CN114086471A - Simple and easy mobile device of bridge annex installation - Google Patents

Simple and easy mobile device of bridge annex installation Download PDF

Info

Publication number
CN114086471A
CN114086471A CN202111237855.2A CN202111237855A CN114086471A CN 114086471 A CN114086471 A CN 114086471A CN 202111237855 A CN202111237855 A CN 202111237855A CN 114086471 A CN114086471 A CN 114086471A
Authority
CN
China
Prior art keywords
bridge
sliding frame
construction
hydraulic telescopic
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111237855.2A
Other languages
Chinese (zh)
Inventor
唐丽
程静波
陈雅缘
罗彬�
杨水平
郑国勋
姜友荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN202111237855.2A priority Critical patent/CN114086471A/en
Publication of CN114086471A publication Critical patent/CN114086471A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a simple and easy moving device for bridge accessories, which solves the technical problem that in the prior art, the cost of construction and installation equipment is high during the installation construction of the accessories on two sides of a bridge. The invention comprises a sliding frame which is positioned on a bridge floor and can freely slide along the length direction of the bridge floor, and two construction hanging baskets which are arranged at two ends of the sliding frame and positioned at two sides of a bridge. The invention has simple structure, scientific and reasonable design and convenient use, can freely walk on the bridge deck, ensures that constructors can carry out accessory construction on two sides of the bridge without obstacles on two sides of the bridge so as to ensure the installation construction efficiency of the accessories on two sides of the bridge and the whole construction progress of the bridge, and can effectively reduce the cost of installation equipment when constructing the accessories on two sides of the bridge relative to the traditional rented hoisting platform or movable platform.

