CN112878462A - Construction method of circular inspection well template - Google Patents

Construction method of circular inspection well template Download PDF

Info

Publication number
CN112878462A
CN112878462A CN202110045198.5A CN202110045198A CN112878462A CN 112878462 A CN112878462 A CN 112878462A CN 202110045198 A CN202110045198 A CN 202110045198A CN 112878462 A CN112878462 A CN 112878462A
Authority
CN
China
Prior art keywords
inspection well
mold
circular
inner mold
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110045198.5A
Other languages
Chinese (zh)
Inventor
尹翔
董志杰
杨添
何亮
招日兴
张文浩
布振华
陈桂鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Third Municipal Engineering Co Ltd
Original Assignee
Guangzhou Third Municipal Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Third Municipal Engineering Co Ltd filed Critical Guangzhou Third Municipal Engineering Co Ltd
Priority to CN202110045198.5A priority Critical patent/CN112878462A/en
Publication of CN112878462A publication Critical patent/CN112878462A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • E03F5/025Manhole shafts or other inspection chambers; Snow-filling openings; accessories provided with a liner
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/125Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the lining of the shaft
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Moulds, Cores, Or Mandrels (AREA)

Abstract

The invention discloses a construction method of a circular inspection well template, which belongs to the field of inspection well construction. A cylinder formed by splicing two semicircular wood molds is used as an inner mold of the inspection well for supporting on the inner mold and the outer mold of the brick mold, a concrete precast strip is used for positioning the outer mold of the inspection well, and the inspection well is obtained by building concrete between the inner mold and the outer mold of the inspection well. The inner mold and the outer mold of the brick tire are conveniently and quickly built, the inner mold and the outer mold of the inspection well are both made of prefabricated wooden templates, the advantages of low construction cost and quick and convenient assembly are achieved, meanwhile, the adaptability is strong, and splicing seams of the inspection well can be effectively reduced. Not only improves the engineering quality, but also improves the construction efficiency, shortens the construction period and has good social and economic benefits.

