CN202689498U - Liftable scaffold for simple and easy building outer wall - Google Patents
Liftable scaffold for simple and easy building outer wall Download PDFInfo
- Publication number
- CN202689498U CN202689498U CN 201220327923 CN201220327923U CN202689498U CN 202689498 U CN202689498 U CN 202689498U CN 201220327923 CN201220327923 CN 201220327923 CN 201220327923 U CN201220327923 U CN 201220327923U CN 202689498 U CN202689498 U CN 202689498U
- Authority
- CN
- China
- Prior art keywords
- track
- working platform
- exterior wall
- simple construction
- lifting scaffold
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a liftable scaffold for a simple and easy building outer wall. The liftable scaffold consists of a track, a working platform and an electric hoist, wherein the track is a detachable two-rail circular pipe track and consists of a left foundation pillar, a right foundation pillar, a lower cross beam, a left stand column, a right stand column and an upper cross beam; a plurality of support frames and positioning pin holes are formed in the foundation pillars and the stand columns respectively; mounting holes are formed in the support frames; the working platform is connected with the track in a movable mode by movable connecting pieces; and lifters are arranged on the movable connecting pieces on left and right sides of the working platform. According to the liftable scaffold, the height of the track is increased with the lifting of a work position, and the working platform can be lifted freely on the track, so that the liftable scaffold has the advantages of saving time and materials along with safety, reliability, flexible operation, convenience for operation and the like.
Description
Technical field
The utility model belongs to the building weapon exercises, relates to the Lifting scaffold of a kind of external wall plastering, installation, finishing use.
Background technology
The external wall scaffold that uses at present sets up with steel pipe and connection fastener, generally will cover whole sidewalls, materials are many, and the time of setting up is long, the heavy difficulty of working, and scaffold and wall are directly unfixing, easily become flexible, rock, tilt even collapse and cause the accident.
Summary of the invention
For overcome existing many with external wall scaffold materials, set up the shortcomings such as difficulty, poor stability, the purpose of this utility model provides that a kind of materials are few, easy for installation, the liftable scaffold of good stability.
The technical scheme that the utility model is taked is:
1, simple construction exterior wall Lifting scaffold is comprised of track, working platform and electric block.Track is pipe double track sectional track, is comprised of left and right sides pilum and lower transverse beam, left and right pillar and top rail.Be respectively arranged with several bracing frames and dowel hole on pilum and the column, installing hole is arranged on the bracing frame.Working platform is flexibly connected by active connection and track.On the active connection of working platform the right and left lifter is set.
2, column lower end is provided with pile extension, and is provided with some as column for subsequent use.
3, working platform is box working platform, and five faces beyond its work plane are set to closed.
4, active connection is comprised of the shape of a hoof collar and channel-section steel, and working platform is fixed on the channel-section steel, and channel-section steel is fixed on the shape of a hoof collar, and the shape of a hoof collar is set with in orbit.
5, lifter is comprised of lifting arm and rod sleeve, and rod sleeve is fixed on the active connection.
6, top rail and lower transverse beam two ends respectively are provided with downward or upward perpendicular positioning stake, and there is pulley the below in the middle of the top rail, and there is hoisting ring the top, two ends.
The utility model simple construction exterior wall Lifting scaffold is along with the continuous rising of operating position, and its track also increases thereupon indirectly, and in orbit lifting of working platform freely.It is installed and using method is such: two foundation posts are inserted in the perpendicular positioning stake at lower transverse beam two ends, working platform is sleeved on the pilum by active connection.Pilum and column are coupled together two root posts pile extension is inserted respectively on the two foundation posts downwards, the perpendicular positioning stake at top rail two ends is inserted on two root posts downwards again, track just frame has been built up.Again the bracing frame on the track is fixed on the wall with swell fixture, electric block and pulley wire rope are installed, just can bring into use.Along with need of work from bottom to top, must progressively increase the height of track.At this moment, working platform can be risen to the highest point of track and fixing in orbit with fastening screw, with lifter top rail be sling from track.Two columns for subsequent use by its lower end pile extension is docked on the track, is restored top rail and are installed on two columns for subsequent use, principal post for subsequent use is fixed on the wall by bracing frame again, so just increased the height of track, remaining person analogizes.According to requirements of one's work, working platform can be risen or descends by electric block, and fixing in orbit with alignment pin.The utility model simple construction exterior wall Lifting scaffold have set up save time, material-saving, safe and reliable, flexible operation, the advantage such as work is convenient.
