JP2000064227A - Bridge erection method - Google Patents

Bridge erection method

Info

Publication number
JP2000064227A
JP2000064227A JP24122598A JP24122598A JP2000064227A JP 2000064227 A JP2000064227 A JP 2000064227A JP 24122598 A JP24122598 A JP 24122598A JP 24122598 A JP24122598 A JP 24122598A JP 2000064227 A JP2000064227 A JP 2000064227A
Authority
JP
Japan
Prior art keywords
erection
bridge
melanin material
melanin
overhanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP24122598A
Other languages
Japanese (ja)
Inventor
Akira Oiso
章 大磯
Kazushi Nakamura
收志 中村
Hirokazu Hoashi
洋和 帆足
Motofumi Saito
基文 斉藤
Hiroshi Masuko
博志 益子
Tatsunori Yoneda
達則 米田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Construction Co Ltd
Kawada Industries Inc
Original Assignee
Sumitomo Construction Co Ltd
Kawada Industries Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Construction Co Ltd, Kawada Industries Inc filed Critical Sumitomo Construction Co Ltd
Priority to JP24122598A priority Critical patent/JP2000064227A/en
Publication of JP2000064227A publication Critical patent/JP2000064227A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve workability, shorten a construction period and reduce erection cost, compared with the cantilever overhanging erection method, after enabling an arch part to be erected even in the erection environment where the field assembly of a Melan material is difficult, regarding a bridge erection method for erecting the arch part of a concrete arch bridge. SOLUTION: Melan material constituent blocks 14b are sequentially suspended from a main cable 112 extended between supports 16 erected as a pair at both sides of a bridge erection position, and connected to each other for assembling a Melan material 14B'. Then, both ends of the Melan material 14B' are connected to the forward ends of each overhanging erection part 14A and closed. As a result, the need of the field assembly of the Melan material 14B' is eliminated and the all weight thereof is held on the main cable 112, thereby eliminating the need of stress control at the time of assembling the Melan material 14B'. At the same time, the Melan material 14B' can be assembled in parallel with the construction work of an overhanging erection part 14A. Furthermore, a direct suspending facility used for other bridge erection works can be transferred for use for the assembly of the Melan material 14B'.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本願発明は、コンクリート製
アーチ橋のアーチ部を架設する橋梁架設方法に関するも
のである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a bridge construction method for constructing an arch portion of a concrete arch bridge.

【0002】[0002]

【従来の技術】従来より、コンクリート製アーチ橋のア
ーチ部を架設する方法として、橋梁架設位置の両側から
延びる1対の張出し架設部をメラン架設部で閉合する、
いわゆるメラン工法が知られている。
2. Description of the Related Art Conventionally, as a method of constructing an arch portion of a concrete arch bridge, a pair of overhanging construction portions extending from both sides of a bridge construction position are closed at a melan joint construction portion.
The so-called melanin method is known.

【0003】このメラン工法としては、地上で組み立て
られたメラン材を両張出し架設部の延長上まで吊り上げ
てこれらに連結する工法が知られているが、アーチ橋の
架橋場所はメラン材の地組みが困難な環境下にある場合
が多く、このような場合には斜吊り材を用いた片持ち張
出し架設工法が一般に用いられる。
As this melanin construction method, there is known a construction method in which a melanin material assembled on the ground is lifted up to the extension of both overhanging portions and connected to these, but the bridge portion of the arch bridge is erected by the melanin material. In many cases, it is in a difficult environment, and in such a case, a cantilever overhanging construction method using an oblique suspension is generally used.

【0004】この片持ち張出し架設工法は、橋梁架設位
置の両側に立設された1対の支柱からあるいはこれら各
支柱に設置したピロンから斜吊り材を架設しながらメラ
ン材を張出し架設して中央閉合を行うようになってい
る。
This cantilever overhanging method is a method of overhanging and extending the melanin material from a pair of pillars erected on both sides of the bridge erection position or from a pillow installed on each of these pillars, and then erectioning and extending the melanin material to the center. It is designed to be closed.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、上記片
持ち張出し架設工法においては、アーチ部をその全範囲
にわたって片持ち張出し架設で施工するため、架設中の
応力管理を厳密に行う必要があり、しかも工期が長くか
かってしまうという問題がある。また、片持ち張出し架
設に用いられる斜吊り材等のPC鋼材は、通常他の橋梁
架設で使用したものを転用することが不可能であり、こ
のため架設工費が高くなってしまうという問題がある。
However, in the above cantilever overhanging construction method, since the arch portion is constructed by cantilever overhanging over the entire range, it is necessary to strictly control stress during the erection. There is a problem that the construction period will be long. Further, it is impossible to divert PC steel materials such as oblique suspension materials used for cantilever overhanging from those normally used for other bridge erection, which causes a problem that construction cost becomes high. .

【0006】本願発明は、このような事情に鑑みてなさ
れたものであって、メラン材の地組みが困難な架橋環境
下においてもアーチ部の架設を可能とした上で、片持ち
張出し架設工法に比して施工性向上、工期短縮および架
設工費削減を図ることができる橋梁架設方法を提供する
ことを目的とするものである。
The present invention has been made in view of the above circumstances, and enables the arch portion to be erected even in a bridging environment where it is difficult to assemble the melanin material, and the cantilever overhanging construction method. It is an object of the present invention to provide a bridge construction method capable of improving the workability, shortening the construction period, and reducing the construction cost compared to

【0007】[0007]

【課題を解決するための手段】本願発明は、メラン材の
組み立てを直吊り状態で行うことにより、上記目的達成
を図るようにしたものである。
According to the present invention, the above object is achieved by assembling the melanin material in a state of being directly suspended.

【0008】すなわち、本願第1の発明は、請求項1に
記載したように、橋梁架設位置の両側から延びる1対の
張出し架設部をメラン架設部で閉合することにより、コ
ンクリート製アーチ橋のアーチ部を架設する橋梁架設方
法において、上記橋梁架設位置の両側に立設された1対
の支柱間にケーブルを張り渡し、このケーブルに複数の
メラン材構成ブロックを吊支持して上記両張出し架設部
の延長上に配置した状態で、これらメラン材構成ブロッ
クを互いに連結してメラン材を組み立てる工程と、上記
メラン材の両端部を上記各張出し架設部の先端部に連結
する工程と、上記メラン材を埋め込むようにコンクリー
トを打設して上記メラン架設部を施工する工程と、を含
むことを特徴とするものである。
That is, according to the first aspect of the present invention, as described in claim 1, the arch of the concrete arch bridge is constructed by closing the pair of overhanging erection portions extending from both sides of the bridge erection position with the melanin erection portion. In the bridge erection method of erection of a portion, a cable is stretched between a pair of stanchions erected on both sides of the bridge erection position, and a plurality of melanin material building blocks are hung and supported on the cable, and the both bulging erection portions are supported. In the state of being placed on the extension of the above, the step of assembling the melanin material by connecting these melanin material building blocks to each other, the step of connecting both ends of the melanin material to the tip end portions of the respective overhanging parts, and the melanin material And a step of placing concrete so as to embed the above and constructing the above-mentioned melanin installation portion.

