CN103696369A - 钢箱梁节段四点定位安装方法 - Google Patents

钢箱梁节段四点定位安装方法 Download PDF

Info

Publication number
CN103696369A
CN103696369A CN201310604820.7A CN201310604820A CN103696369A CN 103696369 A CN103696369 A CN 103696369A CN 201310604820 A CN201310604820 A CN 201310604820A CN 103696369 A CN103696369 A CN 103696369A
Authority
CN
China
Prior art keywords
steel box
box girder
girder segment
point
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310604820.7A
Other languages
English (en)
Other versions
CN103696369B (zh
Inventor
孙一
刘建辉
吴清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Yiye Steel Structure Co Ltd
Original Assignee
Wuhan Yiye Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Yiye Steel Structure Co Ltd filed Critical Wuhan Yiye Steel Structure Co Ltd
Priority to CN201310604820.7A priority Critical patent/CN103696369B/zh
Publication of CN103696369A publication Critical patent/CN103696369A/zh
Application granted granted Critical
Publication of CN103696369B publication Critical patent/CN103696369B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种钢箱梁节段四点定位安装方法,包括以下步骤:对对钢箱梁箱体进行节段的划分并编号,标记节段线;所述节段线向内偏移得到四个交点,所述四个交点为测量定位点;计算出每个测量定位点的标高和定位坐标的理论值;制作所有钢箱梁节段,在每个钢箱梁节段上标记测量定位点的位置,并标记编号;每个钢箱梁节段吊装完成后,测量该钢箱梁节段的四个测量定位点的标高和定位坐标的实际值,将该实际值与上述理论值进行比较,如不同,则调整该钢箱梁节段的位置,直至两值相同,如相同,则完成该钢箱梁节段的吊装定位工作。本发明确保了每个钢箱梁节段吊装位置的精确性,提高了整个钢箱梁箱体吊装的精确性,提高了吊装效率。

