CN101864730A - 跨原有高架的钢结构箱梁吊装施工方法 - Google Patents

跨原有高架的钢结构箱梁吊装施工方法 Download PDF

Info

Publication number
CN101864730A
CN101864730A CN200910049314A CN200910049314A CN101864730A CN 101864730 A CN101864730 A CN 101864730A CN 200910049314 A CN200910049314 A CN 200910049314A CN 200910049314 A CN200910049314 A CN 200910049314A CN 101864730 A CN101864730 A CN 101864730A
Authority
CN
China
Prior art keywords
crane
hoisting
original high
high racks
vapour
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200910049314A
Other languages
English (en)
Inventor
郑磊
陈炜宁
刘懿彬
陈志明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai First Construction Co Ltd
Original Assignee
Shanghai First Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai First Construction Co Ltd filed Critical Shanghai First Construction Co Ltd
Priority to CN200910049314A priority Critical patent/CN101864730A/zh
Publication of CN101864730A publication Critical patent/CN101864730A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种跨原有高架的钢结构箱梁吊装施工方法,包括如下步骤:(1)、分析施工工况,将汽吊车分别就位;(2)、钢梁运输车到达指定位置,由同一侧的第一台和第二台汽吊车起吊将箱梁吊起至第一次就位位置,然后在将箱梁送至两高架上方第二次就位位置;(3)、由对面的第三台汽吊车完成空中接力将箱梁在高空旋转至新匝道安装位置,并进行焊接固定。本发明在钢结构箱梁过原有高架吊装施工过程中,通过采用三台汽车吊配合吊装、分三次吊装到位,在确保钢结构质量和吊装安全的前提下,顺利的完成了钢梁吊装施工,并未对高架及地面道路交通造成较大影响。

Description

跨原有高架的钢结构箱梁吊装施工方法
技术领域
本发明属于建筑施工技术领域,具体涉及一种钢结构箱梁的吊装施工方法,特别是一种跨原有高架的钢结构箱梁吊装施工方法。
背景技术
随着城市建设的发展,道路交通日趋繁忙,现代的交通方式逐渐由平面交通转向立体交通,经常会出现新的高架或匝道跨越原有高架的情况。由于原有高架的存在,给新建高架或匝道施工带来困难,尤其是钢结构箱梁作为重要施工构件,需要将其吊装至高架桥施工位置,由于原有高架的阻挡,无法顺利直接将钢结构箱梁吊装到位,目前还未有施工先例。
因此,如何确保原有高架和地面交通正常通行的条件下,将钢结构箱梁吊装到位,满足施工需要,成为本领域技术人员迫切需要解决的技术问题。
发明内容
本发明所要解决的技术问题是提供一种跨原有高架的钢结构箱梁吊装施工方法,以确保不影响原有交通正常通行,满足施工需要、加快施工进度。
本发明解决技术问题的技术方案如下:
一种跨原有高架的钢结构箱梁吊装施工方法,其特征在于,新施工匝道跨越原有高架施工,呈交叉形式,包括如下步骤:
(1)、分析施工工况,将汽吊车分别就位:分别将第一台和第二台汽吊车放置于新匝道与原有高架交叉处的同一侧,将第三台汽吊车放置于与前两台汽吊车相对的另一侧;
(2)、钢梁运输车到达指定位置,由同一侧的第一台和第二台汽吊车起吊将箱梁吊起至第一次就位位置,然后在将箱梁送至两高架上方第二次就位位置;
(3)、由对面的第三台汽吊车完成空中接力将箱梁在高空旋转至新匝道安装位置,并进行焊接固定。
由以上公开的技术方案可知,本发明在钢结构箱梁过原有高架吊装施工过程中,通过采用三台汽车吊配合吊装、分三次吊装到位,在由第三台汽吊车完成空中接力旋转及最后到位工作,在确保钢结构质量和吊装安全的前提下,顺利的完成了钢梁吊装施工,并未对高架及地面道路交通造成较大影响。
附图说明
图1为本发明一实施例施工工况示意图。
具体实施方式
下面结合附图和实施例对本发明进行进一步描述。
如图1所示,为某高架工程施工工况图,图中A为现有高架,B为新施工匝道,由于B匝道需跨越现有高架进行施工。
本发明跨原有高架的钢结构箱梁吊装施工方法,包括如下步骤:
(1)、分析施工工况,将汽吊车分别就位:分别将第一台1和第二台汽吊车2放置于新匝道B与原有高架A交叉处的同一侧,第一台汽吊车1设置在近原有高架A一侧,第二台汽吊车2设置在近新匝道B一侧。将第三台汽吊车3放置于与前两台汽吊车1、2相对的另一侧;
(2)、钢梁运输车4到达指定位置,由同一侧的第一台1和第二台汽吊车2起吊将箱梁吊起至第一次就位位置C,然后在将箱梁送至两高架交叉处的上方第二次就位位置D;
(3)、由对面的第三台汽吊车3完成空中接力将箱梁在高空旋转至新匝道安装位置E,并进行焊接固定。
所述第一台1和第二台汽吊车2为200t汽吊车,第三台汽吊车3为300t汽吊车。

