CN1330829C - Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge - Google Patents

Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge Download PDF

Info

Publication number
CN1330829C
CN1330829C CNB2004100214863A CN200410021486A CN1330829C CN 1330829 C CN1330829 C CN 1330829C CN B2004100214863 A CNB2004100214863 A CN B2004100214863A CN 200410021486 A CN200410021486 A CN 200410021486A CN 1330829 C CN1330829 C CN 1330829C
Authority
CN
China
Prior art keywords
arch bridge
joist
steel pipe
hoist cable
hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2004100214863A
Other languages
Chinese (zh)
Other versions
CN1673459A (en
Inventor
苗明
滕儒民
王欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian University of Technology
Original Assignee
Dalian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian University of Technology filed Critical Dalian University of Technology
Priority to CNB2004100214863A priority Critical patent/CN1330829C/en
Publication of CN1673459A publication Critical patent/CN1673459A/en
Application granted granted Critical
Publication of CN1330829C publication Critical patent/CN1330829C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to an integral hanging method and a special hanging device for a steel pipe concrete flexible rope arch bridge, wh belongs to the field of bridge construction. The integral hanging method for the steel pipe concrete flexible rope arch bridge uses a floating crane or caterpillar crane hanging hook to lift up the hanging device to hoist and transport the steel pipe concrete flexible rope arch bridge which is hung by the special hanging device and the integral hanging method, and a bearing way adopts the special hanging device of the integral hanging in a lower bearing type four-point hanging way; the special hanging device is composed of a hanging device main beam, a main hanging rope, a balance beam, a supporting beam and a small hanging rope, wherein the main beam of the special hanging device adopts a symmetric space truss structure. The integral hanging transportation and installation can be implemented in rivers or sea areas by using the special hanging device of the present invention, and the present invention has the advantages of good manufacturing and installing quality of the arch bridge, construction risk reduction and construction safety guarantee; furthermore, the present invention can be used for the integral erection and construction for steel pipe concrete flexible rope arch bridges of which the span exceeds hektometers.