Description

Construction method of circular inspection well template
Technical Field
The invention relates to the field of inspection well construction, in particular to a construction method of a circular inspection well template.
Background
At present, a sewage pipeline inspection well in domestic municipal road drainage engineering is mainly constructed in a mode of shaping a steel mould or a narrow strip wood mould during construction. When adopting design steel mould to construct, because steel form self weight is big, artifical unable transport must rely on lifting device to remove, and construction cost is high and the concatenation installation is inconvenient. When adopting the narrow strip wood former to construct, piece into circular template with a plurality of narrow strip wood formers and fix a position and pour, the circular template concatenation seam that constitutes like this is more and the concatenation seam is great, no matter be appearance quality or geometric dimensions all be difficult to control to need more time concatenation mould. The two construction modes both need longer time, and the construction quality is difficult to control, thereby influencing the progress and the quality of the project.
Disclosure of Invention
In order to overcome the defects of the prior art, the invention aims to solve the technical problem of providing the construction method of the circular inspection well template, the template manufacturing and splicing operation in the construction method is simple, convenient and quick, the cost is low, the construction process is convenient and safe, the construction effect is good, and the construction efficiency and the construction quality of the project are greatly improved.
In order to achieve the purpose, the invention adopts the following technical scheme:
the invention provides a construction method of a circular inspection well template, which comprises the following steps:
the method comprises the following steps: and binding steel bars of the inspection well, pouring bottom plate concrete, and determining the side lines of the inner mold and the outer mold on the poured bottom plate concrete.
Step two: and building the inner mold and the outer mold of the brick molding bed according to the side lines of the inner mold and the outer mold.
Step three: and positioning an inner mold side line of the inspection well at the top of the inner mold of the brick molding bed, splicing the inner mold of the inspection well, conveying the inner mold of the inspection well to the inner mold of the brick molding bed for fixing, and reinforcing the inner mold of the inspection well by adopting cross butt support.
Step four: and positioning the relative positions of the outer inspection well mould and the inner inspection well mould by using a concrete precast strip with the same thickness as the wall of the chamber of the inspection well, and reinforcing the outer inspection well mould.
Step five: and pouring concrete between the inspection well inner mold and the inspection well outer mold.
Step six: and removing the reinforcement outside the inspection well external mold, detaching the cross butt brace inside the inspection well internal mold, and detaching the inspection well internal mold.
In a preferred technical scheme of the invention, the heights of the inner mold and the outer mold of the brick molding bed are higher than that of the pipeline by more than 30cm, and the joints of the inner mold and the outer mold of the brick molding bed and the pipeline are blocked by mortar.
In a preferred technical scheme of the invention, in the third step, the inspection well internal mold is a cylinder formed by splicing two semicircular wood molds.
In a preferred technical scheme of the invention, the end parts of the cross braces are fixed with arc-shaped plates, and the radians of the arc-shaped plates are matched with the semi-circular wood pattern. The cross butt support is respectively abutted against the splicing part of the two semicircular wood formers and the middle part of the semicircular wood formers.
In a preferred technical scheme of the invention, the outer part of the outer mold of the inspection well is reinforced by a steel hoop.
In a preferred technical scheme of the invention, a concrete setting period not less than 24 hours is required to be reserved between the fifth step and the sixth step.
In a preferred technical scheme of the invention, after the inner mold of the inspection well is removed, the inner mold of the brick molding bed is chiseled.
In a preferred technical scheme of the invention, after the concrete is poured in the fifth step, the concrete is vibrated by adopting a vibrating rod.
In a preferred technical scheme of the invention, after the outer mold and the inner mold of the inspection well are disassembled, the surface of the inspection well is maintained by covering with a plastic thin mold.
The invention has the beneficial effects that:
according to the construction method of the circular inspection well template, the inner mold and the outer mold of the inspection well are matched with the brick molding bed, the brick molding bed is used for bottoming, the brick molding bed is connected with the pipeline, and bottom mortar is used for plugging the joint of the brick molding bed and the pipeline, so that mortar leakage is avoided. A cylinder formed by splicing two semicircular wood molds is used as an inner mold of the inspection well for supporting on a brick bed mould, a concrete precast strip is used for positioning an outer mold of the inspection well, and the inspection well is obtained by building concrete between the inner mold and the outer mold of the inspection well. The brick bed die is conveniently and quickly built, the inner die and the outer die of the inspection well are both made of prefabricated wooden templates, the advantages of low construction cost and quick and convenient assembly are achieved, meanwhile, the adaptability is strong, and splicing seams of the inspection well can be effectively reduced. The method not only improves the engineering quality, but also improves the construction efficiency, shortens the construction period and has good social and economic benefits.
Drawings
FIG. 1 is a schematic diagram of a circular manhole template configuration of a preferred embodiment of the present invention;
FIG. 2 is a schematic top view of a circular manhole brick pattern according to a preferred embodiment of the present invention;
FIG. 3 is a schematic diagram of the internal mold structure of the inspection well according to the preferred embodiment of the present invention;
FIG. 4 is a schematic structural diagram of an inspection well external mold according to a preferred embodiment of the present invention;
FIG. 5 is a cross bracing configuration of the preferred embodiment of the present invention; .
In the figure:
1. the device comprises a brick molding bed 11, an outer mold of the brick molding bed, 12, an inner mold of the brick molding bed, 21, an inner mold of an inspection well, 31, a steel bar hoop, 32, an outer mold of the inspection well, 41, a cross butt brace, 42 and an arc-shaped plate.
Detailed Description
The technical scheme of the invention is further explained by the specific implementation mode in combination with the attached drawings.
The invention provides a construction method of a circular inspection well template, which comprises the following steps:
the method comprises the following steps: and binding steel bars of the inspection well, pouring bottom plate concrete, and determining the side lines of the inner mold and the outer mold on the poured bottom plate concrete.
Step two: and building an inner mold 12 and an outer mold 11 of the brick molding bed according to the side lines of the inner mold and the outer mold. The brick die inner die 12 and the brick die outer die 11 are penetrated through by a drain pipe from the middle, the building height of the brick die inner die 12 and the brick die outer die 11 is determined according to the diameter of the drain pipe, and the two bricks need to be built above the top of the drain pipe to fix the drain pipe. Meanwhile, in order to prevent slurry leakage at the joints of the brick mould outer mould 11, the brick mould inner mould 12 and the drain pipe, mortar is required to be used for plugging the joints, so that the connection between the brick mould 1 and the drain pipe is sealed.
Step three: positioning an inspection well inner mold 21 side line at the top of the brick mould inner mold 12, wherein the inspection well inner mold 21 consists of two semicircular wood molds which are spliced together on a flat terrain to form a cylindrical inspection well inner mold 21, and brushing a stripper on the inspection well inner mold 21. Meanwhile, the cross bracing 41 is adopted to reinforce the inspection well internal mold 21, the cross bracing 41 is provided with adjustable threaded rod pieces, the cross bracing 41 is respectively arranged in the inspection well from top to bottom, and the threaded rods on the cross bracing 41 are adjusted, so that the cross bracing 41 and the cross bracing 4141 support the inspection well internal mold 21 at 4 fulcrums, and the inspection well internal mold 21 is reinforced. And (4) conveying the reinforced inspection well inner die 21 to the brick moulding bed inner die 12, wherein the inspection well inner die 21 is fixed to the brick moulding bed inner die 12 along the side line of the inspection well inner die 21.
Step four: according to the construction requirement, a concrete prefabricated strip with the same wall thickness as the wall thickness of the manhole chamber is selected, the prefabricated strip is attached to the outer portion of the inner manhole 21, and then the outer manhole 32 is wrapped on the outer portion of the concrete prefabricated strip. The inspection well external mold 32 is formed by splicing 4 arc-shaped modules, and a stripper is also coated on the inspection well external mold 32. After the manhole outer die 32 is used for coating the prefabricated strips, reinforcement treatment is performed on the outer portion of the manhole outer die 32.
And after the inspection well external mold 32 is fixed, checking and accepting the inspection well internal mold 21 and the inspection well external mold 32 according to the engineering specification, and performing the next step after the setting is confirmed to be correct.
Step five: and concrete is poured between the inner inspection well mould 21 and the outer inspection well mould 32, and the concrete and the prefabricated strips are solidified together to form the well wall of the inspection well under the positioning of the inner inspection well mould and the outer inspection well mould. After the concrete pouring is completed, the next step is performed after the concrete is completely solidified.
