CN108442595A - Precast concrete entirety ground floor and installation method for kitchen and toilet - Google Patents

Precast concrete entirety ground floor and installation method for kitchen and toilet Download PDF

Info

Publication number
CN108442595A
CN108442595A CN201810289240.6A CN201810289240A CN108442595A CN 108442595 A CN108442595 A CN 108442595A CN 201810289240 A CN201810289240 A CN 201810289240A CN 108442595 A CN108442595 A CN 108442595A
Authority
CN
China
Prior art keywords
kitchen
wall
toilet
bottom plate
precast concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810289240.6A
Other languages
Chinese (zh)
Inventor
矫贵峰
周波
黄端
顾锦博
何称称
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kang Boda Energy Technology Co Ltd
Jiangsu Nantong Three Construction Group Ltd By Share Ltd
Original Assignee
Kang Boda Energy Technology Co Ltd
Jiangsu Nantong Three Construction Group Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kang Boda Energy Technology Co Ltd, Jiangsu Nantong Three Construction Group Ltd By Share Ltd filed Critical Kang Boda Energy Technology Co Ltd
Priority to CN201810289240.6A priority Critical patent/CN108442595A/en
Publication of CN108442595A publication Critical patent/CN108442595A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/12Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
    • E04H1/125Small buildings, arranged in other buildings
    • E04H1/1266Cubicles for dressing; Toilets

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Residential Or Office Buildings (AREA)

Abstract

The invention discloses a kind of precast concrete entirety ground floors for kitchen and toilet, including kitchen and toilet bottom plate, surrounding, which is equipped with, on kitchen and toilet bottom plate leads wall, it leads wall and kitchen and toilet bottom plate is integrated, wall is led to be directly installed in structural beams or partly lead wall in structural beams or be not installed in structural beams, it leads the outer middle side part of wall and is equipped with groove, groove is trapezoidal, it leads wall lateral surface root and inside inclined-plane slope foot is set, it leads the reserved annular anchoring stirrup in wall periphery and longitudinal reinforcement, the middle side part for leading wall is equipped with door opening.The technology of the present invention is simple and reasonable, it is easy to operate, be easy to grasp, speed of application is fast, the common quality defect that common cast-in-place structural floor leaks frequent occurrence at kitchen and toilet position is thoroughly prevented, solve the problems, such as that prefabrication cannot use precast concrete prefabricated member, remarkable in economical benefits in position between there is boiled water room in the interior such as kitchen and toilet.

