JP4264470B2 - Bridge girder member erection method and erection device - Google Patents

Bridge girder member erection method and erection device Download PDF

Info

Publication number
JP4264470B2
JP4264470B2 JP03576798A JP3576798A JP4264470B2 JP 4264470 B2 JP4264470 B2 JP 4264470B2 JP 03576798 A JP03576798 A JP 03576798A JP 3576798 A JP3576798 A JP 3576798A JP 4264470 B2 JP4264470 B2 JP 4264470B2
Authority
JP
Japan
Prior art keywords
girder
erection
bridge
bridge girder
traveling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP03576798A
Other languages
Japanese (ja)
Other versions
JPH10292317A (en
Inventor
里治 尾下
卓 平井
Original Assignee
株式会社横河ブリッジ
横河工事株式会社
東日本高速道路株式会社
中日本高速道路株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社横河ブリッジ, 横河工事株式会社, 東日本高速道路株式会社, 中日本高速道路株式会社 filed Critical 株式会社横河ブリッジ
Priority to JP03576798A priority Critical patent/JP4264470B2/en
Publication of JPH10292317A publication Critical patent/JPH10292317A/en
Application granted granted Critical
Publication of JP4264470B2 publication Critical patent/JP4264470B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
この発明は、橋梁を構築する際に用いて好適な、橋桁部材の架設方法および架設装置に関し、特には、橋桁部材を桁下で運搬して片持ち張り出し架設する架設方法およびそれに用い得る架設装置に関するものである。
【0002】
【従来の技術および発明が解決しようとする課題】
橋梁を構築する際に、橋桁部材の架設地点が海上や山間部であったり、あるいは作業用地の問題があったりして、架設中の橋桁部材をベントで支持できない場合には従来、送り出し工法や、ケーブルクレーン工法、一括架設工法、片持ち張り出し架設工法等が行われている。
【0003】
ここに、送り出し工法とは、架設する橋梁の両端または片端の位置する場所から橋桁部材を送り出して架設する方法であり、またケーブルクレーン工法とは、橋梁の両端の位置する場所間に架け渡したケーブルクレーンを用いて橋桁部材を吊り上げて架設する方法であり、これらの方法では、架設する橋梁の両端または片端の位置する場所に、架設設備の設置や部材の搬入用の作業用地を確保する必要がある。しかしながら、山間部に橋梁を架設する場合等には、橋梁端部の位置する場所が切り立った斜面であったり、橋梁端部の位置する場所にトンネルや切り土が隣接していたり、橋梁端部への取り付け道路の線形が曲がっていたりすることがあり、このような条件下では、架設に必要な作業用地を確保することが困難な場合が多い。また、たとえ作業用地を確保できても、施工にあたっては、隣接工区の状況等を考慮して施工時期や設備の検討をしなくてはならない。
【0004】
また、一括架設工法とは、別の場所で組み立てておいた橋体を一括して架設する方法であり、架設地点に隣接する広い作業用地を利用して地組立てした橋体を大型のクレーンによって架設する方法と、海上または河川に架ける場合に、地組立てした橋体あるいは台船上で組み立てた橋体をフローティングクレーンを使用して架設する方法とがあるが、いずれの場合も広い作業用地や広い水域が必要となる。
【0005】
そして、片持ち張り出し架設工法とは、既に架設してある橋桁部分に橋桁部材を繋げて片持ち張り出し架設してゆく方法であり、既に架設してある橋桁部分をカウンターウエイトとしてその橋桁部分の先端に繋げて橋桁部材を架設してゆく方法と、中央の橋脚の左右に繋げてバランスをとりながら橋桁部材逐次を架設してゆく方法とがある。
【0006】
かかる片持ち張り出し架設工法用の架設設備としては、一般には、台車上に旋回アーム式クレーンを搭載してなるトラベラークレーンが利用され(昭和49年11月1日株式会社技報堂発行の土木学会編「新版土木工学ハンドブック中巻」中第1288頁参照)、海上や河川上で台船等により橋桁部材を輸送して架設位置の直下に止めておける場合にはそのトラベラークレーンからの直下吊り工法がとられることもあるが、水流等の関係で直下吊りが困難な場合には、橋脚付近の作業ヤードに輸送した橋桁部材を、既に設置してある橋桁部分上へ、橋脚の高さを上回る吊り上げ高さを持つタワークレーン等のクレーン設備で取り上げ、その橋桁部材を橋桁部分上で張り出し部の先端の架設位置まで台車によって運搬してトラベラークレーンに引き渡している。
【0007】
しかしながらこのような従来の架設技術で、橋脚付近の作業ヤードのみを使用して片持ち張り出し架設を行う場合には、トラベラクレーンは重心が高くて不安定であることから橋桁部材を吊り上げたままではバランスが悪くて橋桁部分上での高速移動が困難であるので、橋桁部材を橋桁部分上で運搬してトラベラークレーンに引き渡すための部材運搬台車が必要となり、それゆえトラベラクレーンの配置がその部材運搬台車との関係で制約されて、中央橋脚を挟んだ橋桁部分の左右の張り出し部の先端でそれぞれ橋桁部材を架設するためには二台のトラベラクレーンが必要となり、他にも、既に設置してある橋桁部分上へ橋桁部材を取り上げて上記部材運搬台車へ引き渡すためのクレーン設備等、多くの架設機材を必要とすることから、その経済性に問題があった。
【0008】
ところで、片持ち張り出し架設工法用の他の架設設備として従来、上面上に軌道を設けたエレクションガーダー(架設桁)の片端側下面にジャッキ付きの車輪とベントとを固設してなるトラベリングガーダー(移動式架設桁)と、その軌道上を走行する台車上にウインチを設けてなる架設作業車とが利用される場合もあり、かかる場合の例としては、例えば、岡山県笠岡市と神島とを結ぶ県道に3径間PC連続箱げた橋である神島大橋が建設された際にその橋桁部分の架設に用いられたものが知られている(平成6年2月20日社団法人日本道路協会編集発行の「コンクリート道路橋設計便覧」中 466 467 参照)。
【0009】
このトラベリングガーダーと架設作業車とを利用した架設方法では、既に設置してある橋桁部分の上面とトラベリングガーダーの上面との段差が比較的大きいことから、橋桁部分上に軌道を附設して作業車運搬台車を橋脚付近からトラベリングガーダー後端の位置まで走行し得るようにし、その作業車運搬台車上とトラベリングガーダー上との間で架設作業車を受渡しできるようにしておいて、橋脚付近の作業ヤードに輸送した橋桁部材を、橋桁部分上の作業車運搬台車上に移動させておいた架設作業車のウインチで桁下の位置に吊り上げ、次いで架設作業車が橋桁部材を吊り上げたままの状態で作業車運搬台車をその上に乗った架設作業車ごとトラベリングガーダー後端の位置まで移動させて、架設作業車を作業車運搬台車上からトラベリングガーダー上に移し、そのトラベリングガーダー上で架設作業車を所定の架設場所まで移動させた後、架設作業車のウインチで橋桁部材を架設位置までさらに吊り上げている。
【0010】
しかしながらこのトラベリングガーダーと架設作業車を利用する方法でも、橋脚付近の作業ヤードのみを使用して片持ち張り出し架設を行う場合には、上記のように作業車運搬台車が必要となり、それゆえその作業車運搬台車との関係でトラベリングガーダーの橋桁部分上での配置が制約されるので、中央橋脚を挟んだ橋桁部分の左右の張り出し部の先端でそれぞれ橋桁部材を架設するために手延べ方向が互いに逆になる二台のトラベリングガーダーが必要となり、他にも多くの架設機材を必要とすることからその経済性に問題があった。これがため従来は、送り出し工法やケーブルクレーン工法が、先に述べたような制約があるにもかかわらず経済性の面から採用されていた。
【0011】
【課題を解決するための手段およびその作用・効果】
この発明は、上記従来の片持ち張り出し架設工法の課題を有利に解決した橋桁部材の架設方法および架設装置を提供するものであり、請求項1記載のこの発明の橋桁部材の架設方法は、既に張り出し架設してある橋桁部分上に、エレクションガーダーと、そのエレクションガーダーを支持位置変更可能に支持して前記橋桁部分上を走行する台車とを具えるトラベリングガーダーを配設するとともに、架設する橋桁部材を吊り上げる吊り上げ機を有して前記トラベリングガーダーのエレクションガーダー上を移動する架設作業装置をそのエレクションガーダー上に搭載しておいて、先ず、前記トラベリングガーダーの台車による前記エレクションガーダーの支持位置をそのエレクションガーダーの、前記橋桁部材の架設のための手延べ方向側と逆側の部分とするとともに、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態にして、前記トラベリングガーダーを前記既に張り出し架設してある橋桁部分上の橋脚付近の位置に配置し、次いで、その橋脚付近で、前記架設作業装置の吊り上げ機により、前記橋桁部材を、前記既に張り出し架設してある橋桁部分の下方に吊り上げるとともに、前記架設作業装置を搭載した前記トラベリングガーダーを、その台車により移動させて、前記架設作業装置の吊り上げ機で吊り上げた状態の橋桁部材を、前記既に張り出し架設してある橋桁部分の下方にてその橋桁部分に沿ってその橋桁部分の先端まで運搬し、かつ、前記エレクションガーダーの手延べ方向側部分をその既に張り出し架設してある橋桁部分の先端から前方へ手延べさせ、次いで、前記トラベリングガーダーを前記既に張り出し架設してある橋桁部分に連結して浮き上がり止めしてから、前記架設作業装置を前記エレクションガーダーの前記手延べ方向側部分上に移動させ、次いで、前記架設作業装置の吊り上げ機により、前記吊り上げた状態の橋桁部材を所定の高さまで引き上げて、その橋桁部材の、前記既に張り出し架設してある橋桁部分の先端への張り出し架設を行い、次いで、前記トラベリングガーダーと前記既に張り出し架設してある橋桁部分との連結を解除してから、前記トラベリングガーダーの台車による前記エレクションガーダーの支持位置をそのエレクションガーダーの中央部に変更するとともに、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態に移動させ、その後、前記架設作業装置を搭載した前記トラベリングガーダーをその台車により移動させて、前記既に張り出し架設してある橋桁部分上の橋脚付近の位置まで戻すことを特徴としている。
【0012】
また、請求項2記載のこの発明の橋桁部材の架設方法は、既に張り出し架設してある橋桁部分上に、前記橋桁部分上を走行する台車と、その台車上に固定されたエレクションガーダーとを具えるトラベリングガーダーを配設するとともに、架設する橋桁部材を吊り上げる吊り上げ機を有して前記トラベリングガーダーのエレクションガーダー上を移動する架設作業装置をそのエレクションガーダー上に搭載しておいて、先ず、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態にして、前記トラベリングガーダーを前記既に張り出し架設してある橋桁部分上の橋脚付近の位置に配置し、次いで、その橋脚付近で、前記架設作業装置の吊り上げ機により、前記橋桁部材を、前記既に張り出し架設してある橋桁部分の下方に吊り上げるとともに、前記架設作業装置を搭載した前記トラベリングガーダーを、その台車により移動させて、前記架設作業装置の吊り上げ機で吊り上げた状態の橋桁部材を、前記既に張り出し架設してある橋桁部分の下方にてその橋桁部分に沿ってその橋桁部分の先端まで運搬し、かつ、前記エレクションガーダーの手延べ方向側部分をその既に張り出し架設してある橋桁部分の先端から前方へ手延べさせ、次いで、前記トラベリングガーダーを前記既に張り出し架設してある橋桁部分に連結して浮き上がり止めしてから、前記架設作業装置を前記エレクションガーダーの前記手延べ方向側部分上に移動させ、次いで、前記架設作業装置の吊り上げ機により、前記吊り上げた状態の橋桁部材を所定の高さまで引き上げて、その橋桁部材の、前記既に張り出し架設してある橋桁部分の先端への張り出し架設を行い、次いで、前記トラベリングガーダーと前記既に張り出し架設してある橋桁部分との連結を解除してから、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態に移動させ、その後、前記架設作業装置を搭載した前記トラベリングガーダーをその台車により移動させて、前記既に張り出し架設してある橋桁部分上の橋脚付近の位置まで戻すことを特徴としている。
【0013】
さらに、請求項3記載のこの発明の橋桁部材の架設方法は、既に張り出し架設してある橋桁部分上に、前記橋桁部分上を走行する台車と、その台車上に固定されたエレクションガーダーと、前記エレクションガーダーの延在方向に沿って移動可能なカウンターウエイトとを具えるトラベリングガーダーを配設するとともに、架設する橋桁部材を吊り上げる吊り上げ機を有して前記トラベリングガーダーのエレクションガーダー上を移動する架設作業装置をそのエレクションガーダー上に搭載しておいて、先ず、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態にするとともに、前記カウンターウエイトを前記トラベリングガーダーの台車と上下に整列する状態にして、前記トラベリングガーダーを前記既に張り出し架設してある橋桁部分上の橋脚付近の位置に配置し、次いで、その橋脚付近で、前記架設作業装置の吊り上げ機により、前記橋桁部材を、前記既に張り出し架設してある橋桁部分の下方に吊り上げるとともに、前記架設作業装置を搭載した前記トラベリングガーダーを、その台車により移動させて、前記架設作業装置の吊り上げ機で吊り上げた状態の橋桁部材を、前記既に張り出し架設してある橋桁部分の下方にてその橋桁部分に沿ってその橋桁部分の先端まで運搬し、かつ、前記エレクションガーダーの手延べ方向側部分をその既に張り出し架設してある橋桁部分の先端から前方へ手延べさせ、次いで、前記カウンターウエイトを前記エレクションガーダーの手延べ方向側部分と逆側の部分に移動させながら、前記架設作業装置を前記エレクションガーダーの前記手延べ方向側部分上に移動させ、次いで、前記架設作業装置の吊り上げ機により、前記吊り上げた状態の橋桁部材を所定の高さまで引き上げて、その橋桁部材の、前記既に張り出し架設してある橋桁部分の先端への張り出し架設を行い、次いで、前記カウンターウエイトを前記台車と上下に整列する状態に移動させるとともに、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態に移動させ、その後、前記架設作業装置を搭載した前記トラベリングガーダーをその台車により移動させて、前記既に張り出し架設してある橋桁部分上の橋脚付近の位置まで戻すことを特徴としている。
【0014】
そして、請求項1記載のこの発明の架設方法に用い得る、請求項4記載のこの発明の架設装置は、エレクションガーダーと、そのエレクションガーダーを支持位置変更可能に支持して走行する台車とを具えるトラベリングガーダーと、架設する橋桁部材を吊り上げる吊り上げ機と、その吊り上げ機を支持して前記エレクションガーダー上を移動する移動台とを具え、前記トラベリングガーダーの前記エレクションガーダー上に搭載される架設作業装置と、を組み合わせてなり、前記トラベリングガーダーの台車が、前記架設作業装置の移動台がその台車と上下に整列する状態であってかつ前記吊り上げ機が前記架設する橋桁部材を吊り上げた状態前記エレクションガーダーを支持して前記エレクションガーダーのバランスをとりながら、既に張り出し架設してある橋桁部分の先端から前記エレクションガーダーが前方へ片持ち状態で手延べする位置まで走行することを特徴とし、また、請求項2および3記載のこの発明の架設方法に用い得る、請求項5記載のこの発明の架設装置は、エレクションガーダーと、そのエレクションガーダーを固定支持して走行する台車と、前記エレクションガーダーの延在方向に沿って移動可能なカウンターウエイトとを具えるトラベリングガーダーと、架設する橋桁部材を吊り上げる吊り上げ機と、その吊り上げ機を支持して前記エレクションガーダー上を移動する移動台とを具え、前記トラベリングガーダーの前記エレクションガーダー上に搭載される架設作業装置と、を組み合わせてなり、前記トラベリングガーダーの台車が、前記架設作業装置の移動台および前記カウンターウエイトがその台車と上下に整列する状態であってかつ前記吊り上げ機が前記架設する橋桁部材を吊り上げた状態で前記エレクションガーダーを支持して前記エレクションガーダーのバランスをとりながら、既に張り出し架設してある橋桁部分の先端から前記エレクションガーダーが前方へ片持ち状態で手延べする位置まで走行し、前記トラベリングガーダーのカウンターウエイトが、前記エレクションガーダー上での前記架設作業装置の移動台の移動方向と逆方向へ移動することでそのエレクションガーダーのバランスを取ることを特徴とするものである。
【0015】
かかる請求項1〜請求項3記載のこの発明の架設方法によれば、橋桁部材を、橋脚付近から既に張り出し架設してある橋桁部分の先端まで運搬してその先端に張り出し架設するので、作業用地として、橋梁を構築する際に欠かせない橋脚の施工に使用した作業ヤードを活用することができ、それゆえ橋桁架設のための作業用地の確保や、それに伴う土地の造成、整備の必要がないため、橋梁建設コストが削減でき、周辺環境に対しても影響を少なく抑えることができる。また、橋梁の施工場所が海上や河川上、道路上である場合でも橋下空間高さに余裕があれば、橋脚付近の海域、水域または用地を利用するだけで施工できるので、施工に伴う交通規制を少なく抑えることができる。
【0016】
また、請求項1〜請求項3記載のこの発明の架設方法によれば、ここで使用する、トラベリングガーダーとその上に搭載した架設作業装置とを組み合わせた架設装置が、部材の吊り上げ・運搬・架設を全て一台の装置で行い、かつ、橋脚を挟んで左右の架設を1台で行うことができるので、既に設置してある橋桁部分上へ橋桁部材を取り上げるためのクレーン設備等の種々の架設用機材を省き得て、従来の片持ち張り出し工法を行う場合と比較して架設用機材を少なくすることができる。
【0017】
さらに、請求項1〜請求項3記載のこの発明の架設方法によれば、あらかじめ地組みしておいた橋桁部材を、トラベリングガーダー上に搭載した架設作業装置により吊り上げて運搬し、既に張り出し架設してある橋桁部分の先端に張り出し架設するので、橋上での架設作業が少なくて済むことから、従来の他の工法と比較して工期を同等にでき、もしくはそれよりも短縮することができ、特に請求項2および請求項3記載の方法によれば、トラベリングガーダーの台車上でエレクションガーダーの位置を変える必要がないので、工期をさらに短縮することができる。
【0018】
そして、請求項4および請求項記載のこの発明の架設装置によれば、上述したこの発明の架設方法の作用効果をもたらすことができる。なお、この発明の架設装置においては、前記架設作業装置の前記吊り上げ機は、前記エレクションガーダーの幅方向両端部を越えて水平に突出するフレームを有し、そのフレームの両端部から前記橋桁部材の両端部を吊り上げるものであっても良く、そのようにすれば、前記橋桁部材をバランス良く吊り上げることができるとともに、吊り上げ用のワイヤー等を、既に張り出し架設してある橋桁部分を間に置いてその幅方向両端部の外側に下ろしてその橋桁部分との干渉を容易に避けることができるので、前記橋桁部材の吊り上げおよび、橋桁部分の下方でのその橋桁部分に沿った運搬を迅速かつ安全に行うことができる。
【0019】
またこの発明の架設装置においては、前記架設作業装置の前記吊り上げ機は、ワイヤーロープをクランプして連続的に引き上げるワイヤークランプジャッキを具えていても良く、あるいはPC鋼線からなるストランドをクランプして連続的に引き上げるストランドジャッキを具えていても良い。かかるワイヤークランプジャッキやストランドジャッキを具えることとすれば、吊り上げ機をその吊り上げ能力の割に小型かつ軽量なものとし得て、架設装置全体をコンパクトに構成することができる。
【0020】
一方この発明の架設装置においては、前記架設作業装置の前記吊り上げ機は、通常の、ワイヤーロープを巻き上げるウインチやチェーンを巻き上げるチェーンブロックを具えていても良く、そのようにすれば、ウインチやチェーンブロックは比較的安価に製造あるいは入手し得るので、吊り上げ機を安価に構成することができる。
【0021】
そして、この発明の架設装置においては、前記トラベリングガーダーの台車と前記架設作業装置の台車との少なくとも一方は動力源を搭載して自走するものであっても良く、そのようにすれば別途の動力源を不要とし得て、架設用機材をさらに少なくすることができ、また、前記トラベリングガーダーの台車や前記架設作業装置の移動台は、既に張り出し架設してある橋桁部分上に別途に設置したウインチや油圧シリンダー、ストランドジャッキ等の動力源により駆動されて走行あるいは移動するものでも良く、その場合には台車や移動台の逸走を容易に防止することができる。
【0022】
【発明の実施の形態】
以下に、この発明の実施の形態を実施例によって、図面に基づき詳細に説明する。ここに、図1および図2は、請求項1記載のこの発明の架設方法の一実施例における橋桁部材の架設手順を示す説明図、また図3(a)および(b)は、上記実施例の架設方法に用いられる、請求項4記載のこの発明の架設装置の一実施例を示す側面図および平面図、そして図4は、上記実施例の架設装置を拡大して示す正面図である。
【0023】
先ず上記実施例の架設装置について説明すると、図中符号1は、その実施例の架設装置を示し、この架設装置1は、図3および図4に示すように、トラベリングガーダー2と、架設作業装置としての架設作業車3とを組み合わせてなり、ここにおけるトラベリングガーダー2は、プレートガーダー(鈑桁)によって構成したエレクションガーダー(架設桁)4と、そのエレクションガーダー4を図示しない分離可能な連結機構を介して支持位置変更可能に支持するとともに動力源として電気モーター5aを有していてその電気モーター5aでの駆動により自走する台車5と、を具えてなるものであり、このトラベリングガーダー2は、既に架設してある橋桁部分6上に敷設してある軌道6a上を走行する。なお、上記エレクションガーダー4は、この実施例ではプレートガーダーによって構成しているが、例えばトラス構造等の他の構造のガーダーによって構成することもできる。そして上記台車5に搭載する動力源として、この実施例では電気モーターを用いているが、例えば後述するワイヤークランプジャッキやストランドジャッキ、そして油圧シリンダー等の、他の構造のものを用いても良い。
【0024】
またここにおける架設作業車3は、架設する橋桁部材7を吊り上げる吊り上げ機8と、その吊り上げ機8を支持するとともに動力源として電気モーター9aを有していてその電気モーター9aでの駆動により自走する移動台としての台車9と、を具えてなるものであり、この架設作業車3は、上記トラベリングガーダー2のエレクションガーダー4上に搭載されて、そのエレクションガーダー4上に敷設してある軌道4a上を走行する。
【0025】
なお、上記吊り上げ機8としては、その吊り上げ荷重と吊り上げ高さとを考慮した上で、施工する橋梁に最適なものを選択することができ、この実施例では、図4に示すように、エレクションガーダー4およびそれと実質的に同一幅の既に架設してある橋桁部分6の幅方向両端部を越えて水平に突出するように鋼材を井桁状に組んでフレーム10を形成して、そのフレーム10の横方向(図4では左右方向)両端部上にそれぞれ、ワイヤー11を二つの把持機構によるクランプ位置の切換えと縦置き油圧シリンダーによる牽引との繰り返しによって連続的に引き上げる既知のワイヤークランプジャッキ12を二台づつ搭載するとともに、それら合計四台のワイヤークランプジャッキ12で引き上げるワイヤー11の下端にフレーム10と実質的に同一幅のパレット13を橋桁部材7の吊り上げ用に着脱自在に連結して構成しているが、例えばPC鋼線からなるストランドを二つの把持機構によるクランプ位置の切換えと縦置き油圧シリンダによる牽引との繰り返しによって連続的に引き上げる既知のストランドジャッキや、通常の、ワイヤーロープを巻き上げるウインチや、チェーンを巻き上げるチェーンブロック等を上記フレーム9に搭載することによって構成することもできる。
【0026】
そして上記台車9に搭載する動力源としても、この実施例では台車5と同様に電気モーターを用いているが、例えば上記ワイヤークランプジャッキやストランドジャッキ、油圧シリンダー等の、他の構造のものを用いても良い。
【0027】
次に上記実施例の架設方法について説明すると、この架設方法は、図5(a)に示すような連続桁や図5(b)に示すようなラーメン橋の橋桁14の架設に際して橋脚15から左右二方向へバランスをとりながら橋桁部材7を逐次片持ち張り出し架設してゆく場合および、図6(a)に示すような連続桁や図6(b)に示すようなラーメン桁の橋桁14のうち従来からのベント16等を用いた工法によって既に架設してある橋桁部分6をカウンターウェイトとして橋桁部材7を一方向に片持ち張り出し架設をする場合に、橋脚15付近の最小限の用地と架設機材を利用して橋桁14の架設を行うことができる架設方法であり、この架設方法では、上記の架設装置1を用いて、図1および図2に示す如き手順で橋桁部材7の片持ち張り出し架設を行う。
【0028】
すなわちここでは、図1(a)に示すように、既に架設してある橋桁部分6上の、橋脚15付近の位置に、上記架設装置1のトラベリングガーダー2を配置するとともに、そのトラベリングガーダー2のエレクションガーダー4上に、上記架設装置1の架設作業車3を搭載して、トラベリングガーダー2の台車5がエレクションガーダー4の、橋桁部材7の架設のための手延べ方向側(図1(a)では右側)と逆側の部分(図1(a)では左側の部分)を支持するようにその台車5によるエレクションガーダー4の支持位置を設定するとともに、架設作業車3をそのエレクションガーダー4上で、そのエレクションガーダー4を間に挟んでトラベリングガーダー2の台車5と上下に整列する位置に配置し、エレクションガーダー4の手延べ方向側端部と橋桁部分6との間にジャッキ16を介挿してエレクションガーダー4の手延べ方向側端部を仮受けしておく。
【0029】
しかしてここでは、
(1)先ず、図1(a)に示すように、既に架設してある橋桁部分6の同図では右端に架設する橋桁部材7を、その既に架設してある橋桁部分6の、橋脚15付近の位置の直下の地上の橋桁吊り上げ場所にてパレット13上で地組立てし、または他のヤードで作り、その橋桁吊り上げ場所に輸送してパレット13上に載置し、
(2)次に、図1(b)に示すように、上記橋桁吊り上げ場所に置いた橋桁部材7を架設作業車3の吊り上げ機8によって、既に架設してある橋桁部分6の直ぐ下の高さまで吊り上げ、
(3)そしてその吊り上げと同時もしくはその吊り上げの終了後に、図1(c)に示すように、エレクションガーダー4の手延べ方向側端部を仮受けしたジャッキ16を外してから、架設作業車3を搭載したトラベリングガーダー2をその台車5により移動させて、架設作業車3の吊り上げ機8で吊り上げた状態の橋桁部材7を、既に張り出し架設してある橋桁部分6の下方にてその橋桁部分6に沿ってその橋桁部分6の先端部まで運搬するとともに、トラベリングガーダー2のエレクションガーダー4の手延べ方向側部分(図1(c)では右側の部分)を、その既に張り出し架設してある橋桁部分6の先端から前方(図1(c)では右方)へ手延べさせる。
【0030】
(4)次に、図1(d)に示すように、トラベリングカーダー2のエレクションガーダー4を、台車5の前後の位置で、そのエレクションガーダー4と既に張り出し架設してある橋桁部分6との間に介挿したジャッキ16により支持するとともに、エレクションガーダー4の手延べ方向側と逆側の端部(図1(d)では左端部)を連結部材17により橋桁部分6に連結して、トラベリングカーダー2を浮き上がり止めし、
(5)次に、図1(e)に示すように、架設作業車3をエレクションガーダー4の手延べ方向側部分(図1(e)では右側の部分)上に移動させて、架設作業車3の吊り上げ機8で吊り上げた状態の橋桁部材7を、既に張り出し架設してある橋桁部分6の先端よりも前方へ運搬し、
(6)次に、図1(f)に示すように、架設作業車3の吊り上げ機8により、上記吊り上げた状態の橋桁部材7を、既に張り出し架設してある橋桁部分6の先端の高さまで引き上げて、その橋桁部材7を橋桁部分6の先端に接合する。
【0031】
しかる後ここでは、
(7)先ず、図2(a)に示すように、トラベリングカーダー2のエレクションガーダー4の手延べ方向側端部をさらに、ジャッキ16により支持し、また、パレット13を多少下降させ、
