork used for elevator shaft construction according to claim 1, characterized in that: said side vertical corrugation (1.3) is made of 3-6 mm thick steel strips, the steel strips are 3 meters long, The width is 40 mm, and there are round holes for fasteners and connections in the middle of 100 mm from both ends and at an interval of 250-300 mm. 5.根据权利要求1所述的用于电梯井施工的组合模板,其特征在于:所述的中竖楞(1.4)是用边长30毫米、长1.5米的方钢管制成,与上横楞(1.2)、下横楞(1.6)之间采用焊接连接。 5. The combined formwork for elevator shaft construction according to claim 1, characterized in that: said middle vertical flute (1.4) is made of a square steel pipe with a side length of 30 mm and a length of 1.5 meters, and the upper horizontal The corrugation (1.2) and the lower horizontal corrugation (1.6) are connected by welding. 6.根据权利要求1所述的用于电梯井施工的组合模板,其特征在于:所述的横档(1.5)间的间距500-600毫米,与边竖楞(1.3)、中竖楞(1.4)之间采用焊接连接。 6. The combined template for elevator shaft construction according to claim 1, characterized in that: the distance between the crosspieces (1.5) is 500-600 mm, and the side vertical flute (1.3), the middle vertical flute ( 1.4) Welded connections are used between them. 7.根据权利要求1所述的用于电梯井施工的组合模板,其特征在于:所述的加长模板(5)采用组合钢模板。 7. The combined formwork used for elevator shaft construction according to claim 1, characterized in that: said elongated formwork (5) adopts a combined steel formwork. 8.根据权利要求1所述的用于电梯井施工的组合模板,其特征在于:所述的阴角模板(6)采用组合钢模板的阴角模板。 8. The composite formwork used for elevator shaft construction according to claim 1, characterized in that: the internal corner formwork (6) is a composite steel formwork internal corner formwork.
CN 201220278460 2012-06-14 2012-06-14 Combined template for constructing elevator shaft Expired - Fee Related CN202627493U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220278460 CN202627493U (en) 2012-06-14 2012-06-14 Combined template for constructing elevator shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220278460 CN202627493U (en) 2012-06-14 2012-06-14 Combined template for constructing elevator shaft

Publications (1)

Publication Number Publication Date
CN202627493U true CN202627493U (en) 2012-12-26

Family

ID=47380702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220278460 Expired - Fee Related CN202627493U (en) 2012-06-14 2012-06-14 Combined template for constructing elevator shaft

Country Status (1)

Country Link
CN (1) CN202627493U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104912558A (en) * 2015-05-29 2015-09-16 成都瑞达科恒科技有限公司 Walling crib
CN104947931A (en) * 2015-06-25 2015-09-30 中国水利水电第十四工程局有限公司 Integral turnover formwork for vertical shaft
CN105019908A (en) * 2015-05-29 2015-11-04 成都瑞达科恒科技有限公司 Internal-bracing well loop
CN105064678A (en) * 2015-09-01 2015-11-18 中民筑友有限公司 Formwork folding and unfolding mechanism, interior cylinder formwork and elevator shaft formwork device
CN106193586A (en) * 2016-08-19 2016-12-07 中国三冶集团有限公司 Elevator Telescopic folding Integral lifting core
CN110027096A (en) * 2019-04-04 2019-07-19 中民筑友智能装备科技有限公司 A kind of monoblock type window frame mold
CN114892679A (en) * 2022-05-24 2022-08-12 山东朋奎模板有限公司 Support system subway shaft steel form

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104912558A (en) * 2015-05-29 2015-09-16 成都瑞达科恒科技有限公司 Walling crib
CN105019908A (en) * 2015-05-29 2015-11-04 成都瑞达科恒科技有限公司 Internal-bracing well loop
CN104947931A (en) * 2015-06-25 2015-09-30 中国水利水电第十四工程局有限公司 Integral turnover formwork for vertical shaft
CN105064678A (en) * 2015-09-01 2015-11-18 中民筑友有限公司 Formwork folding and unfolding mechanism, interior cylinder formwork and elevator shaft formwork device
CN106193586A (en) * 2016-08-19 2016-12-07 中国三冶集团有限公司 Elevator Telescopic folding Integral lifting core
CN110027096A (en) * 2019-04-04 2019-07-19 中民筑友智能装备科技有限公司 A kind of monoblock type window frame mold
CN114892679A (en) * 2022-05-24 2022-08-12 山东朋奎模板有限公司 Support system subway shaft steel form

Similar Documents

Publication Publication Date Title
CN202627493U (en) Combined template for constructing elevator shaft
CN207268079U (en) A kind of building template
CN203499229U (en) Operating platform for construction of elevator shaft
CN204280974U (en) A kind of template hoisting device
CN202707066U (en) Manual hole digging pile wall-protecting integral template
CN204001416U (en) For the assemble type truss of the factory building of constructing
CN203834370U (en) Arch ring steel formwork trolley for circular arch culvert
CN203905488U (en) Concrete form support device for floor slab pouring
CN206554500U (en) Steel structure concrete, which is poured, uses adjustable transverse support bar
CN202925883U (en) Large size wooden formwork surrounding purlin device
CN203361641U (en) Combined type steel formwork of cast-in-place staircase
CN206530054U (en) A kind of cast-in-situ concrete columns hang mould
CN202493037U (en) Leveling device for concrete floor
CN201400997Y (en) Stepping type alternate supporting platform device
CN203856199U (en) Prefabricated square steel stepping die
CN203175037U (en) Internal formwork bracket for building
CN203905423U (en) Novel door frame beam supporting system
CN202299429U (en) Circulation adjustable angle iron stiffening system
CN203795845U (en) Portable support for hoisting form board for pipeline blocking
CN202248819U (en) Lightweight wooden structure construction scaffolding
CN102310475A (en) Height and width adjustable fast-dismounting top supported premoulding device
CN204826636U (en) Simple beam ear picking and shaping support
CN201627351U (en) Lifting operation table for construction
CN205224579U (en) Steel framework template and self -supporting truss board combination concrete quick detach system
CN205777484U (en) Elevator Integral lifting core

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121226

Termination date: 20140614

EXPY Termination of patent right or utility model