Description

钢箱梁节段四点定位安装方法
技术领域
本发明具体涉及一种钢箱梁节段四点定位安装方法。
背景技术
随着城市交通的发展,高架桥的建设难度越来越大,城市的交叉路口及车流量较大的路段均采用钢结构的箱梁形式。钢箱梁的施工工艺为:将整联钢箱梁进行节段的划分,一般情况下钢箱梁节段为标准四边行,弧线段为非标准四边形。钢箱梁节段在工厂内进行下料、组装及焊接,最后将钢箱梁节段托运至施工现场进行吊装、定位和焊接。钢箱梁节段在吊装过程中,其安装定位的精度是施工监控的重点之一,每个钢箱梁节段安装精度直接影响到整桥的高程、轴线及线性。但是,传统的钢箱梁测量定位,只需将中间一个钢箱梁节段依据道路中心线进行定位,其余相邻的钢箱梁节段根据对接缝的大小自行调节位置,予以确定其定位,这种方法人为的因素的较大,所存在的误差也较大。
发明内容
本发明要解决的技术问题在于提供一种钢箱梁节段四点定位安装方法,它确保了每个钢箱梁节段吊装位置的精确性,从而极大的提高了整个钢箱梁箱体吊装的精确性,避免了校正,整改,提高了吊装效率。
本发明解决其技术问题所采用的技术方案是:钢箱梁节段四点定位安装方法,包括以下步骤:
S1、先根据钢箱梁箱体的设计图纸,对钢箱梁箱体进行节段的划分并编号,钢箱梁节段编号为MN,并在钢箱梁箱体的平面图纸上标记每个钢箱梁节段的节段线;
S2、然后将所述钢箱梁节段的节段线分别向内偏移一定距离形成偏移线,所述钢箱梁节段面板内的四条偏移线分别两两相交得到四个交点,所述四个交点设为该钢箱梁节段的测量定位点,对所述测量定位点进行编号,测量定位点编号为MN-1、MN-2、MN-3、MN-4;
S3、再计算出每个测量定位点的标高和定位坐标的理论值;
S4、然后制作所有钢箱梁节段,在每个钢箱梁节段的面板上标记四个测量定位点的位置,并标记出所述测量定位点编号;
S5、最后进行钢箱梁节段的现场吊装,沿钢箱梁箱体的宽度方向进行吊装,每个钢箱梁节段吊装完成后,测量该钢箱梁节段的四个测量定位点的标高和定位坐标的实际值,将该实际值与步骤S3中的理论值进行比较,如实际值与理论值不同,则调整该钢箱梁节段的位置,直至实际值与理论值相同,如实际值与理论值相同,则完成该钢箱梁节段的吊装定位工作。
按上述技术方案,所述节段线分别向两侧偏移100~500mm。
按上述技术方案,所述节段线分别向两侧偏移300mm。
按上述技术方案,所述每个测量定位点的标高和定位坐标的理论值由计算机CAD软件结合设计图纸计算得出。
按上述技术方案,所述四个测量定位点的位置通过样冲眼在所对应的钢箱梁节段的面板上进行标记。
本发明产生的有益效果是:该方法操作简单,只需在每个钢箱梁节段上标记出4个测量定位点,现场测量时利用全站仪对每一个钢箱梁节段进行定位,从而确保了每个钢箱梁节段吊装位置的精确性,极大的提高了整个钢箱梁箱体吊装的精确性,避免了校正,整改,提高了吊装效率。
附图说明
下面将结合附图及实施例对本发明作进一步说明,附图中:
图1是钢箱梁箱体面板的结构示意图;
图2是沿图1中A-A线的剖视图;
图3是测量定位点的位置示意图。
其中,1-钢箱梁节段、2-节段线、3-测量定位点、4-偏移线。
具体实施方式
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明。
如图1~图3所示,钢箱梁节段四点定位安装方法,包括以下步骤:
S1、先根据钢箱梁箱体的设计图纸,对钢箱梁箱体进行节段的划分,钢箱梁箱体沿其长度方向划分为M个钢箱梁节段,再沿其宽度方向划分为N个钢箱梁节段,依次对所有钢箱梁节段进行编号,钢箱梁节段编号为MN,编号MN为11、12、…、1N、21、…、M1、M2、…、MN,其中M、N均大于等于1,在本实施例中N=6,并在钢箱梁箱体的平面图纸上标记每个钢箱梁节段的节段线2,节段线2为相邻两个钢箱梁节段1的面板对接缝,钢箱梁节段1的形状为四边形,即每个钢箱梁节段1有四条节段线2;
S2、然后将钢箱梁节段的节段线分别向内偏移一定距离形成偏移线,即每个钢箱梁节段1的四条节段线2分别向内偏移形成四条偏移线4,位于钢箱梁节段面板内的四条偏移线分别两两相交得到四个交点,四个交点设为该钢箱梁节段的测量定位点3,对测量定位点3进行编号,测量定位点编号为MN-1、MN-2、MN-3、MN-4,在本实施例中,节段线分别向两侧偏移100~500mm,以300mm效果最佳;
S3、再计算出每个测量定位点3的标高和定位坐标的理论值,并记录该理论值,该理论值可以由计算机CAD软件结合设计图纸计算得出;
S4、然后制作所有钢箱梁节段1,根据设计详化的图纸,在每个钢箱梁节段1的面板上标记四个测量定位点的位置,并标记出测量定位点编号,在本实施例中,四个测量定位点的位置可以通过样冲眼在所对应的钢箱梁节段的面板上进行标记;
S5、最后进行钢箱梁节段的现场吊装,沿钢箱梁箱体的宽度方向进行吊装,由中间向两边吊装,每个钢箱梁节段吊装完成后,测量该钢箱梁节段的四个测量定位点的标高和定位坐标的实际值,将该实际值与步骤S3中的理论值进行比较,如实际值与理论值不同,则调整该钢箱梁节段的位置,直至实际值与理论值相同,如实际值与理论值相同,则完成该钢箱梁节段的吊装定位工作,在本实施例中,现场测量时用全站仪对每一个钢箱梁节段进行定位,提高定位精度,而后可以通过增加或减少横梁的高度来调整钢箱梁节段的标高,通过千斤顶来调整该钢箱梁节段的定位坐标。 
应当理解的是,对本领域普通技术人员来说,可以根据上述说明加以改进或变换,而所有这些改进和变换都应属于本发明所附权利要求的保护范围。

Claims (5)