Description

Precast concrete entirety ground floor and installation method for kitchen and toilet
Technical field
It is specifically a kind of for the precast concrete entirety ground floor of kitchen and toilet and installation the present invention relates to building field Method.
Background technology
With the continuous improvement that country requires building energy conservation emission reduction, building industry state-of-the-art technology has obtained political affairs at different levels It wideling popularize and continuing to develop in mansion.Precast concrete assembled architecture technology is to realize that architecture production is industrialized most effective Approach realizes architecture production mode and turns from traditional extensive produced on-site to the basic of intensive batch production flow line production Become, the main member of building is prefabricated using the batch of batch production, as precast construction wall, structural column, structural beams, floor, stair, Balcony slab, air-conditioning plate etc..
However, for the indoor floor having between boiled water room such as kitchen and toilet, due to existing common concrete Prefabricated board piece position existing for Tulou plate technique cannot fundamentally solve waterproof problem, still cast-in-place mixed using tradition at present Solidifying earth process construction, this just constrains the prefabricated rate of building element and cannot improve, and labour's input amount is still very big, and speed of application is still It is old slow.If the ground floor having boiled water room to the kitchen of building, toilet etc. realizes integral prefabricated assembly construction, will be to drop The industrialization technology level that low labour's input, quickening speed of application, raising are built is extremely important.
The present invention is based under above-mentioned background condition, and the interiors such as kitchen and toilet for prefabrication have Position between boiled water room, a kind of precast concrete entirety ground floor technology of research and development.
Invention content
To solve the above-mentioned problems, the present invention provides a kind of precast concrete entirety ground floor and peace for kitchen and toilet Dress method.
The technical scheme is that:For the precast concrete entirety ground floor of kitchen and toilet, including kitchen and toilet bottom plate, It is surrounded by kitchen and toilet bottom plate and leads wall, led wall and kitchen and toilet bottom plate is integrated, lead the plan-position of wall and the structural beams of lower part Position is overlapped or part lead wall plan-position it is Chong Die with the structural beams position of lower part or lead the knot of the plan-position of wall and lower part Structure beam position is underlapped, leads wall lateral surface root and inside inclined-plane slope foot is arranged, it is pre- that one jiao of kitchen and toilet bottom plate is equipped with exhaust duct The wall of leading of box out mouth, exhaust duct reserved opening position survives ground higher than kitchen and toilet bottom plate and is no less than 50mm, exhaust duct hole to be provided Mouth side is equipped with floor drain, and pre-buried electric pipeline and pre-buried vertical drainage pipe are equipped in kitchen and toilet bottom plate, and the every side for leading wall is equipped with not Less than 1 lifting point built-in fitting, the middle side part for leading wall are equipped with door opening, and kitchen and toilet plate outer side is equipped with attached superimposed sheet, attached It includes superimposed sheet anchor bar, superimposed sheet cableway to belong to superimposed sheet.
Further, it leads wall and uses armored concrete, the concrete for leading wall, kitchen and toilet bottom plate and attached superimposed sheet uses one Secondary property continuous placing molding, in addition to door opening position is reserved, other positions are continuously arranged along the periphery of whole ground bottom plate, The position not indwelling construction joint of prefabricated monolithic concrete ground floor component.
Further, the wall height of leading at door opening position survives ground higher than kitchen and toilet bottom plate and is no less than 20mm, removes door opening Outside oral area position, the wall height for leading wall survives ground higher than kitchen and toilet bottom plate and is no less than 300mm, and the position and thickness for leading wall should be with Upper part filling partition wall be consistent or be not less than 50mm, or according to filling partition wall thickness 1/2-1/3 guide wall in advance when lead wall Outer middle side part is equipped with groove, and groove is trapezoidal or rectangle, when leading that middle side part is equipped with groove outside wall described in lead wall periphery reserved Annular anchoring stirrup and longitudinal reinforcement.
Further, it kitchen and toilet plate upper surface and leads side within the walls and is equipped with waterproof layer and protective layer, waterproof layer and protective layer It constructs at the scene or in shop.
The installation method of precast concrete entirety ground floor for kitchen and toilet, includes the following steps:
a)The prefabrication in kitchen and toilet monolithic concrete structurally waterproof ground floor;
1)Using prefabricated die station, the mould installation of kitchen and toilet entirety floor side is carried out successively;
2)Wall is led to whole kitchen and toilet bottom plate, surrounding and attached superimposed sheet position carries out the peace of reinforcing bar binding and lifting point built-in fitting Dress is fixed;
3)Pre-buried to the installation of electromechanical supporting pipelines, surrounding is led the template installation of wall and reserved opening and is fixed;
4)Concrete is poured and is conserved, then form removal, which is transported to, stacks place, constructs to ground waterproof layer and protective layer;
b)The lifting of kitchen and toilet precast concrete entirety ground floor member;
1)Before lifting, carry out an acceptance inspection qualification to the reinforcing bar of installation position, template, it is whole to kitchen and toilet precast concrete Body ground floor component carries out minute inspection, and whether each spot size meets whether design requirement, concrete structural surface touch Undermine cracking, it is pre-buried and reserved whether omit and accurate;
2)It when lifting, is fixed using special hanger and rope, hoisting machinery install in place;Check member planar position After meeting design and code requirement with absolute altitude, unloads suspender, completes kitchen and toilet precast concrete entirety ground floor member Lifting;