Claims (3)

1.一种跨原有高架的钢结构箱梁吊装施工方法,其特征在于,新施工匝道跨越原有高架施工,呈交叉形式,包括如下步骤:
(1)、分析施工工况,将汽吊车分别就位:分别将第一台和第二台汽吊车放置于新匝道与原有高架交叉处的同一侧,将第三台汽吊车放置于与前两台汽吊车相对的另一侧;
(2)、钢梁运输车到达指定位置,由同一侧的第一台和第二台汽吊车起吊将箱梁吊起至第一次就位位置,然后在将箱梁送至两高架上方第二次就位位置;
(3)、由对面的第三台汽吊车完成空中接力将箱梁在高空旋转至新匝道安装位置,并进行焊接固定。
2.根据权利要求1所述的跨原有高架的钢结构箱梁吊装施工方法,其特征在于,所述第一台和第二台汽吊车为200t汽吊车,第三台汽吊车为300t汽吊车。
3.根据权利要求1所述的跨原有高架的钢结构箱梁吊装施工方法,其特征在于,所述第一台汽吊车设置在近原有高架一侧,所述第二台汽吊车设置在近新匝道一侧。
CN200910049314A 2009-04-14 2009-04-14 跨原有高架的钢结构箱梁吊装施工方法 Pending CN101864730A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910049314A CN101864730A (zh) 2009-04-14 2009-04-14 跨原有高架的钢结构箱梁吊装施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910049314A CN101864730A (zh) 2009-04-14 2009-04-14 跨原有高架的钢结构箱梁吊装施工方法

Publications (1)

Publication Number Publication Date
CN101864730A true CN101864730A (zh) 2010-10-20

Family

ID=42956642

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910049314A Pending CN101864730A (zh) 2009-04-14 2009-04-14 跨原有高架的钢结构箱梁吊装施工方法

Country Status (1)

Country Link
CN (1) CN101864730A (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425109A (zh) * 2011-06-25 2012-04-25 中铁七局集团有限公司 采用大跨度龙门吊机吊装系杆的施工方法
CN103696369A (zh) * 2013-11-26 2014-04-02 武汉一冶钢结构有限责任公司 钢箱梁节段四点定位安装方法
CN105970811A (zh) * 2015-06-12 2016-09-28 上海绿地建设(集团)有限公司 大跨径空间三维曲面鱼腹式箱型钢结构高架桥梁施工工艺
CN107858936A (zh) * 2017-12-15 2018-03-30 中铁六局集团有限公司 大型履带起重机吊装上跨铁路桥箱梁施工方法
CN110158471A (zh) * 2019-04-22 2019-08-23 中冶天工集团有限公司 一种大跨度弧形钢箱梁高空接力的吊装方法
CN112095482A (zh) * 2020-09-24 2020-12-18 中国五冶集团有限公司 一种钢箱梁跨既有桥梁吊装施工方法
CN112411381A (zh) * 2020-10-26 2021-02-26 中交路桥建设有限公司 深挖路堑区天桥预制箱梁架设施工方法
CN113322823A (zh) * 2021-06-03 2021-08-31 陕西重型机械制造有限公司 一种大跨度钢桥快速吊装方法
CN114214955A (zh) * 2021-12-28 2022-03-22 武船重型工程股份有限公司 一种跨桥钢板梁的架设方法