(8)次に、図2(b)に示すように、台車5の前側のジャッキ16と連結部材17とを取り外して、台車5の後側のジャッキ16とエレクションガーダー4の手延べ方向側端部のジャッキ16とでエレクションガーダー4を台車5から浮かせて支持した状態で台車5を移動させることにより、トラベリングガーダー2の台車5によるエレクションガーダー4の支持位置をそのエレクションガーダー4の中央部に変更するとともに、架設作業車3をエレクションガーダー4上で、そのエレクションガーダー4を間に挟んでトラベリングガーダー2の台車5と上下に整列する位置に移動させる。
【0032】
(9)次に、図2(c)に示すように、架設作業車3を搭載したトラベリングガーダー2をその台車5により移動させて、既に張り出し架設してある橋桁部分6上の、先の橋脚15付近の位置まで戻し、パレット13を地上の橋桁吊り上げ場所まで下ろしてワイヤー11の下端から分離させて、そのパレット13上に次の橋桁部材を準備し、その一方で、トラベリングガーダー2をさらに、先の橋脚15付近の位置とは橋脚15を挟んで反対側の、橋脚15付近の位置まで移動させる。なお、橋桁部材7を吊り上げていない時は図2(b)に示すように架設作業車3と台車5とをエレクションガーダー4の中央部を間に挟んで上下に整列する位置に配置してからトラベリングガーダー2を移動させるのは、その移動中エレクションガーダー4のバランスが崩れるのを防止するためであり、橋桁部材7を吊り上げている時はその橋桁部材7の重量が架設作業車3を介してエレクションガーダー4に加わるので、図1(c)に示すようにエレクションガーダー4が架設作業車3と台車5とから片寄った状態でトラベリングガーダー2を移動させても、エレクションガーダー4のバランスが崩れることはない。
【0033】
(10)次に、図2(d)に示すように、エレクションガーダー4の手延べ方向側の端部および逆側の端部と橋桁部分6との間にそれぞれ介挿したジャッキ16でエレクションガーダー4を台車5から浮かせて支持した状態で台車5を移動させることにより、トラベリングガーダー2の台車5がエレクションガーダー4の、橋桁部材7の架設のための手延べ方向側(今度は図2(d)では左側)と逆側の部分(図1(d)では右側の部分)を支持するようにその台車5によるエレクションガーダー4の支持位置を変更するとともに、架設作業車3をそのエレクションガーダー4上で、そのエレクションガーダー4を間に挟んでトラベリングガーダー2の台車5と上下に整列する位置に配置し、その一方で、既に架設してある橋桁部分6の、上記架設作業車3がその上に位置する橋脚15付近の位置の直下の地上の橋桁吊り上げ場所にもう一つのパレット13を配置して、そのもう一つのパレット13上に先の橋桁部材7と同様にして、橋桁部分6の同図では左端に架設する橋桁部材7を準備しておく。
【0034】
(11)その後、図2(e)に示すように、エレクションガーダー4の手延べ方向側と逆側の端部(図1(d)では右側端部)と橋桁部分6との間のジャッキ16を外して台車5でエレクションガーダー4を支持するとともに、既に架設してある橋桁部分6の、上記橋脚15付近の位置の直下の地上の橋桁吊り上げ場所に配置した上記もう一つのパレット13を吊り上げ機8のワイヤー11の下端に連結して、そのもう一つのパレット13上に準備しておいた橋桁部材7を、先に説明したと同様の手順で吊り上げ運搬して橋桁部分6の同図では左端に張り出し架設する。
【0035】
従って、この実施例の架設方法によれば、橋桁部材7を、橋脚15付近から既に張り出し架設してある橋桁部分6の先端まで運搬してその先端に張り出し架設するので、作業用地として、橋梁を構築する際に欠かせない橋脚15の施工に使用した作業ヤードを活用することができ、それゆえ橋桁架設のための作業用地の確保やそれに伴う土地の造成、整備の必要がないため、橋梁建設コストが削減でき、周辺環境に対しても影響を少なく抑えることができる。また、橋梁の施工場所が海上や河川上、道路上である場合でも橋下空間高さに余裕があれば、橋脚15付近の海域、水域または用地を利用するだけで施工できるので、施工に伴う交通規制を少なく抑えることができる。
【0036】
また、この実施例の架設方法によれば、ここで使用する、トラベリングガーダー2とその上に搭載した架設作業車3とを組み合わせた架設装置1が、橋桁部材7の吊り上げ・運搬・架設を全て一台の装置で行い、かつ、橋脚15を挟んで左右の架設を1台で行うことができるので、既に設置してある橋桁部分6上へ橋桁部材7を取り上げるためのクレーン設備等の種々の架設用機材を省き得て、従来の片持ち張り出し工法を行う場合と比較して架設用機材を大幅に少なくすることができる。
【0037】
さらに、この実施例の架設方法によれば、あらかじめ地組みしておいた橋桁部材7を、トラベリングガーダー2上に搭載した架設作業車3により吊り上げて運搬し、既に張り出し架設してある橋桁部分6の先端に張り出し架設するので、橋上での架設作業が少なくて済むことから、従来の他の工法と比較して工期を同等にでき、もしくはそれよりも短縮することができる。
【0038】
そして、この実施例の架設装置1によれば、上記実施例の架設方法の作用効果をもたらすことができ、しかも架設作業車3の吊り上げ機8が、エレクションガーダー4の幅方向両端部を越えて水平に突出するフレーム10を有し、そのフレーム10の両端部から橋桁部材7の両端部を吊り上げるものであるので橋桁部材7をバランス良く吊り上げることができるとともに、吊り上げ用のワイヤー11を、既に張り出し架設してある橋桁部分6を間に置いてその幅方向両端部の外側に下ろしてその橋桁部分6との干渉を容易に避けることができるので、橋桁部材7の吊り上げおよび、橋桁部分6の下方でのその橋桁部分6に沿った運搬を迅速かつ安全に行うことができる。
【0039】
またこの実施例の架設装置1においては、架設作業車3の吊り上げ機8が、ワイヤー11をクランプして連続的に引き上げるワイヤークランプジャッキ12を具えているものであるので、吊り上げ機8をその吊り上げ能力の割に小型かつ軽量なものとし得て、架設装置全体をコンパクトに構成することができ、さらに、トラベリングガーダー2の台車5と架設作業車3の台車9とが共に動力源として電気モーターを搭載して自走するものであるので、別途の動力源を不要とし得て、架設用機材をさらに少なくすることができる。
【0040】
図7および図8は、請求項2記載のこの発明の架設方法の一実施例における橋桁部材の架設手順を示す説明図、また図9(a)および(b)は、上記実施例の架設方法に用いられる、請求項5記載のこの発明の架設装置の参考例を示す側面図および平面図である。
【0041】
この参考例の架設装置1は、図3および図4に示す先の実施例の架設装置と同様に、トラベリングガーダー2と、架設作業装置としての架設作業車3とを組み合わせてなり、ここにおけるトラベリングガーダー2は先の実施例と異なり、プレートガーダーによって先の実施例のものの概略1.5倍の長さに構成する(先の実施例では例えば全長20mとするのに対しこの参考例では例えば全長30mとする)ことでその長手方向の両方向に手延べ可能としたエレクションガーダー4と、そのエレクションガーダー4の中央部下面に固定されてそのエレクションガーダー4を支持するとともに動力源として電気モーター5aを有していてその電気モーター5aでの駆動により自走する台車5と、を具え、さらに、そのエレクションガーダー4の下面の、台車5に対しエレクションガーダー4の長手方向の両側の位置にそれぞれ固設された仮受け材としてのジャッキ16と、そのエレクションガーダー4の下面の長手方向両端部にそれぞれ固設された浮き上がり止めとしての連結部材17と、を具えてなる。なお、上記エレクションガーダー4は、この参考例ではプレートガーダーによって構成しているが、これも例えばトラス構造等の他の構造のガーダーによって構成することもできる。また、上記ジャッキ16や連結部材17は、先の実施例のようにそれらの使用時に介挿あるいは装着しても良い。そして上記台車5に搭載する動力源として、この参考例では電気モーターを用いているが、これも例えば後述するワイヤークランプジャッキやストランドジャッキ、そして油圧シリンダー等の、他の構造のものを用いても良い。
【0042】
またここにおける架設作業車3は先の実施例と同様、架設する橋桁部材7を吊り上げる吊り上げ機8と、その吊り上げ機8を支持するとともに動力源として電気モーター9aを有していてその電気モーター9aでの駆動により自走する移動台としての台車9と、を具えてなるものであり、この架設作業車3も、上記トラベリングガーダー2のエレクションガーダー4上に搭載されて、そのエレクションガーダー4上に敷設してある軌道4a上を走行する。なお、上記吊り上げ機8および上記台車9としては、先の実施例と同様のものを用いることができる。
【0043】
次に上記実施例の架設方法について説明すると、この架設方法も、図5(a)に示すような連続桁や図5(b)に示すようなラーメン橋の橋桁14の架設に際して橋脚15から左右二方向へバランスをとりながら橋桁部材7を逐次片持ち張り出し架設してゆく場合および、図6(a)に示すような連続桁や図6(b)に示すようなラーメン桁の橋桁14のうち従来からのベント16等を用いた工法によって既に架設してある橋桁部分6をカウンターウェイトとして橋桁部材7を一方向に片持ち張り出し架設をする場合に、橋脚15付近の最小限の用地と架設機材を利用して橋桁14の架設を行うことができる架設方法であり、この架設方法では、図9に示す上記実施例の架設装置1を用いて、図7および図8に示す如き手順で橋桁部材7の片持ち張り出し架設を行う。
【0044】
すなわちここでは、図7(a)に示すように、既に架設してある橋桁部分6上の、橋脚15付近の位置に、上記架設装置1のトラベリングガーダー2を配置するとともに、そのトラベリングガーダー2のエレクションガーダー4上に、上記架設装置1の架設作業車3を搭載して、その架設作業車3をエレクションガーダー4の中央部に配置し、それによって架設作業車3を、エレクションガーダー4を間に挟んでトラベリングガーダー2の台車5と上下に整列させておく。
【0045】
しかしてここでは、
(1)先ず、図7(a)に示すように、既に架設してある橋桁部分6の同図では右端に架設する橋桁部材7を、その既に架設してある橋桁部分6の、橋脚15付近の位置の直下の地上の橋桁吊り上げ場所にてパレット13上で地組立てし、または他のヤードで作り、その橋桁吊り上げ場所に輸送してパレット13上に載置し、
(2)次に、図7(b)に示すように、上記橋桁吊り上げ場所に置いた橋桁部材7を架設作業車3の吊り上げ機8によって、既に架設してある橋桁部分6の直ぐ下の高さまで吊り上げ、
(3)そしてその吊り上げと同時もしくはその吊り上げの終了後に、図7(c)に示すように、架設作業車3を搭載したトラベリングガーダー2をその台車5によって移動させて、架設作業車3の吊り上げ機8で吊り上げた状態の橋桁部材7を、既に張り出し架設してある橋桁部分6の下方にてその橋桁部分6に沿ってその橋桁部分6の先端部まで運搬するとともに、トラベリングガーダー2のエレクションガーダー4の今回の手延べ方向側部分(図7(c)では右側の部分)をその既に張り出し架設してある橋桁部分6の先端から前方(図7(c)では右方)へ手延べさせる。
【0046】
(4)次に、図7(d)に示すように、トラベリングカーダー2のエレクションガーダー4を、台車5の両側の位置で、そのエレクションガーダー4の下面に固設されてそのエレクションガーダー4と既に張り出し架設してある橋桁部分6との間に位置する上記ジャッキ16により支持するとともに、エレクションガーダー4の今回の手延べ方向側と逆側の端部(図7(d)では左端部)を、そのエレクションガーダー4の下面に固設された上記連結部材17により橋桁部分6に連結して、トラベリングカーダー2を浮き上がり止めし、
(5)次に、図7(e)に示すように、架設作業車3をエレクションガーダー4の手延べ方向側部分(図7(e)では右側の部分)上に移動させて、架設作業車3の吊り上げ機8で吊り上げた状態の橋桁部材7を、既に張り出し架設してある橋桁部分6の先端よりも前方へ運搬し、
(6)次に、図7(f)に示すように、架設作業車3の吊り上げ機8により、上記吊り上げた状態の橋桁部材7を、既に張り出し架設してある橋桁部分6の先端の高さまで引き上げて、その橋桁部材7を橋桁部分6の先端に接合する。
【0047】
しかる後ここでは、
(7)先ず、図8(a)に示すように、パレット13を多少下降させ、
(8)次に、図8(b)に示すように、架設作業車3をエレクションガーダー4の中央部に戻して、架設作業車3を、エレクションガーダー4を間に挟んでトラベリングガーダー2の台車5と上下に整列させ、また、台車5の両側のジャッキ16を縮めて橋桁部分6から離間させるとともに、連結部材17を橋桁部分6から取り外す。
【0048】
(9)次に、図8(c)に示すように、架設作業車3を搭載したトラベリングガーダー2をその台車5により移動させて、既に張り出し架設してある橋桁部分6上の、先の橋脚15付近の位置まで戻し、パレット13を地上の橋桁吊り上げ場所まで下ろしてワイヤー11の下端から分離させて、そのパレット13上に次の橋桁部材を準備し、その一方で、トラベリングガーダー2をさらに、先の橋脚15付近の位置とは橋脚15を挟んで反対側の、橋脚15付近の位置まで移動させる。なお、この実施例では台車5がエレクションガーダー4の中央部を固定支持しているので、架設作業車3がエレクションガーダー4の中央部上でエレクションガーダー4を間に挟んで台車5と上下に整列する位置にある間は、トラベリングガーダー2を移動させても、エレクションガーダー4のバランスが崩れることはない。従ってこの実施例の方法では、先の実施例の方法の場合よりもジャッキ16を使用する回数を減らすことができる。
【0049】
(10)次に、図8(d)に示すように、既に架設してある橋桁部分6の、上記架設作業車3がその上に位置する橋脚15付近の位置の直下の地上の橋桁吊り上げ場所にもう一つのパレット13を配置して、そのもう一つのパレット13上に先の橋桁部材7と同様にして、橋桁部分6の同図では左端に架設する橋桁部材7を準備しておく。
【0050】
(11)その後、図8(e)に示すように、既に架設してある橋桁部分6の、上記橋脚15付近の位置の直下の地上の橋桁吊り上げ場所に配置した上記もう一つのパレット13を吊り上げ機8のワイヤー11の下端に連結して、そのもう一つのパレット13上に準備しておいた橋桁部材7を、先に説明したと同様の手順で吊り上げ運搬して橋桁部分6の同図では左端に張り出し架設する。
【0051】
従って、この実施例の方法によっても、先の実施例と同様の効果が得られ、加えてこの実施例の方法によれば、エレクションガーダー4の中央部を台車5で固定支持していることから、架設作業中その台車5上でエレクションガーダー4の位置を変える必要が全くないので、工期をさらに短縮することができる。
【0052】
そしてこの参考例の架設装置1によれば、台車5上でのエレクションガーダー4の位置変更を行わないため、ジャッキ16と連結部材17とをエレクションガーダー4に固定されて具えているので、それらの使用時にそれらを一々配置して装着する必要がなく、この点でも工期をさらに短縮することができる。しかもこの参考例の架設装置1によれば、連結部材17を、そこへの作用力が小さくなる、前方支点(手延べ方向側のジャッキ16)からより離れた位置に設置できるので、連結部材17をより簡易なものとすることができる。
【0053】
図10は、請求項3記載のこの発明の架設方法の一実施例に用いられる、請求項記載のこの発明の架設装置の一実施例を示す側面図であり、この実施例の架設装置1は、図9に示す先の参考例の架設装置と概略同様の構成を具えている。すなわち、この実施例でも、台車5がエレクションガーダー4の中央部を固定支持している。加えてこの実施例の架設装置1では、エレクションガーダー4の長手方向両端部にそれぞれプーリー18が枢支されるとともに、エレクションガーダー4の幅方向両側部に、一個の橋桁部材7の重量に概ね対応する重量のカウンターウエイトユニット19が、図示しないガイドレールによる案内下でエレクションガーダー4の長手方向へ移動自在に支持されており、そのカウンターウエイトユニット19は、エレクションガーダー4の両端部に位置する上記プーリー18の間に張り渡されたワイヤーロープ20により架設作業車3に連結されて架設作業車3の移動と連動し、架設作業車3の移動方向とは逆の方向へ移動するようにされている。そしてこの実施例では、エレクションガーダー4の長手方向両端部の下面に、先の実施例における連結部材17に代えて、ジャッキ16が設けられている。
【0054】
請求項3記載のこの発明の架設方法の上記実施例においては、かかる構成を具える架設装置1を用いることで、図7および図8に示す先の実施例と同様の方法において、エレクションガーダー4上で架設作業車3を手延べ方向に移動させる際に、上記カウンターウエイトユニット19を架設作業車3と反対の方向へ移動させることによって架設装置1のエレクションガーダー4のバランスをとる。
【0055】
従ってこの実施例の方法によれば、作業者による手作業で連結部材17を橋桁部分6に連結する、手間のかかる浮き上がり止め作業を不要とし得て、工期をさらに短縮することができるとともに、橋桁部分6上における架設作業の全自動化をも可能にすることができる。
【0056】
以上、図示例に基づき説明したが、この発明は上述の例に限定されるものでなく、例えばワイヤークランプジャッキ12の搭載数を増減することもできる。また架設作業装置の移動台を移動させる方法として、その移動台に車輪に代えてエレクションガーダー上のレールに沿って滑るスケートを設けて、移動台もしくはエレクションガーダーに設けたウインチ、油圧シリンダー、ストランドジャッキ等でその移動台を滑らせるようにしても良く、その場合には、レールとスケートとの間の摩擦を低減させるために、レールやスケートの表面にグリス等の潤滑剤を塗布したり特殊加工を施したり、あるいはレールとスケートとの間に多数の鋼球を介挿してリニアボールベアリングを構成するようにしても良い。このスケートを用いる方法は、高速移動を行い得ないため長距離の移動には不向きであるが、本発明におけるようにエレクションガーダー上で移動させるのであれば、移動距離が短く、かつ逸走防止等の安全面から移動台を高速で移動させる必要がないので、充分適しており、しかも橋桁部分の先端への橋桁部材の接合時には比較的細かい橋桁部材の位置調整が必要な処、このスケートを用いる方法によれば、その細かい位置調整を容易に行うことができる。
【0057】
またこの発明の橋桁部材の架設装置は、一方向のみに張り出し架設する場合には、エレクションガーダーの手延べ側と反対の側の下面を台車で固定支持するように構成しても良い。そしてこの発明の橋桁部材の架設装置は、海上や河川上で台船等により橋桁部材を輸送して架設位置の直下に止めておける場合には、直下吊り工法にも適用することができる。
【0058】
上記のようにこの発明は、特許請求の範囲の記載範囲内で当業者であれば上述の例から変更し得る種々の形態をも含むものである。なお、この発明の架設方法が適用できる橋梁を分類すると以下の如くである。
(1)支承条件と架設時の橋桁支持条件による分類
T型ラーメン橋の片持ち張り出し架設、多径間連続ラーメン橋の片持ち張り出し架設および多径間連続桁橋の片持ち張り出し架設。
(2)橋梁の構成材料による分類
コンクリート橋、鋼橋およびコンクリート・鋼複合橋等。
(3)主桁形式による分類
箱桁橋、I桁橋、T桁橋およびトラス橋等。
【図面の簡単な説明】
【図1】 この発明の架設方法の一実施例における橋桁部材の架設手順の前半を示す説明図である。
【図2】 この発明の架設方法の一実施例における橋桁部材の架設手順の後半を示す説明図である。
【図3】 上記実施例の架設方法に用いられる、この発明の架設装置の一実施例を示す側面図および平面図である。
【図4】 上記実施例の架設装置を拡大して示す正面図である。
【図5】 上記実施例の架設方法を適用し得る橋梁を例示する説明図である。
【図6】 上記実施例の架設方法を適用し得る橋梁をさらに例示する説明図である。
【図7】 この発明の架設方法の他の一実施例における橋桁部材の架設手順の前半を示す説明図である。
【図8】 この発明の架設方法の上記他の実施例における橋桁部材の架設手順の後半を示す説明図である。
【図9】 上記他の実施例の架設方法に用いられる、この発明の架設装置の参考例を示す側面図および平面図である。
【図10】 この発明の架設方法のさらに他の一実施例に用いられる、この発明の架設装置の他の一実施例を示す側面図である。
【符号の説明】
1 架設装置
2 トラベリングガーダー
3 架設作業車
4 エレクションガーダー
5 台車
6 既に設置してある橋桁部分
7 橋桁部材
8 吊り上げ機
9 台車
10 フレーム
11 ワイヤー
12 ワイヤークランプジャッキ
13 パレット
14 橋桁
15 橋脚
16 ジャッキ
17 連結部材
18 プーリー
19 カウンターウエイトユニット
20 ワイヤーロープ
[0001]
BACKGROUND OF THE INVENTION
TECHNICAL FIELD The present invention relates to a bridge girder member erection method and a erection apparatus suitable for use in building a bridge, and more particularly, a erection method for carrying a bridge girder member under a girder and cantilever erection, and a erection apparatus that can be used therefor. It is about.
[0002]
[Background Art and Problems to be Solved by the Invention]
When constructing a bridge, if the bridge girder member is installed at the sea or in the mountains, or there is a problem with the work site, the bridge girder member being built cannot be supported by a vent. Cable crane construction method, lump erection method, cantilever erection method, etc. are carried out.
[0003]
Here, the delivery method is a method in which the bridge girder member is sent out from the location where both ends or one end of the bridge to be installed, and the cable crane method is installed between the locations where both ends of the bridge are located. It is a method of suspending and installing bridge girder members using a cable crane. In these methods, it is necessary to secure a work site for installation of installation facilities and for carrying in members at locations where both ends or one end of the bridge to be installed There is. However, when building a bridge in a mountainous area, the location where the bridge end is located is a steep slope, the location where the bridge end is located is adjacent to a tunnel or cut soil, The alignment of the road to the road may be bent. Under such conditions, it is often difficult to secure a work site necessary for erection. Even if the work site can be secured, the construction time and equipment should be examined in consideration of the situation of the adjacent work area.
[0004]
In addition, the batch construction method is a method of building a bridge body that has been assembled at a different location in a lump, and the large-scale crane is used to assemble the bridge body that has been assembled using a large work site adjacent to the construction site. There is a method of erection and a method of erection of a bridge assembled on the sea or a river using a floating crane when it is built on the sea or a river. Water area is required.
[0005]
The cantilever extension construction method is a method in which a bridge girder member is connected to a bridge girder part that has already been installed and cantilevered, and the bridge girder part that has already been installed is used as a counterweight. There are a method of erected bridge girder members and a method of erected bridge girder members one after the other while linking them to the left and right of the center pier.
[0006]
As the installation equipment for such a cantilever extension construction method, a traveler crane in which a swing arm type crane is mounted on a carriage is generally used (National Institute of Civil Engineers, published by Gihodo on November 1, 1974) (See page 1288 of the new edition of Civil Engineering Handbook), and when the bridge girder can be transported on the sea or river by a trolley or the like and stopped directly under the installation position, the direct suspension method from the traveler crane should be used. However, if it is difficult to hang directly under water flow, etc., the bridge girder transported to the work yard near the pier is lifted above the height of the pier to the already installed bridge girder. It is taken up by a crane equipment such as a tower crane, and the bridge girder member is transported on the bridge girder part to the installation position at the tip of the overhanging part and delivered to the traveler crane. That.
[0007]
