CN112267628A - 建筑工程内墙装修免抹灰系统施工方法 - Google Patents

建筑工程内墙装修免抹灰系统施工方法 Download PDF

Info

Publication number
CN112267628A
CN112267628A CN202011110636.3A CN202011110636A CN112267628A CN 112267628 A CN112267628 A CN 112267628A CN 202011110636 A CN202011110636 A CN 202011110636A CN 112267628 A CN112267628 A CN 112267628A
Authority
CN
China
Prior art keywords
plastering
wall
mortar
layer
wall surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011110636.3A
Other languages
English (en)
Inventor
王小康
王峥
范明生
张思涛
李林
王保栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN202011110636.3A priority Critical patent/CN112267628A/zh
Publication of CN112267628A publication Critical patent/CN112267628A/zh
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/14Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing calcium sulfate cements
    • C04B28/142Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing calcium sulfate cements containing synthetic or waste calcium sulfate cements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • E04F13/04Bases for plaster
    • E04F13/06Edge-protecting borders
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • E04F13/04Bases for plaster
    • E04F13/06Edge-protecting borders
    • E04F2013/063Edge-protecting borders for corners

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Finishing Walls (AREA)

Abstract

本发明提供了建筑工程内墙装修免抹灰系统施工方法,包括:结构验收、施工准备、基层处理、墙面浇水、墙面喷浆、吊垂直抹灰饼、做护角、抹底、中层灰,在墙面抹灰和抹罩面灰等步骤,采用新型粉刷石膏是为主要胶凝材料,加入耐碱化学物质,以及砂子及一定的掺合料和专用复合添加剂加工制成的一种高效节能的建筑内墙及顶板抹灰材料替代水泥、石灰砂浆等抹灰材料,适用于各种墙体,与水泥砂浆、混合砂浆相比具有良好的和易性、流动性和保水性能,墙面致密光滑细腻,能够与任何基材粘接,解决了目前混凝土内墙和顶棚抹灰工艺存在的干缩性大、粘结力差、工序复杂、劳动生产率低和墙面易老化、超厚部位易开裂、脱落的问题。

Description

建筑工程内墙装修免抹灰系统施工方法
技术领域
本发明涉及建筑工程技术领域,具体涉及建筑工程内墙装修免抹灰系统施工方法。
背景技术
目前,我国混凝土内墙和顶棚抹灰工艺采用的粉刷材料一般为混合砂浆和石灰砂浆为主,此工艺的主要缺点是干缩性大、粘结力差、工序复杂、劳动生产率低,并且混合砂浆对基层的处理和各层砂浆强度的控制要求严格,一旦其中某个环节控制不严,就会导致抹灰层空鼓、开裂、墙面起泡、开花、析白等质量通病,所以目前较多施工单位直接用腻子粉找平施工,此施工方法存在墙面易老化、超厚部位易开裂、脱落等问题。
发明内容
本发明实施例提供了建筑工程内墙装修免抹灰系统施工方法,通过采用新型粉刷石膏是为主要胶凝材料,加入耐碱化学物质,以及砂子及一定的掺合料和专用复合添加剂加工制成的一种高效节能的建筑内墙及顶板抹灰材料替代水泥、石灰砂浆等抹灰材料,适用于各种墙体,作为一种新型墙体装修工艺,它克服了传统抹灰材料干缩性大、粘接力差、收缩、开裂、空鼓等难以避免的缺点,与水泥砂浆、混合砂浆相比具有良好的和易性、流动性和保水性能,墙面致密光滑细腻,适宜低温施工,能够与任何基材粘接,解决了目前混凝土内墙和顶棚抹灰工艺存在的干缩性大、粘结力差、工序复杂、劳动生产率低和墙面易老化、超厚部位易开裂、脱落的问题。
鉴于上述问题,本发明提出的技术方案是:
建筑工程内墙装修免抹灰系统施工方法,包括以下步骤:
S1,结构验收,对结构工程进行验收;
S2,施工准备,对墙面进行检查和预处理;
S2a:全数检查墙面垂直度,基层墙体垂直度在误差在3mm以内的,抹灰厚度控制在5mm;基层墙体垂直度在误差在3mm以上的,抹灰厚度控制在20mm;
S2b:将剪力墙表面凸出部分混凝土剔平,对蜂窝、麻面部位用水泥砂浆找平;脚手架洞眼用C20细石砼堵严;将窗台砼补齐;
S2c:在管道穿越楼板洞的部位安放套管,用提高一个强度等级的细石混凝土填嵌密实;墙上割出线槽处用1∶3水泥砂浆抹实抹平,抹前将线槽部位用水湿润并刷素水泥浆一道,抹好后将线槽上钉好225mm宽的镀锌钢丝网;将电线管、消火栓箱、配电箱安装完毕,并将背后露明部分钉好225mm宽的钢丝网;接线盒用纸堵严,砌体与砼的交界处钉好225mm宽镀锌铁丝网;
S2d:砼、砌体基层表面的灰尘、污垢、油渍和养护液、模板、胶带等清除干净,并浇水湿润;
S2e:根据室内高度和抹灰现场的具体情况,提前准备好抹灰高凳或脚手架,架子离开墙面及墙角200~250mm;
S3,基层处理,在抹灰前将水、电、暖开关及配电箱的安装完成,穿墙管道的埋设,对剔墙的管槽1:3水泥砂浆密封;将墙体基层表面凹凸不平处提前凿平;基层表面砂浆、残浆、污垢、油漆均事先清理干净;将外漏钢筋头剔除,磨平,防锈漆点涂;窗台砼补齐;
S4,墙面浇水,抹灰前4天,用胶皮管自上而下浇水;
S5,墙面喷浆,抹灰前3天,用喷壶将1:0.25水泥细砂掺加砼界面剂均匀喷涂于墙体表面,并浇水养护,待达到强度后抹灰;