Description of drawings
Fig. 1 is the utility model elevation;
Fig. 2 is that (omission lifter) figure is looked on the utility model left side;
Fig. 3 is that (omission lower and upper cross-member) figure is looked at the utility model mansion
Fig. 4 is the utility model pillar construction figure;
Fig. 5 is the utility model top rail structure chart;
Fig. 6 is the utility model Lower Crossbeam Structure figure;
In the accompanying drawing, track (1), working platform (2), electric block (3), pilum (4), lower transverse beam (5), column (6), top rail (7), bracing frame (8), dowel hole (9), bracing frame installing hole (10), active connection (11), lifter (12) is to pile extension (13), the shape of a hoof collar (14), channel-section steel (15), lifting arm (16), rod sleeve (17), perpendicular positioning stake (18), pulley (19), hoisting ring (20), alignment pin (21).
The specific embodiment
With reference to attached Fig. 1 and 2, the utility model simple construction exterior wall Lifting scaffold is comprised of track (1), working platform (2) and electric block (3).Track is that the pipe double track is removable, and by left and right sides pilum (4) and lower transverse beam (5), left and right pillar (6) and top rail (7) form, and pilum, column and crossbeam adopt seamless steel pipe to make.Be respectively arranged with several bracing frames (8) and dowel hole (9) on pilum and the column, installing hole (10) is arranged on the bracing frame.Working platform is flexibly connected by active connection (11) and track.Device has lifter (12) on working platform the right and left active connection.With reference to accompanying drawing 4, column lower end is provided with docking post (13), and column need be made some as column for subsequent use.Working platform is case structure, can adopt angle bar to make, and except towards the work plane of wall, all the other each faces are closed.With reference to accompanying drawing 3, active connection is comprised of the shape of a hoof collar (14) and channel-section steel (15), and working platform is fixed on the channel-section steel, and channel-section steel is fixed on the shape of a hoof collar, and the shape of a hoof collar then is set with in orbit.The shape of a hoof collar is made of seamless steel pipe.Adopting channel-section steel to do middle the connection is in order to increase connection area, to improve its bonding strength.Lifter is comprised of lifting arm (16) and rod sleeve (17), all available steel pipe manufacturing.With reference to accompanying drawing 5 and 6, top rail and lower transverse beam two ends respectively are provided with perpendicular positioning stake (18) up or down, and the below is provided with pulley (19) in the middle of the top rail, and the two ends top is provided with hoisting ring (20), and all available steel pipe is made.
Claims (6)
1. simple construction exterior wall Lifting scaffold, formed by track (1), working platform (2) and electric block (3), it is characterized in that described track (1) is pipe double track sectional track, is comprised of left and right sides pilum (4) and lower transverse beam (5), left and right pillar (6) and top rail (7); Be respectively arranged with several bracing frames (8) and dowel hole (9) on pilum (4) and the column (6), installing hole (10) is arranged on the bracing frame; Described working platform (2) is flexibly connected by active connection (11) and track (1), is provided with lifter (12) on the active connection (11) of working platform (2) the right and left.
2. described simple construction exterior wall Lifting scaffold according to claim 1 is characterized in that described column (6) lower end is provided with pile extension (13), and is provided with some as column for subsequent use.
3. described simple construction exterior wall Lifting scaffold according to claim 1 is characterized in that described working platform (2) is box working platform, and five faces beyond its work plane are set to closed.
4. described simple construction exterior wall Lifting scaffold according to claim 1, it is characterized in that described active connection (11) is comprised of the shape of a hoof collar (14) and channel-section steel (15), working platform (2) is fixed on the channel-section steel (15), channel-section steel is fixed on the shape of a hoof collar (14), and the shape of a hoof collar is sleeved on the track (1).