However, with such a conventional construction technique, when a cantilever construction is performed using only the work yard near the pier, the traveler crane has a high center of gravity and is unstable. Since the balance is poor and it is difficult to move at high speed on the bridge girder part, a member carriage is required to transport the bridge girder member on the bridge girder part and deliver it to the traveler crane. Constrained by the relationship with the bogie, two traveler cranes are required to install the bridge girder members at the ends of the left and right overhanging parts of the bridge girder part sandwiching the central pier. Since it requires a lot of erection equipment such as crane equipment to pick up the bridge girder member over a certain bridge girder part and deliver it to the above-mentioned material carrier cart, There has been a problem in the corner of.
[0008]
  By the way, as other erection equipment for cantilever erection method, conventionally, a traveling girder in which a wheel with a jack and a vent are fixedly installed on the lower surface of one end side of an erection girder (erection girder) provided with a track on the upper surface ( Mobile construction girders) and construction work vehicles with winches on the carriages that run on the track may be used. Examples of such cases include linking Kasaoka City, Okayama Prefecture, and Kamijima. It is known that the bridge was built on the prefectural road when the Kamishima Ohashi Bridge, a 3-span continuous PC box box bridge, was built (February 20, 1994, published by the Japan Road Association) "Concrete Road Bridge Design Handbook"First 466 ~ 467 pagereference).
[0009]
In this construction method using a traveling girder and an erection work vehicle, since the step between the upper surface of the already installed bridge girder part and the upper surface of the traveling girder is relatively large, a track is attached to the bridge girder part and the work vehicle is installed. Make it possible for the carriage to travel from the vicinity of the pier to the rear edge of the traveling girder so that the construction work vehicle can be delivered between the carriage and the traveling girder. The bridge girder member transported to the bridge girder is lifted to the position under the girder by the winch of the construction work vehicle that has been moved onto the work vehicle carriage on the bridge girder, and then the construction work vehicle works with the bridge girder member suspended. The vehicle carrier is moved to the position of the rear end of the traveling girder together with the installation work vehicle on it. Transferred onto Gugada, its after the erection work vehicle on traveling girder is moved to a predetermined erection site, further lifting up erection position bridge girder member in erection work vehicle winch.
[0010]
However, even with this method using a traveling girder and a construction work vehicle, when a cantilever construction is performed using only the work yard near the bridge pier, a work vehicle transport carriage is required as described above. Since the placement of the traveling girder on the bridge girder is restricted due to the relationship with the car carrier cart, the direction of the extension of the bridge girder is mutually different in order to construct the bridge girder members at the ends of the left and right overhanging parts of the bridge girder with the central pier sandwiched between them. Two traveling girders that are reversed are necessary, and many other construction equipment is required, so there is a problem in its economic efficiency. For this reason, conventionally, the feeding method and the cable crane method have been adopted from the viewpoint of economy, despite the limitations described above.
[0011]
[Means for solving the problems and their functions and effects]
The present invention provides a bridge girder member erection method and a erection apparatus that advantageously solve the problems of the conventional cantilever overhanging construction method, and the bridge girder member erection method according to claim 1 has already been provided. On the overhanging bridge girder part, a traveling girder including an erection girder and a carriage that supports the erection girder so that the support position can be changed and travels on the bridge girder part is disposed, and a bridge girder member to be installed. A construction work device that has a lifting machine that lifts the traveling girder and moves on the traveling girder of the traveling girder is mounted on the erection girder. First, the supporting position of the erection girder by the traveling girder carriage is determined by the erection. A girder's hand-stretching direction side for erection of the bridge girder member and The erection work device on the erection girder so that the erection girder is sandwiched between the erection girder and vertically aligned with the traveling girder carriage, and the traveling girder is already overhanging and installed. It is arranged at a position near the pier on a certain bridge girder part, and then the bridge girder member is lifted below the already overhanging bridge girder part by the lifting machine of the construction work device near the pier, The traveling girder mounted with the erection work device is moved by the carriage, and the bridge girder member is lifted by the lifting machine of the erection work device, the bridge girder portion below the bridge girder portion that has already been overlaid. Along the edge of the bridge girder and the hand of the erection girder The front side portion is extended forward from the tip of the bridge girder already overhanging, and then the traveling girder is connected to the bridge girder already overhanging to prevent the bridge girder from rising. The working device is moved onto the handrail direction side portion of the erection girder, and then the bridge girder member in the suspended state is pulled up to a predetermined height by the lifting machine of the erection work device, and the bridge girder member An extension girder is installed at the tip of the bridge girder that has already been overlaid, and then the traveling girder is disconnected from the bridge girder that has already been overlaid, and then the erection girder by the carriage of the traveling girder The support position is changed to the center of the erection girder and The construction work device is moved on the erection girder so as to be vertically aligned with the traveling girder carriage with the erection girder sandwiched therebetween, and then the traveling girder on which the construction work device is mounted is moved by the carriage. And returning to a position near the pier on the bridge girder already overhanging.
[0012]
According to a second aspect of the present invention, there is provided a bridge girder member erection method comprising: a carriage traveling on the bridge girder part on an already overhanging bridge girder part; and an erection girder fixed on the carriage. A traveling work apparatus that has a lifting machine for lifting a bridge girder member to be installed and moves on the traveling girder of the traveling girder is mounted on the erection girder. Position the work device on the erection girder, with the erection girder sandwiched between it and the trolley of the traveling girder so that the traveling girder is overhanging on the bridge girder part that has already been extended. And then in the vicinity of the pier, the lifting device for the construction work device Thus, the bridge girder member is lifted below the bridge girder portion that has already been overhanging, and the traveling girder on which the construction work device is mounted is moved by the carriage, and is lifted by the lifting machine of the construction work device. The bridge girder member in a state of being stretched is transported to the tip of the bridge girder portion along the bridge girder portion under the already overhanging bridge girder portion, and the extension girder side portion of the erection girder is already overhanging The bridge girder is extended from the tip of the bridge girder to the front, and then the traveling girder is connected to the bridge girder already overhanging to prevent the bridge girder from being lifted. Moved to the handrail direction side part, and then the lifting machine of the erection work device, The bridge girder member in the raised state is pulled up to a predetermined height, and the bridge girder member is erected to the tip of the bridge girder part that has already been erected, and then the already existing erection with the traveling girder. After the connection with a bridge girder portion is released, the erection work device is moved on the erection girder so as to align with the carriage of the traveling girder with the erection girder interposed therebetween, and then the erection girder The traveling girder on which the working device is mounted is moved by the carriage and returned to the position near the bridge pier on the bridge girder already overhanging.
[0013]
  Further, according to the third aspect of the present invention, there is provided a bridge girder member erection method on a bridge girder part that has already been overlaid, a carriage that runs on the bridge girder part, an erection girder fixed on the carriage, An installation work in which a traveling girder having a counterweight movable along the extending direction of the erection girder is disposed and a lifting machine for lifting a bridge girder member to be installed is moved on the erection girder of the traveling girder. The device is mounted on the erection girder, and first, the construction work device is placed on the erection girder so as to be vertically aligned with the traveling girder carriage with the erection girder therebetween. Counterweight on the traveling girder trolley The traveling girder is arranged at a position near the pier on the bridge girder already overhanging, and then the bridge girder member is moved near the pier by the lifting machine of the construction work device. The bridge girder member is lifted below the bridge girder already overhanging, and the traveling girder on which the construction work device is mounted is moved by the carriage and is lifted by the lifting machine of the construction work device. The bridge girder part that is transported along the bridge girder part to the tip of the bridge girder part below the already overhanging bridge girder part, and the extension girder side part of the erection girder is already overhanging. Reach the front from the tip, and then the counterweightAboveThe construction work device is moved onto the handrail direction side portion of the erection girder while being moved to the portion opposite to the hand travel direction side portion of the erection girder, and then the lifting device of the construction work device The bridge girder member in a lifted state is pulled up to a predetermined height, and the bridge girder member is erected to the end of the bridge girder portion that has already been erected, and then the counterweight is vertically aligned with the carriage. And moving the construction work device on the erection girder so that it is vertically aligned with the traveling girder carriage with the erection girder in between, and then mounting the erection work device The traveling girder is moved by the cart, It is characterized in that return to a position near the pier on the bridge girder portions that.
[0014]
  The erection device according to claim 4, which can be used in the erection method according to claim 1, comprises an erection girder and a carriage that supports the erection girder so that the support position can be changed. A traveling girder, a lifting machine for lifting a bridge girder member to be installed, and a moving table that supports the lifting machine and moves on the erection girder. The erection work device mounted on the erection girder of the traveling girder The traveling girder cart is in a state where the moving platform of the erection work device is vertically aligned with the cart, and the lifting machine lifts the bridge girder member to be erectedsoWhile supporting the erection girder and balancing the erection girder, the erection girder travels from the tip of the bridge girder already overhanging to the position where the erection girder cantilevered forward, and , Claims2 and 3The erection device of the present invention according to claim 5, which can be used in the erection method of the present invention described above, includes an erection girder, and a carriage that travels with the erection girder fixedly supported.A counterweight movable along the extending direction of the erection girderA traveling girder comprising a traveling girder, a lifting machine for lifting a bridge girder member to be erected, and a moving platform that supports the lifting machine and moves on the erection girder, and is mounted on the erection girder of the traveling girder And the traveling girder carriage is a moving platform of the construction work apparatus.And the counterweightBridge girder that is already overhanging while maintaining the balance of the erection girder while supporting the erection girder while the hoisting machine lifts the erection bridge girder member in a state of being vertically aligned with the carriage. Traveling from the tip of the part to the position where the erection girder cantilevered forwardThe counter girder of the traveling girder moves in the direction opposite to the moving direction of the moving table of the construction work device on the erection girder to balance the erection girder.It is characterized by.