S6,吊垂直抹灰饼,在抹灰前再将墙体浇水湿润,抹灰前基层表面不得有可见水珠或水层,根据抹灰质量等级,按基层表面平整垂直情况,吊垂直、套方、找规矩,经检查后确定抹灰厚度,墙面凹度较大时要分层衬平,操作时先抹上灰饼再抹下灰饼;抹灰饼时要根据室内抹灰的要求,确定下灰饼的正确位置,用靠尺板找好垂直与平整;灰饼施工完成后设标筋,层高3m竖筋间距为1.5m,冲筋宽为30~50mm;
S7,做护角,室内墙面的阳角、柱面的阳角和门窗洞口的阳角,用1∶3水泥砂浆打底与所抹灰饼找平,待砂浆稍干后,再用素石膏抹出楞角,每侧宽度为5cm,内门洞口宽度≤200mm的墙面用1∶3水泥砂浆全抹,墙面两侧各伸出5cm,阳台门、门联窗、更衣室入卫生间门洞口阳角用1∶3水泥砂浆每侧各抹5cm;
S8,抹底、中层灰,在墙面抹灰;
S8a,材料配制:
(1)底层、中层粉刷石膏:开动搅拌机后,先加入预计用水量80%,在连续搅拌过程中加入成品粉刷石膏砂浆进行搅拌,按实际情况补充水分,使砂浆搅拌均匀达到所需求的稠度;
(2)面层粉刷石膏净浆罩面:先将水先注入搅拌桶内,再加入石膏粉料搅拌,搅拌均匀,即可使用;
S8b,抹面操作,抹灰采用成品粉刷石膏砂浆,稠度一般控制在8-12㎝,先抹10mm一层,等此层砂浆初凝后,再抹中层灰,控制在8~10mm,再用大杠垂直、水平刮找一遍,用木抹子搓毛,然后全面检查是否平整,阴阳角是否方正,管道处灰是否抹齐,墙与顶交接是否光滑顺直,并用托线板检查墙面的垂直与平整情况,抹灰后及时将散落的砂浆清理干净,石膏砂浆随拌随用,不能用过夜灰;
S8c,修抹预留孔洞、电气箱、槽、盒,当底、中层灰抹平后,把洞、箱、槽、盒周边抹光滑、平整;
S9,抹罩面灰,在底灰六、七成干时,开始抹罩面灰,罩面灰二遍完成,厚度约2mm,两人同时操作,一人先薄薄刮一遍,另一人随即抹平,按先上后下顺序进行,再赶光压实,然后用铁抹子压一遍,然后压光,搓平、压光工作要在净浆终凝前完成,随后用毛刷蘸水将罩面灰污染处清刷于净,抹灰厚度小于5mm的可以直接使用面层型粉刷石膏,抹灰厚度为5~20mm的,可以先用底层型粉刷石膏打底,再用面层型粉刷石膏罩面,抹时,用灰板和抹子将料浆抹在墙面上,用靠尺或刮板紧贴标筋上下刮平压实,达到墙面平整垂直,抹灰层厚度超过8mm时,分层施抹,每层厚度控制在8mm以内,待上一层料浆终凝后再抹下一层。
进一步的,所述步骤S2b中水泥砂浆的比例为1∶2~2.5。
进一步的,所述步骤S2c中细石混凝土添加有微膨胀剂。
进一步的,所述步骤S2c中素水泥浆添加有砼界面剂。
进一步的,所述步骤S2c中固定镀锌钢丝网时,砼墙面采用保温钉,砌体墙面采用钢钉,钉距为250mm并在交界面的两侧交错布置呈梅花形,钢钉、保温钉距钢丝网的网边为6㎝,钢丝网搭接重叠处,四角用钢钉、保温钉固定牢固且距钢丝网的网边为6㎝。
进一步的,所述步骤S5中水泥细砂与砼界面剂的比例为1:0.25。
进一步的,所述步骤S8a步骤(2)中石膏粉料与水的比例为1:0.3-0.4。
相对于现有技术而言,本发明的有益效果是:本建筑工程内墙装修免抹灰系统施工方法通过采用新型粉刷石膏是为主要胶凝材料,加入耐碱化学物质,以及砂子及一定的掺合料和专用复合添加剂加工制成的一种高效节能的建筑内墙及顶板抹灰材料替代水泥、石灰砂浆等抹灰材料,适用于各种墙体,作为一种新型墙体装修工艺,它克服了传统抹灰材料干缩性大、粘接力差、收缩、开裂、空鼓等难以避免的缺点,与水泥砂浆、混合砂浆相比具有良好的和易性、流动性和保水性能,墙面致密光滑细腻,适宜低温施工,能够与任何基材粘接,解决了目前混凝土内墙和顶棚抹灰工艺存在的干缩性大、粘结力差、工序复杂、劳动生产率低和墙面易老化、超厚部位易开裂、脱落的问题。