c)Precast concrete entirety ground member is connect with perimeter body structure reinforcing bars and concreting;
1)After the floor member lifting of precast concrete entirety ground is in place, in time with the progress reinforcing bar binding of perimeter body structure and in advance Bury electromechanical pipeline connection;
2)Check and accept verification, be determined for compliance with design requirement and it is accurate after, be attached the concrete pouring construction at position;
3)Concrete is conserved, after the strength of mould stripping for reaching code requirement, form removal.
The invention has the beneficial effects that:It is directly prefabricated in the factory and finishes, improve prefabrication and assembly construction rate, trapezoidal or rectangular recess Increase contact surface, increases bonding strength, when factory makes precast concrete entirety ground floor, internal pre-buried electrical pipe Line, drainpipe, floor drain etc. have all fixed good position, need not construct at the scene, accelerate speed of application, skill of the present invention Art is simple and reasonable, it is easy to operate, be easy to grasp, speed of application is fast, has thoroughly prevented common cast-in-place structural floor in kitchen The common quality defect in room and toilet position easy to leak, solve prefabrication has boiled water room in the interiors such as kitchen and toilet Between ground bottom plate cannot use precast concrete prefabricated member problem, remarkable in economical benefits.
Description of the drawings
Fig. 1 be the present invention kitchen and toilet lead wall plan-position it is Chong Die with the structural beams position of lower part when component vertical view Structural schematic diagram;
Fig. 2 be the present invention kitchen and toilet lead wall plan-position it is Chong Die with the structural beams position of lower part when component main view graph structure Schematic diagram;
Fig. 3 be the present invention kitchen and toilet lead wall plan-position it is Chong Die with the structural beams position of lower part when component left view graph structure Schematic diagram;
Fig. 4 be the present invention kitchen and toilet lead wall plan-position it is Chong Die with the structural beams position of lower part when component section graph structure Schematic diagram;
Fig. 5 be the present invention kitchen and toilet only partly lead wall plan-position it is Chong Die with the structural beams position of lower part when component vertical view Figure structure schematic representation;
Fig. 6 be the present invention kitchen and toilet only partly lead wall plan-position it is Chong Die with the structural beams position of lower part when component main view Figure structure schematic representation;
Fig. 7 be the present invention kitchen and toilet only partly lead wall plan-position it is Chong Die with the structural beams position of lower part when component left view Figure structure schematic representation;
Fig. 8 be the present invention kitchen and toilet only partly lead wall plan-position it is Chong Die with the structural beams position of lower part when component section Figure structure schematic representation;
Fig. 9 be the present invention kitchen and toilet lead wall plan-position and lower part structural beams position it is underlapped when component vertical view Structural schematic diagram;
Figure 10 be the present invention kitchen and toilet lead wall plan-position and lower part structural beams position it is underlapped when component main view Figure structure schematic representation;
Figure 11 be the present invention kitchen and toilet lead wall plan-position and lower part structural beams position it is underlapped when component left view Figure structure schematic representation;
Figure 12 be the present invention kitchen and toilet lead wall plan-position and lower part structural beams position it is underlapped when component section Figure structure schematic representation;
Wherein 1, kitchen and toilet bottom plate, 2, lead wall, 3, exhaust duct reserved opening, 4, door opening, 5, lifting point built-in fitting, 6, pre-buried electricity Gas pipeline, 7, pre-buried vertical drainage pipe, 8, floor drain, 9, reserved annular anchoring stirrup and longitudinal reinforcement, 10, attached superimposed sheet;11、 Superimposed sheet anchor bar;12, superimposed sheet cableway, 13, waterproof layer, 14, groove.
Specific implementation mode
The present invention is further described below in conjunction with the accompanying drawings.
For the precast concrete entirety ground floor of kitchen and toilet, including kitchen and toilet bottom plate 1, surrounding on kitchen and toilet bottom plate 1 Equipped with wall 2 is led, lead wall 2 and kitchen and toilet bottom plate 1 be integrated, lead wall 2 plan-position is Chong Die with the structural beams position of lower part or portion The plan-position for point leading wall 2 is Chong Die with the structural beams position of lower part or lead the plan-position of wall 2 and the structural beams position of lower part is equal It is underlapped, it leads 2 lateral surface root of wall and inside inclined-plane slope foot is set, 1 one jiaos of kitchen and toilet bottom plate is equipped with exhaust duct reserved opening 3, 2 height of wall of leading at 3 position of exhaust duct reserved opening survives ground higher than kitchen and toilet bottom plate 1 and is no less than 50mm, exhaust duct hole to be provided 3 sides of mouth are equipped with floor drain 8, are equipped with pre-buried electric pipeline 6 and pre-buried vertical drainage pipe 7 in kitchen and toilet bottom plate 1, lead every side of wall 2 Equipped with no less than 1 lifting point built-in fitting 5, the middle side part for leading wall 2 is equipped with door opening 4, and 1 outside of kitchen and toilet bottom plate is equipped with attached Superimposed sheet 10, attached superimposed sheet 10 include superimposed sheet anchor bar 11, superimposed sheet cableway 12.
It leads wall 2 and uses armored concrete, the concrete use for leading wall 2, kitchen and toilet bottom plate 1 and attached superimposed sheet disposably connects Continuous pouring molding, in addition to 4 position of door opening is reserved, other positions are continuously arranged along the periphery of whole ground bottom plate, prefabricated The position not indwelling construction joint of monolithic concrete ground floor component.