[0015]
According to the construction method of the present invention as set forth in claims 1 to 3, the bridge girder member is transported from the vicinity of the bridge pier to the tip of the bridge girder portion which has already been erected, and is erected at the tip of the bridge girder. As a result, it is possible to utilize the work yard used for the construction of the piers that are indispensable when building bridges, so there is no need to secure work sites for bridge girder construction, and to create and maintain land accordingly. Therefore, the bridge construction cost can be reduced and the influence on the surrounding environment can be reduced. Also, even if the bridge construction site is on the sea, river or road, if there is enough space under the bridge, it can be constructed simply by using the sea area, water area or land near the pier, so traffic restrictions associated with construction Can be reduced.
[0016]
Moreover, according to the construction method of this invention of Claims 1-3, the construction apparatus which combined the traveling girder used here and the construction work apparatus mounted on it is used for lifting, carrying, Since all the installations can be done with a single device, and the left and right installations can be done with one unit across the bridge pier, various crane facilities for picking up the bridge girder members on the bridge girder already installed The construction equipment can be omitted, and the construction equipment can be reduced as compared with the conventional cantilever extension method.
[0017]
Furthermore, according to the construction method of the present invention as set forth in claims 1 to 3, the bridge girder member that has been pre-assembled in advance is lifted and transported by a construction work device mounted on a traveling girder and already overlaid. Since it is installed overhanging at the tip of the bridge girder part, the construction work on the bridge can be reduced, so the construction period can be made equivalent or shorter than other conventional methods, especially According to the method of Claim 2 and Claim 3, since it is not necessary to change the position of the erection girder on the cart of the traveling girder, the construction period can be further shortened.
[0018]
  And claim 4andClaim5According to the described construction apparatus of the present invention, the operational effects of the above-described construction method of the present invention can be brought about. In the erection device according to the present invention, the lifting machine of the erection work device has a frame that protrudes horizontally beyond both end portions in the width direction of the erection girder, and the bridge girder member extends from both ends of the frame. The bridge girder member can be lifted in a well-balanced manner, and a lifting wire or the like is placed between the bridge girder portions already overhanging. Since it is possible to easily avoid interference with the bridge girder portion by lowering it to the outside of both ends in the width direction, the bridge girder member is lifted up and transported along the bridge girder portion under the bridge girder portion quickly and safely. be able to.
[0019]
In the erection device of the present invention, the lifting machine of the erection work device may include a wire clamp jack that clamps a wire rope and continuously pulls it up, or clamps a strand made of PC steel wire. You may provide the strand jack which pulls up continuously. If such wire clamp jacks and strand jacks are provided, the lifting machine can be made small and lightweight for its lifting capacity, and the entire erection device can be made compact.
[0020]
On the other hand, in the erection apparatus according to the present invention, the lifting machine of the erection work apparatus may include a normal winch for winding a wire rope or a chain block for hoisting a chain. Can be manufactured or obtained at a relatively low cost, so that the lifting machine can be constructed at a low cost.
[0021]
And in the erection device of this invention, at least one of the cart of the traveling girder and the trolley of the erection work device may be self-propelled by mounting a power source. The power source can be made unnecessary, and the construction equipment can be further reduced, and the traveling girder carriage and the construction work device moving base are separately installed on the bridge girder already overhanging. It may be driven or moved by a power source such as a winch, a hydraulic cylinder, or a strand jack, and in that case, the carriage or the moving table can be easily prevented from running away.
[0022]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 and FIG. 2 are explanatory views showing the installation procedure of the bridge girder member in one embodiment of the erection method of the present invention described in claim 1, and FIGS. 3 (a) and 3 (b) are the above embodiments. A side view and a plan view showing an embodiment of the erection device of the present invention according to claim 4 used in the erection method of FIG. 4, and FIG. 4 is an enlarged front view showing the erection device of the above embodiment.
[0023]
First, the construction apparatus of the above embodiment will be described. Reference numeral 1 in the figure denotes the construction apparatus of the embodiment, and this construction apparatus 1 includes a traveling girder 2 and a construction work apparatus as shown in FIGS. The traveling girder 2 is combined with an erection girder (erection girder) 4 constituted by a plate girder (girder) and a separable connecting mechanism (not shown). The traveling girder 2 is already provided with a carriage 5 that has an electric motor 5a as a power source and is self-propelled by being driven by the electric motor 5a. It travels on the track 6a laid on the bridge girder portion 6 that has been erected. In addition, although the said erection girder 4 is comprised by the plate girder in this Example, it can also be comprised by the girder of other structures, such as a truss structure, for example. In this embodiment, an electric motor is used as a power source to be mounted on the carriage 5. However, other structures such as a wire clamp jack, a strand jack, and a hydraulic cylinder, which will be described later, may be used.
[0024]
Further, the construction work vehicle 3 here has a lifting machine 8 for lifting the bridge girder member 7 to be installed, and supports the lifting machine 8 and has an electric motor 9a as a power source, and is self-propelled by being driven by the electric motor 9a. The construction work vehicle 3 is mounted on the erection girder 4 of the traveling girder 2 and is laid on the erection girder 4. Drive on top.
[0025]
As the lifting machine 8, it is possible to select an optimum one for the bridge to be constructed in consideration of the lifting load and the lifting height. In this embodiment, as shown in FIG. The frame 10 is formed by assembling steel materials in a cross-beam shape so as to protrude horizontally beyond both ends in the width direction of the bridge girder portion 6 and the bridge girder portion 6 having substantially the same width as that of the frame 10. Two known wire clamp jacks 12 that continuously pull up the wire 11 by repeatedly switching the clamp position by two gripping mechanisms and pulling by a vertical hydraulic cylinder on both ends of the direction (left and right in FIG. 4) At the same time, a pallet of substantially the same width as the frame 10 is attached to the lower end of the wire 11 pulled up by the four wire clamp jacks 12 in total. 13 is detachably connected for lifting the bridge girder member 7, but for example, a strand made of PC steel wire is continuously repeated by switching the clamp position by two gripping mechanisms and pulling by a vertically placed hydraulic cylinder. A known strand jack that pulls up, a winch that winds up a wire rope, a chain block that winds up a chain, and the like can be mounted on the frame 9.
[0026]
As a power source mounted on the carriage 9, an electric motor is used in this embodiment as with the carriage 5. However, for example, a wire clamp jack, a strand jack, a hydraulic cylinder, or the like is used. May be.
[0027]
Next, the erection method of the above embodiment will be described. This erection method is performed from the pier 15 to the left and right when erection of the continuous girder as shown in FIG. 5A and the bridge girder 14 of the ramen bridge as shown in FIG. In the case where the bridge girder member 7 is sequentially cantilevered while being balanced in two directions, and among the continuous girder as shown in FIG. 6 (a) and the bridge girder 14 of the ramen girder as shown in FIG. 6 (b) When the bridge girder part 6 is cantilevered in one direction with the bridge girder part 6 already installed by the construction method using the conventional vent 16 etc. as a counterweight, the minimum site and installation equipment near the pier 15 The bridge girder 14 can be erected by using the above-described erection method. In this erection method, the bridge girder member 7 is cantilevered by the procedure shown in FIGS. I do.
[0028]
That is, here, as shown in FIG. 1 (a), the traveling girder 2 of the erection device 1 is disposed at a position near the pier 15 on the bridge girder portion 6 that has already been erected. The erection work vehicle 3 of the erection device 1 is mounted on the erection girder 4 so that the carriage 5 of the traveling girder 2 is on the side of the erection girder 4 in the direction of reaching the bridge girder member 7 (FIG. 1A). Then, the support position of the erection girder 4 by the carriage 5 is set so as to support the part opposite to the right side (the left part in FIG. 1A), and the construction work vehicle 3 is placed on the erection girder 4 The erection girder 4 is placed at a position vertically aligned with the carriage 5 of the traveling girder 2 with the erection girder 4 in between, Keep receiving tentative hand total direction side end portion of the erection girders 4 by inserting a jack 16 between the end portion and the bridge girder portion 6.
[0029]
But here,
(1) First, as shown in FIG. 1 (a), in the same figure of the bridge girder part 6 already installed, the bridge girder member 7 installed at the right end is near the pier 15 of the bridge girder part 6 already installed. Assembling the ground on the pallet 13 at the place where the bridge girder is lifted directly below the position, or making it in another yard, transporting to the bridge girder lifting place and placing it on the pallet 13
(2) Next, as shown in FIG. 1 (b), the bridge girder member 7 placed at the bridge girder lifting place is lifted by a lifting machine 8 of the erection work vehicle 3 directly below the bridge girder portion 6 that has already been erected. Lift it up,
(3) At the same time as the lifting or after the lifting is finished, as shown in FIG. 1 (c), the jack 16 temporarily receiving the end of the erection girder 4 in the handrail direction side is removed, and then the construction work vehicle 3 The bridge girder member 7 is moved under the bridge girder portion 6 that has already been overhanging the bridge girder member 7 that has been lifted by the lifting machine 8 of the construction work vehicle 3. The bridge girder part that is transported to the tip of the bridge girder part 6 along the side of the erection girder 4 of the traveling girder 2 (the right side part in FIG. 1 (c)) is overhanging. 6 is pushed forward from the tip of 6 (to the right in FIG. 1C).
[0030]
(4) Next, as shown in FIG. 1 (d), the erection girder 4 of the traveling carder 2 is positioned between the erection girder 4 and the bridge girder part 6 that is already overhanging at positions before and after the carriage 5. The end of the erection girder 4 on the opposite side (the left end in FIG. 1 (d)) is connected to the bridge girder portion 6 by the connecting member 17 and supported by the jack 16 inserted in the traveling carder. 2 to lift up,