Description

Concrete filled steel tube soft rope arch bridge integral hoisting method and special hanger
Technical field concrete filled steel tube of the present invention soft rope arch bridge integral hoisting method and special hanger belong to technical field of bridge construction, can be used for the erection construction of concrete-filled steel tubes arch bridge.
The soft rope arch bridge of the present concrete filled steel tube of background technology technology is widely used in the bridge construction, the steel pipe skeleton of the soft rope arch bridge of concrete filled steel tube is gently many compared with the bridge construction of steel concrete, but the integral erection of the soft rope arch bridge of concrete filled steel tube has sizable difficulty.For striding the footpath above the soft rope arch bridge of concrete filled steel tube more than hundred meters, the main erection method that adopts at present has three kinds both at home and abroad: the method that cable lifting cantilever is constructed; Rotation swivel construction method; Adopt the method for integral hoisting.Cable lifting cantilever job practices is that the bow member segmental hoisting is joined the two sections of a bridge, etc again.In the rotation swivel construction method, the vertical transfer method and the method for flatting turn all have application, and the method that vertical transfer is also arranged, flat turn and combine will be through processes such as closure and system conversions.More than two kinds of methods very big risk and difficulty are all arranged.In the environmental permission part, can adopt the method for integral hoisting.But the notion of integral hoisting at present is confined to the integral hoisting of monolithic arch rib basically, is not that complete arch bridge is striden in lifting one.And can only handling stride the less arch rib in footpath, be difficult to resolve the certainly soft rope arch bridge of concrete filled steel tube skeleton less difficult problem of relative rigidity when striding the footpath more greatly.
Summary of the invention the objective of the invention is to propose a kind of concrete filled steel tube soft rope arch bridge integral hoisting method and special hanger, and this is a kind of new job practices.Can solve the soft rope arch bridge of concrete filled steel tube skeleton less difficult problem of relative rigidity when striding the footpath more greatly.The soft rope arch bridge of concrete filled steel tube can be in factory building or place whole in advance the manufacturing, utilize special hanger of the present invention then, use large-tonnage derrick barge or crawler crane with the whole handling assembling of arch bridge,, guarantee the safety of erection construction with workmanship and the erection weight of guaranteeing bridge; Can be used for striding the footpath and surpass hundred meters the soft rope arch bridge of concrete filled steel tube integral erection construction.
The soft rope arch bridge of a kind of concrete filled steel tube of the technical solution used in the present invention integral hoisting method is by derrick barge or the caterpillar crane hook soft rope arch bridge of suspender lifting transportation concrete filled steel tube of slinging, and it is characterized in that: adopt the method lifting of special hanger and integral hoisting.Concrete implementation step is: will build operator's working platform 2 earlier, construction on working platform 2; Before lifting, earlier joist 3 is hung on the little hoist cable 4 in the steel pipe arch bridge arch rib outside, tangling otic placode 23 by Chain block 8 hangs on the other end of joist 3 on another little hoist cable 4 of inboard of steel pipe arch bridge arch rib, special hanger then hoists, make joist 3 and steel pipe arch bridge arch rib, it is the contact of arch bridge suspension centre, utilize the derrick barge suspension hook main hoist cable 6 of slinging, the main hoist cable 6 special hanger girder 5 of slinging, the two ends of girder 5 hang with 4 equalizer bars 7, be hung with two little hoist cables 4 under each equalizer bar, little hoist cable 4 joist 3 of will slinging, joist 3 will hold up the suspension centre of steel pipe arch bridge 1, start the lifting mechanism of derrick barge like this, the transportation installation in position of just the soft rope arch bridge of concrete filled steel tube integral body can being sling.
When steel pipe arch bridge by handling to the destination and after being installed on the bridge pier, must untie the connection of 3 pairs of arch bridges 1 of joist. the concrete practice is, the suspension hook of derrick barge descends a little, tangle by the otic placode 23 of Chain block 8 joist 3 of arch bridge inboard, pulling Chain block 8 makes the little hoist cable 4 that hangs on the arch rib inboard be in relaxed state, little hoist cable is taken, and then pull down and start to draw cucurbit 8,3 of joists are hung on the little hoist cable in the arch rib outside, Chain block 8 is taken again, finished the work that suspender and joist break away from arch bridge, special hanger can leave arch bridge, extension is plucked the joist end-of-job, and working platform 2 is promptly dismountable.
The special hanger of the soft rope arch bridge of a kind of concrete filled steel tube integral hoisting, form by suspender girder, main hoist cable, equalizer bar, joist, little hoist cable, it is characterized in that: the special hanger girder adopts the symmetrical expression space truss structure, and bearing mode adopts 4 lifting modes of lower support type;