Step six: removing the reinforcement outside the inspection well external mold 32, detaching 4 arc molds of the inspection well external mold 32 from the inspection well, detaching the cross butt support 41 and the cross butt support 4141 inside the inspection well internal mold 21 from top to bottom, prying the staggered opening along the splicing part of the inspection well by using a crowbar after detaching the cross butt support 41 and the cross butt support 4141. The detached arc-shaped die and the half-round wood die can be reused.
Compared with the traditional mode of adopting a shaped steel die or a narrow strip wood die to pour the inspection well, the construction method provided by the embodiment greatly reduces the construction difficulty, the mode of combining the inner die and the outer die of the inspection well with the brick bed mould 1 improves the construction effect of the inspection well, the template can be repeatedly utilized, the construction cost is reduced, meanwhile, the construction method is high in construction speed, the construction period is shortened, and good social benefits and economic benefits are achieved.
In one embodiment of the invention, the heights of the inner brick molding bed 12 and the outer brick molding bed 11 are higher than the height of the pipeline by more than 30cm, so that the drain pipe is fully wrapped by the brick molding bed 1 and protected. And simultaneously, mortar is used for plugging joints of the inner mold 12 of the brick molding bed, the outer mold 11 of the brick molding bed and the pipeline. Preventing the slurry leakage.
In one embodiment of the present invention, in step three, the manhole inner mold 21 is formed by splicing two semicircular wood molds into a cylinder. The semi-circular wood formers are manufactured according to the size of the inspection well to be built, and the two semi-circular wood formers are spliced together to form a cylinder for supporting and shaping the interior of the inspection well.
In one embodiment of the present invention, the cross brace 41 and the cross brace 4141 are fixed with the arc plate 42 at the end, and the arc of the arc plate 42 is matched with the semicircle wood pattern. The cross counter support 41 and the cross counter support 4141 respectively abut against the splicing part of the two semicircular wood formers and the middle part of the semicircular wood formers. The arc plate 42 of setting can laminate to the semicircle wood pattern on, enlarges the support area to the semicircle wood pattern, makes the support that the semicircle wood pattern received more even, non-deformable. .
In one embodiment of the present invention, the manhole outer mold 32 and the manhole outer mold 3232 are externally reinforced by steel hoops 31. When the 4 arc-shaped molds are positioned and decocted on the concrete prefabricated strip, the concrete prefabricated strip is wrapped by the steel hoop 31, the tightness of the steel hoop 31 is adjusted by screwing the screws on the steel hoop 31, the screws are screwed, so that the arc-shaped molds tightly clamp the concrete prefabricated strip, and the deformation of the inspection well external mold 3232 of the inspection well external mold 32 is effectively controlled.
In one embodiment of the invention, a concrete setting period not less than 24 hours needs to be reserved between the fifth step and the sixth step, so that the poured inspection well is ensured to be sufficiently set, and collapse caused by insufficient setting is avoided.
In one embodiment of the invention, after the inner mold 21 of the inspection well is removed, the inner mold 12 of the brick mould is chiseled. After the inner mold 12 of the brick molding bed is removed, the outer mold 11 of the brick molding bed can be reserved according to the actual situation and the use requirement.
In one embodiment of the invention, after the concrete is poured in the fifth step, the concrete is vibrated by a vibrating rod. The vibration elimination of the vibrating rod prevents the foaming in the poured concrete, and prevents the honeycomb pitted surface from appearing inside the well wall, thereby preventing the strength of the well wall from being influenced.
In an embodiment of the invention, after the outer inspection well mold 32 and the inner inspection well mold 21 are removed in the sixth step, the surface of the inspection well is maintained by covering with a thin plastic mold. The surface of the concrete is sealed by an anti-evaporation material, so that the water in the concrete is prevented from evaporating, the concrete is kept or close to a water saturation state, and the normal operation of the hydration reaction of the cement is ensured.
While the invention has been described with reference to a preferred embodiment, it will be understood by those skilled in the art that various changes may be made and equivalents may be substituted for elements thereof without departing from the spirit and scope of the invention. The present invention is not to be limited by the specific embodiments disclosed herein, and other embodiments that fall within the scope of the claims of the present application are intended to be within the scope of the present invention.