(5) Next, as shown in FIG. 1 (e), the erection work vehicle 3 is moved onto the handrail direction side portion of the erection girder 4 (the right side portion in FIG. 1 (e)), and the erection work vehicle is moved. The bridge girder member 7 lifted by the lifting machine 8 of No. 3 is transported further forward than the tip of the bridge girder part 6 that is already overhanging,
(6) Next, as shown in FIG. 1 (f), the bridge girder member 7 in the state of being lifted up to the height of the tip of the bridge girder portion 6 that has already been overlaid by the lifting machine 8 of the erection work vehicle 3. The bridge girder member 7 is joined to the tip of the bridge girder portion 6 by pulling up.
[0031]
After that, here,
(7) First, as shown in FIG. 2 (a), the end of the traveling girder 4 of the traveling carder 2 in the direction of the handrail direction is further supported by the jack 16, and the pallet 13 is lowered slightly.
(8) Next, as shown in FIG. 2 (b), the jack 16 on the front side of the carriage 5 and the connecting member 17 are removed, and the jack 16 on the rear side of the carriage 5 and the end of the erection girder 4 in the handrail direction side. The support position of the erection girder 4 by the trolley 5 of the traveling girder 2 is changed to the central part of the erection girder 4 by moving the trolley 5 while the erection girder 4 is lifted from the trolley 5 and supported by the jack 16 of the head At the same time, the construction work vehicle 3 is moved on the erection girder 4 to a position vertically aligned with the carriage 5 of the traveling girder 2 with the erection girder 4 interposed therebetween.
[0032]
(9) Next, as shown in FIG. 2 (c), the traveling girder 2 on which the erection work vehicle 3 is mounted is moved by the cart 5, and the previous pier on the bridge girder portion 6 that has already been overlaid. Return to the position near 15 and lower the pallet 13 to the lifting position of the bridge girder on the ground and separate it from the lower end of the wire 11 to prepare the next bridge girder member on the pallet 13, while the traveling girder 2 is further It is moved to a position near the pier 15 on the opposite side of the pier 15 from the position near the previous pier 15. When the bridge girder member 7 is not lifted, the construction work vehicle 3 and the carriage 5 are arranged at positions where they are vertically aligned with the central portion of the erection girder 4 interposed therebetween as shown in FIG. The reason why the traveling girder 2 is moved is to prevent the balance of the erection girder 4 from being lost during the movement, and when the bridge girder member 7 is lifted, the weight of the bridge girder member 7 passes through the construction work vehicle 3. Since it is added to the erection girder 4, the balance of the erection girder 4 is lost even if the traveling girder 2 is moved while the erection girder 4 is offset from the construction work vehicle 3 and the carriage 5 as shown in FIG. There is no.
[0033]
(10) Next, as shown in FIG. 2 (d), the erection girder is inserted with jacks 16 respectively inserted between the end of the erection girder 4 in the handrail direction side and the opposite end and the bridge girder part 6. When the carriage 5 is moved in a state where the carriage 4 is lifted from the carriage 5 and supported, the carriage 5 of the traveling girder 2 moves to the side of the erection girder 4 in the direction of extending the bridge girder member 7 (this time FIG. ), The support position of the erection girder 4 by the carriage 5 is changed so as to support the part opposite to the left side (the part on the right side in FIG. 1D), and the construction work vehicle 3 is placed on the erection girder 4 Then, the above-mentioned bridge girder portion 6 is arranged at a position that is vertically aligned with the carriage 5 of the traveling girder 2 with the erection girder 4 in between. Another pallet 13 is arranged at the place where the bridge girder is lifted on the ground just below the pier 15 on which the construction work vehicle 3 is located, and the same pallet member 7 is placed on the other pallet 13. In the figure of the bridge girder portion 6, a bridge girder member 7 to be installed at the left end is prepared.
[0034]
(11) Thereafter, as shown in FIG. 2 (e), the jack 16 between the bridge girder portion 6 and the end of the erection girder 4 on the opposite side to the handrail direction side (the right end in FIG. 1 (d)). The pallet 5 supports the erection girder 4 and the above-mentioned another pallet 13 arranged at the bridge girder lifting position on the ground bridge 6 immediately below the position of the pier 15 is lifted. The bridge girder member 7 which is connected to the lower end of the wire 11 and is prepared on the other pallet 13 is lifted and transported in the same procedure as described above, and the left end of the bridge girder portion 6 in the figure. Overhang and erection.
[0035]
Therefore, according to the erection method of this embodiment, the bridge girder member 7 is transported from the vicinity of the pier 15 to the tip of the bridge girder portion 6 that has already been erected, and is erected and erected at the tip of the bridge girder. It is possible to utilize the work yard used for the construction of the pier 15 which is indispensable for construction, and therefore there is no need to secure a working site for bridge girder construction, and to create and maintain land accordingly. Costs can be reduced and the impact on the surrounding environment can be minimized. In addition, even if the bridge construction site is on the sea, river, or road, if there is enough space under the bridge, it can be constructed simply by using the sea area, water area, or land near the pier 15; Regulations can be kept low.
[0036]
Moreover, according to the erection method of this embodiment, the erection device 1 that combines the traveling girder 2 and the erection work vehicle 3 mounted thereon is used for lifting, transporting and erection of the bridge girder member 7 all. Since it can be performed by a single device and can be erected on both sides of the bridge pier 15 by one unit, various equipment such as crane equipment for taking up the bridge girder member 7 onto the already installed bridge girder portion 6 can be used. The construction equipment can be omitted, and the construction equipment can be greatly reduced as compared with the conventional cantilever projecting method.
[0037]
Furthermore, according to the erection method of this embodiment, the bridge girder member 7 that has been pre-assembled is lifted and transported by the erection work vehicle 3 mounted on the traveling girder 2, and the bridge girder portion 6 that has already been overhanging is carried out. Since the construction is overhanging at the tip of the bridge, the construction work on the bridge can be reduced, so that the construction period can be made equal or shorter than that of other conventional construction methods.
[0038]
And according to the erection apparatus 1 of this embodiment, the effect of the erection method of the above embodiment can be brought about, and the lifting machine 8 of the erection work vehicle 3 extends beyond both ends in the width direction of the erection girder 4. Since the frame 10 protrudes horizontally and both ends of the bridge girder member 7 are lifted from both ends of the frame 10, the bridge girder member 7 can be lifted in a well-balanced manner, and the lifting wire 11 has already been extended. Since the bridge girder portion 6 is placed between the bridge girder portions 6 and can be lowered to the outside of both ends in the width direction to avoid interference with the bridge girder portion 6. Can be transported along the bridge girder portion 6 quickly and safely.
[0039]
Further, in the erection apparatus 1 of this embodiment, the lifting machine 8 of the erection work vehicle 3 includes the wire clamp jack 12 that clamps the wire 11 and continuously pulls it up. It can be made small and lightweight for its capacity, and the entire construction device can be made compact. Furthermore, the carriage 5 of the traveling girder 2 and the carriage 9 of the construction work vehicle 3 both use an electric motor as a power source. Since it is mounted and self-propelled, it can eliminate the need for a separate power source and further reduce the construction equipment.
[0040]
  FIGS. 7 and 8 are explanatory views showing the construction procedure of the bridge girder member in one embodiment of the construction method of the present invention as set forth in claim 2, and FIGS. 9A and 9B are construction methods of the above embodiment. The erection device of the present invention according to claim 5 used inReference exampleIt is the side view and top view which show.
[0041]
  thisReference exampleSimilarly to the construction apparatus of the previous embodiment shown in FIG. 3 and FIG. 4, the construction apparatus 1 is composed of a traveling girder 2 and a construction work vehicle 3 as a construction work apparatus. Unlike the previous embodiment, the plate girder is configured to be approximately 1.5 times the length of the previous embodiment (in the previous embodiment, for example, the total length is 20 m.Reference exampleIn this case, the erection girder 4 can be extended in both the longitudinal directions by being fixed to the lower surface of the central part of the erection girder 4 to support the erection girder 4 and an electric motor as a power source. A carriage 5 that has 5a and is self-propelled by being driven by the electric motor 5a, and further, on the lower surface of the erection girder 4 at positions on both sides in the longitudinal direction of the erection girder 4 with respect to the carriage 5. It comprises a jack 16 as a temporary support member fixed and a connecting member 17 as a lift stop fixed at both ends in the longitudinal direction of the lower surface of the erection girder 4. The above erection girder 4 isReference exampleIn this case, the plate girder is used, but it can also be constituted by a girder having another structure such as a truss structure. Further, the jack 16 and the connecting member 17 may be inserted or mounted when they are used as in the previous embodiment. And as a power source to be mounted on the cart 5,Reference exampleIn this example, an electric motor is used. However, another structure such as a wire clamp jack, a strand jack, and a hydraulic cylinder, which will be described later, may be used.
[0042]
Further, the erection work vehicle 3 here has a lifting machine 8 for lifting the bridge girder member 7 to be installed, and an electric motor 9a as a power source for supporting the lifting machine 8 and supporting the lifting machine 8, and the electric motor 9a. The construction work vehicle 3 is also mounted on the erection girder 4 of the traveling girder 2, and is mounted on the erection girder 4. Travel on the track 4a. In addition, as the said lifting machine 8 and the said trolley | bogie 9, the thing similar to the previous Example can be used.
[0043]
Next, the erection method of the above embodiment will be described. This erection method is also determined from the pier 15 when the continuous girder as shown in FIG. 5 (a) or the bridge girder 14 of the ramen bridge as shown in FIG. 5 (b) is erected. In the case where the bridge girder member 7 is sequentially cantilevered while being balanced in two directions, and among the continuous girder as shown in FIG. 6 (a) and the bridge girder 14 of the ramen girder as shown in FIG. 6 (b) When the bridge girder part 6 is cantilevered in one direction with the bridge girder part 6 already installed by the construction method using the conventional vent 16 etc. as a counterweight, the minimum site and installation equipment near the pier 15 The bridge girder 14 can be erected by using the erection method. In this erection method, the girder member is constructed by the procedure shown in FIGS. 7 and 8 using the erection apparatus 1 of the above-described embodiment shown in FIG. 7 cantilever erection Do.
[0044]
That is, here, as shown in FIG. 7 (a), the traveling girder 2 of the erection device 1 is disposed at a position near the pier 15 on the bridge girder portion 6 that has already been erected. The erection work vehicle 3 of the erection device 1 is mounted on the erection girder 4, and the erection work vehicle 3 is arranged at the center of the erection girder 4, whereby the erection work vehicle 3 is placed between the erection girder 4 and the erection girder 4 therebetween. It is vertically aligned with the cart 5 of the traveling girder 2 by sandwiching it.
[0045]
But here,
(1) First, as shown in FIG. 7 (a), in the same figure of the bridge girder part 6 already installed, the bridge girder member 7 installed at the right end is near the pier 15 of the bridge girder part 6 already installed. Assembling the ground on the pallet 13 at the place where the bridge girder is lifted directly below the position, or making it in another yard, transporting to the bridge girder lifting place and placing it on the pallet 13
