CN112412037A - 炼钢厂房与屋面大口径管道的同步施工方法 - Google Patents

炼钢厂房与屋面大口径管道的同步施工方法 Download PDF

Info

Publication number
CN112412037A
CN112412037A CN202011246581.9A CN202011246581A CN112412037A CN 112412037 A CN112412037 A CN 112412037A CN 202011246581 A CN202011246581 A CN 202011246581A CN 112412037 A CN112412037 A CN 112412037A
Authority
CN
China
Prior art keywords
roof
dust removal
construction
span
sealing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011246581.9A
Other languages
English (en)
Inventor
段永林
王敏
杨俊�
张海亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN202011246581.9A priority Critical patent/CN112412037A/zh
Publication of CN112412037A publication Critical patent/CN112412037A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及一种炼钢厂房与屋面大口径管道的同步施工方法,它包括如下步骤:一、施工前根据施工平面布置图及除尘管道布置图,选择合理的履带吊退场路线;二、在确定好履带吊退场路线后,进行施工技术交底,确定主要施工工序;三:主要施工工序为:每一跨屋面封闭→履带吊退出屋面封闭跨→安装屋面除尘支架→履带吊跨内吊装一段屋面除尘管道→继续封闭屋面、履带吊退装屋面除尘管道。本发明使炼钢厂房屋面和屋面除尘管道同步施工,效率高,安全风险低。

Description

炼钢厂房与屋面大口径管道的同步施工方法
技术领域
本发明涉及一种钢结构技术领域,具体的说是炼钢厂房与屋面大口径管道的同步施工方法。
背景技术
在目前,炼钢厂房一般是封闭后再利用大型履带吊进行跨外吊装屋面除尘管道,按照此施工方法,势必对整个炼钢厂房的施工进度、安全都带来不便。
发明内容
本发明旨在克服现有技术的缺陷,提供一种炼钢厂房与屋面大口径管道的同步施工方法,解决炼钢厂房屋面除尘管道施工时在屋面封闭后,再利用大型履带吊进行跨外吊装带来作业效率低,安全风险大,费用高问题。
为了解决上述技术问题,本发明是这样实现的:
一种炼钢厂房与屋面大口径管道的同步施工方法,其特征在于它包括如下步骤:
步骤一、施工前根据施工平面布置图及除尘管道布置图,选择合理的履带吊退场路线;
步骤二、在确定好履带吊退场路线后,进行施工技术交底,确定主要施工工序;
步骤三:主要施工工序为:每一跨屋面封闭→履带吊退出屋面封闭跨→安装屋面除尘支架→履带吊跨内吊装一段屋面除尘管道→继续封闭屋面、履带吊退装屋面除尘管道。
本发明的有益效果是:使炼钢厂房屋面和屋面除尘管道同步施工,效率高,安全风险低、费用低,节约成本。
具体实施方式
一种炼钢厂房与屋面大口径管道的同步施工方法,其特征在于它包括如下步骤:
步骤一、施工前根据施工平面布置图及除尘管道布置图,选择合理的履带吊退场路线;
步骤二、在确定好履带吊退场路线后,进行施工技术交底,确定主要施工工序;
步骤三:主要施工工序为:每一跨屋面封闭→履带吊退出屋面封闭跨→安装屋面除尘支架→履带吊跨内吊装一段屋面除尘管道→继续封闭屋面、履带吊退装屋面除尘管道。

Claims (1)

1.一种炼钢厂房与屋面大口径管道的同步施工方法,其特征在于它包括如下步骤:
步骤一、施工前根据施工平面布置图及除尘管道布置图,选择合理的履带吊退场路线;
步骤二、在确定好履带吊退场路线后,进行施工技术交底,确定主要施工工序;
步骤三:主要施工工序为:每一跨屋面封闭→履带吊退出屋面封闭跨→安装屋面除尘支架→履带吊跨内吊装一段屋面除尘管道→继续封闭屋面、履带吊退装屋面除尘管道。
CN202011246581.9A 2020-11-10 2020-11-10 炼钢厂房与屋面大口径管道的同步施工方法 Pending CN112412037A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011246581.9A CN112412037A (zh) 2020-11-10 2020-11-10 炼钢厂房与屋面大口径管道的同步施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011246581.9A CN112412037A (zh) 2020-11-10 2020-11-10 炼钢厂房与屋面大口径管道的同步施工方法