上述说明仅是本发明技术方案的概述,为了能够更清楚了解本发明的技术手段,而可依照说明书的内容予以实施,并且为了让本发明的上述和其它目的、特征和优点能够更明显易懂,以下特举本发明的具体实施方式。
附图说明
图1为本发明实施例公开的建筑工程内墙装修免抹灰系统施工方法流程示意图。
具体实施例
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。
建筑工程内墙装修免抹灰系统施工方法,其特征在于,包括以下步骤:
S1,结构验收,对结构工程进行验收,合格后方可进行抹灰工程;
S2,施工准备,对墙面进行检查和预处理;
S2a:全数检查墙面垂直度,基层墙体垂直度在误差在3mm以内的,抹灰厚度控制在5mm;基层墙体垂直度在误差在3mm以上的,抹灰厚度控制在20mm;
S2b:将剪力墙表面凸出部分混凝土剔平,对蜂窝、麻面部位用水泥砂浆找平;脚手架洞眼用C20细石砼堵严;将窗台砼补齐;
S2c:在管道穿越楼板洞的部位安放套管,用提高一个强度等级的细石混凝土填嵌密实;墙上割出线槽处用1∶3水泥砂浆抹实抹平,抹前将线槽部位用水湿润并刷素水泥浆一道,抹好后将线槽上钉好225mm宽镀锌钢丝网(网眼规格为13mm×13mm,钢丝直径为0.8mm);电线管、消火栓箱、配电箱安装完毕,并将背后露明部分钉好钢丝网;接线盒用纸堵严,砌体与砼(梁底、过梁、剪力墙、结构柱)的交界处钉好225mm宽镀锌铁丝网,固定镀锌钢丝网时,砼墙面采用保温钉,砌体墙面采用钢钉,钉距为250mm并在交界面的两侧交错布置呈梅花形,钢钉、保温钉距钢丝网的网边为6㎝,钢丝网搭接重叠处,四角必须用钢钉、保温钉固定牢固且距钢丝网的网边为6㎝;
S2d:砼、砌体基层表面的灰尘、污垢、油渍和养护液、模板、胶带等清除干净,并浇水湿润;
S2e:根据室内高度和抹灰现场的具体情况,提前准备好抹灰高凳或脚手架,架子离开墙面及墙角200~250mm,以利操作;
S2f:室内大面积施工前,先做样板间,经鉴定合格后才能大面积施工;
S2g:屋面防水工程完工前进行室内抹灰时,必须采取防护措施;
S3,基层处理,在抹灰前做好水、电、暖开关及配电箱的安装,穿墙管道的埋设,对剔墙的管槽1:3水泥砂浆密封;将墙体基层表面凹凸不平处提前凿平;基层表面砂浆、残浆、污垢、油漆均事先清理干净;外漏钢筋头剔除,磨平,防锈漆点涂;窗台砼补齐;
S4,墙面浇水,抹灰前4天,用胶皮管自上而下浇水;
S5,墙面喷浆,采用专用砼界面粘结剂,它具有粘结强度高,对多种基材具有良好的附着力,抹灰前3天,用喷壶将1:0.25水泥细砂掺加砼界面剂喷涂于墙体表面,喷涂要均匀、满涂,并浇水养护,待达到强度后抹灰;
S6,吊垂直抹灰饼,在抹灰前再将墙体浇水湿润,但抹灰前基层表面不得有可见水珠或水层,根据抹灰质量等级,按基层表面平整垂直情况,吊垂直、套方、找规矩,经检查后确定抹灰厚度,但最少不小于5mm,墙面凹度较大时要分层衬平(石膏砂浆每层厚度宜为7~9mm),操作时先抹上灰饼再抹下灰饼;抹灰饼时要根据室内抹灰的要求,以确定下灰饼的正确位置,用靠尺板找好垂直与平整;灰饼施工完成后设标筋(冲筋),层高3m竖筋间距1.5m,冲筋宽为30~50mm;
S7,做护角,室内墙面的阳角、柱面的阳角和门窗洞口的阳角,用1∶3水泥砂浆打底与所抹灰饼找平,待砂浆稍干后,再用素石膏抹出楞角,每侧宽度为5cm,内门洞口宽度≤200mm的墙面用1∶3水泥砂浆全抹,墙面两侧各伸出5cm,阳台门、门联窗、更衣室入卫生间门洞口阳角用1∶3水泥砂浆每侧各抹5cm;