Equalizer bar 7 is a welded construction, is made up of two risers 11, upper pin 10, loaded plate 12, lower bearing pin 14, pulley 13, cottor pin 15, lower cover 16.Two risers 11 are formed carrier bar with lower cover 16, the centre is worn with upper pin 10 and is connected with the special hanger girder, two loaded plates 12 are respectively inserted at two ends, top is welded on two risers 11, the bottom penetrates pulley 13 with lower bearing pin 14, to hang little hoist cable 4 by the joist 3 soft rope arch bridge of concrete filled steel tube of slinging;
Joist 3 is a welded construction, by joist body 17, arc plate 18, rubber arc plate 19, end casing 20, Shackle assembly 21, stiffener 22 and otic placode 23 are formed, joist body 17 is formed by three block plate assembly weldings, its cross section is the ingot shape, above with arc plate 18 welding, two ends are with end casing 20 welding, tilt to be welded with Shackle assembly 21 in joist body 17 outsides, make joist 3 hold up the arch bridge suspension centre to connect little hoist cable 4, otic placode 23 is used for the Chain block 8 rotation joist 3 of slinging, rubber arc plate 18 is bonded on the arc plate 17, rubber arc plate 18 will also be furnished with some for improving the stiffener 22 of strength and stiffness as the cushion pad of joist 3 with the steel pipe arch bridge 1 that is hung in the structure.
The invention has the beneficial effects as follows:, can guarantee the manufacturing and the assembly quality of arch bridge because the soft rope arch bridge of concrete filled steel tube is to assemble whole manufacturing of factory building or place.With special hanger integral lifting transportation and the soft rope arch bridge of concrete filled steel tube is installed, can guarantee to realize the safe construction that transports and install, solved because the less constructional difficulties of bringing of steel pipe arch bridge relative rigidity and the difficult problem of greater risk is arranged.Can be in the river or the marine site carry out the integral hoisting transportation and install, the manufacturing installation quality of arch bridge is good, can reduce construction risk, guarantees construction safety.
The front view of the soft rope arch bridge of description of drawings 1-lifting concrete filled steel tube; The lateral view of Fig. 2-soft rope arch bridge of lifting concrete filled steel tube; Fig. 3-equalizer bar constructional drawing; Fig. 4-joist front view; Fig. 5-joist lateral view.Wherein: the soft rope arch bridge of 1-concrete filled steel tube, 2-working platform, 3-joist, the little hoist cable of 4-, 5-special hanger girder, 6-master's hoist cable, 7-equalizer bar, 8-Chain block, the 9-wire rope, 10-upper pin, 11-riser, 12-loaded plate, the 13-pulley, 14-lower bearing pin, 15-cottor pin, 16-lower cover, 17-joist body, 18-arc plate, 19-rubber arc plate, 20-end casing, the 21-Shackle assembly, 22-stiffener, 23-otic placode.
The specific embodiment is described with reference to the accompanying drawings the specific embodiment, equalizer bar 7 structures that welding is good are seen Fig. 3, joist 3 structures that welding is good are seen Fig. 4, Fig. 5, earlier main hoist cable 6 is installed on the special hanger girder 5, then little hoist cable 4 is installed on the equalizer bar 7, little hoist cable 4 bottom joists 3 are seen accompanying drawing 1, accompanying drawing 2, have so just finished the installation of special hanger.Utilize special hanger to realize the integral hoisting of the soft rope arch bridge of concrete filled steel tube, steel pipe arch bridge can wholely in advance be made, before lifting, earlier joist 3 is hung on the little hoist cable 4 in the steel pipe arch bridge arch rib outside, tangling otic placode 23 by Chain block 8 hangs on the other end of joist 3 on another little hoist cable 4 of inboard of steel pipe arch bridge arch rib, the suspender that hoists then makes joist 3 contact with steel pipe arch bridge arch rib (being the arch bridge suspension centre), has so just finished special hanger to the preceding preparation of steel pipe arch bridge lifting.Utilize the derrick barge suspension hook main hoist cable 6 of slinging, the main hoist cable 6 special hanger girder 5 of slinging, the two ends of girder 5 hang with 4 equalizer bars 7, be hung with two little hoist cables 4 under each equalizer bar, little hoist cable 4 joist 3 of will slinging, joist 3 will hold up the suspension centre lifting of steel pipe arch bridge 1, start the lifting mechanism of derrick barge, the transportation installation in position of just the soft rope arch bridge of concrete filled steel tube integral body can being sling.When steel pipe arch bridge by handling to the destination and after being installed on the bridge pier, must untie the connection of 3 pairs of arch bridges 1 of joist. the concrete practice is, the suspension hook of derrick barge descends a little, tangle by the otic placode 23 of Chain block 8 joist 3 of arch bridge inboard, pulling Chain block 8 makes the little hoist cable 4 that hangs on the arch rib inboard be in relaxed state, little hoist cable is taken, and then pull down and start to draw cucurbit 8,3 of joists are hung on the little hoist cable in the arch rib outside, again Chain block 8 is taken, finish the work that suspender and joist break away from arch bridge, suspender can leave arch bridge.
The workpeople is complete operation on working platform 2, and behind the end-of-job, working platform 2 is promptly dismountable.