Claims (9)

1.一种圆形检查井模板的施工方法,其特征在于:包括以下步骤:1. a construction method of circular inspection well formwork, is characterized in that: comprise the following steps: 步骤一:绑扎检查井钢筋、浇筑底板混凝土,在浇筑完成的底板混凝土上确定出内外模边线;Step 1: Bind the steel bars of the inspection well, pour the bottom plate concrete, and determine the inner and outer mold edges on the bottom plate concrete that has been poured; 步骤二:根据所述内外模边线砌筑砖胎模内模(12)与砖胎模外模(11);Step 2: build a brick tire mold inner mold (12) and a brick tire mold outer mold (11) according to the edge lines of the inner and outer molds; 步骤三:在所述砖胎模内模(12)的顶部定位检查井内模(21)边线,将检测井内模拼接好,并且将所述检查井内模(21)搬运至砖胎模内模(12)上固定,所述检查井内模(21)的内部采用十字对撑(41)加固;Step 3: Position the edge of the inspection well inner mold (21) on the top of the brick tire mold inner mold (12), splicing the inspection well inner mold (21), and transport the inspection well inner mold (21) to the brick tire mold inner mold ( 12) fixed on the top, and the inside of the inspection well mold (21) is reinforced with cross braces (41); 步骤四:使用与检查井室壁厚度相同的混凝土预制条来定位检查井外模(32)与所述检查井内模(21)的相对位置,并且对所述检查井外模(32)进行加固;Step 4: Use the concrete prefabricated strip with the same thickness as the inspection well wall to locate the relative position of the inspection well outer mold (32) and the inspection well inner mold (21), and reinforce the inspection well outer mold (32) ; 步骤五:在所述检查井内模(21)与所述检查井外模(32)之间浇筑混凝土;Step 5: pouring concrete between the inner mold (21) of the inspection well and the outer mold (32) of the inspection well; 步骤六:去除所述检查井外模(32)外部的加固,拆除所述检查井外模(32),拆除所述检查井内模(21)内部的所述十字对撑(41),拆除所述检查井内模(21)。Step 6: Remove the reinforcement outside the inspection well outer mold (32), remove the inspection well outer mold (32), remove the cross braces (41) inside the inspection well inner mold (21), remove the The inner mold (21) of the inspection well is described. 2.根据权利要求1所述的一种圆形检查井模板的施工方法,其特征在于:2. the construction method of a kind of circular inspection well template according to claim 1, is characterized in that: 所述砖胎模内模(12)以及所述砖胎模外模(11)的高度高于管道30cm以上,且所述砖胎模内模(12)、所述砖胎模外模(11)与管道的接缝处使用砂浆进行封堵。The height of the inner mold (12) of the brick tire mold and the outer mold (11) of the brick tire mold is higher than that of the pipeline by more than 30 cm, and the inner mold of the brick tire mold (12) and the outer mold of the brick tire mold (11) ) and the joints of the pipes are sealed with mortar. 3.根据权利要求1所述的一种圆形检查井模板的施工方法,其特征在于:3. the construction method of a kind of circular inspection well template according to claim 1, is characterized in that: 步骤三中,所述检查井内模(21)由两个半圆木模拼接成圆筒。In step 3, the inner mold (21) of the inspection well is formed by splicing two semi-circular wooden molds into a cylinder. 4.根据权利要求3所述的一种圆形检查井模板的施工方法,其特征在于:4. the construction method of a kind of circular inspection well template according to claim 3, is characterized in that: 所述十字对撑(41)的端部固定有弧形板(42),所述弧形板(42)的弧度与所述半圆木模相适配;An arc-shaped plate (42) is fixed at the end of the cross brace (41), and the arc of the arc-shaped plate (42) is adapted to the semi-circular wood mold; 所述十字对撑(41)分别抵于两个所述半圆木模的拼接处、所述半圆木模的中部。The cross braces (41) respectively abut against the splicing point of the two semi-circular wooden molds and the middle of the semi-circular wooden molds. 5.根据权利要求1所述的一种圆形检查井模板的施工方法,其特征在于:5. the construction method of a kind of circular inspection well template according to claim 1, is characterized in that: 所述检查井外模(32)外部采用钢条抱箍进行加固。The outside of the inspection well outer mold (32) is reinforced with a steel bar hoop. 6.根据权利要求1所述的一种圆形检查井模板的施工方法,其特征在于:6. the construction method of a kind of circular inspection well template according to claim 1, is characterized in that: 步骤五与步骤六之间需留有不小于24小时的混凝土凝固期。A concrete setting period of not less than 24 hours should be left between Steps 5 and 6. 7.根据权利要求1所述的一种圆形检查井模板的施工方法,其特征在于:7. the construction method of a kind of circular inspection well template according to claim 1, is characterized in that: 所述检查井内模(21)拆除后,对所述砖胎模内模(12)进行凿除。After the inner mold (21) of the inspection well is removed, the inner mold (12) of the brick tire mold is chiseled. 8.根据权利要求1所述的一种圆形检查井模板的施工方法,其特征在于:8. the construction method of a kind of circular inspection well template according to claim 1, is characterized in that: 步骤五中浇筑了混凝土后,对混凝土采用振捣棒振捣。After the concrete is poured in step 5, the concrete is vibrated with a vibrating rod. 9.根据权利要求1所述的一种圆形检查井模板的施工方法,其特征在于:9. The construction method of a circular inspection well template according to claim 1, wherein: 所述检查井外模(32)、所述检查井内模(21)拆除后,对检查井表面使用塑料薄模覆盖进行养护。After the inspection well outer mold (32) and the inspection well inner mold (21) are removed, the surface of the inspection well is covered with a plastic thin mold for maintenance.
CN202110045198.5A 2021-01-13 2021-01-13 Construction method of circular inspection well template Pending CN112878462A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110045198.5A CN112878462A (en) 2021-01-13 2021-01-13 Construction method of circular inspection well template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110045198.5A CN112878462A (en) 2021-01-13 2021-01-13 Construction method of circular inspection well template