(2) Next, as shown in FIG. 7 (b), the bridge girder member 7 placed at the bridge girder lifting location is lifted by a lifting machine 8 of the erection work vehicle 3 to a height just below the bridge girder portion 6 already erected. Lift it up,
(3) At the same time as the lifting or after the lifting is finished, as shown in FIG. 7C, the traveling girder 2 on which the construction work vehicle 3 is mounted is moved by the carriage 5 to lift the construction work vehicle 3 The bridge girder member 7 lifted by the machine 8 is transported along the bridge girder part 6 to the front end of the bridge girder part 6 below the overhanging bridge girder part 6 and the erection girder of the traveling girder 2. 4 is extended to the front side (right side in FIG. 7C) from the front end of the bridge girder part 6 that has been overhanging (the right side part in FIG. 7C).
[0046]
(4) Next, as shown in FIG. 7 (d), the erection girder 4 of the traveling carder 2 is fixed to the lower surface of the erection girder 4 at positions on both sides of the carriage 5, and the erection girder 4 While supporting by the said jack 16 located between the overhanging bridge girder part 6, the edge part (the left edge part in FIG.7 (d)) on the opposite side to the current reach direction side of the erection girder 4 is provided. The above-mentioned connecting member 17 fixed to the lower surface of the erection girder 4 is connected to the bridge girder portion 6 to prevent the traveling carder 2 from being lifted,
(5) Next, as shown in FIG. 7 (e), the construction work vehicle 3 is moved onto the handrail direction side portion of the erection girder 4 (the right side portion in FIG. 7 (e)), and the construction work vehicle is moved. The bridge girder member 7 lifted by the lifting machine 8 of No. 3 is transported further forward than the tip of the bridge girder part 6 that is already overhanging,
(6) Next, as shown in FIG. 7 (f), the bridge girder member 7 that has been lifted up to the height of the tip of the bridge girder portion 6 that has already been overhanged by the lifting machine 8 of the erection work vehicle 3. The bridge girder member 7 is joined to the tip of the bridge girder portion 6 by pulling up.
[0047]
After that, here,
(7) First, as shown in FIG. 8 (a), the pallet 13 is lowered slightly,
(8) Next, as shown in FIG. 8 (b), the construction work vehicle 3 is returned to the center of the erection girder 4, and the erection work vehicle 3 is sandwiched between the erection girder 4 and the carriage of the traveling girder 2. 5, the jacks 16 on both sides of the carriage 5 are contracted to be separated from the bridge girder portion 6, and the connecting member 17 is removed from the bridge girder portion 6.
[0048]
(9) Next, as shown in FIG. 8 (c), the traveling girder 2 on which the erection work vehicle 3 is mounted is moved by the cart 5, and the previous pier on the bridge girder portion 6 that has already been overlaid. Return to the position near 15 and lower the pallet 13 to the lifting position of the bridge girder on the ground and separate it from the lower end of the wire 11 to prepare the next bridge girder member on the pallet 13, while the traveling girder 2 is further It is moved to a position near the pier 15 on the opposite side of the pier 15 from the position near the previous pier 15. In this embodiment, since the cart 5 supports the central portion of the erection girder 4 in a fixed manner, the construction work vehicle 3 is vertically aligned with the trolley 5 on the central portion of the erection girder 4 with the erection girder 4 in between. As long as the traveling girder 2 is moved, the balance of the erection girder 4 is not lost. Therefore, in the method of this embodiment, the number of times the jack 16 is used can be reduced as compared with the method of the previous embodiment.
[0049]
(10) Next, as shown in FIG. 8 (d), the bridge girder lifting place on the ground just below the bridge girder portion 6 that has already been erected, near the position of the pier 15 on which the construction work vehicle 3 is located. Another pallet 13 is arranged, and a bridge girder member 7 is prepared on the other pallet 13 in the same manner as the previous bridge girder member 7 in the same manner as the bridge girder portion 6.
[0050]
(11) After that, as shown in FIG. 8 (e), the other pallet 13 placed on the bridge girder lifting place on the ground just below the position of the bridge pier 15 of the already installed bridge girder part 6 is lifted. The bridge girder member 7 connected to the lower end of the wire 11 of the machine 8 and prepared on the other pallet 13 is lifted and transported in the same procedure as described above. Extend over the left end.
[0051]
Therefore, also by the method of this embodiment, the same effect as the previous embodiment can be obtained. In addition, according to the method of this embodiment, the central portion of the erection girder 4 is fixedly supported by the carriage 5. Since it is not necessary to change the position of the erection girder 4 on the cart 5 during the erection work, the construction period can be further shortened.
[0052]
  And thisReference exampleAccording to the erection apparatus 1, since the position of the erection girder 4 on the carriage 5 is not changed, the jack 16 and the connecting member 17 are fixed to the erection girder 4. There is no need to arrange and install them one by one, and the construction period can be further shortened in this respect. And thisReference exampleAccording to this construction device 1, the connecting member 17 can be installed at a position farther from the front fulcrum (jack 16 on the hand-stretching direction side) where the acting force on the connecting member 17 becomes small. Can be.
[0053]
  FIG. 10 is used in an embodiment of the erection method of the present invention as set forth in claim 3.5It is a side view which shows one Example of the construction apparatus of this invention of description, The construction apparatus 1 of this ExampleReference exampleThe construction is almost the same as that of the installation device. That is, also in this embodiment, the carriage 5 fixedly supports the central portion of the erection girder 4. In addition, in the erection apparatus 1 of this embodiment, pulleys 18 are pivotally supported at both longitudinal ends of the erection girder 4 and generally correspond to the weight of one bridge girder member 7 at both sides in the width direction of the erection girder 4. The counterweight unit 19 is supported by a guide rail (not shown) so as to be movable in the longitudinal direction of the erection girder 4, and the counterweight unit 19 is located at both ends of the erection girder 4. It is connected to the construction work vehicle 3 by a wire rope 20 stretched between 18 and interlocked with the movement of the construction work vehicle 3 so as to move in the direction opposite to the movement direction of the construction work vehicle 3. . In this embodiment, jacks 16 are provided on the lower surfaces of both ends in the longitudinal direction of the erection girder 4 instead of the connecting member 17 in the previous embodiment.
[0054]
In the above-described embodiment of the erection method according to the third aspect of the present invention, the erection girder 4 can be obtained by using the erection device 1 having such a configuration in the same manner as in the previous embodiment shown in FIGS. When the erection work vehicle 3 is moved in the reach direction, the counterweight unit 19 is moved in the opposite direction to the erection work vehicle 3 to balance the erection girder 4 of the erection device 1.
[0055]
Therefore, according to the method of this embodiment, it is possible to eliminate the time-consuming lifting work of manually connecting the connecting member 17 to the bridge girder portion 6 by an operator, further shortening the work period, and the bridge girder. It is also possible to fully automate the construction work on the part 6.
[0056]
As mentioned above, although demonstrated based on the example of illustration, this invention is not limited to the above-mentioned example, For example, the mounting number of the wire clamp jack 12 can also be increased / decreased. In addition, as a method of moving the moving base of the construction work device, a skate that slides along the rail on the erection girder is provided on the moving base, and a winch, a hydraulic cylinder, and a strand jack provided on the moving pedestal or the erection girder are provided. It may be possible to slide the moving table by applying grease or other lubricant on the surface of the rail or skate or special processing to reduce the friction between the rail and skate. Alternatively, a linear ball bearing may be configured by inserting a number of steel balls between the rail and the skate. This method using skate is not suitable for long-distance movement because it cannot move at high speed, but if it is moved on the erection girder as in the present invention, the movement distance is short, and escape prevention etc. Since it is not necessary to move the moving platform at high speed from the safety aspect, this method is suitable, and this skate is a method that requires a relatively fine position adjustment of the bridge girder member when joining the bridge girder member to the tip of the bridge girder part. Therefore, the fine position adjustment can be easily performed.
[0057]
Moreover, the bridge girder member erection device of the present invention may be configured to fix and support the lower surface of the erection girder on the side opposite to the reach side of the erection girder when it is erected in only one direction. The bridge girder erection device of the present invention can also be applied to a direct suspension method when the bridge girder member can be transported by a trolley or the like on the sea or on a river and stopped just below the erection position.
[0058]
As described above, the present invention includes various forms that can be modified from the above examples by those skilled in the art within the scope of the claims. The bridges to which the erection method of the present invention can be applied are classified as follows.
(1) Classification according to bearing conditions and bridge girder support conditions during erection
Cantilever construction of T-type rigid frame bridge, cantilever construction of multi-span continuous rigid frame bridge, and cantilever construction of multi-span continuous girder bridge.
(2) Classification by bridge material
Concrete bridges, steel bridges and concrete / steel composite bridges.
(3) Classification by main digit format
Box girder bridge, I girder bridge, T girder bridge, truss bridge, etc.
[Brief description of the drawings]
FIG. 1 is an explanatory view showing the first half of a bridge girder erection procedure in one embodiment of the erection method of the present invention.
FIG. 2 is an explanatory diagram showing the latter half of the bridge girder erection procedure in one embodiment of the erection method of the present invention.
FIGS. 3A and 3B are a side view and a plan view showing an embodiment of the erection device of the present invention used in the erection method of the embodiment.
FIG. 4 is an enlarged front view showing the erection apparatus according to the embodiment.
FIG. 5 is an explanatory diagram illustrating a bridge to which the erection method of the above embodiment can be applied.
FIG. 6 is an explanatory diagram further illustrating a bridge to which the erection method of the above embodiment can be applied.
FIG. 7 is an explanatory view showing the first half of a bridge girder erection procedure in another embodiment of the erection method of the present invention.
FIG. 8 is an explanatory view showing the second half of the bridge girder erection procedure in the other embodiment of the erection method of the present invention.
FIG. 9 shows a construction apparatus according to the present invention used in the construction method of the other embodiment.Reference exampleIt is the side view and top view which show.
FIG. 10 is a perspective view of a construction apparatus according to the present invention used in still another embodiment of the construction method of the present invention.otherIt is a side view which shows one Example.
[Explanation of symbols]
  1 Construction equipment
  2 Traveling girder
  3 Construction work vehicle
  4 Erection girder
  5 carts
  6 Bridge girder already installed
  7 Bridge girder members
  8 Lifting machine
  9 carts
  10 frames
  11 wire
  12 Wire clamp jack
  13 palettes
  14 Bridge girder
  15 Pier
  16 Jack
  17 Connecting member
  18 pulley
  19 Counterweight unit
  20 wire rope