2 height of wall of leading at 4 position of door opening survives ground higher than kitchen and toilet bottom plate 1 and is no less than 20mm, removes 4 position of door opening Outside, the wall height for leading wall 2 survives ground higher than kitchen and toilet bottom plate 1 and is no less than 300mm, leads position and the thickness Ying Yuqi of wall 2 Top filling partition wall is consistent or not less than 50mm and no more than 100mm, or prefabricated according to the 1/3-1/2 of filling partition wall thickness 2 outer middle side part of wall is led when leading wall 2 and is equipped with groove 14, and groove 14 is trapezoidal or rectangle, and groove 14 is equipped with when leading 2 outer middle side part of wall Shi Suoshu leads the reserved annular anchoring stirrup in 2 periphery of wall and longitudinal reinforcement 9.
It 1 upper surface of kitchen and toilet bottom plate and leads the inside of wall 2 and is equipped with waterproof layer 13 and protective layer, waterproof layer 13 and protective layer are existing It constructs or in shop in field.
The installation method of precast concrete entirety ground floor for kitchen and toilet, includes the following steps:
a)The prefabrication in kitchen and toilet monolithic concrete structurally waterproof ground floor;
1)Using prefabricated die station, the mould installation of kitchen and toilet entirety floor side is carried out successively;
2)Wall 2 is led to whole kitchen and toilet bottom plate 1, surrounding and 10 position of attached superimposed sheet carries out reinforcing bar binding and lifting point built-in fitting Installation fix;
3)Pre-buried to the installation of electromechanical supporting pipelines, surrounding is led the template installation of wall 2 and reserved opening and is fixed;
4)Concrete is poured and is conserved, then form removal, which is transported to, stacks place, constructs to ground waterproof layer and protective layer;
b)The lifting of kitchen and toilet precast concrete entirety ground floor member;
1)Before lifting, carry out an acceptance inspection qualification to the reinforcing bar of installation position, template, it is whole to kitchen and toilet precast concrete Body ground floor component carries out minute inspection, and each spot size meets design requirement, concrete structural surface without clashing and breaking and cracking, Pre-buried and reserved exhaustive is simultaneously accurate;
2)It when lifting, is fixed using special hanger and rope, hoisting machinery install in place;Check member planar position After meeting design and code requirement with absolute altitude, unloads suspender, completes kitchen and toilet precast concrete entirety ground floor member Lifting.
c)Precast concrete entirety ground member is connect with perimeter body structure reinforcing bars and concreting;
1)After the floor member lifting of precast concrete entirety ground is in place, in time with the progress reinforcing bar binding of perimeter body structure and in advance Bury electromechanical pipeline connection;
2)Check and accept verification, be determined for compliance with design requirement and it is accurate after, be attached the concrete pouring construction at position;
3)Concrete is conserved, after the strength of mould stripping for reaching code requirement, form removal.
According to the position for leading wall and installation position structural beams of kitchen and toilet precast concrete entirety ground floor member Relationship has following 3 kinds of embodiments respectively.
Kitchen and toilet lead wall plan-position it is Chong Die with the structural beams position of lower part on when, element structure figure institute picture 1-4 Show:
After kitchen and toilet precast concrete entirety ground floor member is transported to construction site, lifted just using lifting equipment Position.At this point, the plan-position for leading wall of kitchen and toilet ground surrounding is Chong Die with the structural beams position of lower part;Component negative is set up per side It is not less than 10mm in precast concrete beam(Or the side template inside of cast-in-place structural beam is stretched into not less than 10mm);For pressing Wall is guided in advance according to the 1/2-1/3 of filling partition wall thickness, and the filling wall thickness on wall top is led according to kitchen and toilet, carries out leading wall outside portion The reinforcing bar binding and template installation of position;Finally, to kitchen and toilet precast concrete entirety ground floor member and peripheral structure Connecting portion carry out concreting, complete the installation of kitchen and toilet precast concrete entirety ground floor member.
Kitchen and toilet only partly lead wall plan-position it is Chong Die with the structural beams position of lower part on when, element structure figure as scheme Shown in 5-8:
After kitchen and toilet precast concrete entirety ground floor member is transported to construction site, lifted just using lifting equipment Position.At this point, the plan-position that kitchen and toilet ground surrounding only partly leads wall is Chong Die with the structural beams position of lower part;For partly leading When the plan-position of wall and the not be overlapped structural beams position of lower part, close on the attached superimposed sheet edge for leading wall ride upon it is prefabricated It is not less than 10mm on concrete structured beam(Or the side template inside of cast-in-place structural beam is stretched into not less than 10mm);It leads component part When the plan-position of wall is Chong Die with the structural beams position of lower part, the bottom edge for leading wall lower part rides upon precast concrete Beam is not less than 10mm(Or the side template inside of cast-in-place structural beam is stretched into not less than 10mm);For according to filling partition wall thickness Wall is guided in advance, the filling wall thickness on wall top is led according to kitchen and toilet, carries out the reinforcing bar binding for leading wall outside left and mould Plate is installed;Finally, concreting is carried out to the connecting portion of component and peripheral structure, completes kitchen and toilet precast concrete The installation of whole ground floor member.
Kitchen and toilet lead wall plan-position and lower part structural beams position it is underlapped when, element structure figure such as Fig. 9-12 It is shown:
After kitchen and toilet precast concrete entirety ground floor member is transported to construction site, lifted just using lifting equipment Position.At this point, the plan-position for leading wall of kitchen and toilet ground surrounding and the structural beams position of lower part are underlapped, close on this and lead wall Attached superimposed sheet edge ride upon on precast concrete beam be not less than 10mm(Or stretch into the side template of cast-in-place structural beam Inside is not less than 10mm);Finally, concreting is carried out to the connecting portion of component and peripheral structure, it is prefabricated completes kitchen and toilet The installation of concrete structure entirety ground floor member.

