CN202323112U - Ingot casing furnace group - Google Patents

Ingot casing furnace group Download PDF

Info

Publication number
CN202323112U
CN202323112U CN2011204364102U CN201120436410U CN202323112U CN 202323112 U CN202323112 U CN 202323112U CN 2011204364102 U CN2011204364102 U CN 2011204364102U CN 201120436410 U CN201120436410 U CN 201120436410U CN 202323112 U CN202323112 U CN 202323112U
Authority
CN
China
Prior art keywords
vacuum pump
furnace group
valve
ingot
ingot furnace
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011204364102U
Other languages
Chinese (zh)
Inventor
宋丽平
何娅妮
杨帅国
赖晓健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGXI SORNID HI-TECH Co Ltd
Original Assignee
JIANGXI SORNID HI-TECH Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGXI SORNID HI-TECH Co Ltd filed Critical JIANGXI SORNID HI-TECH Co Ltd
Priority to CN2011204364102U priority Critical patent/CN202323112U/en
Application granted granted Critical
Publication of CN202323112U publication Critical patent/CN202323112U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Compressors, Vaccum Pumps And Other Relevant Systems (AREA)
  • Crystals, And After-Treatments Of Crystals (AREA)

Abstract

The utility model relates to an ingot casting furnace group, which comprises ingot casing furnaces and a vacuum, wherein a valve is arranged at an outlet of a reserved port of the vacuum pump; the outlet of the reserved port of the vacuum pump is connected with a manually-operated valve; a outlet of the manually-operated valve is connected with a tee joint through a valve; and two ends of the two joint are connected with the vacuum pump of the ingot casting furnace group through connecting pipes. The ingot casting furnace group disclosed by the utility model solves the problem that a plurality of ingot casting furnace group cannot share one vacuum pump, has the characteristics of high efficiency and energy saving, and is simple in structure and easy to operate.

Description

A kind of ingot furnace group
Technical field
The utility model relates to a kind of ingot furnace group, particularly a kind of ingot furnace group of many shared vacuum pumps of ingot furnace.
Background technology
The silicon chip of polysilicon solar cell is that polycrystalline silicon material forms through ingot casting, slice processing, so ingot furnace is the visual plant in photovoltaic field.In the polycrystalline silicon material ingot casting process, to vacuumize usually in the body of heater and in that to vacuumize the silicon material that injects in the argon shield stove back not oxidized, so vacuum pump is the critical facility of DSS stove.Vacuum pump of present DSS stove configuration.Through long-term practice and analysis, vacuum pump of a DSS stove configuration, there is certain effect surplus in vacuum pump, when many vacuum pump effect surplus summations are too big, the waste that can bring the energy.
The effect of DSS stove when operation vacuum pump: along with vacuumizing, the gas that ingot furnace contains certain heat and impurity is discharged from outside the stove, and vacuum pump plays the impurity got rid of in the silicon material and the effect of heat radiation.
The utility model content
Its purpose of the utility model just is to provide a kind of ingot furnace group, thereby has solved the problem of many shared vacuum pumps of ingot furnace group.Characteristics with efficient height, save energy, and simple in structure, easy to operate.
The technical scheme that realizes above-mentioned purpose and take; Comprise ingot furnace and vacuum pump, the outlet of vacuum pump reserved opening is provided with valve, described vacuum pump reserved opening outlet connection hand movable valve; The manually-operated gate outlet connects threeway through valve, and said threeway two ends connect ingot furnace group vacuum pump through connecting leg.
Compared with prior art the utlity model has following advantage.
Owing to adopted the shared structure design of vacuum pump, thereby solved the problem of many shared vacuum pumps of ingot furnace group.Characteristics with efficient height, save energy, and simple in structure, easy to operate.
Description of drawings
Below in conjunction with accompanying drawing the utility model is done further to detail.
Accompanying drawing is this apparatus structure principle schematic.
Embodiment
This device comprises ingot furnace 8 and vacuum pump 1; The outlet of vacuum pump 1 reserved opening is provided with valve, shown in accompanying drawing, and described vacuum pump reserved opening outlet connection hand movable valve; The manually-operated gate outlet connects threeway 4 through valve 3, and said threeway 4 two ends connect ingot furnace group vacuum pump through connecting leg 2.
Described connecting leg 2 is a flexible pipe.
Described connecting leg 2 one ends are provided with plug 5.
The ingot casting process of ingot furnace is divided into heating, fusing, long crystalline substance, annealing, five stages of cooling.Approximately need 57 hours for 450Kg polycrystalline silicon material ingot casting, and the long brilliant stage needs 25 hours, accounts for 43% of total time; And the long brilliant stage is constant voltage (600mber) state; Temperature variation very little (having only 10-20 ℃), the air inlet switch of vacuum pump are in opens 40% constant position, and the control of giving vent to anger is that it should the stage main task; This moment, air output was very little, and a vacuum pump can satisfy many ingot furnaces during long brilliant stage.When a vacuum pump just can satisfy many ingot casting furnace superintendents crystalline substance stage needs, opening many vacuum pumps will inevitably waste energy.
During ingot furnace work, the corresponding whole unlatchings of vacuum pump.The vacuum pump exhaust capacity is in heating, and the task of fusing, annealing, cooling four-stage is suitable basically, but superfluous in long brilliant its ability of stage.Energy dissipation for fear of this moment; Just install a Y-tube 4 (seeing accompanying drawing) additional on the manual valve reserved opening with every vacuum pump; And the ingot furnace 1 vacuum pump 8 usefulness flexible pipes 2 in each district all are connected together, after the vacuum pump of a certain regional 10 ingot furnaces all is communicated with flexible pipe, manual valve cut out and (prevent when oily when impure in the vacuum pump; Cause that sealing property is bad to be had in the air admission extraction pipe, influence the production quality product).Grow crystalline substance during the stage when it is in, a unlatching wherein vacuum pump just can be satisfied the control requirement of giving vent to anger, and vacuum pump can have days off by turns like this, has not only practiced thrift electric energy but also help the vacuum pump prolongs life.
When many vacuum pumps all are connected together with flexible pipe, need every vacuum pump reserved opening is closed.For this reason, install valve 3 additional, the vacuum pump reserved opening is closed.Install valve 3 additional, can prevent effectively that vacuum pump oil and air from flowing into, realize the blocking-up of vacuum pump reserved opening place oil and air.
After many vacuum pumps all are communicated with flexible pipe; In case during wherein a certain damage; Other unspoiled vacuum pumps can provide service temporarily; Gain time for rushing to repair under not blowing out of the ingot casting state, the silicon ingot in the castingprocesses is not scrapped, obtain many vacuum pumps and all be communicated with the benefit of bringing with flexible pipe.
During work, vacuum pump 1 outlet valve 7 is opened with reserved opening outlet valve 6.