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425109A (zh) * 2011-06-25 2012-04-25 中铁七局集团有限公司 采用大跨度龙门吊机吊装系杆的施工方法
CN103696369A (zh) * 2013-11-26 2014-04-02 武汉一冶钢结构有限责任公司 钢箱梁节段四点定位安装方法
CN103696369B (zh) * 2013-11-26 2015-11-18 武汉一冶钢结构有限责任公司 钢箱梁节段四点定位安装方法
CN105970811A (zh) * 2015-06-12 2016-09-28 上海绿地建设(集团)有限公司 大跨径空间三维曲面鱼腹式箱型钢结构高架桥梁施工工艺
CN107858936A (zh) * 2017-12-15 2018-03-30 中铁六局集团有限公司 大型履带起重机吊装上跨铁路桥箱梁施工方法
CN110158471A (zh) * 2019-04-22 2019-08-23 中冶天工集团有限公司 一种大跨度弧形钢箱梁高空接力的吊装方法
CN112095482A (zh) * 2020-09-24 2020-12-18 中国五冶集团有限公司 一种钢箱梁跨既有桥梁吊装施工方法
CN112411381A (zh) * 2020-10-26 2021-02-26 中交路桥建设有限公司 深挖路堑区天桥预制箱梁架设施工方法
CN113322823A (zh) * 2021-06-03 2021-08-31 陕西重型机械制造有限公司 一种大跨度钢桥快速吊装方法
CN114214955A (zh) * 2021-12-28 2022-03-22 武船重型工程股份有限公司 一种跨桥钢板梁的架设方法
CN114214955B (zh) * 2021-12-28 2024-03-22 武船重型工程股份有限公司 一种跨桥钢板梁的架设方法

Similar Documents

Publication Publication Date Title
CN101864730A (zh) 跨原有高架的钢结构箱梁吊装施工方法
JP6986656B1 (ja) 大トン数箱桁の橋への直上吊り上げ施工方法及びその架設方法
CN107268463A (zh) 一种连续梁拆除方法
CN102220811B (zh) 一种特大跨径钢管桁架拱立拼装方法
CN101487232A (zh) 一种钢箱梁拼装施工方法
CN105970836A (zh) 一种大跨度下弦变桁高连续钢桁梁悬臂架设方法
CN203383148U (zh) 一种预制小箱梁跨内起梁装置
CN103692096B (zh) 单节起重臂流水线生产方法和流水线生产装置
CN105201198A (zh) 一种工具式悬挑钢梁及其施工方法
CN202658532U (zh) 桥梁湿接缝施工模板
CN109252693A (zh) 无支撑底托的混凝土支护体系机械分段切割施工方法
CN207553606U (zh) 一种高架车站施工移动支架装置
CN205444937U (zh) 弧形导轨式运输装置
CN106638323B (zh) 一种系杆拱桥拱肋拼装施工方法
CN107142832B (zh) 一种弧形钢箱梁的施工方法
CN205152802U (zh) 一种提高拱桥劲性骨架工地现场制作精度的结构
CN102003074B (zh) 室内大型钢连桥施工方法
CN110159057A (zh) 技改厂房烟筒安装施工方法
CN107285200A (zh) 一种高大跨度桁架整体平移吊装施工方法
CN108277994A (zh) 上跨高铁营运线安全防护棚快速拆除方法
CN107973222A (zh) 用于安装水工钢闸门的架桥机及其施工方法
CN102430866A (zh) 防止吊车梁上翼缘焊接补强钢板变形的方法
CN208871564U (zh) 一种拼装式大跨距组合照明灯桥
CN103192189A (zh) 一种半挂车大梁结构及其焊接工艺
CN202337945U (zh) 外侧就地提升梁体的装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20101020