Claims (5)

1. for the precast concrete entirety ground floor of kitchen and toilet, including kitchen and toilet bottom plate, it is characterised in that:The kitchen and toilet It is surrounded by bottom plate and leads wall, it is described to lead wall and kitchen and toilet bottom plate is integrated, the structure of the plan-position and lower part for leading wall Beam position is overlapped or part lead wall plan-position it is Chong Die with the structural beams position of lower part or lead the plan-position of wall and lower part Structural beams position is underlapped, and inside inclined-plane slope foot is arranged in the wall lateral surface root of leading, and one jiao of the kitchen and toilet bottom plate is set There is exhaust duct reserved opening, the wall height of leading below the exhaust duct reserved opening survives ground higher than kitchen and toilet bottom plate and is no less than 50mm, exhaust duct reserved opening side are equipped with floor drain, and the kitchen and toilet bottom plate is interior equipped with pre-buried electric pipeline and pre-buried perpendicular To drainpipe, the every side for leading wall is equipped with no less than 1 lifting point built-in fitting, and the middle side part for leading wall is equipped with door opening Mouthful, the kitchen and toilet plate outer side is equipped with attached superimposed sheet, and the attached superimposed sheet includes superimposed sheet anchor bar, overlapping grillage Vertical reinforcing bar.
2. the precast concrete entirety ground floor according to claim 1 for kitchen and toilet, it is characterised in that:It is described to lead Wall use armored concrete, the concrete for leading wall, kitchen and toilet bottom plate and attached superimposed sheet using disposable continuous placing at Type, in addition to door opening position is reserved, other positions are continuously arranged along the periphery of whole ground bottom plate, in prefabricated monolithic concrete The position not indwelling construction joint of ground floor component.
3. the precast concrete entirety ground floor according to claim 1 for kitchen and toilet, it is characterised in that:The door The wall height of leading of hole part survives ground higher than kitchen and toilet bottom plate and is no less than 20mm, in addition to door opening position, leads the wall of wall Height survives ground higher than kitchen and toilet bottom plate and is no less than 300mm, and the position for leading wall and thickness should fill partition wall with upper part It is led described in when being consistent or be not less than 50mm and be not more than 100mm, or wall is guided in advance according to the 1/3-1/2 of filling partition wall thickness The outer middle side part of wall is equipped with groove, and the groove is trapezoidal or rectangle, when it is described lead that middle side part is equipped with groove outside wall when described in lead The reserved annular anchoring stirrup in wall periphery and longitudinal reinforcement.
4. the precast concrete entirety ground floor according to claim 1 for kitchen and toilet, it is characterised in that:The kitchen Defend a plate upper surface and lead side within the walls and be equipped with waterproof layer and protective layer, the waterproof layer and protective layer construct at the scene or Shop.
5. the installation method of the precast concrete entirety ground floor for kitchen and toilet, it is characterised in that:Include the following steps:
a)The prefabrication in kitchen and toilet monolithic concrete structurally waterproof ground floor;
1)Using prefabricated die station, the mould installation of kitchen and toilet entirety floor side is carried out successively;
2)Wall is led to whole kitchen and toilet bottom plate, surrounding and attached superimposed sheet position carries out the peace of reinforcing bar binding and lifting point built-in fitting Dress is fixed;
3)Pre-buried to the installation of electromechanical supporting pipelines, surrounding is led the template installation of wall and reserved opening and is fixed;
4)Concrete is poured and is conserved, then form removal, which is transported to, stacks place, constructs to ground waterproof layer and protective layer;
b)The lifting of kitchen and toilet precast concrete entirety ground floor member;
1)Before lifting, carry out an acceptance inspection qualification to the reinforcing bar of installation position, template, it is whole to kitchen and toilet precast concrete Body ground floor component carries out minute inspection, and each spot size meets design requirement, concrete structural surface without clashing and breaking and cracking, Pre-buried and reserved exhaustive is simultaneously accurate;
2)It when lifting, is fixed using special hanger and rope, hoisting machinery install in place;Check member planar position After meeting design and code requirement with absolute altitude, unloads suspender, completes kitchen and toilet precast concrete entirety ground floor member Lifting;
c)Precast concrete entirety ground member is connect with perimeter body structure reinforcing bars and concreting;
1)After the floor member lifting of precast concrete entirety ground is in place, in time with the progress reinforcing bar binding of perimeter body structure and in advance Bury electromechanical pipeline connection;
2)Check and accept verification, be determined for compliance with design requirement and it is accurate after, be attached the concrete pouring construction at position;
3)Concrete is conserved, after the strength of mould stripping for reaching code requirement, form removal.
CN201810289240.6A 2018-04-03 2018-04-03 Precast concrete entirety ground floor and installation method for kitchen and toilet Withdrawn CN108442595A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810289240.6A CN108442595A (en) 2018-04-03 2018-04-03 Precast concrete entirety ground floor and installation method for kitchen and toilet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810289240.6A CN108442595A (en) 2018-04-03 2018-04-03 Precast concrete entirety ground floor and installation method for kitchen and toilet