Claims (2)

1, the soft rope arch bridge of a kind of concrete filled steel tube integral hoisting method is by derrick barge or the caterpillar crane hook soft rope arch bridge of suspender lifting transportation concrete filled steel tube of slinging, it is characterized in that, adopt the method lifting of special hanger and integral hoisting, bearing mode adopts 4 hanging methods of lower support type;
Concrete implementation step is: go up construction at working platform [2], before the lifting, earlier joist [3] is hung on the little hoist cable [4] in the steel pipe arch bridge arch rib outside, tangling otic placode [23] by Chain block [8] hangs on the other end of joist [3] on another little hoist cable [4] of inboard of steel pipe arch bridge arch rib, special hanger then hoists, make joist [3] and steel pipe arch bridge arch rib, it is the contact of arch bridge suspension centre, utilize the derrick barge suspension hook main hoist cable [6] of slinging, main hoist cable [6] the special hanger girder [5] of slinging, the two ends of girder [5] hang with 4 equalizer bars [7], be hung with two little hoist cables [4] under each equalizer bar, little hoist cable [4] joist [3] of will slinging, joist [3] will hold up the suspension centre of steel pipe arch bridge [1], start the lifting mechanism of derrick barge like this, the transportation installation in position of just the soft rope arch bridge of concrete filled steel tube integral body can being sling;
When steel pipe arch bridge by handling to the destination and after being installed on the bridge pier, untie the connection of joist [3] to arch bridge [1], suspension hook with derrick barge descends a little earlier, tangle by the otic placode [23] of Chain block [8] the joist [3] of arch bridge inboard, pulling Chain block [8] makes the little hoist cable [4] that hangs on the arch rib inboard be in relaxed state, little hoist cable is taken, and then pull down and start to draw cucurbit [8], joist [3] is only hung on the little hoist cable in the arch rib outside, Chain block [8] is taken again, finished the work that suspender and joist break away from arch bridge, special hanger can leave arch bridge, extension is plucked the joist end-of-job, and working platform [2] is promptly dismountable.
2, the special hanger of the soft rope arch bridge of a kind of concrete filled steel tube integral hoisting, form by suspender girder, main hoist cable, equalizer bar, joist, little hoist cable, it is characterized in that: special hanger girder [5] adopts the symmetrical expression space truss structure, and bearing mode adopts 4 lifting modes of lower support type;
Equalizer bar [7] is a welded construction, is made up of two risers [11], upper pin [10], loaded plate [12], lower bearing pin [14], pulley [13], cottor pin [15], lower cover [16].Two risers [11] are formed carrier bar with lower cover [16], the centre is worn with upper pin [10] and is connected with the special hanger girder, two loaded plates [12] are respectively inserted at two ends, top is welded on two risers [11], the bottom penetrates pulley [13] with lower bearing pin [14], to hang little hoist cable [4] by joist [3] the soft rope arch bridge of concrete filled steel tube of slinging;
Joist [3] is a welded construction, by joist body [17], arc plate [18], rubber arc plate [19], end casing [20], Shackle assembly [21], stiffener [22] and otic placode [23] are formed, joist body [17] is formed by three block plate assembly weldings, its cross section is the ingot shape, weld with arc plate [18] above, weld with end casing [20] at two ends, tilt to be welded with Shackle assembly [21] in joist body [17] outside, make joist [3] hold up the arch bridge suspension centre to connect little hoist cable [4], otic placode [23] for Chain block [8] sling the rotation joist [3] used, rubber arc plate [18] is bonded on the arc plate [17], rubber arc plate [18] will also be furnished with some for improving the stiffener [22] of strength and stiffness as the cushion pad of joist [3] with the steel pipe arch bridge [1] that is hung in the structure.
CNB2004100214863A 2004-03-24 2004-03-24 Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge Expired - Fee Related CN1330829C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2004100214863A CN1330829C (en) 2004-03-24 2004-03-24 Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2004100214863A CN1330829C (en) 2004-03-24 2004-03-24 Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge

Publications (2)

Publication Number Publication Date
CN1673459A CN1673459A (en) 2005-09-28
CN1330829C true CN1330829C (en) 2007-08-08

Family

ID=35046218

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2004100214863A Expired - Fee Related CN1330829C (en) 2004-03-24 2004-03-24 Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge

Country Status (1)

Country Link
CN (1) CN1330829C (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100567644C (en) * 2007-05-09 2009-12-09 华东交通大学 A kind of joist type cable arch bridge structure and job practices
CN101195460B (en) * 2007-12-25 2010-06-16 中铁四局集团有限公司 Large-scale girder bottom hoisting device and method thereof
CN102234979B (en) * 2010-04-30 2013-07-10 华泰(南通)船务有限公司 Main pier steel sinking well for bridge and process for integrally hoisting and installing steel sinking well sections thereof
CN101927958B (en) * 2010-09-12 2012-06-27 中国石油天然气第七建设公司 Method for realizing eccentric hoisting by matching crane and hoisting frame
CN102425150B (en) * 2011-08-24 2014-10-08 徐工集团工程机械股份有限公司 Dynamic compaction machinery balancing hook and balancing hook mechanism provided with same
CN105839546B (en) * 2016-06-01 2018-05-25 中交四公局第五工程有限公司 A kind of steel pipe arch bridge arch rib buckling and hanging mounting structure
CN106592962A (en) * 2016-12-24 2017-04-26 中铁十八局集团有限公司 Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus
CN107902549B (en) * 2017-10-31 2019-06-14 中国二十冶集团有限公司 The simple and easy method of unloading heavy equipment
CN110094577B (en) * 2019-06-11 2024-02-27 中国葛洲坝集团国际工程有限公司 Device and method for installing oversized-diameter inclined dam rear open pipe under strong wind condition
CN113802478B (en) * 2021-10-29 2022-08-02 合肥工业大学 Arch bridge deck structure demolishs device based on arch rib supports atress