Claims (10)

既に張り出し架設してある橋桁部分上に、エレクションガーダーと、そのエレクションガーダーを支持位置変更可能に支持して前記橋桁部分上を走行する台車とを具えるトラベリングガーダーを配設するとともに、架設する橋桁部材を吊り上げる吊り上げ機を有して前記トラベリングガーダーのエレクションガーダー上を移動する架設作業装置をそのエレクションガーダー上に搭載しておいて、
先ず、前記トラベリングガーダーの台車による前記エレクションガーダーの支持位置をそのエレクションガーダーの、前記橋桁部材の架設のための手延べ方向側と逆側の部分とするとともに、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態にして、前記トラベリングガーダーを前記既に張り出し架設してある橋桁部分上の橋脚付近の位置に配置し、
次いで、その橋脚付近で、前記架設作業装置の吊り上げ機により、前記橋桁部材を、前記既に張り出し架設してある橋桁部分の下方に吊り上げるとともに、前記架設作業装置を搭載した前記トラベリングガーダーを、その台車により移動させて、前記架設作業装置の吊り上げ機で吊り上げた状態の橋桁部材を、前記既に張り出し架設してある橋桁部分の下方にてその橋桁部分に沿ってその橋桁部分の先端まで運搬し、かつ、前記エレクションガーダーの手延べ方向側部分をその既に張り出し架設してある橋桁部分の先端から前方へ手延べさせ、
次いで、前記トラベリングガーダーを前記既に張り出し架設してある橋桁部分に連結して浮き上がり止めしてから、前記架設作業装置を前記エレクションガーダーの前記手延べ方向側部分上に移動させ、
次いで、前記架設作業装置の吊り上げ機により、前記吊り上げた状態の橋桁部材を所定の高さまで引き上げて、その橋桁部材の、前記既に張り出し架設してある橋桁部分の先端への張り出し架設を行い、
次いで、前記トラベリングガーダーと前記既に張り出し架設してある橋桁部分との連結を解除してから、前記トラベリングガーダーの台車による前記エレクションガーダーの支持位置をそのエレクションガーダーの中央部に変更するとともに、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態に移動させ、
その後、前記架設作業装置を搭載した前記トラベリングガーダーをその台車により移動させて、前記既に張り出し架設してある橋桁部分上の橋脚付近の位置まで戻すことを特徴とする、橋桁部材の架設方法。
A traveling girder having an erection girder and a carriage that runs on the bridge girder by supporting the erection girder so that the supporting position of the erection girder can be changed is disposed on the bridge girder already overhanging. A construction work device that has a lifting machine for lifting a member and moves on the traveling girder of the traveling girder is mounted on the electoric girder,
First, the support position of the erection girder by the traveling girder carriage is a part of the erection girder on the side opposite to the handrail direction side for erection of the bridge girder member, and the erection work device is placed on the erection girder. Then, with the erection girder sandwiched between them, the traveling girder is vertically aligned with the cart of the traveling girder, and the traveling girder is arranged at a position near the pier on the bridge girder part that has already been overhanging,
Next, in the vicinity of the bridge pier, the bridge girder member is lifted below the bridge girder portion that has already been overhanged by the lifting machine of the erection work device, and the traveling girder equipped with the erection work device is mounted on the carriage. Transporting the bridge girder member in a state lifted by the lifting machine of the erection work device along the bridge girder part below the bridge girder part already overhanging to the tip of the bridge girder part, and , The hand side direction part of the erection girder is handed forward from the tip of the bridge girder part already overhanging,
Next, the traveling girder is connected to the already extended overhanging bridge girder part and stopped from lifting, and then the construction work device is moved onto the handrail direction side part of the erection girder,
Next, by lifting the bridge girder member in the suspended state to a predetermined height by the lifting machine of the erection work device, the bridge girder member is erected to the tip of the bridge girder part that has already been erected,
Next, after the connection between the traveling girder and the bridge girder already overhanging is released, the support position of the erection girder by the traveling girder carriage is changed to the center of the erection girder and the erection girder Move the working device on the erection girder so that it is vertically aligned with the traveling girder carriage with the erection girder in between,
Thereafter, the traveling girder on which the erection work device is mounted is moved by the carriage and returned to a position near the pier on the bridge girder already overhanging, and the bridge girder member erection method is characterized.
既に張り出し架設してある橋桁部分上に、前記橋桁部分上を走行する台車と、その台車上に固定されたエレクションガーダーとを具えるトラベリングガーダーを配設するとともに、架設する橋桁部材を吊り上げる吊り上げ機を有して前記トラベリングガーダーのエレクションガーダー上を移動する架設作業装置をそのエレクションガーダー上に搭載しておいて、
先ず、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態にして、前記トラベリングガーダーを前記既に張り出し架設してある橋桁部分上の橋脚付近の位置に配置し、
次いで、その橋脚付近で、前記架設作業装置の吊り上げ機により、前記橋桁部材を、前記既に張り出し架設してある橋桁部分の下方に吊り上げるとともに、前記架設作業装置を搭載した前記トラベリングガーダーを、その台車により移動させて、前記架設作業装置の吊り上げ機で吊り上げた状態の橋桁部材を、前記既に張り出し架設してある橋桁部分の下方にてその橋桁部分に沿ってその橋桁部分の先端まで運搬し、かつ、前記エレクションガーダーの手延べ方向側部分をその既に張り出し架設してある橋桁部分の先端から前方へ手延べさせ、
次いで、前記トラベリングガーダーを前記既に張り出し架設してある橋桁部分に連結して浮き上がり止めしてから、前記架設作業装置を前記エレクションガーダーの前記手延べ方向側部分上に移動させ、
次いで、前記架設作業装置の吊り上げ機により、前記吊り上げた状態の橋桁部材を所定の高さまで引き上げて、その橋桁部材の、前記既に張り出し架設してある橋桁部分の先端への張り出し架設を行い、
次いで、前記トラベリングガーダーと前記既に張り出し架設してある橋桁部分との連結を解除してから、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態に移動させ、
その後、前記架設作業装置を搭載した前記トラベリングガーダーをその台車により移動させて、前記既に張り出し架設してある橋桁部分上の橋脚付近の位置まで戻すことを特徴とする、橋桁部材の架設方法。
A lifting machine that arranges a traveling girder including a carriage traveling on the bridge girder part and an erection girder fixed on the bridge girder part, and lifting the bridge girder member to be constructed. The construction work device that moves on the traveling girder of the traveling girder is mounted on the electoric girder,
First, the construction work device is placed on the erection girder so as to be vertically aligned with the carriage girder carriage with the erection girder interposed therebetween, and the traveling girder is overlaid on the bridge girder part that has already been erected. Placed near the pier,
Next, in the vicinity of the bridge pier, the bridge girder member is lifted below the bridge girder portion that has already been overhanged by the lifting machine of the erection work device, and the traveling girder equipped with the erection work device is mounted on the carriage. Transporting the bridge girder member in a state lifted by the lifting machine of the erection work device along the bridge girder part below the bridge girder part already overhanging to the tip of the bridge girder part, and , The hand side direction part of the erection girder is handed forward from the tip of the bridge girder part already overhanging,
Next, the traveling girder is connected to the already extended overhanging bridge girder part and stopped from lifting, and then the construction work device is moved onto the handrail direction side part of the erection girder,
Next, by lifting the bridge girder member in the suspended state to a predetermined height by the lifting machine of the erection work device, the bridge girder member is erected to the tip of the bridge girder part that has already been erected,
Next, after the connection between the traveling girder and the bridge girder already overhanging is released, the erection work device is placed on the erection girder with the erection girder in between, Move it to a state that aligns with
Thereafter, the traveling girder on which the erection work device is mounted is moved by the carriage and returned to a position near the pier on the bridge girder already overhanging, and the bridge girder member erection method is characterized.
既に張り出し架設してある橋桁部分上に、前記橋桁部分上を走行する台車と、その台車上に固定されたエレクションガーダーと、前記エレクションガーダーの延在方向に沿って移動可能なカウンターウエイトとを具えるトラベリングガーダーを配設するとともに、架設する橋桁部材を吊り上げる吊り上げ機を有して前記トラベリングガーダーのエレクションガーダー上を移動する架設作業装置をそのエレクションガーダー上に搭載しておいて、
先ず、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態にするとともに、前記カウンターウエイトを前記トラベリングガーダーの台車と上下に整列する状態にして、前記トラベリングガーダーを前記既に張り出し架設してある橋桁部分上の橋脚付近の位置に配置し、
次いで、その橋脚付近で、前記架設作業装置の吊り上げ機により、前記橋桁部材を、前記既に張り出し架設してある橋桁部分の下方に吊り上げるとともに、前記架設作業装置を搭載した前記トラベリングガーダーを、その台車により移動させて、前記架設作業装置の吊り上げ機で吊り上げた状態の橋桁部材を、前記既に張り出し架設してある橋桁部分の下方にてその橋桁部分に沿ってその橋桁部分の先端まで運搬し、かつ、前記エレクションガーダーの手延べ方向側部分をその既に張り出し架設してある橋桁部分の先端から前方へ手延べさせ、
次いで、前記カウンターウエイトを前記エレクションガーダーの手延べ方向側部分と逆側の部分に移動させながら、前記架設作業装置を前記エレクションガーダーの前記手延べ方向側部分上に移動させ、
次いで、前記架設作業装置の吊り上げ機により、前記吊り上げた状態の橋桁部材を所定の高さまで引き上げて、その橋桁部材の、前記既に張り出し架設してある橋桁部分の先端への張り出し架設を行い、
次いで、前記カウンターウエイトを前記台車と上下に整列する状態に移動させるとともに、前記架設作業装置を前記エレクションガーダー上で、そのエレクションガーダーを間に挟んで前記トラベリングガーダーの台車と上下に整列する状態に移動させ、
その後、前記架設作業装置を搭載した前記トラベリングガーダーをその台車により移動させて、前記既に張り出し架設してある橋桁部分上の橋脚付近の位置まで戻すことを特徴とする、橋桁部材の架設方法。
On a bridge girder part that is already overhanging, a carriage traveling on the bridge girder part, an erection girder fixed on the trolley, and a counterweight movable along the extending direction of the erection girder are provided. A traveling girder that has a lifting machine for lifting a bridge girder member to be installed and moves on the traveling girder of the traveling girder is mounted on the erection girder.
First, the construction work device is placed on the erection girder so as to be vertically aligned with the traveling girder carriage with the erection girder sandwiched therebetween, and the counterweight is vertically aligned with the traveling girder carriage. In the state, the traveling girder is arranged at a position near the pier on the already overhanging bridge girder part,
Next, in the vicinity of the bridge pier, the bridge girder member is lifted below the bridge girder portion that has already been overhanged by the lifting machine of the erection work device, and the traveling girder equipped with the erection work device is mounted on the carriage. Transporting the bridge girder member in a state lifted by the lifting machine of the erection work device along the bridge girder part below the bridge girder part already overhanging to the tip of the bridge girder part, and , The hand side direction part of the erection girder is handed forward from the tip of the bridge girder part already overhanging,
Next, while moving the counterweight to the portion of the erection girder on the side of the handrail direction, the erection work device is moved onto the portion of the erection girder on the handwheel direction side,
Next, by lifting the bridge girder member in the suspended state to a predetermined height by the lifting machine of the erection work device, the bridge girder member is erected to the tip of the bridge girder part that has already been erected,
Next, the counterweight is moved to a state in which the counterweight is vertically aligned with the cart, and the construction work device is vertically aligned with the cart of the traveling girder on the erection girder with the erection girder interposed therebetween. Move
Thereafter, the traveling girder on which the erection work device is mounted is moved by the carriage and returned to a position near the pier on the bridge girder already overhanging, and the bridge girder member erection method is characterized.
エレクションガーダーと、そのエレクションガーダーを支持位置変更可能に支持して走行する台車とを具えるトラベリングガーダーと、
架設する橋桁部材を吊り上げる吊り上げ機と、その吊り上げ機を支持して前記エレクションガーダー上を移動する移動台とを具え、前記トラベリングガーダーの前記エレクションガーダー上に搭載される架設作業装置と、
を組み合わせてなり、
前記トラベリングガーダーの台車が、前記架設作業装置の移動台がその台車と上下に整列する状態であってかつ前記吊り上げ機が前記架設する橋桁部材を吊り上げた状態前記エレクションガーダーを支持して前記エレクションガーダーのバランスをとりながら、既に張り出し架設してある橋桁部分の先端から前記エレクションガーダーが前方へ片持ち状態で手延べする位置まで走行することを特徴とする、橋桁部材の架設装置。
A traveling girder comprising an erection girder and a carriage that supports the erection girder so that the support position can be changed.
A construction work apparatus comprising: a lifting machine for lifting a bridge girder member to be installed; and a moving base that supports the lifting machine and moves on the erection girder; and mounted on the erection girder of the traveling girder;
A combination of
The traveling girder cart supports the erection girder in a state where the moving platform of the erection work device is vertically aligned with the trolley and the lifting machine lifts the bridge girder member to be erected. A bridge girder member erection device characterized in that, while balancing the girder, the erection girder travels from the tip of a bridge girder portion that has already been overhanging to a position where it can be pushed forward in a cantilevered state.
エレクションガーダーと、そのエレクションガーダーを固定支持して走行する台車と、前記エレクションガーダーの延在方向に沿って移動可能なカウンターウエイトとを具えるトラベリングガーダーと、
架設する橋桁部材を吊り上げる吊り上げ機と、その吊り上げ機を支持して前記エレクションガーダー上を移動する移動台とを具え、前記トラベリングガーダーの前記エレクションガーダー上に搭載される架設作業装置と、
を組み合わせてなり、
前記トラベリングガーダーの台車が、前記架設作業装置の移動台および前記カウンターウエイトがその台車と上下に整列する状態であってかつ前記吊り上げ機が前記架設する橋桁部材を吊り上げた状態で前記エレクションガーダーを支持して前記エレクションガーダーのバランスをとりながら、既に張り出し架設してある橋桁部分の先端から前記エレクションガーダーが前方へ片持ち状態で手延べする位置まで走行し、
前記トラベリングガーダーのカウンターウエイトが、前記エレクションガーダー上での前記架設作業装置の移動台の移動方向と逆方向へ移動することでそのエレクションガーダーのバランスを取ることを特徴とする、橋桁部材の架設装置。
A traveling girder comprising an erection girder, a carriage that supports and supports the erection girder, and a counterweight movable along the extending direction of the erection girder ,
A construction work apparatus comprising: a lifting machine for lifting a bridge girder member to be installed; and a moving base that supports the lifting machine and moves on the erection girder; and mounted on the erection girder of the traveling girder;
A combination of
The traveling girder cart supports the erection girder in a state where the moving platform of the erection work device and the counterweight are vertically aligned with the trolley and the lifting machine lifts the bridge girder member to be erected. And while balancing the erection girder, run from the tip of the bridge girder already overhanging to the position where the erection girder cantilevered forward ,
The Traveling girder counterweight, characterized in Rukoto preparative balance of its erection girders by moving the moving base to mobile direction opposite to the direction of the erection work device on the erection girder, erection of the bridge girder members apparatus.
前記架設作業装置の前記吊り上げ機は、前記エレクションガーダーの幅方向両端部を越えて水平に突出するフレームを有し、そのフレームの両端部から前記橋桁部材の両端部を吊り上げるものであることを特徴とする、請求項4または請求項5に記載の橋桁部材の架設装置。The lifting machine of the construction work device has a frame that protrudes horizontally beyond both ends of the erection girder in the width direction, and lifts both ends of the bridge girder member from both ends of the frame. The bridge girder member erection device according to claim 4 or 5 . 前記架設作業装置の前記吊り上げ機は、ワイヤーロープをクランプして連続的に引き上げるワイヤークランプジャッキを具えていることを特徴とする、請求項4から請求項までの何れかに記載の橋桁部材の架設装置。The lifting machine of the construction work device is characterized in that it comprises a wire clamp jack to raise continuously clamp the wire rope, the bridge beam member according to any one of claims 4 to claim 6 Construction device. 前記架設作業装置の前記吊り上げ機は、PC鋼線からなるストランドをクランプして連続的に引き上げるストランドジャッキを具えていることを特徴とする、請求項4から請求項までの何れかに記載の橋桁部材の架設装置。The lifting machine of the construction work device is characterized in that it comprises a strand jack to raise continuously clamping the strands consisting of PC steel wire, according to any of claims 4 to claim 6 Bridge girder erection device. 前記架設作業装置の前記吊り上げ機は、ワイヤーロープを巻き上げるウインチもしくはチェーンを巻き上げるチェーンブロックを具えていることを特徴とする、請求項4から請求項までの何れかに記載の橋桁部材の架設装置。The bridge girder member erection device according to any one of claims 4 to 6 , wherein the hoisting machine of the erection work device comprises a winch for winding a wire rope or a chain block for winding a chain. . 前記トラベリングガーダーの台車と前記架設作業装置の移動台との少なくとも一方は、動力源を搭載して自走するものであることを特徴とする、請求項4から請求項までの何れかに記載の橋桁部材の架設装置。The Traveling girder carriage with at least one of the moving base of the erection work apparatus is characterized in that it is intended to self-propelled and equipped with a power source, according to any one of claims 4 to claim 6 Bridge girder erection device.
JP03576798A 1997-02-19 1998-02-18 Bridge girder member erection method and erection device Expired - Lifetime JP4264470B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP03576798A JP4264470B2 (en) 1997-02-19 1998-02-18 Bridge girder member erection method and erection device