S8,抹底、中层灰,在墙面抹灰;
S8a,材料搅拌及配合比:
1)底层、中层粉刷石膏:开动搅拌机后,先加入预计用水量80%,在连续搅拌过程中加入成品粉刷石膏砂浆进行搅拌,可按实际情况补充水分,使砂浆搅拌均匀达到所需求的稠度即可使用;
2)面层粉刷石膏净浆罩面:先将水先注入搅拌桶内,再加入粉料搅拌,搅拌均匀,即可使用,配合比(石膏:水=1:0.3-0.4);
S8b,抹面操作,抹灰采用成品粉刷石膏砂浆,稠度一般控制在8-12㎝为宜,先抹10mm一层,等此层砂浆初凝后(用手指按不动但有手印),再抹中层灰,控制在8~10mm,再用大杠垂直、水平刮找一遍,用木抹子搓毛,然后全面检查是否平整,阴阳角是否方正,管道处灰是否抹齐,墙与顶交接是否光滑顺直,并用托线板检查墙面的垂直与平整情况,抹灰后及时将散落的砂浆清理干净,石膏砂浆随拌随用,不能用过夜灰;
S8c,修抹预留孔洞、电气箱、槽、盒,当底、中层灰抹平后,把洞、箱、槽、盒周边抹光滑、平整;
S9,抹罩面灰,当底灰六、七成干时,即可开始抹罩面灰(如底灰过干浇水湿润),罩面灰二遍成活,厚度约2mm,最好两人同时操作,一人先薄薄刮一遍,另一人随即抹平,按先上后下顺序进行,再赶光压实,然后用铁抹子压一遍,然后压光,搓平、压光工作要在净浆终凝前完成,随后用毛刷蘸水将罩面灰污染处清刷于净,净浆面层还可采用石膏:细砂为1:0.5的砂浆,已经硬化的砂浆、净浆,不得再加入拌和使用,不准二次使用,石膏砂浆不得与水泥砂浆混用,抹灰厚度小于5mm的可以直接使用面层型粉刷石膏,抹灰厚度为5~20mm的,可以先用底层型粉刷石膏打底,再用面层型粉刷石膏罩面,抹时,用灰板和抹子将料浆抹在墙面上,用靠尺或刮板(刮杠)紧贴标筋上下刮平压实,达到墙面平整垂直,抹灰层厚度超过8mm时,分层施抹,每层厚度控制在8mm以内,待上一层料浆终凝后再抹下一层。
在本实施例中,粉刷石膏凝结时间不少于60分钟、不大于8小时,细度0.2MM,筛余量≤40%,产品必须有出厂合格证、产品检测报告单、进厂需对产品名称、代号、净含量、强度等级、生产许可证编号、生产地址、出厂编号、执行标准、生产日期等进行外观检查,做好进场验收记录。
具体的,本建筑工程内墙装修免抹灰系统施工方法所用粉刷石膏是氟石膏,其是硫酸与氟石制取氟化氢的副产品,属于人造石膏,氟石膏加水拌合后,水化成二水石膏晶体和少量其他物质,二水石膏晶体逐渐长大,共生和相互交错排列成网络结构,逐渐产生强度,并不断增长,直至完全干燥,根据施工图的抹灰位置,先在不同结构的地方钉钢丝网,之后进行墙面浇水和墙面喷浆,当喷浆达到一定强度后,在墙面上掉垂直抹灰饼、做护角、三天后再进行抹灰操作,形成光滑细腻,质量稳定的墙面,采用粉刷石膏为主要胶凝材料,加入耐碱化学物质,以及砂子及一定的掺合料和专用复合添加剂加工制成的一种高效节能的建筑内墙及顶板抹灰材料替代水泥、石灰砂浆等抹灰材料,适用于各种墙体,作为一种新型墙体装修工艺,它克服了传统抹灰材料干缩性大、粘接力差、收缩、开裂、空鼓等难以避免的缺点,与水泥砂浆、混合砂浆相比具有良好的和易性、流动性和保水性能,墙面致密光滑细腻,适宜低温施工,能够与任何基材粘接,解决了目前混凝土内墙和顶棚抹灰工艺存在的干缩性大、粘结力差、工序复杂、劳动生产率低和墙面易老化、超厚部位易开裂、脱落的问题。
显然,本领域的技术人员可以对本发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包含这些改动和变型在内。

