CN109138272B - 一种超高层钢棒群连接固定装置及方法 - Google Patents
一种超高层钢棒群连接固定装置及方法 Download PDFInfo
- Publication number
- CN109138272B CN109138272B CN201811119086.4A CN201811119086A CN109138272B CN 109138272 B CN109138272 B CN 109138272B CN 201811119086 A CN201811119086 A CN 201811119086A CN 109138272 B CN109138272 B CN 109138272B
- Authority
- CN
- China
- Prior art keywords
- steel bar
- steel
- welded
- fixing device
- group
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/30—Columns; Pillars; Struts
- E04C3/34—Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/16—Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
- E04C5/162—Connectors or means for connecting parts for reinforcements
- E04C5/163—Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/16—Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
- E04C5/18—Spacers of metal or substantially of metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种超高层钢棒群连接固定装置及方法,该装置包括固定装置和连接装置,所述固定装置包括两个边跨装置以及两个或两个以上的中跨装置,所述的边跨装置是由钢板以及焊接在钢板一侧的两个以上的半圆形卡箍构成,所述的中跨装置是由钢板以及对称地焊接在钢板一侧的两个以上的半圆形卡箍构成,在半圆形卡箍的两侧焊接有耳板,在耳板上开设有通孔,边跨装置以及中跨装置的通孔内穿入有加长螺栓。本发明解决了钢棒内侧无法进行焊接,将钢棒的连接固定由水平向不满足焊缝要求改为竖向连接,满足连接要求,同时满足永久连接和临时固定作用;降低焊接施工难度,减少工厂焊接施工时间,且保证钢棒焊接质量。
Description
技术领域
本发明涉及一种超高层钢棒群连接固定装置及方法,属于建筑施工技术领域。
背景技术
随着国家经济的发展,超高层建筑数量日益增长,超高层建筑的建筑形式较多。为减少超高层钢结构用量和降低建设成本,研究了新型筒中筒结构形式。该新型筒中筒结构的劲性混凝土柱采用混凝土中内置多根钢棒的形式,在受力过程中只承受压力。作为超高层竖向主要受力构件,钢棒连接已成为质量控制关键要点,产生的新型连接方法和施工工艺对超高层的结构安全起到关键作用。
在现有的钢棒连接方法中,钢棒内侧无法进行焊接;施工时钢棒的垂直度难以保证;采用塔吊来吊装单根钢棒,耗时时间长,对于工期和经济效益的影响较大。因此,如何在保证钢棒连接连接可靠的同时,提升施工速度和减少施工成本是一个较为关注的问题。
发明内容
本发明的目的在于,提供一种安装方便快捷、连接牢靠、能够提高施工效率的超高层钢棒群连接固定装置及方法,以克服现有技术中的不足。
本发明的技术方案:一种超高层钢棒群连接固定装置,包括固定装置和连接装置,所述固定装置包括两个边跨装置以及两个或两个以上的中跨装置,所述的边跨装置是由钢板以及焊接在钢板一侧的两个以上的半圆形卡箍构成,所述的中跨装置是由钢板以及对称地焊接在钢板一侧的两个以上的半圆形卡箍构成,在半圆形卡箍的两侧焊接有耳板,在耳板上开设有通孔,边跨装置以及中跨装置的通孔内穿入有加长螺栓;所述的连接装置包括焊接在两根被连接钢棒端部的一对法兰盘,该对法兰盘通过一组紧固螺栓固定连接。
进一步,所述钢棒呈阵列布置,半圆形卡箍的半径小于钢棒的半径。
同时,本发明还提供一种超高层钢棒群连接固定方法,该方法首先采用固定装置将一组钢棒连接在一起,使该组钢棒形成呈阵列布置的钢棒群,然后采用塔吊将固定好的钢棒群吊运至待连接的钢棒群上方,并采用采用连接装置将两组钢棒群连接起来即可。
上述方法中,当采用连接装置连接上下两组钢棒群时,先将钢棒群四个转角处的钢棒连接好,然后将钢棒群与塔吊脱开连接,再调整上下钢棒群的垂直度后,将继续采用连接装置将所有的钢棒连接起来。
由于采用上述技术方案,本发明的优点在于:
1、本发明解决了钢棒内侧无法进行焊接,将钢棒的连接固定由水平向不满足焊缝要求改为竖向连接,满足连接要求,同时满足永久连接和临时固定作用;降低焊接施工难度,减少工厂焊接施工时间,且保证钢棒焊接质量;此外,焊接工作均在工厂完成,无需现场焊接,加快钢棒安装速度;
2、本发明可减少塔吊的施工占用率,缩短施工工期和成本,加快现场安装速度;可以较好的保证钢棒群体的垂直度,减少施工误差。
附图说明
图1为本发明的整体结构示意图;
图2为固定装置的结构示意图;
图3为边跨装置的结构示意图;
图4为中跨装置的结构示意图;
图5为连接装置的结构示意图。