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP9-34986 1997-02-19
JP3498697 1997-02-19
JP03576798A JP4264470B2 (en) 1997-02-19 1998-02-18 Bridge girder member erection method and erection device

Publications (2)

Publication Number Publication Date
JPH10292317A JPH10292317A (en) 1998-11-04
JP4264470B2 true JP4264470B2 (en) 2009-05-20

Family

ID=26373869

Family Applications (1)

Application Number Title Priority Date Filing Date
JP03576798A Expired - Lifetime JP4264470B2 (en) 1997-02-19 1998-02-18 Bridge girder member erection method and erection device

Country Status (1)

Country Link
JP (1) JP4264470B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522095A (en) * 2016-08-27 2017-03-22 江苏中铁山桥重工有限公司 Truss section intra-site multi-directional transferring method

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4489872B2 (en) * 1999-07-05 2010-06-23 三菱重工鉄構エンジニアリング株式会社 Bridge erection method and apparatus
JP2001049622A (en) * 1999-08-05 2001-02-20 Vsl Japan Kk Bridge erecting apparatus and bridge erecting method
JP2001049617A (en) * 1999-08-11 2001-02-20 East Japan Railway Co Elevated bridge
JP3999586B2 (en) * 2002-07-05 2007-10-31 鹿島建設株式会社 Positioning device and positioning method
JP4128887B2 (en) * 2003-02-20 2008-07-30 三井住友建設株式会社 How to install a three-dimensional crossover viaduct
JP4748420B2 (en) * 2006-05-26 2011-08-17 株式会社ピーエス三菱 Construction method of corrugated steel web bridge using girder for erection work
JP4884082B2 (en) * 2006-06-01 2012-02-22 三菱重工鉄構エンジニアリング株式会社 Bridge replacement method
JP4777922B2 (en) * 2007-03-02 2011-09-21 三井住友建設株式会社 Mobile suspension support
JP4719179B2 (en) * 2007-03-29 2011-07-06 オリエンタル白石株式会社 Dismantling / removal method of support work and upper support work
JP4949202B2 (en) * 2007-10-31 2012-06-06 三井住友建設株式会社 Bridge erection method
JP6794235B2 (en) * 2016-12-06 2020-12-02 三井住友建設株式会社 How to erection a bridge
CN108532462A (en) * 2017-03-06 2018-09-14 秦皇岛天业通联重工科技有限公司 A kind of symmetrically set a roof beam in place and its is set a roof beam in place, passing method at formula Bridge Erector
JP6956037B2 (en) * 2018-03-26 2021-10-27 三井住友建設株式会社 A method of erection of a bridge girder of a concrete bridge with a rigid frame structure and a temporary closure structure that can be used for that method.
CN110629677B (en) * 2019-09-29 2021-01-26 中铁大桥局集团有限公司 Method for erecting section steel beam on pier top short slideway beam
CN114182633B (en) * 2021-10-22 2023-04-28 中交第二航务工程局有限公司 Suspension bridge catwalk span-setting method
CN114934447B (en) * 2022-06-01 2023-04-25 中交第二航务工程局有限公司 Multi-span suspension bridge tower zone beam section system conversion method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522095A (en) * 2016-08-27 2017-03-22 江苏中铁山桥重工有限公司 Truss section intra-site multi-directional transferring method
CN106522095B (en) * 2016-08-27 2019-11-19 江苏中铁山桥重工有限公司 Multidirectional method of operation in a kind of truss segment

Also Published As

Publication number Publication date
JPH10292317A (en) 1998-11-04

Similar Documents

Publication Publication Date Title
JP4264470B2 (en) Bridge girder member erection method and erection device
CN202899044U (en) Vierendeel box-shaped double-girder bridge crane
CN111139743A (en) Method for improving speed of highway beam frame and installation method of gantry crane
JP3026545B2 (en) Bridge girder erection method and device
CN110820602A (en) Single-segment box girder bridge girder erection machine and operation method thereof
CN112575694A (en) Mounting construction method for long-span T beam
CN113120771A (en) Double-side synchronous hoisting equipment suitable for rear cantilever arm of composite-section beam bridge and construction method
CN107476195B (en) Girder transporting pulley system for transporting stiffening girder by suspension bridge
CN114808747A (en) Multifunctional bridge girder erection machine and bridge girder erection construction method
CN112030777B (en) Descending movable formwork support bracket crossing type transfer construction method
CN108396749B (en) Installation system and installation method of steel support in foundation pit
CN210366808U (en) Lifting and dismantling device for rail walking
CN111705682A (en) Construction method and equipment for removing and rebuilding superstructure of widened bridge across electrified railway
JP4489872B2 (en) Bridge erection method and apparatus
CN113235460B (en) Prefabricated segment swinging method for bridge cantilever assembly
CN212687392U (en) Cable crane hoisting device for bridge erection
JP2994935B2 (en) Bridge overhang erection method and equipment
CN211446612U (en) Operating platform for steel box girder aerial work
JP2004115174A (en) Movable carriage for member erection, and bridging member erection method using it
CN210368664U (en) Wide-body bridge girder erection machine
CN114086471A (en) Simple and easy mobile device of bridge annex installation
CN108130864B (en) Integrally-assembled bridge whole-span beam transportation and erection equipment
CN107245957B (en) Method and equipment for erecting stiffening beam of suspension bridge in air without track
CN220539633U (en) Prefabricated inverted arch assembling trolley
CN110697571A (en) Single-guide-beam descending type beam feeding device and beam feeding method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050214

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20060720

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070402

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070703

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070831

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080318

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080514

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080722

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080922

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20081028

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20081126

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20081127

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20081127

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20081126

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090107

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20090107

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120227

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150227

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

EXPY Cancellation because of completion of term