Description

Simple and easy mobile device of bridge annex installation
Technical Field
The invention belongs to the technical field of bridge construction, and particularly relates to a simple moving device for mounting bridge accessories.
Background
The bridge generally comprises an upper structure, a lower structure, a support and an auxiliary structure, wherein the upper structure is also called a bridge span structure and is a main structure for spanning obstacles; the lower structure comprises a bridge abutment, a bridge pier and a foundation; the support is a force transmission device arranged at the supporting positions of the bridge span structure and the bridge pier or the bridge abutment; the auxiliary structures refer to bridge end butt straps, tapered revetments, diversion works and the like.
The bridge is divided according to the stress characteristics and comprises five basic types, namely a beam bridge, an arch bridge, a rigid bridge, a suspension bridge and a combined system bridge (a cable-stayed bridge).
A bridge generally consists of five major components and five minor components.
The five parts refer to bridge span upper structure and lower structure of the bridge bearing the transportation load of automobiles or other vehicles, and guarantee the safety of the bridge structure. The bridge comprises a bridge span structure (or called a bridge hole structure or a superstructure), a bridge support system, a bridge pier, a bridge abutment, a bearing platform and a well digging or pile foundation.
Widgets refer to components that are directly related to bridge service functions and have been referred to in the past as deck constructions. The large-scale bridge auxiliary structure comprises bridge deck pavement, a waterproof and drainage system, railings, expansion joints, lighting, a large-scale bridge auxiliary structure, a bridge head fort, an approach bridge and the like.
In the bridge construction process, the conventional installation operation of the accessories (auxiliary structures) on two sides of the bridge is to adopt a hoisting platform or a movable platform for installation and construction. The hoisting platform or the movable platform is generally supplied by leasing, and the leasing cost of installation equipment is high when the accessories on two sides of the bridge are installed and constructed.
Therefore, the simple and easy mobile device for installing the bridge accessories is designed, so that the cost of installation equipment is effectively reduced on the basis of ensuring the installation and construction efficiency of the accessories on two sides of the bridge and the construction progress, and the technical problem to be solved by technical personnel in the technical field is urgently needed.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: the utility model provides a bridge annex installation simple and easy mobile device to solve at least some technical problems.
In order to achieve the purpose, the technical scheme adopted by the invention is as follows:
the utility model provides a simple and easy mobile device of bridge accessories installation, is including being located the bridge floor and can freely slide along bridge floor length direction's the frame that slides to and locate two construction hanging baskets that slide frame both ends and be located the bridge both sides.
Furthermore, a tool box for placing bridge accessory parts is arranged on the sliding frame.
Furthermore, the bottom of the tool box is provided with a counterweight layer filled with stones or iron blocks.
Furthermore, a sunshade is arranged between the tool box and the construction hanging basket.
Furthermore, the bottom of the sliding frame is at least provided with four universal wheels.
Furthermore, the bottom of the sliding frame is provided with a first hydraulic telescopic sleeve, and the universal wheel is installed at the bottom of the first hydraulic telescopic sleeve.
Furthermore, a small hydraulic station which is connected with the first hydraulic telescopic sleeve and used for providing power for the first hydraulic telescopic sleeve is arranged in the tool box.
Furthermore, the end part of the sliding frame is provided with a second hydraulic telescopic sleeve connected with the small hydraulic station, and the sliding frame, the second hydraulic telescopic sleeve and the construction hanging basket are sequentially connected.
Furthermore, the end part of the sliding frame and the top of the construction hanging basket are respectively provided with a hydraulic telescopic sleeve mounting seat, and a second hydraulic telescopic sleeve is arranged between the two hydraulic telescopic sleeve mounting seats.
Furthermore, the end part of the sliding frame is hung with a pedestrian ladder leading to the construction hanging basket, the top of the pedestrian ladder is provided with a hook, the pedestrian ladder is hung at the end part of the sliding frame through the hook, and the sliding frame and the construction hanging basket are of a steel frame structure.
Compared with the prior art, the invention has the following beneficial effects:
the invention has simple structure, scientific and reasonable design and convenient use, can freely walk on the bridge deck, ensures that constructors can carry out accessory construction on two sides of the bridge without obstacles on two sides of the bridge so as to ensure the installation construction efficiency of the accessories on two sides of the bridge and the whole construction progress of the bridge, and can effectively reduce the cost of installation equipment when constructing the accessories on two sides of the bridge relative to the traditional rented hoisting platform or movable platform.
The invention mainly comprises a sliding frame and a construction hanging basket, wherein the sliding frame can freely slide along the length direction of a bridge deck, bridge accessories constructors can install and construct bridge accessories in the construction hanging basket, the constructors in the construction hanging basket can comprehensively install and construct the accessories on two sides of the bridge along with the free sliding of the sliding frame along the length direction of the bridge deck, the price of the whole installation equipment is quite low, meanwhile, the installation efficiency of the accessories on two sides of the bridge can be effectively ensured, and the arrangement construction progress of the bridge is ensured.