1.一种钢箱梁节段四点定位安装方法,其特征在于,包括以下步骤:
S1、先根据钢箱梁箱体的设计图纸,对钢箱梁箱体进行节段的划分并编号,钢箱梁节段编号为MN,并在钢箱梁箱体的平面图纸上标记每个钢箱梁节段的节段线;
S2、然后将所述钢箱梁节段的节段线分别向内偏移一定距离形成偏移线,所述钢箱梁节段面板内的四条偏移线分别两两相交得到四个交点,所述四个交点设为该钢箱梁节段的测量定位点,对所述测量定位点进行编号,测量定位点编号为MN-1、MN-2、MN-3、MN-4;
S3、再计算出每个测量定位点的标高和定位坐标的理论值;
S4、然后制作所有钢箱梁节段,在每个钢箱梁节段的面板上标记四个测量定位点的位置,并标记出所述测量定位点编号;
S5、最后进行钢箱梁节段的现场吊装,沿钢箱梁箱体的宽度方向进行吊装,每个钢箱梁节段吊装完成后,测量该钢箱梁节段的四个测量定位点的标高和定位坐标的实际值,将该实际值与步骤S3中的理论值进行比较,如实际值与理论值不同,则调整该钢箱梁节段的位置,直至实际值与理论值相同,如实际值与理论值相同,则完成该钢箱梁节段的吊装定位工作。
2.根据权利要求1所述的钢箱梁节段四点定位安装方法,其特征在于,所述节段线分别向两侧偏移100~500mm。
3.根据权利要求2所述的钢箱梁节段四点定位安装方法,其特征在于,所述节段线分别向两侧偏移300mm。
4.根据权利要求1所述的钢箱梁节段四点定位安装方法,其特征在于,所述每个测量定位点的标高和定位坐标的理论值由计算机CAD软件结合设计图纸计算得出。
5.根据权利要求1所述的钢箱梁节段四点定位安装方法,其特征在于,所述四个测量定位点的位置通过样冲眼在所对应的钢箱梁节段的面板上进行标记。
CN201310604820.7A 2013-11-26 2013-11-26 钢箱梁节段四点定位安装方法 Expired - Fee Related CN103696369B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310604820.7A CN103696369B (zh) 2013-11-26 2013-11-26 钢箱梁节段四点定位安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310604820.7A CN103696369B (zh) 2013-11-26 2013-11-26 钢箱梁节段四点定位安装方法

Publications (2)

Publication Number Publication Date
CN103696369A true CN103696369A (zh) 2014-04-02
CN103696369B CN103696369B (zh) 2015-11-18

Family

ID=50358019

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310604820.7A Expired - Fee Related CN103696369B (zh) 2013-11-26 2013-11-26 钢箱梁节段四点定位安装方法

Country Status (1)

Country Link
CN (1) CN103696369B (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105133500A (zh) * 2015-08-28 2015-12-09 中交第二航务工程局有限公司 无测量塔的箱梁预制节段的预制安装方法
CN107142833A (zh) * 2017-05-23 2017-09-08 中建钢构有限公司 一种分段式大跨钢箱梁及其焊接方法
CN110144828A (zh) * 2019-06-03 2019-08-20 中建钢构有限公司 钢箱梁拼装的定位结构、支撑结构及桥梁的线形控制方法
CN110487143A (zh) * 2019-07-10 2019-11-22 沪东中华造船(集团)有限公司 一种斜面分段节点快速取点测量方法
CN113958135A (zh) * 2021-09-14 2022-01-21 中国人民解放军63653部队 一种多段h型钢梁快速高精度对齐装置及对齐方法
CN114674296A (zh) * 2022-02-21 2022-06-28 中交二航局结构工程有限公司 一种钢箱梁拼装精调自动调控系统

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0637647A1 (fr) * 1993-08-04 1995-02-08 Campenon Bernard Sge Elément de poutre métallique pour réaliser une structure allongée mixte à section transversale du type en caisson, procédé pour la mise en oeuvre de cet élément, et structure allongée réalisée par la mise en oeuvre de ce procédé
US7296317B2 (en) * 2006-02-09 2007-11-20 Lawrence Technological University Box beam bridge and method of construction
CN101864730A (zh) * 2009-04-14 2010-10-20 上海市第一建筑有限公司 跨原有高架的钢结构箱梁吊装施工方法
CN201648975U (zh) * 2010-04-14 2010-11-24 江苏中泰钢结构股份有限公司 大型钢箱梁桥梁段对线总拼结构
CN101985826A (zh) * 2010-09-19 2011-03-16 湖南路桥建设集团公司 一种大型混凝土箱梁高空分段预制、移梁、存梁、拼装的施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0637647A1 (fr) * 1993-08-04 1995-02-08 Campenon Bernard Sge Elément de poutre métallique pour réaliser une structure allongée mixte à section transversale du type en caisson, procédé pour la mise en oeuvre de cet élément, et structure allongée réalisée par la mise en oeuvre de ce procédé
US7296317B2 (en) * 2006-02-09 2007-11-20 Lawrence Technological University Box beam bridge and method of construction
CN101864730A (zh) * 2009-04-14 2010-10-20 上海市第一建筑有限公司 跨原有高架的钢结构箱梁吊装施工方法
CN201648975U (zh) * 2010-04-14 2010-11-24 江苏中泰钢结构股份有限公司 大型钢箱梁桥梁段对线总拼结构
CN101985826A (zh) * 2010-09-19 2011-03-16 湖南路桥建设集团公司 一种大型混凝土箱梁高空分段预制、移梁、存梁、拼装的施工方法