Publications (1)

Publication Number Publication Date
CN108442595A true CN108442595A (en) 2018-08-24

Family

ID=63198086

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810289240.6A Withdrawn CN108442595A (en) 2018-04-03 2018-04-03 Precast concrete entirety ground floor and installation method for kitchen and toilet

Country Status (1)

Country Link
CN (1) CN108442595A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109025016A (en) * 2018-09-21 2018-12-18 中国二十二冶集团有限公司 Plate and its construction method integrally drop in concrete
CN109750831A (en) * 2019-01-30 2019-05-14 山西三建集团有限公司 The template system and mold method that kitchen toilet water-stopping platform and floor drop plate pour simultaneously
CN112411798A (en) * 2020-12-02 2021-02-26 贵州建工集团第六建筑工程有限责任公司 Synchronous construction method for prefabricated guide wall and main structure of toilet
CN114108917A (en) * 2021-12-09 2022-03-01 中铁建设集团有限公司 Height-adjustable assembly type composite floor slab construction method
CN114525926A (en) * 2022-02-24 2022-05-24 中国五冶集团有限公司 Construction structure for integrally forming water stop and structure of kitchen and bathroom and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU8468391A (en) * 1990-09-27 1992-04-02 Caulley, Allan A building system using transportable service modules in slab on ground construction
KR20080086329A (en) * 2007-03-21 2008-09-25 이존경 Floor waterproofing structure of prefabricated bathroom and method of executing the same
CN102777033A (en) * 2011-03-17 2012-11-14 有利华建筑预制件有限公司 Method for mounting prefabricated kitchen
CN105421818A (en) * 2015-12-08 2016-03-23 徐州中煤百甲重钢科技股份有限公司 Embedded steel structure assembling residence
CN206189908U (en) * 2016-09-29 2017-05-24 中民筑友科技投资有限公司 Bathroom room
CN107795017A (en) * 2017-10-25 2018-03-13 长沙远大住宅工业集团股份有限公司 A kind of attachment structure and its construction method of caisson and partition wall
CN208280410U (en) * 2018-04-03 2018-12-25 江苏南通三建集团股份有限公司 Precast concrete entirety ground floor for kitchen and toilet