The sliding frame is provided with a tool box, a weight layer, a sunshade and four universal wheels. The accessory parts on the two sides of the bridge can be placed in the tool box, construction personnel can conveniently take the accessory parts on the site, the construction efficiency can be effectively improved, the design of the weight layer in the tool box can effectively prevent the construction personnel from turning on one's side when the accessory parts on the two sides of the bridge are installed and constructed, and the construction safety is guaranteed. The sunshade can effectively improve the construction environment of bridge constructors and reduce the discomfort of the constructors in the installation and construction of accessories on two sides of the bridge. The design of four universal wheels can ensure that the sliding frame slides freely on the bridge deck.
According to the invention, the first hydraulic telescopic sleeves are arranged between the bottom of the sliding frame and the universal wheels, and when higher attachments are arranged on two sides of the bridge, the first hydraulic telescopic sleeves are driven to extend through the small hydraulic station so as to avoid the attachments on the two sides of the bridge, so that the attachments on the two sides of the bridge can be rapidly and efficiently installed on the parts with the higher attachments on the two sides of the bridge, and the bridge arrangement construction progress can be effectively ensured.
According to the invention, the hydraulic telescopic sleeve mounting seat and the second hydraulic telescopic sleeve are arranged between the sliding frame and the construction hanging basket, when higher attachments are arranged on two sides of the bridge and the first hydraulic telescopic sleeve extends to avoid the attachments on the two sides of the bridge, the situation that the construction hanging basket rises to carry out incomplete installation and construction on the attachments below the two sides of the bridge occurs, and at the moment, the second hydraulic telescopic sleeve is driven to extend through the small hydraulic station, so that the requirement of bridge construction personnel on the complete installation and construction of the attachments on the two sides of the bridge is met, and the installation and construction quality and efficiency of the attachments on the two sides of the bridge are ensured.
The invention is characterized in that the end part of the sliding frame is hung with a pedestrian ladder leading to the construction hanging basket, so that constructors can smoothly enter the construction hanging basket, and the length of the pedestrian ladder is not shorter than the distance from the end part of the sliding frame to the inner bottom part of the construction hanging basket when the second hydraulic telescopic sleeve extends to the maximum stroke.
Drawings
FIG. 1 is a schematic view of the structure of the present invention.
Fig. 2 is a schematic view of the pedestrian ladder of the present invention.
Figure 3 is a side view of the pedestrian ladder of the present invention.
Wherein, the names corresponding to the reference numbers are:
the method comprises the following steps of 1-sliding frame, 2-construction hanging basket, 3-tool box, 4-counterweight layer, 5-sunshade, 6-universal wheel, 7-first hydraulic telescopic sleeve, 8-small hydraulic station, 9-second hydraulic telescopic sleeve, 10-hydraulic telescopic sleeve mounting seat, 11-pedestrian ladder and 12-hook.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail below with reference to the accompanying drawings. It is to be understood that the described embodiments are merely exemplary of the invention, and not restrictive of the full scope of the invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1-3, the simple moving device for mounting bridge accessories provided by the invention has the advantages of simple structure, scientific and reasonable design and convenient use, can freely walk on the bridge floor, ensures that constructors can carry out accessory construction on two sides of a bridge without obstacles on two sides of the bridge, ensures the mounting construction efficiency of the accessories on two sides of the bridge and the overall construction progress of the bridge, and can effectively reduce the cost of mounting equipment compared with the traditional renting hoisting platform or moving platform for the accessories on two sides of the bridge. The invention comprises a sliding frame 1 which is positioned on a bridge floor and can freely slide along the length direction of the bridge floor, and two construction hanging baskets 2 which are arranged at two ends of the sliding frame 1 and positioned at two sides of a bridge.
The invention mainly comprises a sliding frame and a construction hanging basket, wherein the sliding frame can freely slide along the length direction of a bridge deck, bridge accessories constructors can install and construct bridge accessories in the construction hanging basket, the constructors in the construction hanging basket can comprehensively install and construct the accessories on two sides of the bridge along with the free sliding of the sliding frame along the length direction of the bridge deck, the price of the whole installation equipment is quite low, meanwhile, the installation efficiency of the accessories on two sides of the bridge can be effectively ensured, and the arrangement construction progress of the bridge is ensured.
The sliding frame 1 is provided with a tool box 3 for placing bridge accessory parts. The bottom of the tool box 3 is provided with a balance weight layer 4 filled with stones or iron blocks. A sunshade 5 is arranged between the tool box 3 and the construction hanging basket 2. The bottom of the sliding frame 1 is at least provided with four universal wheels 6.
The sliding frame is provided with a tool box, a weight layer, a sunshade and four universal wheels. The accessory parts on the two sides of the bridge can be placed in the tool box, construction personnel can conveniently take the accessory parts on the site, the construction efficiency can be effectively improved, the design of the weight layer in the tool box can effectively prevent the construction personnel from turning on one's side when the accessory parts on the two sides of the bridge are installed and constructed, and the construction safety is guaranteed. The sunshade can effectively improve the construction environment of bridge constructors and reduce the discomfort of the constructors in the installation and construction of accessories on two sides of the bridge. The design of four universal wheels can ensure that the sliding frame slides freely on the bridge deck.