Publications (1)

Publication Number Publication Date
CN112878462A true CN112878462A (en) 2021-06-01

Family

ID=76045828

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110045198.5A Pending CN112878462A (en) 2021-01-13 2021-01-13 Construction method of circular inspection well template

Country Status (1)

Country Link
CN (1) CN112878462A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113199602A (en) * 2021-06-04 2021-08-03 中冶交投善筑成都装配式建筑科技发展有限公司 Cambered surface prefabricated part mold and manufacturing method of prefabricated part
CN116290112A (en) * 2023-03-20 2023-06-23 中国一冶集团有限公司 A concrete inspection well formwork device and construction method
CN116695849A (en) * 2023-04-28 2023-09-05 钟春芳 Construction method of circular internal mold sewage inspection well
CN117266245A (en) * 2023-08-18 2023-12-22 湖北省路桥集团有限公司 Construction equipment and construction methods of inspection wells
CN118601042A (en) * 2024-06-29 2024-09-06 中冶建工集团有限公司 Reinforcement structure of circular inspection well construction
CN119041548A (en) * 2024-09-28 2024-11-29 广东粤昊建筑有限公司 Sewage inspection well auxiliary installation device and construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5855102A (en) * 1998-02-18 1999-01-05 Chang; Houn-I Molded brick module
US6869553B1 (en) * 2002-07-12 2005-03-22 John D. Gentile Method for forming a precast brick riser
CN103088844A (en) * 2013-03-04 2013-05-08 济南城建集团有限公司 Reinforced concrete inspection well whole prefabricated hoisting construction method
CN106638697A (en) * 2016-11-08 2017-05-10 安徽水安建设集团股份有限公司 Method for rapidly constructing light formwork of reinforced-concrete-cast-in-place circular draining inspection well
CN107816059A (en) * 2017-12-12 2018-03-20 叶香雄 Sunk type basement constructs
CN207469307U (en) * 2017-10-20 2018-06-08 中交第二航务工程局有限公司 A kind of gang form structure of the inspection shaft cast-in-place construction of town road pipeline
CN109826233A (en) * 2019-03-05 2019-05-31 车明凤 A kind of minor diameter inspection well set shaped steel formwork pouring construction method
CN111074943A (en) * 2020-01-10 2020-04-28 广西建工集团联合建设有限公司 Construction method for integrally casting inspection well shaping steel mould in situ

