CN112411798A - Synchronous construction method for prefabricated guide wall and main structure of toilet - Google Patents

Synchronous construction method for prefabricated guide wall and main structure of toilet Download PDF

Info

Publication number
CN112411798A
CN112411798A CN202011389312.8A CN202011389312A CN112411798A CN 112411798 A CN112411798 A CN 112411798A CN 202011389312 A CN202011389312 A CN 202011389312A CN 112411798 A CN112411798 A CN 112411798A
Authority
CN
China
Prior art keywords
guide wall
precast concrete
toilet
hoisting
hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011389312.8A
Other languages
Chinese (zh)
Inventor
傅之鹏
胡芳
戚明
谭家起
杨丽
詹奉平
李贵玺
杨用
许恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Ceg 6 Architectural Engineering Co ltd
Original Assignee
Guizhou Ceg 6 Architectural Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Ceg 6 Architectural Engineering Co ltd filed Critical Guizhou Ceg 6 Architectural Engineering Co ltd
Priority to CN202011389312.8A priority Critical patent/CN112411798A/en
Publication of CN112411798A publication Critical patent/CN112411798A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Abstract

A synchronous construction method for a prefabricated guide wall and a main structure of a toilet comprises the following steps: s1, splitting and designing the precast concrete guide wall: the length of the guide wall is increased by 10mm at the junction with the shear wall, and the thickness of the guide wall is increased by 10mm at the junction with the floor slab; s2, manufacturing the precast concrete guide wall: pre-burying hanging nails on the precast concrete guide wall; s3, steel frame hanging die processing and manufacturing: the hanging die is formed by welding four L30 multiplied by 30 multiplied by 3mm steel square tubes, two angle steels are evenly arranged at the position of the hanging die where the prefabricated part needs to be placed according to the size of the prefabricated part and are welded with the steel square tubes; s4, hoisting a mould and prefabricating a concrete guide wall by a tower crane: installing the shaping hanging die on the horizontal supporting steel bars in the vertical limiting steel bars; hoisting the precast concrete guide wall to the corresponding position of the toilet, and connecting and fixing the precast concrete guide wall with a hoisting die bolt; s5, pouring concrete; and S6, removing the steel frame hanging mould. According to the invention, the prefabricated guide wall and the floor slab structure are cast at one time, so that the structural construction joint is prevented from being formed by secondary casting.