【0009】また、本願第2の発明は、請求項2に記載
したように、橋梁架設位置の両側から延びる1対の張出
し架設部をメラン架設部で閉合することにより、コンク
リート製アーチ橋のアーチ部を架設する橋梁架設方法に
おいて、上記橋梁架設位置の両側に立設された1対の支
柱間に、中央部が地表面近くまで垂れ下がるようにケー
ブルを張り渡し、このケーブルに複数のメラン材構成ブ
ロックを吊支持した状態で、これらメラン材構成ブロッ
クを互いに連結してメラン材を組み立てる工程と、上記
メラン材の両端部間をタイドケーブルで連結する工程
と、上記各張出し架設部の先端部から上記メラン材の両
端部を吊支持して該メラン材を上記両張出し架設部の延
長上まで吊り上げる工程と、上記メラン材の両端部を上
記各張出し架設部の先端部に連結する工程と、上記メラ
ン材を埋め込むようにコンクリートを打設して上記メラ
ン架設部を施工する工程と、を含むことを特徴とするも
のである。
According to a second aspect of the present invention, the arch of a concrete arch bridge is constructed by closing a pair of overhanging erection portions extending from both sides of the bridge erection position with a melan section. In a bridge erection method of erection a part, a cable is stretched between a pair of stanchions erected on both sides of the bridge erection position so that the central part hangs close to the ground surface, and a plurality of melanin materials are formed on this cable. In a state where the blocks are suspended and supported, a step of assembling the melanin material by connecting these melanin material constituting blocks to each other, a step of connecting both ends of the melanin material with a tide cable, and a tip portion of each of the overhanging parts A step of suspending and supporting both ends of the melanin material and hoisting the melanin up to an extension of both of the overhanging parts; A step of connecting to an end, and Da設 concrete to fill the Melan material is characterized in that comprising the steps of applying the Melan-installing portion.

【0010】[0010]

【発明の作用効果】上記構成に示すように、本願発明に
係る橋梁架設方法は、橋梁架設位置の両側に立設された
1対の支柱間に張り渡されたケーブルに複数のメラン材
構成ブロックを吊支持した状態で、これらメラン材構成
ブロックを互いに連結してメラン材を組み立てるように
なっているので、メラン材の地組みが困難な架橋環境下
においてもメラン材の組み立てを行うことができ、しか
もその上で次のような作用効果を得ることができる。
As described above, according to the bridge construction method of the present invention, a plurality of melanin material building blocks are attached to a cable stretched between a pair of stanchions erected on both sides of the bridge construction position. Since the melanin material building blocks are linked together to assemble the melanin material, the melanin material can be assembled even in a bridging environment where the foundation of the melanin material is difficult. In addition, the following effects can be obtained.

【0011】すなわち、本願発明に係る橋梁架設方法に
おいては、メラン材の重量がすべて上記ケーブルに支持
されるので、メラン材を組み立てる際の応力管理が不要
となり、片持ち張出し架設工法に比して施工性が大幅に
向上する。また、メラン材の組み立てを張出し架設部の
施工と並行して行うことができるので、片持ち張出し架
設工法に比して大幅に工期を短縮することができる。さ
らに、メラン材の組み立てに用いられる直吊り架設設備
は、他の橋梁架設で使用したものを転用することができ
るので、片持ち張出し架設工法に比して架設工費を削減
することができる。
That is, in the bridge erection method according to the present invention, since the weight of the melanin material is entirely supported by the cable, stress management when assembling the melanin material is not required, and compared with the cantilever overhanging method. Workability is greatly improved. In addition, assembling the melanin material can be performed in parallel with the construction of the overhanging erection portion, so that the construction period can be significantly shortened as compared with the cantilever overhanging construction method. Further, since the direct suspension installation equipment used for assembling the melanin material can be diverted from another bridge installation, the installation cost can be reduced as compared with the cantilever overhang installation method.

【0012】このように本願発明によれば、メラン材の
地組みが困難な架橋環境下においてもアーチ部の架設を
可能とした上で、片持ち張出し架設工法に比して施工性
向上、工期短縮および架設工費削減を図ることができ
る。
As described above, according to the present invention, the arch portion can be erected even in a bridging environment where it is difficult to assemble the melanin material, and the workability is improved and the construction period is improved as compared with the cantilever overhanging construction method. It is possible to reduce the length and the construction cost.

【0013】特に、本願第1の発明に係る橋梁架設方法
においては、メラン材を組み立てる際、ケーブルに吊支
持された複数のメラン材構成ブロックを上記両張出し架
設部の延長上に配置した状態で互いに連結するようにな
っているので、組み立てられたメラン材の両端部をその
場で各張出し架設部の先端部に連結してその閉合を行う
ことができ、これにより施工性をさらに向上させること
ができる。
Particularly, in the bridge erection method according to the first aspect of the present invention, when assembling the melanin material, a plurality of melanin material building blocks suspended and supported by the cable are arranged on the extension of the two overhanging and erection parts. Since they are designed to be connected to each other, both ends of the assembled melanin material can be connected to the tips of the overhanging erection parts on the spot to perform the closing, thereby further improving the workability. You can

【0014】一方、本願第2の発明に係る橋梁架設方法
においては、メラン材を組み立てる際、中央部が地表面
近くまで垂れ下がるように張り渡されたケーブルに複数
のメラン材構成ブロックを吊支持するようになっている
ので、組み立てられたメラン材を両張出し架設部の延長
上まで吊り上げる作業は必要となるが、ケーブルのサグ
量を十分に確保することができるので、直吊り架設設備
の負荷を大幅に軽減することができ、これにより架設工
費を大幅に削減することができる。また、地表面に支持
されたクレーンを使用することが可能となるので、作業
性が良好となる。
On the other hand, in the bridge erection method according to the second aspect of the present invention, when assembling the melanin material, a plurality of melanin material building blocks are suspended and supported by the cable stretched so that the central portion hangs near the ground surface. Therefore, it is necessary to lift the assembled Melan material up to the extension of the erection section on both sides, but it is possible to secure a sufficient sag amount of the cable, so the load of the direct suspension installation equipment can be reduced. It can be significantly reduced, which can significantly reduce the construction cost. Further, since it is possible to use a crane supported on the ground surface, workability is improved.

【0015】ところで、本願発明においてはメラン材の
組み立てを直吊り状態で行うようになっているので、メ
ラン材を無応力状態で組み立てることができ、このため
該メラン材にプレストレスを導入することが可能であ
る。
By the way, in the present invention, since the melanin material is assembled in a state of being directly suspended, it is possible to assemble the melanin material in a stress-free state. Therefore, prestress is introduced into the melanin material. Is possible.

【0016】そこで、請求項3に記載したように、メラ
ン材の両端部を各張出し架設部に連結する前に該メラン
材にプレストレスを導入するとともに、該連結終了後に
プレストレスを解除するようにすれば、組み立てられた
メラン材の応力管理を容易に行うことができる。また、
このようにプレストレスを付与した状態でメラン材の両
端部を各張出し架設部の先端部に連結することにより、
その後メラン材を埋め込むようにコンクリートを打設し
たときに生じる引張応力に対して十分に抵抗させること
ができる。そしてこれによりメラン材断面の縮小化を図
ることができるので、鋼材重量の減少による架設工費の
削減を図ることができる。
Therefore, as described in claim 3, a prestress is introduced into the melanin material before connecting both ends of the melanin material to each overhanging portion, and the prestress is released after the connection is completed. By doing so, stress management of the assembled melanin material can be easily performed. Also,
By connecting both ends of the melanin material to the tips of the respective overhanging parts while prestressing in this way,
After that, it is possible to sufficiently resist the tensile stress generated when concrete is poured so as to embed the melanin material. As a result, the cross section of the melanin material can be reduced, so that the construction cost can be reduced due to the reduction of the weight of the steel material.