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2856361A1 (en) * 1978-01-02 1979-07-12 Beyer Bauges Wide span bridge arch scaffolding erection - involves linking truss parts into lattices from base upwards and consolidating hinges
CH645944A5 (en) * 1979-01-12 1984-10-31 Bung Ingenieurbuero Gemeinscha Method of building a bridge arch
JP2000064227A (en) * 1998-08-27 2000-02-29 Sumitomo Constr Co Ltd Bridge erection method
CN2377279Y (en) * 1999-01-22 2000-05-10 四川公路桥梁建设集团有限公司 Compound cable crane
JP2000352017A (en) * 1999-06-09 2000-12-19 Kawada Industries Inc Bridge erection method
JP2002294633A (en) * 2001-03-30 2002-10-09 Mitsubishi Heavy Ind Ltd Method and device for constructing arch-shaped structural body

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2856361A1 (en) * 1978-01-02 1979-07-12 Beyer Bauges Wide span bridge arch scaffolding erection - involves linking truss parts into lattices from base upwards and consolidating hinges
CH645944A5 (en) * 1979-01-12 1984-10-31 Bung Ingenieurbuero Gemeinscha Method of building a bridge arch
JP2000064227A (en) * 1998-08-27 2000-02-29 Sumitomo Constr Co Ltd Bridge erection method
CN2377279Y (en) * 1999-01-22 2000-05-10 四川公路桥梁建设集团有限公司 Compound cable crane
JP2000352017A (en) * 1999-06-09 2000-12-19 Kawada Industries Inc Bridge erection method
JP2002294633A (en) * 2001-03-30 2002-10-09 Mitsubishi Heavy Ind Ltd Method and device for constructing arch-shaped structural body

Also Published As

Publication number Publication date
CN1673459A (en) 2005-09-28

Similar Documents

Publication Publication Date Title
CN102561191A (en) Integral lifting system and construction method for arch bridge ribs
CN1330829C (en) Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge
CN101559905A (en) Deck unit erection gantry
CN111335187B (en) Construction process for triangular area of open-web rigid frame bridge
CN100354477C (en) Swing-construction method for mounting dual-hoist at land-shoul beam section for steel box girder suspension bridge
CN205328487U (en) Dismantlement system of superelevation extra -large -size tower crane
CN102826459A (en) Device and method for hoisting underwater structural part of ocean platform
CN209194361U (en) A kind of fixed structure of suspension cable bridge section lifting hoisting platform
CN214828306U (en) A auxiliary device for hoisting box girder steel reinforcement framework
CN211338564U (en) Tower top main cable saddle mounting system
CN113882280A (en) Construction method of steel-concrete mixed combined continuous rigid frame bridge
CN201128882Y (en) Lifting and supporting brackets integrated construction device for bridge arch rib
CN110886242B (en) Method for installing composite cable saddle in anchor hole of suspension bridge tunnel in mountainous area
CN210797277U (en) Public road bridge roof beam construction bracket convenient to it is fixed
CN201530682U (en) Hoisting lifting device suitable for hoisting steel box girder
CN201649667U (en) Reinforcement cage immersion guide frame
CN110697570A (en) Tower top main cable saddle mounting system and using method thereof
CN112520578A (en) Hoisting construction method for lightering-span steel truss girder pontoon
CN111453630A (en) Bridge deck crane and using method thereof
CN220908153U (en) Bridge precast beam hoisting point conversion equipment
CN217758347U (en) Suspension bridge hoisting system capable of realizing offset hoisting of steel box girder in unilateral tower area
CN219671112U (en) A tackle on arch for installation of steel pipe arch bridge jib
CN214879483U (en) Multifunctional hanging bracket for mounting high-pile wharf component
CN217762355U (en) Large-span underground pipeline protection structure
CN217051336U (en) Device for transferring bearing steel beam of internal climbing tower crane

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20070808

Termination date: 20100324