Description

Synchronous construction method for prefabricated guide wall and main structure of toilet
Technical Field
The invention belongs to the field of building construction, and particularly relates to a synchronous construction method of a prefabricated guide wall and a main structure of a toilet.
Background
At present, a concrete flanging guide wall with the height not less than 200mm is generally required to be manufactured before building of a sanitary wall body in building engineering construction, a secondary formwork and concrete pouring method is adopted in traditional guide wall construction, the water stop effect is not ideal, the main quality problem is that secondary structure construction is generally adopted, and as a construction joint exists between the guide wall and a structural floor slab and the interface treatment is not in place in the pouring process, the root of the wall body of a toilet and the like is easy to leak or get damp in the later use process, the later treatment of the engineering is difficult, the material waste amount is large, and the engineering cost is increased.
Disclosure of Invention
In order to avoid the defects caused by the traditional guide wall construction, the invention provides the synchronous construction method of the prefabricated guide wall and the main structure of the toilet.
The purpose of the invention is achieved by the following technical scheme:
a synchronous construction method for a prefabricated guide wall and a main structure of a toilet comprises the following steps:
s1, splitting and designing the precast concrete guide wall: carrying out preliminary analysis on the standard layer toilet plan to determine the position of the concrete guide wall; splitting the precast concrete guide wall by using CAD drawing software, increasing the length of the guide wall by 10mm at the junction with the shear wall, and increasing the thickness of the guide wall by 10mm at the junction with a floor slab; marking the position of the embedded hanging nail;
s2, manufacturing the precast concrete guide wall: the precast concrete guide wall is prefabricated and processed by a precast concrete processing factory according to the split design drawing requirement of the precast concrete guide wall, and hanging nails are pre-buried on the precast concrete guide wall;
s3, steel frame hanging die processing and manufacturing: the hanging die is formed by welding four L30 multiplied by 30 multiplied by 3mm steel square tubes, two angle steels are evenly arranged at the position of the hanging die where the prefabricated part needs to be placed according to the size of the prefabricated part and are welded with the steel square tubes;
s4, hoisting a mould and prefabricating a concrete guide wall by a tower crane: manufacturing a suspended mold bottom support and a vertical limiting steel bar at the suspended mold bottom of the toilet; hoisting the hoisting mould to a toilet area by using a tower crane; installing the shaping hanging die on the horizontal supporting steel bars in the vertical limiting steel bars; hoisting the precast concrete guide wall to the corresponding position of the toilet, and connecting and fixing the precast concrete guide wall with a hoisting die bolt;
s5, pouring concrete: when concrete is poured, a small-sized vibrating rod is used for lifting and vibrating the slurry, and the surface of the concrete is smeared along with tamping; the position of the steel bar is checked and corrected at any time in the concrete pouring and tamping process;
and S6, removing the steel frame hanging mould.
Further, in step S4, before hoisting, a surveyor bounces the line on the floor to determine the position of each guide wall, and the line releasing error is within 2 mm.
Further, step S5, before pouring concrete, the joint of the precast concrete guide wall, the shear wall and the floor slab is subjected to hidden project acceptance.
The invention has the following characteristics:
1. the precast concrete guide wall is prefabricated, the guide wall and a floor slab structure are poured once, secondary formwork support is reduced, a structural construction joint is prevented from being formed by secondary pouring, construction is simple, speed is high, and construction period and construction cost can be saved for engineering.
2. The quality is promoted, and precast concrete guide wall is located reinforced concrete floor top, and two precast concrete guide walls set up respectively around the bathroom, and two precast concrete that meet are pre-buried to the floor in, and close as an organic whole with cast in situ concrete floor, and waterproof nature is better between the precast concrete guide wall, has solved the poor problem of suspended formwork and water-proof effects, has promoted construction quality.
3. Green construction, factory processing of the prefabricated guide wall in the toilet, field hoisting and field non-wet operation, and can effectively control pollution caused by secondary construction.
4. The concrete flanging guide wall is suitable for kitchens, toilets and the like which are specified to be made into concrete flanging guide walls in building engineering.
Drawings
FIG. 1 is a process flow diagram of the present invention;
FIG. 2 is a plan view of a precast concrete guide wall for a toilet according to an embodiment of the present invention;