【0017】上記「プレストレスを導入する」ための具
体的方法は特に限定されるものではないが、例えば、本
願第1の発明においては、メラン材の両端部間をタイド
ケーブルで連結して該タイドケーブルを用いてプレスト
レスを導入する方法、あるいはメラン材の両端部と各張
出し架設部の先端部との間に油圧ジャッキを介装してプ
レストレスを導入する方法等が採用可能であり、また、
本願第2の発明においては、メラン材の吊上げに先立っ
てその両端部間に連結されるタイドケーブルを用いてプ
レストレスを導入する方法等が採用可能である。
Although the specific method for "introducing prestress" is not particularly limited, for example, in the first invention of the present application, both ends of the melanin material are connected by tie cables. It is possible to adopt a method of introducing prestress using a tide cable, or a method of introducing prestress by inserting a hydraulic jack between both ends of the melanin material and the tip of each overhanging construction, Also,
In the second invention of the present application, a method of introducing prestress using a tied cable connected between both ends of the melanin material prior to lifting it can be adopted.

【0018】[0018]

【発明の実施の形態】以下、図面を用いて、本願発明の
実施の形態について説明する。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings.

【0019】まず、本願第1の発明の一実施形態につい
て説明する。
First, an embodiment of the first invention of the present application will be described.

【0020】図1は、本実施形態に係る橋梁架設方法の
対象となるコンクリート製アーチ橋10を示す図であ
る。
FIG. 1 is a view showing a concrete arch bridge 10 which is a target of the bridge construction method according to this embodiment.

【0021】図示のように、このアーチ橋10は、橋梁
架設位置の両側の地表面2に施工された1対の基礎12
の間にアーチ部14を架設し、このアーチ部14の上部
に橋脚16および鉛直材18を介して上床版20を施工
することにより、その架設が行われるようになってい
る。
As shown, the arch bridge 10 includes a pair of foundations 12 constructed on the ground surface 2 on both sides of the bridge erection position.
The arch portion 14 is installed between the two, and the upper floor slab 20 is installed on the upper portion of the arch portion 14 via the bridge pier 16 and the vertical member 18, whereby the installation is performed.

【0022】上記アーチ部14は、後述するように、両
基礎12から延びる1対の張出し架設部14Aをメラン
架設部14Bで閉合することにより架設されるようにな
っている。
As described later, the arch portion 14 is constructed by closing a pair of overhanging construction portions 14A extending from both foundations 12 with a melan joint construction portion 14B.

【0023】図2は、上記アーチ部14の架設工程を示
す図である。
FIG. 2 is a diagram showing a process of constructing the arch portion 14.

【0024】まず、同図(a)に示すように、橋梁架設
位置の両側に1対の基礎12を施工し、これら各基礎1
2に上記橋脚16となるべき支柱を各々立設する。さら
に、これら各支柱16の上端にピロン102を設置する
とともにその背後にバックステー104を設置する。
First, as shown in FIG. 1 (a), a pair of foundations 12 are installed on both sides of the bridge erection position.
The columns to be the bridge piers 16 are respectively installed on the column 2. Further, the pillow 102 is installed on the upper end of each of the columns 16 and the back stay 104 is installed behind it.

【0025】次に、ワーゲン106を用いて各基礎12
からコンクリート製のアーチリブ14A´をアーチ軸に
沿って各々片持ち状に張り出し、各支柱16から斜めに
張設された斜吊りケーブル108でアーチリブ14A´
を支持しながら該アーチリブ14A´を伸長施工するこ
とにより、上記張出し架設部14Aを構築する。なお、
両方の張出し架設部14Aが完成するのは図(c)の段
階である。
Next, each foundation 12 using the Wagen 106
Concrete arch ribs 14A ′ are cantilevered along the arch axis, and the arch ribs 14A ′ are diagonally stretched from the columns 16 by diagonally extending cables 108.
By extending the arch ribs 14A ′ while supporting the above, the overhanging erected portion 14A is constructed. In addition,
Completion of both overhanging installation parts 14A is a stage of Drawing (c).

【0026】これと並行して、両支柱16のピロン10
2の先端相互間にケーブルクレーン110および主索ケ
ーブル112を張り渡し、支柱16の背後にはバックケ
ーブル114を張設する。そして、ケーブルクレーン1
10に移動可能に取り付けられたキャリア116によ
り、主索ケーブル112に複数のハンガー索118を所
定間隔で設置する。
In parallel with this, the pillars 10 of both columns 16 are
A cable crane 110 and a main rope cable 112 are stretched between the two ends, and a back cable 114 is stretched behind the column 16. And the cable crane 1
A plurality of hanger ropes 118 are installed at predetermined intervals on the main rope cable 112 by the carrier 116 movably attached to the cable 10.

【0027】続いて、同図(b)に示すように、キャリ
ア116にメラン材構成ブロック14bを1つずつ吊支
持して、これをハンガー索118に吊り換え、メラン材
構成ブロック14bを一方の張出し架設部14Aの先端
部から順次その延長上(アーチ軸上)に配置するととも
に、これらメラン材構成ブロック14bを互いに連結す
る。そして、このメラン材構成ブロック14bの直吊り
連結作業を他方の張出し架設部14Aの先端部に至るま
で行うことにより、メラン材14B´を組み立てる。
Subsequently, as shown in FIG. 3B, the melanin material constituting blocks 14b are hung and supported on the carrier 116 one by one, and the hanger ropes 118 are hung to suspend the melanin material constituting block 14b on one side. The extension portions (14A) are sequentially arranged on the extension (on the arch axis) from the tip portion of the overhanging portion (14A), and these melanic material constituting blocks (14b) are connected to each other. Then, the melanin material 14B 'is assembled by performing the direct suspension connection work of the melanin material block 14b up to the tip of the other overhanging and constructing portion 14A.

【0028】次に、同図(c)に示すように、メラン材
14B´の両端部間をタイドケーブル120で連結し、
該タイドケーブル120によりメラン材14B´にプレ
ストレスを導入する(これについては後述する)。そし
てこの状態で、メラン材14B´の両端部を各張出し架
設部14Aの先端部に連結する。
Next, as shown in FIG. 3C, both ends of the melanin material 14B 'are connected by a tide cable 120,
Prestress is introduced into the melanin material 14B 'by the tide cable 120 (this will be described later). Then, in this state, both end portions of the melanin material 14B 'are connected to the tip portions of the respective projecting and extending portions 14A.

【0029】その後、同図(d)に示すように、タイド
ケーブル120によるプレストレスを解除して該タイド
ケーブル120を撤去するとともに、主索ケーブル11
2やハンガー索118等の直吊り設備も撤去する。
Thereafter, as shown in FIG. 3D, the prestressing by the tide cable 120 is released to remove the tide cable 120 and the main cable 11
2 and the hanging equipment such as the hanger rope 118 are also removed.

【0030】最後に、ワーゲン106を用いて、メラン
材14B´を埋め込むようにコンクリートを打設するこ
とにより、上記メラン架設部14Bの施工を行い上記ア
ーチ部14を完成させる。
Finally, by using the wagen 106, concrete is placed so as to embed the melanin material 14B ', thereby constructing the melanin installation portion 14B and completing the arch portion 14.

【0031】図3は、上記プレストレスの導入によるメ
ラン材14B´の変形の様子を示す図であり、図4は、
図3のIV部詳細図である。
FIG. 3 is a diagram showing how the melanin material 14B 'is deformed by the introduction of the prestress, and FIG.
FIG. 4 is a detailed view of IV section in FIG. 3.

【0032】図3に示すように、メラン材14B´は、
その両端部間に連結されたタイドケーブル120に張力
Tを付与することによりプレストレスが導入され、その
曲げモーメント作用により図中破線で示すように僅かに
撓み変形する。
As shown in FIG. 3, the melanin material 14B 'is
Prestress is introduced by applying tension T to the tide cable 120 connected between both ends thereof, and the bending moment causes the prestress to slightly deform as shown by the broken line in the figure.