Publications (1)

Publication Number Publication Date
CN112412037A true CN112412037A (zh) 2021-02-26

Family

ID=74781580

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011246581.9A Pending CN112412037A (zh) 2020-11-10 2020-11-10 炼钢厂房与屋面大口径管道的同步施工方法

Country Status (1)

Country Link
CN (1) CN112412037A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113931457A (zh) * 2021-09-30 2022-01-14 上海宝冶集团有限公司 加热炉区受限作业面大跨度钢结构的吊装方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201776265U (zh) * 2010-08-05 2011-03-30 安徽龙华竹业有限公司 用于大型生产车间的除尘装置
CN104178595A (zh) * 2014-09-12 2014-12-03 山东莱钢建设有限公司 炼钢车间用除尘管道的更换方法
CN104531931A (zh) * 2015-01-19 2015-04-22 中国十九冶集团有限公司 高炉出铁场下部除尘管道安装方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201776265U (zh) * 2010-08-05 2011-03-30 安徽龙华竹业有限公司 用于大型生产车间的除尘装置
CN104178595A (zh) * 2014-09-12 2014-12-03 山东莱钢建设有限公司 炼钢车间用除尘管道的更换方法
CN104531931A (zh) * 2015-01-19 2015-04-22 中国十九冶集团有限公司 高炉出铁场下部除尘管道安装方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
曾求洪等: "210t转炉除尘管道施工方法研究", 《机械工程师》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113931457A (zh) * 2021-09-30 2022-01-14 上海宝冶集团有限公司 加热炉区受限作业面大跨度钢结构的吊装方法

Similar Documents

Publication Publication Date Title
CN112412037A (zh) 炼钢厂房与屋面大口径管道的同步施工方法
CN110307395A (zh) 跨屋面大直径超长管道分段安装施工方法
CN100480398C (zh) 高炉大修拆装炉自吊装施工方法及炉顶起重装置
CN101864730A (zh) 跨原有高架的钢结构箱梁吊装施工方法
CN110172922B (zh) 一种环境友好型下行自行式钢栈桥结构施工方法
CN101264845A (zh) 天车高空整体悬吊换位施工方法
CN107419907B (zh) 一种炼钢塔楼钢结构平台的交错安装焊接方法
CN101545267B (zh) 大面积厂房设备基础闭口施工方法
CN105756368A (zh) 一种简便的重型工业厂房托梁拔柱施工方法
CN105274976A (zh) 水中钢平台预制安装施工方法
CN108374351B (zh) 一种拆除箱梁贝雷片的简易起重装置及方法
CN216809623U (zh) 一种钢箱梁大节段无支架搭接安装结构
CN109138272B (zh) 一种超高层钢棒群连接固定装置及方法
CN204876526U (zh) 一种工具式悬挑钢梁
CN215289748U (zh) 一种t梁横向连接板缝施工装置
CN205711786U (zh) 大断面多孔超长现浇箱涵支模体系
CN211849413U (zh) 一种多功能钢管桩桩帽结构
CN103103923B (zh) 一种悬索桥钢桁架加劲梁架设的窗口铰接法
CN210122447U (zh) 起吊大型组合模板的专用吊具
CN205046828U (zh) 一种环形轨道可移动式吊篮幕墙施工装置
CN111608202A (zh) 一种逆作法地下室环梁钢筋安装方法及装置
CN110860685A (zh) 炼钢连铸厂房的施工方法
CN110093944A (zh) 厚板轧机的在线升级改造施工方法
CN113333991B (zh) 转炉炉壳的组对安装方法
CN101832141A (zh) 一种隧道临时支撑连接方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210226

RJ01 Rejection of invention patent application after publication