FIG. 3 is a plan view showing a disassembled state of a precast concrete guide wall for a toilet according to an embodiment of the present invention;
FIG. 4 is a plan view showing a disassembled design of the precast concrete guide wall in the toilet according to the embodiment of the present invention;
FIG. 5 is a diagram illustrating the pre-burying of the precast concrete wall-guiding hanging nail in the toilet according to the embodiment of the invention;
fig. 6 shows a shaped steel form hanging model according to an embodiment of the present invention.
In the figure: 1. toilet, 2, guide wall, 3, shear wall.
Detailed Description
The technical solution of the present invention is further illustrated by the accompanying drawings and examples.
An embodiment, referring to fig. 1, a method for synchronously constructing a prefabricated guide wall and a main structure of a toilet includes the following steps:
1. splitting and designing of precast concrete guide wall
1.1, carrying out preliminary analysis on a standard layer toilet plan to determine the positions of concrete guide walls (in the figure 2, the toilet 1, the guide walls 2 and the shear walls 3 are shown in the figure);
1.2, splitting and designing the precast concrete guide wall by using CAD drawing software (figure 3);
1.3, increasing the length of the guide wall by 10mm at the interface of the guide wall and the shear wall (figure 4);
1.4, increasing the thickness of the guide wall by 10mm at the junction of the guide wall and a floor slab;
1.5 marking the position of the embedded hanging nail (figure 5);
2. precast concrete guide wall manufacturing method
2.1, prefabricating and processing the precast concrete component in a processing plant according to the requirement of a prefabricated concrete guide wall splitting design drawing;
2.2, hanging nails are pre-buried on the precast concrete guide wall, so that later-stage hoisting is facilitated;
3. processing and manufacturing of steel frame hanging die
3.1, transporting the L30 multiplied by 30 multiplied by 3mm steel square pipe which is qualified after detection to a construction site;
3.2 the hanging mould is formed by welding four L30 multiplied by 30 multiplied by 3mm steel square tubes;
3.3 evenly arranging two angle steels according to the size of the prefabricated part at the mould hanging position where the prefabricated part needs to be placed, welding the angle steels with the square steel pipes to form the angle steels, and fixing the prefabricated part at the later stage; (FIG. 6)
4. Tower crane hoisting hanging mould and precast concrete guide wall
4.1 before hoisting, a measurer bounces a line on the floor to determine the positions of all the guide walls, the paying-off errors are within 2mm, and a hanging die bottom support and a vertical limiting steel bar are manufactured at the bottom of a hanging die in a toilet;
4.2, hoisting the hanging mould to a toilet area by using a tower crane;
4.3, installing the shaping hanging die on the horizontal supporting steel bars in the vertical limiting steel bars;
4.4 hoisting the precast concrete guide wall to the corresponding position of the toilet, and connecting and fixing the precast concrete guide wall with a hoisting die bolt;
5. pouring of concrete
5.1 before the concrete is poured, carrying out concealed engineering acceptance on the joints of the precast concrete guide wall, the shear wall and the floor slab;
5.2 when pouring concrete, using a small-sized vibrating rod to carry slurry and vibrate, and smearing the surface of the concrete along with tamping;
5.3, checking and correcting the position of the reinforcing steel bar at any time in the concrete pouring and tamping process;
6. and (5) dismantling the steel frame hanging mould.
The prefabricated concrete guide wall adopted by the invention ensures the verticality of the internal and external corners of the guide wall, avoids the formwork supporting difficulty caused by one-time pouring or two-time pouring of the cast-in-place concrete guide wall and the main structure, and the synchronous construction of the prefabricated concrete guide wall and the main structure avoids two-time scattered construction and repeated construction, thereby eliminating the pollution caused by the two-time construction, enhancing the integrity of the water stop wall and the floor slab, improving the self-waterproof capability of the structure, reducing the later repair cost, and conforming to the current concept of energy conservation, consumption reduction, low carbon and environmental protection.
The prefabricated concrete guide wall is adopted, the hoisting is convenient, the operation time of workers is greatly saved, and the work efficiency is improved. The steel frame is adopted to hang the die, so that the turnover utilization rate is high, the accurate positioning can be realized, the material loss rate under the traditional reinforcement mode is reduced, and the cost is saved. Adopt precast concrete to lead wall and the synchronous construction technique of major structure, the concrete member impression quality is better, has effectively guaranteed structural member cross-sectional dimension, reduces the later stage because of the required expense of chiseling and repairing of expanding die.