附图标记说明:1-固定装置;2-钢棒;3-连接装置;4-边跨装置;5-中跨装置;6-半圆形卡箍;7-钢板;8-加长螺栓;9-耳板;10-通孔;11-法兰盘;12-紧固螺栓。
具体实施方式
为了使本发明的目的、技术方案和优点更加清楚,下面结合附图和实施例对本发明作进一步的详细说明。
本发明的实施例:超高层钢棒群连接固定装置的结构示意图如图1~5所示,包括固定装置1和连接装置3,所述固定装置1包括两个边跨装置4以及两个或两个以上的中跨装置5,所述的边跨装置4是由钢板7以及焊接在钢板7一侧的两个以上的半圆形卡箍6构成,所述的中跨装置5是由钢板7以及对称地焊接在钢板7一侧的两个以上的半圆形卡箍6构成,在半圆形卡箍6的两侧焊接有耳板9,在耳板9上开设有通孔10,边跨装置4以及中跨装置5的通孔10内穿入有加长螺栓8;所述的连接装置3包括焊接在两根被连接钢棒2端部的一对法兰盘11,该对法兰盘11通过一组紧固螺栓12固定连接。所述钢棒2呈阵列布置,半圆形卡箍6的半径小于钢棒2的半径。
施工时,首先采用固定装置1将一组钢棒2连接在一起,使该组钢棒2形成呈阵列布置的钢棒群,然后采用塔吊将固定好的钢棒群吊运至待连接的钢棒群上方,并采用采用连接装置3将两组钢棒群连接起来即可。
当采用连接装置3连接上下两组钢棒群时,先将钢棒群四个转角处的钢棒2连接好,然后将钢棒群与塔吊脱开连接,再调整上下钢棒群的垂直度后,将继续采用连接装置3将所有的钢棒2连接起来。
Claims (1)
1.一种超高层钢棒群连接固定方法,包括固定装置(1)和连接装置(3),其特征在于:所述固定装置(1)包括两个边跨装置(4)以及两个或两个以上的中跨装置(5),所述的边跨装置(4)是由钢板(7)以及焊接在钢板(7)一侧的两个以上的半圆形卡箍(6)构成,所述的中跨装置(5)是由钢板(7)以及对称地焊接在钢板(7)一侧的两个以上的半圆形卡箍(6)构成,在半圆形卡箍(6)的两侧焊接有耳板(9),在耳板(9)上开设有通孔(10),边跨装置(4)以及中跨装置(5)的通孔(10)内穿入有加长螺栓(8);所述的连接装置(3)包括焊接在两根被连接钢棒(2)端部的一对法兰盘(11),该对法兰盘(11)通过一组紧固螺栓(12)固定连接;所述钢棒(2)呈阵列布置,半圆形卡箍(6)的半径小于钢棒(2)的半径;具体固定方法如下:首先采用固定装置(1)将一组钢棒(2)连接在一起,使该组钢棒(2)形成呈阵列布置的钢棒群,然后采用塔吊将固定好的钢棒群吊运至待连接的钢棒群上方,并采用连接装置(3)将两组钢棒群连接起来即可;当采用连接装置(3)连接上下两组钢棒群时,先将钢棒群四个转角处的钢棒(2)连接好,然后将钢棒群与塔吊脱开连接,再调整上下钢棒群的垂直度后,将继续采用连接装置(3)将所有的钢棒(2)连接起来。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811119086.4A CN109138272B (zh) | 2018-09-25 | 2018-09-25 | 一种超高层钢棒群连接固定装置及方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811119086.4A CN109138272B (zh) | 2018-09-25 | 2018-09-25 | 一种超高层钢棒群连接固定装置及方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109138272A CN109138272A (zh) | 2019-01-04 |
CN109138272B true CN109138272B (zh) | 2023-09-19 |
Family
ID=64812237
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811119086.4A Active CN109138272B (zh) | 2018-09-25 | 2018-09-25 | 一种超高层钢棒群连接固定装置及方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109138272B (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110005136A (zh) * | 2019-04-26 | 2019-07-12 | 中建四局第六建筑工程有限公司 | 一种钢棒群的快速安装结构 |
CN110593488A (zh) * | 2019-07-31 | 2019-12-20 | 中建四局第六建筑工程有限公司 | 一种快速安装固定钢棒群的装置及其安装方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202380647U (zh) * | 2011-11-29 | 2012-08-15 | 中国建筑第七工程局有限公司 | 钢筋定位装置 |
KR101415883B1 (ko) * | 2014-05-15 | 2014-07-11 | (주)케이아이씨 | 지중배전용 전력케이블 지지장치 |
CN105604187A (zh) * | 2016-01-27 | 2016-05-25 | 北京工业大学 | 一种装配式钢结构梁柱节点连接装置 |
CN206554956U (zh) * | 2017-03-14 | 2017-10-13 | 山东科技大学 | 一种新型单体液压支柱防倒固定装置 |