【0033】そしてこの状態で、図4に示すように、メ
ラン材14B´の両端部と各張出し架設部14Aの先端
部との連結を行った後、メラン材14B´の両端部端面
と各張出し架設部14Aの先端部端面との間に、モルタ
ル(早強モルタル)Mを打設して端面相互間の間詰めを
行い、この間詰めが完了した後にタイドケーブル120
によるプレストレスを解除するようになっている。
In this state, as shown in FIG. 4, after connecting both ends of the melanin material 14B 'and the tip of each overhanging erection portion 14A, the end surfaces of both ends of the melanin material 14B' and each bulge are connected. Mortar (early-strength mortar) M is placed between the end portion of the erection portion 14A and the end surfaces to close the space between the end surfaces.
The prestress caused by

【0034】以上詳述したように、本実施形態に係る橋
梁架設方法は、橋梁架設位置の両側に立設された1対の
支柱16間に張り渡された主索ケーブル112に複数の
メラン材構成ブロック14bを吊支持した状態で、これ
らメラン材構成ブロック14bを互いに連結してメラン
材14B´を組み立てるようになっているので、メラン
材の地組みが困難な架橋環境下においてもメラン材の組
み立てを行うことができる。
As described above in detail, in the bridge construction method according to this embodiment, the main rope cable 112 stretched between the pair of stanchions 16 erected on both sides of the bridge construction position is provided with a plurality of melanin materials. Since the melanin material block 14b 'is assembled by connecting the melanin material block 14b to each other in a state where the building block 14b is suspended and supported, the melanin material can be formed even in a bridging environment where it is difficult to assemble the melanin material. Assembly can be done.

【0035】しかも本実施形態においては、メラン材1
4B´の重量がすべて主索ケーブル112に支持される
ので、メラン材14B´を組み立てる際の応力管理が不
要となり、片持ち張出し架設工法に比して施工性が大幅
に向上する。特に本実施形態においては、メラン材14
B´を組み立てる際、主索ケーブル112に吊支持され
た複数のメラン材構成ブロック14bを両張出し架設部
14Aの延長上に配置した状態で互いに連結するように
なっているので、組み立てられたメラン材14B´の両
端部をその場で各張出し架設部14Aの先端部に連結し
てその閉合を行うことができ、これにより施工性をさら
に向上させることができる。
Moreover, in this embodiment, the melanin material 1 is used.
Since the weight of 4B 'is entirely supported by the main cable 112, stress management at the time of assembling the melanin material 14B' is not required, and the workability is greatly improved as compared with the cantilever overhanging method. Particularly in the present embodiment, the melanin material 14
When assembling B ′, the plurality of melanin material building blocks 14b suspended and supported by the main rope cable 112 are connected to each other in a state of being arranged on the extension of both overhanging erection portions 14A, so that the assembled melanin is assembled. Both ends of the material 14B 'can be connected to the tip end portions of the respective projecting and overhanging portions 14A on the spot to perform the closing, and thus the workability can be further improved.

【0036】また本実施形態においては、メラン材14
B´の組み立てを張出し架設部14Aの施工と並行して
行うことができるので、片持ち張出し架設工法に比して
大幅に工期を短縮することができる。
In this embodiment, the melanin material 14 is used.
Since B'can be assembled in parallel with the construction of the overhanging erection portion 14A, the construction period can be significantly shortened as compared with the cantilever overhanging construction method.

【0037】さらに、本実施形態においてメラン材14
B´の組み立てに用いられる主索ケーブル112、ハン
ガー索118等の直吊り架設設備は、他の橋梁架設で使
用したものを転用することができるので、片持ち張出し
架設工法に比して架設工費を削減することができる。
Further, in this embodiment, the melanin material 14 is used.
Since the directly suspended erection equipment such as the main cable 112 and the hanger cable 118 used for assembling B ′ can be diverted from those used in other bridge erection, the erection cost is higher than that of the cantilever erection method. Can be reduced.

【0038】このように本実施形態によれば、メラン材
の地組みが困難な架橋環境下においてもアーチ部の架設
を可能とした上で、片持ち張出し架設工法に比して施工
性向上、工期短縮および架設工費削減を図ることができ
る。
As described above, according to the present embodiment, the arch portion can be erected even in a bridge environment where it is difficult to assemble the melanin material, and the workability is improved as compared with the cantilever overhanging construction method. It is possible to reduce the construction period and the construction cost.

【0039】また本実施形態においては、メラン材14
B´の組み立てを直吊りの無応力状態で行うことができ
ることに鑑み、該メラン材14B´にプレストレスを導
入するようになっているので、組み立てられたメラン材
14B´の応力管理を容易に行うことができる。また、
このようにプレストレスを付与した状態でメラン材14
B´の両端部を各張出し架設部14Aの先端部に連結す
ることにより、その後メラン材14B´を埋め込むよう
にコンクリートを打設したときに生じる引張応力に対し
て十分に抵抗させることができる。そしてこれによりメ
ラン材14B´の断面の縮小化を図ることができるの
で、鋼材重量の減少による架設工費の削減を図ることが
できる。
Further, in this embodiment, the melanin material 14 is used.
In view of the fact that B ′ can be assembled in a stress-free state of direct suspension, prestress is introduced into the melanin material 14B ′, so that stress management of the assembled melanin material 14B ′ is facilitated. It can be carried out. Also,
In such a prestressed state, the melanin material 14
By connecting both ends of B'to the tip of each overhanging erection portion 14A, it is possible to sufficiently resist the tensile stress generated when concrete is placed so as to bury the melanin material 14B 'thereafter. As a result, it is possible to reduce the cross section of the melanin material 14B ', so that it is possible to reduce the construction cost due to the reduction of the weight of the steel material.

【0040】ところで本実施形態においては、メラン材
14B´の両端部間に連結されたタイドケーブル120
に張力Tを付与することによりメラン材14B´にプレ
ストレスを導入するようになっているが、図5および6
に示すように、メラン材14B´の両端部端面と各張出
し架設部14Aの先端部端面との間に油圧ジャッキ12
2を介装してメラン材14B´に圧縮力Pを付与するこ
とにより、メラン材14B´にプレストレスを導入する
ことも可能である。この場合、メラン材14B´の両端
部と各張出し架設部14Aの先端部との連結を行った
後、メラン材14B´の両端部端面と各張出し架設部1
4Aの先端部端面との間にスペーサSを介装して間詰め
を行い、この間詰めが完了した後に油圧ジャッキ122
によるプレストレスを解除するようにすればよい。
By the way, in this embodiment, the tide cable 120 connected between both ends of the melanin material 14B '.
By applying tension T to the melanin material 14B ', prestress is introduced.
As shown in FIG. 2, the hydraulic jack 12 is provided between the end faces of both ends of the melanin material 14B 'and the end faces of the overhanging portions 14A.
It is also possible to introduce a prestress to the melanin material 14B 'by applying a compressive force P to the melanin material 14B' through the interposition of 2. In this case, after connecting both end portions of the melanin material 14B 'and the tip end portions of the respective overhanging erected portions 14A, both end portions of the melanin material 14B' and the respective overhanging erected portions 1 are connected.
Spacer S is interposed between the end surface of the front end of 4A and the end face, and the hydraulic jack 122 is provided after the completion of the space filling.
The prestress caused by should be released.

【0041】次に、本願第2の発明の一実施形態につい
て説明する。
Next, an embodiment of the second invention of the present application will be described.

【0042】図7および8は、本実施形態に係る橋梁架
設方法による、コンクリート製アーチ橋のアーチ部の架
設工程を示す図である。
7 and 8 are views showing a process of constructing an arch portion of a concrete arch bridge by the bridge constructing method according to this embodiment.