Claims (3)

1. A synchronous construction method of a prefabricated guide wall and a main structure of a toilet is characterized in that: the method comprises the following steps:
s1, splitting and designing the precast concrete guide wall: carrying out preliminary analysis on the standard layer toilet plan to determine the position of the concrete guide wall; splitting the precast concrete guide wall by using CAD drawing software, increasing the length of the guide wall by 10mm at the junction with the shear wall, and increasing the thickness of the guide wall by 10mm at the junction with a floor slab; marking the position of the embedded hanging nail;
s2, manufacturing the precast concrete guide wall: the precast concrete guide wall is prefabricated and processed by a precast concrete processing factory according to the split design drawing requirement of the precast concrete guide wall, and hanging nails are pre-buried on the precast concrete guide wall;
s3, steel frame hanging die processing and manufacturing: the hanging die is formed by welding four L30 multiplied by 30 multiplied by 3mm steel square tubes, two angle steels are evenly arranged at the position of the hanging die where the prefabricated part needs to be placed according to the size of the prefabricated part and are welded with the steel square tubes;
s4, hoisting a mould and prefabricating a concrete guide wall by a tower crane: manufacturing a suspended mold bottom support and a vertical limiting steel bar at the suspended mold bottom of the toilet; hoisting the hoisting mould to a toilet area by using a tower crane; installing the shaping hanging die on the horizontal supporting steel bars in the vertical limiting steel bars; hoisting the precast concrete guide wall to the corresponding position of the toilet, and connecting and fixing the precast concrete guide wall with a hoisting die bolt;
s5, pouring concrete: when concrete is poured, a small-sized vibrating rod is used for lifting and vibrating the slurry, and the surface of the concrete is smeared along with tamping; the position of the steel bar is checked and corrected at any time in the concrete pouring and tamping process;
and S6, removing the steel frame hanging mould.
2. The synchronous construction method of the prefabricated guide wall and the main structure of the toilet as claimed in claim 1, wherein: and step S4, before hoisting, a surveyor bounces the line on the floor to determine the position of each guide wall, and the line releasing error is within 2 mm.
3. The synchronous construction method of the prefabricated guide wall and the main structure of the toilet as claimed in claim 1, wherein: and step S5, before concrete pouring, performing concealed engineering acceptance on the joints of the precast concrete guide wall, the shear wall and the floor slab.
CN202011389312.8A 2020-12-02 2020-12-02 Synchronous construction method for prefabricated guide wall and main structure of toilet Pending CN112411798A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011389312.8A CN112411798A (en) 2020-12-02 2020-12-02 Synchronous construction method for prefabricated guide wall and main structure of toilet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011389312.8A CN112411798A (en) 2020-12-02 2020-12-02 Synchronous construction method for prefabricated guide wall and main structure of toilet

Publications (1)

Publication Number Publication Date
CN112411798A true CN112411798A (en) 2021-02-26

Family

ID=74829538

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011389312.8A Pending CN112411798A (en) 2020-12-02 2020-12-02 Synchronous construction method for prefabricated guide wall and main structure of toilet

Country Status (1)

Country Link
CN (1) CN112411798A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115538782A (en) * 2022-11-03 2022-12-30 中国水利水电第三工程局有限公司 Secondary optimization construction method for concrete structure of high-rise building
CN116290456A (en) * 2023-01-18 2023-06-23 北京房修一建筑工程有限公司 Assembled building construction technology

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030000068A (en) * 2001-06-22 2003-01-06 동영금속 주식회사 Assembling mold of water proof concrete sill
US20040093824A1 (en) * 2002-09-19 2004-05-20 Huber Donald G. Concrete forming apparatus for foundation pier blocks and a method for constructing pier blocks
CN102383593A (en) * 2011-08-29 2012-03-21 浙江城建建设集团有限公司 Support formwork device and construction method for one-step formed flange concrete in kitchens and toilets
CN107143076A (en) * 2017-07-04 2017-09-08 上海宝悦房地产开发有限公司 A kind of Prefabricated stacking floor with side flanging and its construction method for being used to drop plate region
CN108442595A (en) * 2018-04-03 2018-08-24 江苏南通三建集团股份有限公司 Precast concrete entirety ground floor and installation method for kitchen and toilet
CN109025268A (en) * 2018-08-17 2018-12-18 重庆中科建设(集团)有限公司 Kitchen and toilet concrete flanging construction method
CN208950302U (en) * 2018-09-05 2019-06-07 广宏建设集团有限公司 One kind making floor and the one-time formed erecting device of concrete flanging
CN110735485A (en) * 2019-09-16 2020-01-31 浙江绿筑集成科技有限公司 Construction method of precast concrete guide walls
CN111075190A (en) * 2020-01-10 2020-04-28 浙江省建设投资集团股份有限公司 Bathroom concrete turn-ups steel mould with adjustable pull