CN208934257U (zh) * | 2018-09-25 | 2019-06-04 | 中建四局第六建筑工程有限公司 | 一种超高层钢棒群连接固定装置 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7922012B2 (en) * | 2008-07-24 | 2011-04-12 | Power Bus Way Ltd. | Cable tray |
-
2018
- 2018-09-25 CN CN201811119086.4A patent/CN109138272B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202380647U (zh) * | 2011-11-29 | 2012-08-15 | 中国建筑第七工程局有限公司 | 钢筋定位装置 |
KR101415883B1 (ko) * | 2014-05-15 | 2014-07-11 | (주)케이아이씨 | 지중배전용 전력케이블 지지장치 |
CN105604187A (zh) * | 2016-01-27 | 2016-05-25 | 北京工业大学 | 一种装配式钢结构梁柱节点连接装置 |
CN206554956U (zh) * | 2017-03-14 | 2017-10-13 | 山东科技大学 | 一种新型单体液压支柱防倒固定装置 |
CN208934257U (zh) * | 2018-09-25 | 2019-06-04 | 中建四局第六建筑工程有限公司 | 一种超高层钢棒群连接固定装置 |
Also Published As
Publication number | Publication date |
---|---|
CN109138272A (zh) | 2019-01-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110412206B (zh) | 火灾实验用可移动式空间自平衡反力架系统及其使用方法 | |
CN201972269U (zh) | 预制钢筋混凝土剪力墙 | |
CN201437639U (zh) | 整体式变形缝钢模板 | |
CN109138272B (zh) | 一种超高层钢棒群连接固定装置及方法 | |
CN103362069A (zh) | 钢混结合箱梁混凝土翼板模板及施工方法 | |
CN207160223U (zh) | 一种可变支点销接式钢桁架平台 | |
CN203475310U (zh) | 钢混结合箱梁混凝土翼板模板 | |
CN203808237U (zh) | 一种预制装配式防屈曲钢板剪力墙高层建筑结构体系 | |
CN206233656U (zh) | 钢框架厂房结构 | |
CN201972271U (zh) | 新型预制钢筋混凝土剪力墙 | |
CN204960324U (zh) | 一种悬挂式楼板模板支撑装置 | |
CN204691201U (zh) | 一种可升降悬挂式脚手架体系 | |
CN210151938U (zh) | 一种用于低位顶升模架系统的柱顶支承装置 | |
CN104805901B (zh) | 一种即插即用的钢结构梁柱连接装置及方法 | |
CN208934257U (zh) | 一种超高层钢棒群连接固定装置 | |
CN109505412B (zh) | 大板梁立拼防倾覆方法 | |
CN201942968U (zh) | 一种铁路收轨装置 | |
CN104652833A (zh) | 钢结构厂房檩条安装提升滑轮的固定装置制作方法 | |
CN218931529U (zh) | 一种柱顶钢梁提升装置 | |
CN219343707U (zh) | 一种钢桁架楼承板补偿装置 | |
CN216075214U (zh) | 一种用于施工升降机的定型化型钢基础 | |
CN218909592U (zh) | 一种桥梁施工用钢箱梁吊装装置 | |
CN219638481U (zh) | 在已有钢柱新增管道梁的节点结构 | |
CN219386680U (zh) | 基于bim的高铁站房快速柱梁连接节点结构 | |
CN217652147U (zh) | 一种钢管桩侧壁牛腿焊接加固结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 230000 building 3, 262 Heping Road, Yaohai District, Hefei City, Anhui Province Applicant after: No 6 Construction Co.,Ltd. of China Construction Fourth Engineering Bureau Address before: 230000 Zhongjian building at the intersection of Tongling Road and Heping Road, Yaohai District, Hefei City, Anhui Province Applicant before: CHINA CONSTRUCTION 4TH ENGINEERING BUREAU, 6TH Co.,Ltd. |
|
GR01 | Patent grant | ||
GR01 | Patent grant |