The bottom of the sliding frame 1 is provided with a first hydraulic telescopic sleeve 7, and the universal wheel 6 is arranged at the bottom of the first hydraulic telescopic sleeve 7. A small hydraulic station 8 connected with the first hydraulic telescopic sleeve 7 and used for providing power for the first hydraulic telescopic sleeve 7 is arranged in the tool box 3.
According to the invention, the first hydraulic telescopic sleeves are arranged between the bottom of the sliding frame and the universal wheels, and when higher attachments are arranged on two sides of the bridge, the first hydraulic telescopic sleeves are driven to extend through the small hydraulic station so as to avoid the attachments on the two sides of the bridge, so that the attachments on the two sides of the bridge can be rapidly and efficiently installed on the parts with the higher attachments on the two sides of the bridge, and the bridge arrangement construction progress can be effectively ensured.
The end part of a sliding frame 1 is provided with a second hydraulic telescopic sleeve 9 connected with a small hydraulic station 8, and the sliding frame 1, the second hydraulic telescopic sleeve 9 and a construction hanging basket 2 are sequentially connected. The end part of the sliding frame 1 and the top of the construction hanging basket 2 are respectively provided with a hydraulic telescopic sleeve mounting seat 10, and a second hydraulic telescopic sleeve 9 is arranged between the two hydraulic telescopic sleeve mounting seats 10.
According to the invention, the hydraulic telescopic sleeve mounting seat and the second hydraulic telescopic sleeve are arranged between the sliding frame and the construction hanging basket, when higher attachments are arranged on two sides of the bridge and the first hydraulic telescopic sleeve extends to avoid the attachments on the two sides of the bridge, the situation that the construction hanging basket rises to carry out incomplete installation and construction on the attachments below the two sides of the bridge occurs, and at the moment, the second hydraulic telescopic sleeve is driven to extend through the small hydraulic station, so that the requirement of bridge construction personnel on the complete installation and construction of the attachments on the two sides of the bridge is met, and the installation and construction quality and efficiency of the attachments on the two sides of the bridge are ensured.
The end part of a sliding frame 1 is hung with a pedestrian ladder 11 leading to a construction hanging basket 2, the top of the pedestrian ladder 11 is provided with a hook 12, the pedestrian ladder 11 is hung at the end part of the sliding frame 1 through the hook 12, and the sliding frame 1 and the construction hanging basket 2 are both of steel frame structures.
The invention is characterized in that the end part of the sliding frame is hung with a pedestrian ladder leading to the construction hanging basket, so that constructors can smoothly enter the construction hanging basket, and the length of the pedestrian ladder is not shorter than the distance from the end part of the sliding frame to the inner bottom part of the construction hanging basket when the second hydraulic telescopic sleeve extends to the maximum stroke.
The invention uses lever principle to support the sliding frame on the bridge floor by four pulleys to walk. Through four universal wheels walking on the bridge floor, the middle toolbox is put some instrument and the part that need in the work progress to can also prevent that both sides construction hanging flower basket weight is overweight and topples. The two-side construction hanging baskets facilitate the installation operation of the accessories on the two sides of the bridge when a person stands on the construction hanging baskets. The sliding frame and the construction hanging basket are formed by welding small rectangular pipes, so that the self weight is light, the use is light and the sliding frame can be repeatedly used. When the bridges on the two sides have higher attachments, the barriers can be effectively avoided by extending the first hydraulic telescopic sleeve and the second hydraulic telescopic sleeve, and the application range of the invention can be effectively expanded.
The invention utilizes the universal wheels to walk, is simple, convenient and easy to realize, has low cost and can meet the requirement. The invention uses two construction hanging baskets to cross two sides of the bridge floor, can effectively apply force and can move quickly, and the thought is ingenious and easy to realize. The invention can cross the barrier by increasing the height of the travelling mechanism, and can effectively and quickly carry out the installation operation of accessories on two sides of the bridge when high accessories are arranged on two sides of the bridge. The tool box on the sliding frame can be used for placing more components, and the components do not need to be manually moved on the bridge floor, so that labor force is liberated.
Finally, it should be noted that: the above embodiments are only preferred embodiments of the present invention to illustrate the technical solutions of the present invention, but not to limit the technical solutions, and certainly not to limit the patent scope of the present invention; while the invention has been described in detail and with reference to the foregoing embodiments, it will be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; the modifications or the substitutions do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the embodiments of the present invention; that is, the technical problems to be solved by the present invention, which are not substantially changed or supplemented by the spirit and the concept of the main body of the present invention, are still consistent with the present invention and shall be included in the scope of the present invention; in addition, the technical scheme of the invention is directly or indirectly applied to other related technical fields, and the technical scheme is included in the patent protection scope of the invention.