5. described simple construction exterior wall Lifting scaffold according to claim 1 is characterized in that described lifter (12) is comprised of lifting arm (16) and rod sleeve (17), and rod sleeve (17) is fixed on the active connection (11).
6. described simple construction exterior wall Lifting scaffold according to claim 1, it is characterized in that described top rail (7) and lower transverse beam (5) two ends respectively are provided with perpendicular positioning stake (18) downward or upward, there is pulley (19) below in the middle of the top rail (7), and there is hoisting ring (20) top, two ends.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220327923 CN202689498U (en) | 2012-07-07 | 2012-07-07 | Liftable scaffold for simple and easy building outer wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220327923 CN202689498U (en) | 2012-07-07 | 2012-07-07 | Liftable scaffold for simple and easy building outer wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202689498U true CN202689498U (en) | 2013-01-23 |
Family
ID=47545134
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220327923 Expired - Fee Related CN202689498U (en) | 2012-07-07 | 2012-07-07 | Liftable scaffold for simple and easy building outer wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202689498U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103334383A (en) * | 2013-07-19 | 2013-10-02 | 济南金曰公路工程有限公司 | Elevating device special for viaduct maintenance construction |
CN110950278A (en) * | 2019-11-19 | 2020-04-03 | 沪东中华造船(集团)有限公司 | Pump tower construction platform |
CN110950279A (en) * | 2019-11-19 | 2020-04-03 | 沪东中华造船(集团)有限公司 | Operation method of pump tower construction platform |
-
2012
- 2012-07-07 CN CN 201220327923 patent/CN202689498U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103334383A (en) * | 2013-07-19 | 2013-10-02 | 济南金曰公路工程有限公司 | Elevating device special for viaduct maintenance construction |
CN103334383B (en) * | 2013-07-19 | 2015-07-08 | 济南金曰公路工程有限公司 | Elevating device special for viaduct maintenance construction |
CN110950278A (en) * | 2019-11-19 | 2020-04-03 | 沪东中华造船(集团)有限公司 | Pump tower construction platform |
CN110950279A (en) * | 2019-11-19 | 2020-04-03 | 沪东中华造船(集团)有限公司 | Operation method of pump tower construction platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106939707B (en) | A kind of restricted clearance large-scale steel structure supporting platform from method for improving | |
CN105544984A (en) | Large-span steel structure jig frame integrity slip construction process | |
CN202689498U (en) | Liftable scaffold for simple and easy building outer wall | |
CN202347842U (en) | Hydraulic climbing template device of high-rise building | |
CN203113793U (en) | Large formwork installation system of oblique structure | |
CN104989111A (en) | Construction method for steel structure high-rise hoisting | |
CN202577925U (en) | Lifting type platform in elevator shaft | |
CN204625045U (en) | A kind of steel structure hoisting door shaped stent formula hanging apparatus | |
CN202785387U (en) | Indoor cantilever crane | |
CN203462736U (en) | Operating platform for lift shaft structural steel construction | |
CN202881858U (en) | Jig frame used for vertical assembly construction of truss arc bridge | |
CN202023353U (en) | Integral lifting scaffold for building operations | |
CN205077842U (en) | Multi -use architecture support | |
CN203715115U (en) | Supporting point structure for self-hoisting system of portal crane | |
CN103711299A (en) | Liftable scaffold for building outer wall | |
CN203238967U (en) | Large steel structure frame whole lifting device | |
CN201915614U (en) | Integral electric climbing frame suitable for shear wall structure | |
CN201128882Y (en) | Lifting and supporting brackets integrated construction device for bridge arch rib | |
CN203701552U (en) | Attached scaffold for lifted through worm, gear and screw rod | |
CN109372242B (en) | Elevator shaft construction safety lifting platform device and using method | |
CN203654707U (en) | Detachable gantry installation frame | |
CN201826524U (en) | Frame column type hydraulic climbing mould | |
CN207774680U (en) | A kind of portable mechanism jacking apparatus | |
CN201738563U (en) | Hydraulic climbing scaffold for building construction | |
CN104695694A (en) | Worm and gear lead screw lifting type attached scaffold |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130123 Termination date: 20150707 |
|
EXPY | Termination of patent right or utility model |