【0043】本実施形態に係る橋梁架設方法の対象とな
るアーチ橋は、上記実施形態と同じアーチ橋10(図1
参照)であるが、その架橋環境は上記実施形態の場合に
比して良好なものとなっている。しかしながらこの架橋
環境下においても、地表面2の形状はメラン材14B´
の地組みを行うには困難なものとなっている。
The arch bridge which is the target of the bridge construction method according to this embodiment is the same as the arch bridge 10 (see FIG. 1).
However, the cross-linking environment is better than that of the above embodiment. However, even in this cross-linking environment, the shape of the ground surface 2 is melanin 14B '.
It is difficult to assemble the ground.

【0044】まず、図7(a)に示すように、橋梁架設
位置の両側に1対の基礎12を施工し、これら各基礎1
2に上記橋脚16となるべき支柱を各々立設する。さら
に、これら各支柱16の背後にバックステー104を設
置する。
First, as shown in FIG. 7 (a), a pair of foundations 12 are installed on both sides of the bridge erection position.
The columns to be the bridge piers 16 are respectively installed on the column 2. Further, the back stay 104 is installed behind each of these columns 16.

【0045】次に、ワーゲン106を用いて各基礎12
からコンクリート製のアーチリブ14A´をアーチ軸に
沿って各々片持ち状に張り出し、各支柱16から斜めに
張設された斜吊りケーブル108でアーチリブ14A´
を支持しながら該アーチリブ14A´を伸長施工するこ
とにより、上記張出し架設部14Aを構築する。なお、
両方の張出し架設部14Aが完成するのは図(c)の段
階である。
Next, each foundation 12 using the Wagen 106
Concrete arch ribs 14A ′ are cantilevered along the arch axis, and the arch ribs 14A ′ are diagonally stretched from the columns 16 by diagonally extending cables 108.
By extending the arch ribs 14A ′ while supporting the above, the overhanging erected portion 14A is constructed. In addition,
Completion of both overhanging installation parts 14A is a stage of Drawing (c).

【0046】これと並行して、両支柱16の先端相互間
に主索ケーブル112をその中央部が地表面2近くまで
垂れ下がるように張り渡し、支柱16の背後にバックケ
ーブル114を張設する。主索ケーブル112には複数
のハンガー索118を所定間隔で設置する。
In parallel with this, a main cable 112 is stretched between the tips of both columns 16 so that the central portion thereof hangs down to near the ground surface 2, and a back cable 114 is stretched behind the column 16. A plurality of hanger cables 118 are installed on the main cable 112 at predetermined intervals.

【0047】次に、同図(b)に示すように、地表面2
に1対の架台124を所定間隔で設置した後、トラック
クレーン126によりメラン材構成ブロック14bを吊
支持して、両端に位置するハンガー索118に吊り換え
るとともに、該メラン材構成ブロック14bを架台12
4に係止する。
Next, as shown in FIG.
After a pair of pedestals 124 are installed at predetermined intervals, the melan material constituting block 14b is hung and supported by a truck crane 126 and is suspended by the hanger ropes 118 located at both ends, and the melan material constituting block 14b is hung.
Lock to 4.

【0048】そして、同図(c)に示すように、トラッ
ククレーン126により次のメラン材構成ブロック14
bを吊支持して隣接するハンガー索118に吊り換え、
両メラン材構成ブロック14bを互いに連結する。以
下、このメラン材構成ブロック14bの直吊り連結作業
を中央に向けて順次行い、最後に中央に位置するハンガ
ー索118に吊り換えたメラン材構成ブロック14bを
その両側のメラン材構成ブロック14bに連結すること
によりメラン材14B´を組み立てる。
Then, as shown in FIG. 7C, the next melanin material building block 14 is moved by the truck crane 126.
Suspend and support b and hang it on the adjacent hanger rope 118,
Both melanin material building blocks 14b are connected to each other. Hereinafter, the direct hanging connection work of the melanin constituent block 14b is sequentially performed toward the center, and finally the melanin constituent block 14b suspended on the hanger rope 118 located in the center is connected to the melanin constituent blocks 14b on both sides thereof. By doing so, the melanin material 14B 'is assembled.

【0049】続いて、同図(d)に示すように、メラン
材14B´の両端部間をタイドケーブル120で連結す
る。
Subsequently, as shown in FIG. 6D, both ends of the melan material 14B 'are connected by a tide cable 120.

【0050】次に、図8(e)に示すように、両張出し
架設部14Aの先端部のワーゲン106から垂下したス
テップロッド128の下端部をメラン材14B´の両端
部に連結するとともに、タイドケーブル120に初期張
力T1を付与してメラン材14B´に暫定的なプレスト
レスを導入する。
Next, as shown in FIG. 8 (e), the lower end of the step rod 128 hanging from the wagon 106 at the tip of the two overhanging parts 14A is connected to both ends of the melanin material 14B ', and at the same time, the tide is applied. An initial tension T1 is applied to the cable 120 to introduce a temporary prestress into the melanin material 14B '.

【0051】その後、図(f)に示すように、主索ケー
ブル112、バックケーブル114およびハンガー索1
18を撤去するとともに、各ワーゲン106に設置され
たリフトアップジャッキ130によりメラン材14B´
を僅かに吊り上げて架台124も撤去し、この状態で、
タイドケーブル120に2次張力T2を付与してメラン
材14B´に所期のプレストレスを導入する。
After that, as shown in FIG. 6F, the main cable 112, the back cable 114 and the hanger cable 1
18 is removed, and the melanin material 14B 'by the lift-up jacks 130 installed on each wagon 106.
Is slightly lifted and the gantry 124 is also removed. In this state,
The secondary tension T2 is applied to the tide cable 120 to introduce the desired prestress to the melanin material 14B '.

【0052】次に、図(g)に示すように、リフトアッ
プジャッキ130によりメラン材14B´を両張出し架
設部14Aの延長上(アーチ軸上)まで吊り上げる。ス
テップロッド128は、所定長の鋼棒を連結してなるロ
ッドであって、上記吊上げの際、所定量吊り上げるたび
に、上端に位置する鋼棒を順次取り外せるようになって
いる。
Next, as shown in FIG. 7G, the melanin material 14B 'is lifted up by the lift-up jack 130 to the extension of the bulging parts 14A (on the arch shaft). The step rod 128 is a rod formed by connecting steel rods of a predetermined length, and the steel rod located at the upper end can be sequentially removed each time a predetermined amount is lifted during the lifting.

【0053】その後、図(h)に示すように、メラン材
14B´の両端部を各張出し架設部14Aの先端部に連
結した後、タイドケーブル120によるプレストレスを
解除し、該タイドケーブル120を撤去する。
After that, as shown in FIG. 6 (h), both ends of the melanin material 14B 'are connected to the tips of the overhanging portions 14A, and then the prestress by the tide cable 120 is released, and the tide cable 120 is removed. To remove.

【0054】最後に、ワーゲン106を用いて、メラン
材14B´を埋め込むようにコンクリートを打設するこ
とにより、上記メラン架設部14Bの施工を行い上記ア
ーチ部14を完成させる。
Finally, by using the wagon 106, concrete is placed so as to embed the melanin material 14B ', thereby constructing the melanin installation portion 14B and completing the arch portion 14.

【0055】以上詳述したように、本実施形態に係る橋
梁架設方法は、橋梁架設位置の両側に立設された1対の
支柱16間に張り渡された主索ケーブル112に複数の
メラン材構成ブロック14bを吊支持した状態で、これ
らメラン材構成ブロック14bを互いに連結してメラン
材14B´を組み立てるようになっているので、メラン
材の地組みが困難な架橋環境下においてもメラン材の組
み立てを行うことができる。
As described above in detail, in the bridge construction method according to this embodiment, the main rope cable 112 stretched between the pair of stanchions 16 erected on both sides of the bridge construction position is provided with a plurality of melanin materials. Since the melanin material block 14b 'is assembled by connecting the melanin material block 14b to each other in a state where the building block 14b is suspended and supported, the melanin material can be formed even in a bridging environment where it is difficult to assemble the melanin material. Assembly can be done.