Claims (2)

1. ingot furnace group; Comprise ingot furnace (8) and vacuum pump (1); The outlet of vacuum pump (1) reserved opening is provided with valve, it is characterized in that described vacuum pump (1) reserved opening outlet connection hand movable valve; The manually-operated gate outlet connects threeway (4) through valve (3), and said threeway (4) two ends connect ingot furnace group vacuum pump through connecting leg (2).
2. the described a kind of ingot furnace group of root a tree name claim 1 is characterized in that described connecting leg (2) is a flexible pipe.
CN2011204364102U 2011-11-07 2011-11-07 Ingot casing furnace group Expired - Fee Related CN202323112U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011204364102U CN202323112U (en) 2011-11-07 2011-11-07 Ingot casing furnace group

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011204364102U CN202323112U (en) 2011-11-07 2011-11-07 Ingot casing furnace group

Publications (1)

Publication Number Publication Date
CN202323112U true CN202323112U (en) 2012-07-11

Family

ID=46435099

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011204364102U Expired - Fee Related CN202323112U (en) 2011-11-07 2011-11-07 Ingot casing furnace group

Country Status (1)

Country Link
CN (1) CN202323112U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385162A (en) * 2018-05-14 2018-08-10 扬州晶樱光电科技有限公司 A kind of intelligentized energy-saving apparatus for polycrystalline silicon ingot or purifying furnace pumped vacuum systems

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385162A (en) * 2018-05-14 2018-08-10 扬州晶樱光电科技有限公司 A kind of intelligentized energy-saving apparatus for polycrystalline silicon ingot or purifying furnace pumped vacuum systems

Similar Documents

Publication Publication Date Title
CN204779921U (en) Novel polycrystalline silicon side layering heating device
CN101629551B (en) Solar hot gas flow generating device
CN202323112U (en) Ingot casing furnace group
CN204027265U (en) The barn system of the solar energy stored with heat collection and air energy
CN207585382U (en) A kind of drag compensation formula Air-Cooling Island system
CN105674760A (en) Joint air-cooling system and control method
CN201474860U (en) Solar hot air flow power generating device
CN203976978U (en) A kind of novel diffusion furnace
CN203530506U (en) Silicon chip diffusion furnace for solar battery
CN203641890U (en) Heating device of natural gas transportation and distribution pressure regulator
CN101608869A (en) A kind of electrode baking forced cooling method and device
CN207442791U (en) Photovoltaic battery panel heat sink
CN209162249U (en) A kind of single crystal growing furnace cooling system
CN203065166U (en) Novel polycrystalline silicon ingot impurity removal device
CN202519366U (en) Diffusion air inlet pipeline of polycrystalline silicon solar photovoltaic cell silicon wafer
CN202989270U (en) Non-vacuum step-by-step pass type fast selenizing device
CN203518693U (en) Vertical sealed cooling tower
CN218203171U (en) Vacuumizing device of polycrystalline silicon ingot furnace
CN207504367U (en) A kind of composite energy-saving distribution power cabinet
CN201314792Y (en) Furnace cooling device
CN204818074U (en) Titanium powder apparatus for producing
CN211701968U (en) High-efficiency solar photovoltaic power generation device
CN209131413U (en) A kind of cooling device of sintering furnace
CN214470008U (en) Solar cell nitrogen protection tunnel furnace
CN216694524U (en) Novel split type energy-saving cooling tower

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120711

Termination date: 20161107

CF01 Termination of patent right due to non-payment of annual fee