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030000068A (en) * 2001-06-22 2003-01-06 동영금속 주식회사 Assembling mold of water proof concrete sill
US20040093824A1 (en) * 2002-09-19 2004-05-20 Huber Donald G. Concrete forming apparatus for foundation pier blocks and a method for constructing pier blocks
CN102383593A (en) * 2011-08-29 2012-03-21 浙江城建建设集团有限公司 Support formwork device and construction method for one-step formed flange concrete in kitchens and toilets
CN107143076A (en) * 2017-07-04 2017-09-08 上海宝悦房地产开发有限公司 A kind of Prefabricated stacking floor with side flanging and its construction method for being used to drop plate region
CN108442595A (en) * 2018-04-03 2018-08-24 江苏南通三建集团股份有限公司 Precast concrete entirety ground floor and installation method for kitchen and toilet
CN109025268A (en) * 2018-08-17 2018-12-18 重庆中科建设(集团)有限公司 Kitchen and toilet concrete flanging construction method
CN208950302U (en) * 2018-09-05 2019-06-07 广宏建设集团有限公司 One kind making floor and the one-time formed erecting device of concrete flanging
CN110735485A (en) * 2019-09-16 2020-01-31 浙江绿筑集成科技有限公司 Construction method of precast concrete guide walls
CN111075190A (en) * 2020-01-10 2020-04-28 浙江省建设投资集团股份有限公司 Bathroom concrete turn-ups steel mould with adjustable pull

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115538782A (en) * 2022-11-03 2022-12-30 中国水利水电第三工程局有限公司 Secondary optimization construction method for concrete structure of high-rise building
CN116290456A (en) * 2023-01-18 2023-06-23 北京房修一建筑工程有限公司 Assembled building construction technology

Similar Documents

Publication Publication Date Title
CN107130791A (en) Combining aluminum alloy mould plate is used for the construction method of assembly concrete precast construction
CN102383593B (en) Support formwork device and construction method for one-step formed flange concrete in kitchens and toilets
CN104631512A (en) Post-cast strip beam and slab construction method adopting formwork hanging method
CN104790676A (en) Rapid leveling and alignment device and method for installation of prefabricated wallboards
CN206616862U (en) Formwork root bracing means
CN112411798A (en) Synchronous construction method for prefabricated guide wall and main structure of toilet
CN104652815A (en) Construction method for pouring water-stopping upstanding beams in kitchens and toilets
CN210263131U (en) Assembled is from stagnant water underground pipe gallery structure
CN205712565U (en) A kind of prefabricated two-sided wall
CN210421568U (en) Assembled beam and plate structure
CN116378428A (en) Construction method of longitudinal rib superimposed shear wall structure wall
CN111058628A (en) Construction method of post-cast strip formwork support system
CN207140033U (en) Assembly concrete exterior wall board mold
CN206016099U (en) A kind of light prefabricated shears ladder of configuration butterfly beam
CN215055273U (en) A assembled template for installing support bracket embedded box
CN108442698B (en) Deformation joint split bolt pvc sleeve plugging method and plugging fixing sleeve
CN210685368U (en) Convenient reinforcing complete die set for concrete wall formworks on two sides of deformation joint
CN206829428U (en) A kind of light steel lightweight concrete exempts from form removal wall body structure
CN112878462A (en) Construction method of circular inspection well template
CN105756323A (en) Civil building kitchen and toilet-based construction method for sunk suspended form mold
CN211762449U (en) Evaporate and press aerated concrete block wall body to bury a mounting structure
CN210597670U (en) Integrated aluminum mould hanging mould pouring water-stopping concrete ridge structure
CN214403026U (en) Novel prefabricated formula enclosure
CN216634843U (en) Prefabricated constructional column exocoel mould
CN211949003U (en) Integrated stamp concrete wallboard of steel construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210226

RJ01 Rejection of invention patent application after publication