【0056】しかも本実施形態においては、メラン材1
4B´の重量がすべて主索ケーブル112に支持される
ので、メラン材14B´を組み立てる際の応力管理が不
要となり、片持ち張出し架設工法に比して施工性が大幅
に向上する。
Moreover, in this embodiment, the melanin material 1 is used.
Since the weight of 4B 'is entirely supported by the main cable 112, stress management at the time of assembling the melanin material 14B' is not required, and the workability is greatly improved as compared with the cantilever overhanging method.

【0057】また本実施形態においては、メラン材14
B´の組み立てを張出し架設部14Aの施工と並行して
行うことができるので、片持ち張出し架設工法に比して
大幅に工期を短縮することができる。
In this embodiment, the melanin material 14 is used.
Since B'can be assembled in parallel with the construction of the overhanging erection portion 14A, the construction period can be significantly shortened as compared with the cantilever overhanging construction method.

【0058】さらに本実施形態においてメラン材14B
´の組み立てに用いられる主索ケーブル112、ハンガ
ー索118等の直吊り架設設備は、他の橋梁架設で使用
したものを転用することができるので、片持ち張出し架
設工法に比して架設工費を削減することができる。
Further, in this embodiment, the melanin material 14B is used.
Since the directly suspended erection equipment such as the main cable 112 and the hanger rope 118 used for assembling ′ can be diverted from those used in other bridge erection, the erection cost is higher than that of the cantilever erection method. Can be reduced.

【0059】このように本実施形態によれば、メラン材
の地組みが困難な架橋環境下においてもアーチ部の架設
を可能とした上で、片持ち張出し架設工法に比して施工
性向上、工期短縮および架設工費削減を図ることができ
る。
As described above, according to the present embodiment, the arch portion can be erected even in a bridge environment where it is difficult to assemble the melanin material, and the workability is improved as compared with the cantilever overhanging construction method. It is possible to reduce the construction period and the construction cost.

【0060】特に本実施形態においては、メラン材14
B´を組み立てる際、中央部が地表面2近くまで垂れ下
がるように張り渡された主索ケーブル112に複数のメ
ラン材構成ブロック14bを吊支持するようになってい
るので、組み立てられたメラン材14B´を両張出し架
設部14Aの延長上まで吊り上げる作業は必要となる
が、主索ケーブル112のサグ量を十分に確保すること
ができるので、直吊り架設設備の負荷(バックケーブル
114の必要アンカー力等)を大幅に軽減することがで
き、また上記実施形態のように支柱16の上端にピロン
102を設置する必要がなくなり、これにより架設工費
を大幅に削減することができる。さらに、地表面2に支
持されたトラッククレーン126を使用することが可能
となるので、作業性が良好となる。
Particularly in this embodiment, the melanin material 14 is used.
When assembling B ′, a plurality of melanin constituent blocks 14b are hung and supported by the main rope cable 112 stretched so that the central portion hangs down to near the ground surface 2, so that the assembled melanin 14B Although it is necessary to suspend ‘′ to the extension of both overhanging erection parts 14A, it is possible to secure a sufficient sag amount of the main rope cable 112, so the load of the direct erection installation equipment (required anchor force of the back cable 114). Etc.) can be significantly reduced, and it is not necessary to install the pyrone 102 on the upper end of the column 16 as in the above-described embodiment, and thus the construction cost can be significantly reduced. Further, since the truck crane 126 supported on the ground surface 2 can be used, workability is improved.

【0061】さらに本実施形態においても、メラン材1
4B´にプレストレスを導入するようになっているの
で、組み立てられたメラン材14B´の応力管理を容易
に行うことができる。また、このようにプレストレスを
付与した状態でメラン材14B´の両端部を各張出し架
設部14Aの先端部に連結することにより、その後メラ
ン材14B´を埋め込むようにコンクリートを打設した
ときに生じる引張応力に対して十分に抵抗させることが
できる。そしてこれによりメラン材14B´の断面の縮
小化を図ることができるので、鋼材重量の減少による架
設工費の削減を図ることができる。
Further, also in this embodiment, the melanin material 1 is used.
Since the prestress is introduced into 4B ', the stress of the assembled melanin material 14B' can be easily controlled. Further, by connecting both ends of the melanin material 14B 'to the tip of each overhanging erection portion 14A in a state where the prestress is applied in this way, when concrete is subsequently poured to embed the melanin material 14B'. It is possible to sufficiently resist the tensile stress that occurs. As a result, it is possible to reduce the cross section of the melanin material 14B ', so that it is possible to reduce the construction cost due to the reduction of the weight of the steel material.

【図面の簡単な説明】[Brief description of drawings]

【図1】本願第1の発明の一実施形態に係る橋梁架設方
法の対象となるコンクリート製アーチ橋を示す図
FIG. 1 is a diagram showing a concrete arch bridge which is a target of a bridge construction method according to an embodiment of the first invention of the present application.

【図2】本願第1の発明の一実施形態に係る橋梁架設方
法によるアーチ部の架設工程を示す図
FIG. 2 is a diagram showing a process of constructing an arch portion by a bridge construction method according to an embodiment of the first invention of the present application.

【図3】本願第1の発明の一実施形態に係る橋梁架設方
法において、プレストレスの導入によるメラン材の変形
の様子を示す図
FIG. 3 is a diagram showing how the melanin material is deformed by the introduction of prestress in the bridge construction method according to the embodiment of the first invention of the present application.

【図4】図3のIV部詳細図FIG. 4 is a detailed view of section IV in FIG.

【図5】本願第1の発明の一実施形態に係る橋梁架設方
法の変形例において、プレストレスの導入によるメラン
材の変形の様子を示す図
FIG. 5 is a diagram showing how the melanin material is deformed by the introduction of prestress in the modification example of the bridge construction method according to the embodiment of the first invention of the present application.

【図6】図5のVI部詳細図FIG. 6 is a detailed view of VI part of FIG.

【図7】本願第2の発明の一実施形態に係る橋梁架設方
法によるアーチ部の架設工程を示す図(その1)
FIG. 7 is a view showing an arch erection process by a bridge erection method according to an embodiment of the second invention of the present application (No. 1)

【図8】本願第2の発明の一実施形態に係る橋梁架設方
法によるアーチ部の架設工程を示す図(その2)
FIG. 8 is a diagram showing an erection process of an arch portion by a bridge erection method according to an embodiment of the second invention of the present application (No. 2).