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU8468391A (en) * 1990-09-27 1992-04-02 Caulley, Allan A building system using transportable service modules in slab on ground construction
KR20080086329A (en) * 2007-03-21 2008-09-25 이존경 Floor waterproofing structure of prefabricated bathroom and method of executing the same
CN102777033A (en) * 2011-03-17 2012-11-14 有利华建筑预制件有限公司 Method for mounting prefabricated kitchen
CN105421818A (en) * 2015-12-08 2016-03-23 徐州中煤百甲重钢科技股份有限公司 Embedded steel structure assembling residence
CN206189908U (en) * 2016-09-29 2017-05-24 中民筑友科技投资有限公司 Bathroom room
CN107795017A (en) * 2017-10-25 2018-03-13 长沙远大住宅工业集团股份有限公司 A kind of attachment structure and its construction method of caisson and partition wall
CN208280410U (en) * 2018-04-03 2018-12-25 江苏南通三建集团股份有限公司 Precast concrete entirety ground floor for kitchen and toilet

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109025016A (en) * 2018-09-21 2018-12-18 中国二十二冶集团有限公司 Plate and its construction method integrally drop in concrete
CN109750831A (en) * 2019-01-30 2019-05-14 山西三建集团有限公司 The template system and mold method that kitchen toilet water-stopping platform and floor drop plate pour simultaneously
CN112411798A (en) * 2020-12-02 2021-02-26 贵州建工集团第六建筑工程有限责任公司 Synchronous construction method for prefabricated guide wall and main structure of toilet
CN114108917A (en) * 2021-12-09 2022-03-01 中铁建设集团有限公司 Height-adjustable assembly type composite floor slab construction method
CN114525926A (en) * 2022-02-24 2022-05-24 中国五冶集团有限公司 Construction structure for integrally forming water stop and structure of kitchen and bathroom and construction method thereof

Similar Documents

Publication Publication Date Title
CN108442595A (en) Precast concrete entirety ground floor and installation method for kitchen and toilet
CN207228684U (en) Integrated precast toilet
GB2362659A (en) Self-contained bathroom unit construction method
WO2007134519A1 (en) A concrete load-bearing wall with compound heat-insulating layer
CN108301466B (en) Integral prefabricated bathroom caisson, bathroom caisson structure and construction method thereof
CN106894445A (en) One kind assembling superposed type pipe gallery and its method of construction
CN206667459U (en) A kind of pre-splicing Standard formula building of prefabrication type reinforced concrete shear wall
CN109707091A (en) A kind of assembled stealth beam laminated floor slab for the pipeline separation installed from up to down
CN110625732A (en) Method for manufacturing laminated plate
CN208280410U (en) Precast concrete entirety ground floor for kitchen and toilet
CN204753834U (en) Partition plate of scissors stair and connection structure of floor roof beam
CN110778154A (en) Integral prefabricated toilet
CN207959747U (en) A kind of precast prestressed concrete cranked slab stairs
CN207063610U (en) A kind of transformer station by prefabricated components splicing builds
CN109779322A (en) A kind of co-layer draining hard-cover integral vacuum toilet of inner wall provided pipe line groove hole
CN109797988A (en) A kind of co-layer draining hard-cover precast block toilet of outer wall provided pipe line groove hole
CN206916767U (en) A kind of prefabricated assembled elevator basis
KR20170000255A (en) Construction method for bathroom and Bathroom using the same
CN202882098U (en) In-pit floor drain automatic drainage structure capable of preventing toilet from leaking
CN211313514U (en) Integral prefabricated toilet
CN210798043U (en) Prefabricated partition wall
CN211850319U (en) Laminated plate
CN208088439U (en) Integral prefabricated caisson of toilet and caisson of toilet construction
CN109779310A (en) A kind of co-layer draining blank integral vacuum toilet of outer wall provided pipe line groove hole
CN205688636U (en) Prefabricated assembled have floorboard component between boiled water room

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20180824

WW01 Invention patent application withdrawn after publication