Claims (10)

1. The utility model provides a simple and easy mobile device of bridge accessories installation which characterized in that, including be located the bridge floor and can freely slide along bridge floor length direction's frame (1) that slides to and locate two construction hanging flower baskets (2) that slide frame (1) both ends and be located the bridge both sides.
2. The simple moving device for bridge accessory installation according to claim 1, wherein the sliding frame (1) is provided with a tool box (3) for placing bridge accessory parts.
3. The simple moving device for bridge accessories installation according to claim 2, characterized in that the bottom of the tool box (3) is provided with a weight layer (4) filled with stones or iron blocks.
4. The simple moving device for bridge accessories installation according to claim 2, characterized in that a sunshade (5) is arranged between the tool box (3) and the construction basket (2).
5. The simple moving device for bridge accessory installation according to claim 2, characterized in that the bottom of the sliding frame (1) is provided with at least four universal wheels (6).
6. The simple moving device for bridge accessory installation according to claim 5, wherein a first hydraulic telescopic sleeve (7) is arranged at the bottom of the sliding frame (1), and the universal wheels (6) are arranged at the bottom of the first hydraulic telescopic sleeve (7).
7. The simple moving device for bridge accessory installation according to claim 6, characterized in that a small hydraulic station (8) connected with the first hydraulic telescopic sleeve (7) for providing power for the first hydraulic telescopic sleeve (7) is arranged in the tool box (3).
8. The simple moving device for bridge accessory installation according to claim 7, characterized in that the end of the sliding frame (1) is provided with a second hydraulic telescopic sleeve (9) connected with the small hydraulic station (8), and the sliding frame (1), the second hydraulic telescopic sleeve (9) and the construction hanging basket (2) are connected in sequence.
9. The simple moving device for bridge accessory installation according to claim 8, characterized in that the end of the sliding frame (1) and the top of the construction hanging basket (2) are respectively provided with a hydraulic telescopic sleeve installation seat (10), and the second hydraulic telescopic sleeve (9) is installed between the two hydraulic telescopic sleeve installation seats (10).
10. The simple moving device for bridge accessory installation according to claim 1, characterized in that a pedestrian ladder (11) leading to the construction hanging basket (2) is hung at the end of the sliding frame (1), a hook (12) is arranged at the top of the pedestrian ladder (11), the pedestrian ladder (11) is hung at the end of the sliding frame (1) through the hook (12), and the sliding frame (1) and the construction hanging basket (2) are both of steel frame structure.
CN202111237855.2A 2021-10-25 2021-10-25 Simple and easy mobile device of bridge annex installation Pending CN114086471A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111237855.2A CN114086471A (en) 2021-10-25 2021-10-25 Simple and easy mobile device of bridge annex installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111237855.2A CN114086471A (en) 2021-10-25 2021-10-25 Simple and easy mobile device of bridge annex installation

Publications (1)

Publication Number Publication Date
CN114086471A true CN114086471A (en) 2022-02-25

Family

ID=80297497

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111237855.2A Pending CN114086471A (en) 2021-10-25 2021-10-25 Simple and easy mobile device of bridge annex installation

Country Status (1)

Country Link
CN (1) CN114086471A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114890069A (en) * 2022-06-24 2022-08-12 安徽康新建设工程有限公司 Transfer device capable of conveniently conveying objects to two ends of bridge and conveying method thereof

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000144635A (en) * 1998-11-18 2000-05-26 Dekku:Kk Method of constructing sound absorbing scaffold under elevated bridge
KR100619277B1 (en) * 2006-01-16 2006-09-08 사단법인 대한산업안전협회 Apparatus diagnosing safety movable of suspension bridge
CN106869025A (en) * 2017-03-27 2017-06-20 鲁东大学 A kind of Detection System for Bridge and its method
CN107476202A (en) * 2017-09-29 2017-12-15 中国十七冶集团有限公司 A kind of plug-in template of Collison fence for bridge can adjust peace and tear support and its application method open
CN109763423A (en) * 2018-12-24 2019-05-17 中建三局集团有限公司 A kind of adjustable split-type movable hanging basket and operating method for bridge maintenance
CN110158460A (en) * 2019-05-24 2019-08-23 中铁十局集团第一工程有限公司 Construction operation movable hanging basket and its construction method under across electric railway Bridge Beam
CN210262739U (en) * 2019-06-10 2020-04-07 中交二公局第三工程有限公司 Bridge drainage pipe installation trolley system
CN210288107U (en) * 2019-05-28 2020-04-10 宁波交通工程咨询监理有限公司 Hanging basket for bridge engineering
CN211571394U (en) * 2020-01-06 2020-09-25 广西正景机械制造有限公司 Novel bridge inspection construction equipment
CN112942110A (en) * 2021-01-21 2021-06-11 北京市政路桥股份有限公司 Convenient and fast movable type bridge centralized drainage pipeline installation operation platform