【符号の説明】[Explanation of symbols]

2 地表面 10 コンクリート製アーチ橋 12 基礎 14 アーチ部 14A 張出し架設部 14A´ アーチリブ 14B メラン架設部 14B´ メラン材 14b メラン材構成ブロック 16 橋脚(支柱) 18 鉛直材 20 上床版 102 ピロン 104 バックステー 106 ワーゲン 108 斜吊りケーブル 110 ケーブルクレーン 112 主索ケーブル(ケーブル) 114 バックケーブル 116 キャリア 118 ハンガー索 120 タイドケーブル 122 油圧ジャッキ 124 架台 126 トラッククレーン 128 ステップロッド 130 リフトアップジャッキ M モルタル(早強モルタル) S スペーサ 2 ground surface 10 Concrete arch bridge 12 basics 14 Arch 14A Overhanging installation section 14A 'arch rib 14B Melan erection section 14B 'Mellan wood 14b Mellan material building block 16 Piers (posts) 18 Vertical material 20 Upper floor version 102 Pilon 104 backstay 106 Wagen 108 oblique suspension cable 110 cable crane 112 Main cable (cable) 114 back cable 116 career 118 Hanger rope 120 tide cable 122 hydraulic jack 124 mount 126 truck crane 128 step rod 130 lift up jack M mortar (early strong mortar) S spacer

───────────────────────────────────────────────────── フロントページの続き (72)発明者 中村 收志 東京都新宿区荒木町13番地の4 住友建設 株式会社内 (72)発明者 帆足 洋和 東京都新宿区荒木町13番地の4 住友建設 株式会社内 (72)発明者 斉藤 基文 東京都新宿区荒木町13番地の4 住友建設 株式会社内 (72)発明者 益子 博志 東京都新宿区荒木町13番地の4 住友建設 株式会社内 (72)発明者 米田 達則 富山県東砺波郡福野町苗島4610 川田工業 株式会社内 Fターム(参考) 2D059 AA05 BB31 BB39 CC04 GG55   ─────────────────────────────────────────────────── ─── Continued front page    (72) Inventor Nakamura Reiji             4 Sumitomo Construction, 13 Araki-cho, Shinjuku-ku, Tokyo             Within the corporation (72) Inventor Hirokazu Hoashi             4 Sumitomo Construction, 13 Araki-cho, Shinjuku-ku, Tokyo             Within the corporation (72) Inventor Motofumi Saito             4 Sumitomo Construction, 13 Araki-cho, Shinjuku-ku, Tokyo             Within the corporation (72) Inventor Hiroshi Mashiko             4 Sumitomo Construction, 13 Araki-cho, Shinjuku-ku, Tokyo             Within the corporation (72) Inventor Tatsunori Yoneda             4610 Naeshima, Fukuno-cho, Tonami-gun, Toyama Prefecture Kawada Industry             Within the corporation F term (reference) 2D059 AA05 BB31 BB39 CC04 GG55

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 橋梁架設位置の両側から延びる1対の張
出し架設部をメラン架設部で閉合することにより、コン
クリート製アーチ橋のアーチ部を架設する橋梁架設方法
において、 上記橋梁架設位置の両側に立設された1対の支柱間にケ
ーブルを張り渡し、このケーブルに複数のメラン材構成
ブロックを吊支持して上記両張出し架設部の延長上に配
置した状態で、これらメラン材構成ブロックを互いに連
結してメラン材を組み立てる工程と、 上記メラン材の両端部を上記各張出し架設部の先端部に
連結する工程と、 上記メラン材を埋め込むようにコンクリートを打設して
上記メラン架設部を施工する工程と、を含むことを特徴
とする橋梁架設方法。
1. A bridge erection method for constructing an arch portion of a concrete arch bridge by closing a pair of overhanging erection portions extending from both sides of the bridge erection position with a melan joint erection portion. A cable is stretched between a pair of upright columns, and a plurality of melanin material building blocks are hung and supported on the cable and arranged on the extension of both of the overhanging erection parts. The step of connecting and assembling the melanin material, the step of connecting both ends of the melanin material to the tip of each of the overhanging erection parts, and the concrete laid to embed the melanin material to construct the melanin erection part The method for constructing a bridge, comprising:
【請求項2】 橋梁架設位置の両側から延びる1対の張
出し架設部をメラン架設部で閉合することにより、コン
クリート製アーチ橋のアーチ部を架設する橋梁架設方法
において、 上記橋梁架設位置の両側に立設された1対の支柱間に、
中央部が地表面近くまで垂れ下がるようにケーブルを張
り渡し、このケーブルに複数のメラン材構成ブロックを
吊支持した状態で、これらメラン材構成ブロックを互い
に連結してメラン材を組み立てる工程と、 上記メラン材の両端部間をタイドケーブルで連結する工
程と、 上記各張出し架設部の先端部から上記メラン材の両端部
を吊支持して該メラン材を上記両張出し架設部の延長上
まで吊り上げる工程と、 上記メラン材の両端部を上記各張出し架設部の先端部に
連結する工程と、 上記メラン材を埋め込むようにコンクリートを打設して
上記メラン架設部を施工する工程と、を含むことを特徴
とする橋梁架設方法。
2. A bridge erection method for constructing an arch portion of a concrete arch bridge by closing a pair of overhanging erection portions extending from both sides of the bridge erection position with a melan joint erection portion. Between a pair of upright columns,
Assembling the melanin material by connecting the melanin material building blocks to each other while suspending and supporting the cable so that the center part hangs down to near the ground surface and suspending and supporting the plurality of melanin material building blocks on the cable. A step of connecting both end portions of the material with a tide cable, and a step of suspending and supporting both end portions of the melanin material from the tip end portion of each of the overhanging erection portions and lifting the melanin material up to an extension of the both erection overhanging portions. And a step of connecting both ends of the melanin material to the tip of each of the overhanging portions, and a step of placing concrete by embedding the melanin material to construct the melanin erection portion. How to build a bridge.
【請求項3】 上記メラン材の両端部を上記各張出し架
設部に連結する前に該メラン材にプレストレスを導入す
るとともに、該連結終了後に上記プレストレスを解除す
ることを特徴とする請求項1または2記載の橋梁架設方
法。
3. The prestress is introduced into the melanin material before connecting both ends of the melanin material to each of the overhanging erection parts, and the prestress is released after the connection is completed. The bridge construction method described in 1 or 2.
JP24122598A 1998-08-27 1998-08-27 Bridge erection method Pending JP2000064227A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24122598A JP2000064227A (en) 1998-08-27 1998-08-27 Bridge erection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24122598A JP2000064227A (en) 1998-08-27 1998-08-27 Bridge erection method

Publications (1)

Publication Number Publication Date
JP2000064227A true JP2000064227A (en) 2000-02-29

Family

ID=17071073

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24122598A Pending JP2000064227A (en) 1998-08-27 1998-08-27 Bridge erection method

Country Status (1)

Country Link
JP (1) JP2000064227A (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1330829C (en) * 2004-03-24 2007-08-08 大连理工大学 Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge
JP2012122305A (en) * 2010-12-10 2012-06-28 Ihi Infrastructure Systems Co Ltd Arched bridge cross-linking method
CN103643637A (en) * 2013-12-03 2014-03-19 中铁八局集团市政工程有限公司 Long-span concrete filled steel tube arch bridge construction method achieved through integral lifting on site after vertical turning
CN105019356A (en) * 2015-04-28 2015-11-04 中国电建集团贵阳勘测设计研究院有限公司 Suspending and pulling combined erection construction method and device
JP2016023523A (en) * 2014-07-24 2016-02-08 株式会社Ihiインフラシステム Construction method for arch bridge
CN106120573A (en) * 2016-06-30 2016-11-16 中国化学工程第三建设有限公司 Multispan cable-carried arch bridge self-balancing button over strait hangs construction method
CN106284083A (en) * 2016-08-15 2017-01-04 云南云岭桥隧科技有限公司 Pushing tow climbs shifting formula cable crane arch bridge hanging method
CN106758752A (en) * 2016-12-21 2017-05-31 北京建筑大学 Leaning tower oblique pull abnormity arch bridge and its construction method
CN107905108A (en) * 2017-11-14 2018-04-13 宝鸡中铁宝桥天元实业发展有限公司 Tubular arch bolted web member hole group's accuracy control method
CN108894114A (en) * 2018-07-12 2018-11-27 贵州路桥集团有限公司 A kind of pylon based on ultrasonic displacement sensor adjusts cable system automatically
CN108894115A (en) * 2018-07-12 2018-11-27 贵州路桥集团有限公司 A kind of pylon based on laser range sensor adjusts cable system automatically
CN108894113A (en) * 2018-07-12 2018-11-27 贵州路桥集团有限公司 A kind of pylon adjusts cable system and method automatically
CN108894112A (en) * 2018-07-12 2018-11-27 贵州路桥集团有限公司 A kind of deformation of pylon pre-tightens and system for automatically correcting
CN109000601A (en) * 2018-07-12 2018-12-14 贵州路桥集团有限公司 A kind of pylon offset dynamic observation system
CN109235269A (en) * 2018-09-29 2019-01-18 中铁建大桥工程局集团第工程有限公司 A kind of steel box arch rib buckling and hanging method construction method of installation
CN109853352A (en) * 2019-01-30 2019-06-07 中铁大桥局第七工程有限公司 Rib-lifting section operation platform and its setting method
CN109898425A (en) * 2019-03-29 2019-06-18 中铁八局集团有限公司 A kind of construction method with Inclined cable-stayed cantilever pouring concrete arch-type bridge arch ring
CN110685232A (en) * 2019-11-05 2020-01-14 广西路桥工程集团有限公司 Method for installing support-free arch ring of concrete-filled steel tube arch bridge
CN110904854A (en) * 2019-12-25 2020-03-24 中交路桥华南工程有限公司 Arch bridge construction method adapting to removal progress
CN117230716A (en) * 2023-08-23 2023-12-15 中铁广州工程局集团有限公司 Pedestrian bridge and existing building connecting pedestrian ramp construction method