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105133500A (zh) * 2015-08-28 2015-12-09 中交第二航务工程局有限公司 无测量塔的箱梁预制节段的预制安装方法
CN105133500B (zh) * 2015-08-28 2016-11-23 中交第二航务工程局有限公司 无测量塔的箱梁预制节段的预制安装方法
CN107142833A (zh) * 2017-05-23 2017-09-08 中建钢构有限公司 一种分段式大跨钢箱梁及其焊接方法
CN110144828A (zh) * 2019-06-03 2019-08-20 中建钢构有限公司 钢箱梁拼装的定位结构、支撑结构及桥梁的线形控制方法
CN110487143A (zh) * 2019-07-10 2019-11-22 沪东中华造船(集团)有限公司 一种斜面分段节点快速取点测量方法
CN113958135A (zh) * 2021-09-14 2022-01-21 中国人民解放军63653部队 一种多段h型钢梁快速高精度对齐装置及对齐方法
CN114674296A (zh) * 2022-02-21 2022-06-28 中交二航局结构工程有限公司 一种钢箱梁拼装精调自动调控系统
CN114674296B (zh) * 2022-02-21 2024-02-20 中交二航局结构工程有限公司 一种钢箱梁拼装精调自动调控系统

Also Published As

Publication number Publication date
CN103696369B (zh) 2015-11-18

Similar Documents

Publication Publication Date Title
CN103696369B (zh) 钢箱梁节段四点定位安装方法
CN103711080B (zh) 利用坐标对比法确定钢管拱桥拱肋之间定位的方法
CN103084806B (zh) 一种大型曲线钢箱梁制作方法
CN109281328B (zh) 钢围堰定位桩精确施工方法
CN108345318A (zh) 一种节段梁悬臂拼装墩顶块安装测量方法
CN111254835A (zh) 一种厂内钢箱梁节段连续匹配施工方法
CN101691797B (zh) 一种屋面桁架的制作方法
CN104110140A (zh) 一种网架节点定位调节装置及定位调节方法
CN104748732A (zh) 一种节段预制桥梁架设现场测量方法
CN203768942U (zh) 预埋地脚螺栓定位装置
CN104074364A (zh) 一种铸钢件漏斗型结构预拼装定位施工方法
CN102535863B (zh) 一种不规则异型大空间钢结构的制作安装方法
CN107905108B (zh) 钢管拱栓接式腹杆孔群精度控制方法
CN103344214A (zh) 一种1.6次抛物线型特大桥墩测量及墩身线形控制方法
CN105544982A (zh) 一种双曲面扭转钢柱施工方法
CN107881914B (zh) 一种分丝管式索鞍后场装配式定位装置及装配方法
CN105040992A (zh) 逆作法结构型钢柱倒插式施工方法
CN111691682A (zh) 双层斜交斜放鼓节点网壳单元拼装方法
CN110145159A (zh) 一种焊接连接的接触网硬横梁及其施工方法
CN108425321A (zh) 一种新型变截面桥梁线性控制装置的安装方法
CN111139808B (zh) 一种自升式钻井平台悬臂梁搭载方法
CN110030019B (zh) 一种隧道初期支护钢拱架快速定位放样方法
CN210622423U (zh) 一种焊接连接的接触网硬横梁
CN105441614A (zh) 一种高炉五通球组对方法
CN205157047U (zh) 一种木结构古建筑振动监测拾振器安装装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151118

Termination date: 20211126

CF01 Termination of patent right due to non-payment of annual fee