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000144635A (en) * 1998-11-18 2000-05-26 Dekku:Kk Method of constructing sound absorbing scaffold under elevated bridge
KR100619277B1 (en) * 2006-01-16 2006-09-08 사단법인 대한산업안전협회 Apparatus diagnosing safety movable of suspension bridge
CN106869025A (en) * 2017-03-27 2017-06-20 鲁东大学 A kind of Detection System for Bridge and its method
CN107476202A (en) * 2017-09-29 2017-12-15 中国十七冶集团有限公司 A kind of plug-in template of Collison fence for bridge can adjust peace and tear support and its application method open
CN109763423A (en) * 2018-12-24 2019-05-17 中建三局集团有限公司 A kind of adjustable split-type movable hanging basket and operating method for bridge maintenance
CN110158460A (en) * 2019-05-24 2019-08-23 中铁十局集团第一工程有限公司 Construction operation movable hanging basket and its construction method under across electric railway Bridge Beam
CN210288107U (en) * 2019-05-28 2020-04-10 宁波交通工程咨询监理有限公司 Hanging basket for bridge engineering
CN210262739U (en) * 2019-06-10 2020-04-07 中交二公局第三工程有限公司 Bridge drainage pipe installation trolley system
CN211571394U (en) * 2020-01-06 2020-09-25 广西正景机械制造有限公司 Novel bridge inspection construction equipment
CN112942110A (en) * 2021-01-21 2021-06-11 北京市政路桥股份有限公司 Convenient and fast movable type bridge centralized drainage pipeline installation operation platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114890069A (en) * 2022-06-24 2022-08-12 安徽康新建设工程有限公司 Transfer device capable of conveniently conveying objects to two ends of bridge and conveying method thereof

Similar Documents

Publication Publication Date Title
JP4264470B2 (en) Bridge girder member erection method and erection device
CN109505309B (en) Pipe gallery segment displacement system and pipe gallery installation method using same
CN205294665U (en) Jack -up tower crane based on engineering mechanics
CN217378620U (en) Intelligent bridge erecting system
CN116553372A (en) Lifting equipment for bridge construction and bridge construction method
CN210561749U (en) Multi-frame juxtaposed double-cantilever bridge girder erection machine
CN210684480U (en) Steel arch assembling and transverse moving system for deck type arch bridge construction
CN114086471A (en) Simple and easy mobile device of bridge annex installation
CN112160773A (en) Tunnel lining reinforcing steel bar trolley and lining reinforcing steel bar binding construction method
CN114104990A (en) Cable crane steel pipe assembling type cable buckle integrated tower construction process
CN112323657A (en) Integrated prefabricated bridge dismantling machine and prefabricated bridge dismantling method
CN210366808U (en) Lifting and dismantling device for rail walking
CN102225580B (en) Method for longitudinally moving box girder internal mold
CN215925692U (en) Overlength multispan assembly type integrated multifunctional bridge girder erection machine
CN216549362U (en) Assembling and hoisting device for components above foundation pit
CN215208144U (en) Erection equipment
CN211524104U (en) Novel bridge girder erection machine
CN214997669U (en) Climbing type tunnel multi-step excavation rack
CN209779679U (en) Displacement system of pipe gallery segment
CN210263847U (en) Stride and establish portable construction platform on subway U type groove
CN110748163A (en) Novel bridge girder erection machine
CN112376437A (en) Steel beam crane suspension splicing equipment and construction method
CN213869897U (en) Tunnel lining reinforcing steel bar trolley
CN214143330U (en) Steel beam carrying crane suspension splicing equipment
CN115613477B (en) Main girder cantilever trackless triangular hanging basket and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220225