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1330829C (en) * 2004-03-24 2007-08-08 大连理工大学 Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge
JP2012122305A (en) * 2010-12-10 2012-06-28 Ihi Infrastructure Systems Co Ltd Arched bridge cross-linking method
CN103643637A (en) * 2013-12-03 2014-03-19 中铁八局集团市政工程有限公司 Long-span concrete filled steel tube arch bridge construction method achieved through integral lifting on site after vertical turning
CN103643637B (en) * 2013-12-03 2015-08-05 中铁八局集团市政工程有限公司 Original position construction method for lifting whole after the first vertical transfer of Long-Span Concrete Filled Steel Tubular Arch Bridges
JP2016023523A (en) * 2014-07-24 2016-02-08 株式会社Ihiインフラシステム Construction method for arch bridge
CN105019356A (en) * 2015-04-28 2015-11-04 中国电建集团贵阳勘测设计研究院有限公司 Suspending and pulling combined erection construction method and device
CN106120573A (en) * 2016-06-30 2016-11-16 中国化学工程第三建设有限公司 Multispan cable-carried arch bridge self-balancing button over strait hangs construction method
CN106120573B (en) * 2016-06-30 2018-03-16 中国化学工程第三建设有限公司 Multispan cable-carried arch bridge self-balancing button over strait hangs construction method
CN106284083A (en) * 2016-08-15 2017-01-04 云南云岭桥隧科技有限公司 Pushing tow climbs shifting formula cable crane arch bridge hanging method
CN106758752A (en) * 2016-12-21 2017-05-31 北京建筑大学 Leaning tower oblique pull abnormity arch bridge and its construction method
CN106758752B (en) * 2016-12-21 2019-06-21 北京建筑大学 Leaning tower oblique pull abnormity arch bridge and its construction method
CN107905108A (en) * 2017-11-14 2018-04-13 宝鸡中铁宝桥天元实业发展有限公司 Tubular arch bolted web member hole group's accuracy control method
CN108894115A (en) * 2018-07-12 2018-11-27 贵州路桥集团有限公司 A kind of pylon based on laser range sensor adjusts cable system automatically
CN108894114A (en) * 2018-07-12 2018-11-27 贵州路桥集团有限公司 A kind of pylon based on ultrasonic displacement sensor adjusts cable system automatically
CN108894112A (en) * 2018-07-12 2018-11-27 贵州路桥集团有限公司 A kind of deformation of pylon pre-tightens and system for automatically correcting
CN109000601A (en) * 2018-07-12 2018-12-14 贵州路桥集团有限公司 A kind of pylon offset dynamic observation system
CN108894113A (en) * 2018-07-12 2018-11-27 贵州路桥集团有限公司 A kind of pylon adjusts cable system and method automatically
CN109235269A (en) * 2018-09-29 2019-01-18 中铁建大桥工程局集团第工程有限公司 A kind of steel box arch rib buckling and hanging method construction method of installation
CN109235269B (en) * 2018-09-29 2020-05-01 中铁建大桥工程局集团第一工程有限公司 Steel box arch rib buckling and hanging method installation and construction method
CN109853352A (en) * 2019-01-30 2019-06-07 中铁大桥局第七工程有限公司 Rib-lifting section operation platform and its setting method
CN109898425A (en) * 2019-03-29 2019-06-18 中铁八局集团有限公司 A kind of construction method with Inclined cable-stayed cantilever pouring concrete arch-type bridge arch ring
CN110685232A (en) * 2019-11-05 2020-01-14 广西路桥工程集团有限公司 Method for installing support-free arch ring of concrete-filled steel tube arch bridge
CN110904854A (en) * 2019-12-25 2020-03-24 中交路桥华南工程有限公司 Arch bridge construction method adapting to removal progress
CN110904854B (en) * 2019-12-25 2021-06-04 中交路桥华南工程有限公司 Arch bridge construction method adapting to removal progress
CN117230716A (en) * 2023-08-23 2023-12-15 中铁广州工程局集团有限公司 Pedestrian bridge and existing building connecting pedestrian ramp construction method
CN117230716B (en) * 2023-08-23 2024-05-07 中铁广州工程局集团有限公司 Pedestrian bridge and existing building connecting pedestrian ramp construction method

Similar Documents

Publication Publication Date Title
JP2000064227A (en) Bridge erection method
US3921362A (en) Method of and means for multi-story building construction
JP6702835B2 (en) Bridge girder erection method for multi span span bridge
CN105839536A (en) Construction method of cable-stayed bridge pylon
CN111926715B (en) Installation method of steel box girder bridge
CN104594193B (en) A kind of Hollow Slab Beam Bridge superstructure and construction method thereof
JPH11181725A (en) Method for constructing horizontal beam of main tower made of concrete
KR20070010449A (en) Construction method for arched bridge
CN104314013B (en) Two Cantilever Construction Methods of a kind of pole asymmetrical array beam
JP2001098514A (en) Method for constructing arch rib of concrete arch bridge
JP3635004B2 (en) Bridge cantilever construction method
CN107882328A (en) The construction method of large span steel truss overhung construction
JP2750368B2 (en) Construction method of reactor containment top slab
JP4104910B2 (en) How to build arch ribs for concrete arch bridges
JP2639361B2 (en) Construction method of steel pipe / concrete composite structure pier
AU2016405888A1 (en) An improved reinforcement apparatus for reinforcing a structure comprising a pier and a cross- beam
JPH0721165B2 (en) How to construct a concrete cable-stayed bridge
JP3940212B2 (en) Construction method of horizontal beams for concrete main tower.
KR101232704B1 (en) The installation and dismantlement method of main girder for bridge temporary
JP2001049622A (en) Bridge erecting apparatus and bridge erecting method
JP3908816B2 (en) Construction method of suspended floor slab bridge
JP2584418B2 (en) Overhang construction method and stress improvement device for synthetic cable-stayed bridge
JP2020186516A (en) Method of constructing bridge railing
JPS6135325B2 (en)
JPH11323838A (en) Construction method of bridge

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050518

A977 Report on retrieval

Effective date: 20070629

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Effective date: 20070710

Free format text: JAPANESE INTERMEDIATE CODE: A131

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20071113