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5855102A (en) * 1998-02-18 1999-01-05 Chang; Houn-I Molded brick module
US6869553B1 (en) * 2002-07-12 2005-03-22 John D. Gentile Method for forming a precast brick riser
CN103088844A (en) * 2013-03-04 2013-05-08 济南城建集团有限公司 Reinforced concrete inspection well whole prefabricated hoisting construction method
CN106638697A (en) * 2016-11-08 2017-05-10 安徽水安建设集团股份有限公司 Method for rapidly constructing light formwork of reinforced-concrete-cast-in-place circular draining inspection well
CN207469307U (en) * 2017-10-20 2018-06-08 中交第二航务工程局有限公司 A kind of gang form structure of the inspection shaft cast-in-place construction of town road pipeline
CN107816059A (en) * 2017-12-12 2018-03-20 叶香雄 Sunk type basement constructs
CN109826233A (en) * 2019-03-05 2019-05-31 车明凤 A kind of minor diameter inspection well set shaped steel formwork pouring construction method
CN111074943A (en) * 2020-01-10 2020-04-28 广西建工集团联合建设有限公司 Construction method for integrally casting inspection well shaping steel mould in situ

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113199602A (en) * 2021-06-04 2021-08-03 中冶交投善筑成都装配式建筑科技发展有限公司 Cambered surface prefabricated part mold and manufacturing method of prefabricated part
CN116290112A (en) * 2023-03-20 2023-06-23 中国一冶集团有限公司 A concrete inspection well formwork device and construction method
CN116695849A (en) * 2023-04-28 2023-09-05 钟春芳 Construction method of circular internal mold sewage inspection well
CN117266245A (en) * 2023-08-18 2023-12-22 湖北省路桥集团有限公司 Construction equipment and construction methods of inspection wells
CN117266245B (en) * 2023-08-18 2025-12-02 湖北省路桥集团有限公司 Construction equipment and methods for manholes
CN118601042A (en) * 2024-06-29 2024-09-06 中冶建工集团有限公司 Reinforcement structure of circular inspection well construction
CN119041548A (en) * 2024-09-28 2024-11-29 广东粤昊建筑有限公司 Sewage inspection well auxiliary installation device and construction method

Similar Documents

Publication Publication Date Title
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN103015717B (en) Rear superelevation steel pipe column outsourcing Construction technology of fair-faced concrete closed by a kind of floor
CN100582421C (en) A formwork method for concrete pillars
CN201443203U (en) A mold with reserved holes for cast-in-place reinforced concrete floor slabs
CN112112295A (en) A kind of rear-enclosed exterior wall post-casting belt reinforcement construction method
CN106760502A (en) Shear wall end cylinder construction method
CN106638697A (en) Method for rapidly constructing light formwork of reinforced-concrete-cast-in-place circular draining inspection well
CN107366353B (en) A kind of assembled steel reinforced concrete frame column with variable cross-sections and its construction method
CN110905113A (en) Construction method of large-span concrete dome structure
CN111188459B (en) Construction process for bonding prestressed reinforced concrete beam
CN110629787A (en) Core mold for pipe gallery pouring and construction method
CN214246617U (en) Unilateral mould bearing structure is striden to height
CN210976588U (en) Template reinforcing system for double shear walls at deformation joint
CN115506593B (en) Garage roof and wall column construction method
CN109853953A (en) Controllable wall pours the outer wall template split bolt of thickness and its peace tears method open
CN215889453U (en) Temporary support for two sides of post-cast strip of building floor
CN104975715A (en) Formwork sealing method for walls or columns
CN116290421A (en) A construction method of steel-concrete structure prefabricated and cast with wall panels
CN209907926U (en) Pouring formwork system of secondary structure wall structure column which can realize segmental vibration
CN104929154A (en) One-time pouring and forming construction technology for totally enclosed columns of cover and excavation top-down subway station
CN113417458A (en) Post-cast strip mold sealing method
CN206956933U (en) A kind of assembled steel reinforced concrete frame column with variable cross-sections and its making mould
CN107700752A (en) One kind exempts from template iron net concrete cast beam, post and its construction method
CN209798958U (en) Pouring system for drainage ditch of bottom plate post-cast strip and shaping hanging die for drainage ditch
CN108755700B (en) Installation method of curved surface superposed ring beam device for supporting underground enclosure wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210601