Claims (7)

1.建筑工程内墙装修免抹灰系统施工方法,其特征在于,包括以下步骤:
S1,结构验收,对结构工程进行验收;
S2,施工准备,对墙面进行检查和预处理;
S2a:全数检查墙面垂直度,基层墙体垂直度在误差在3mm以内的,抹灰厚度控制在5mm;基层墙体垂直度在误差在3mm以上的,抹灰厚度控制在20mm;
S2b:将剪力墙表面凸出部分混凝土剔平,对蜂窝、麻面部位用水泥砂浆找平;脚手架洞眼用C20细石砼堵严;将窗台砼补齐;
S2c:在管道穿越楼板洞的部位安放套管,用提高一个强度等级的细石混凝土填嵌密实;墙上割出线槽处用1∶3水泥砂浆抹实抹平,抹前将线槽部位用水湿润并刷素水泥浆一道,抹好后将线槽上钉好225mm宽的镀锌钢丝网;将电线管、消火栓箱、配电箱安装完毕,并将背后露明部分钉好225mm宽的钢丝网;接线盒用纸堵严,砌体与砼的交界处钉好225mm宽镀锌铁丝网;
S2d:砼、砌体基层表面的灰尘、污垢、油渍和养护液、模板、胶带等清除干净,并浇水湿润;
S2e:根据室内高度和抹灰现场的具体情况,提前准备好抹灰高凳或脚手架,架子离开墙面及墙角200~250mm;
S3,基层处理,在抹灰前将水、电、暖开关及配电箱的安装完成,穿墙管道的埋设,对剔墙的管槽1:3水泥砂浆密封;将墙体基层表面凹凸不平处提前凿平;基层表面砂浆、残浆、污垢、油漆均事先清理干净;将外漏钢筋头剔除,磨平,防锈漆点涂;窗台砼补齐;
S4,墙面浇水,抹灰前4天,用胶皮管自上而下浇水;
S5,墙面喷浆,抹灰前3天,用喷壶将1:0.25水泥细砂掺加砼界面剂均匀喷涂于墙体表面,并浇水养护,待达到强度后抹灰;
S6,吊垂直抹灰饼,在抹灰前再将墙体浇水湿润,抹灰前基层表面不得有可见水珠或水层,根据抹灰质量等级,按基层表面平整垂直情况,吊垂直、套方、找规矩,经检查后确定抹灰厚度,墙面凹度较大时要分层衬平,操作时先抹上灰饼再抹下灰饼;抹灰饼时要根据室内抹灰的要求,确定下灰饼的正确位置,用靠尺板找好垂直与平整;灰饼施工完成后设标筋,层高3m竖筋间距为1.5m,冲筋宽为30~50mm;
S7,做护角,室内墙面的阳角、柱面的阳角和门窗洞口的阳角,用1∶3水泥砂浆打底与所抹灰饼找平,待砂浆稍干后,再用素石膏抹出楞角,每侧宽度为5cm,内门洞口宽度≤200mm的墙面用1∶3水泥砂浆全抹,墙面两侧各伸出5cm,阳台门、门联窗、更衣室入卫生间门洞口阳角用1∶3水泥砂浆每侧各抹5cm;
S8,抹底、中层灰,在墙面抹灰;
S8a,材料配制:
(1)底层、中层粉刷石膏:开动搅拌机后,先加入预计用水量80%,在连续搅拌过程中加入成品粉刷石膏砂浆进行搅拌,按实际情况补充水分,使砂浆搅拌均匀达到所需求的稠度;
(2)面层粉刷石膏净浆罩面:先将水先注入搅拌桶内,再加入石膏粉料搅拌,搅拌均匀,即可使用;
S8b,抹面操作,抹灰采用成品粉刷石膏砂浆,稠度一般控制在8-12cm,先抹10mm一层,等此层砂浆初凝后,再抹中层灰,控制在8~10mm,再用大杠垂直、水平刮找一遍,用木抹子搓毛,然后全面检查是否平整,阴阳角是否方正,管道处灰是否抹齐,墙与顶交接是否光滑顺直,并用托线板检查墙面的垂直与平整情况,抹灰后及时将散落的砂浆清理干净,石膏砂浆随拌随用,不能用过夜灰;
S8c,修抹预留孔洞、电气箱、槽、盒,当底、中层灰抹平后,把洞、箱、槽、盒周边抹光滑、平整;
S9,抹罩面灰,在底灰六、七成干时,开始抹罩面灰,罩面灰二遍完成,厚度约2mm,两人同时操作,一人先薄薄刮一遍,另一人随即抹平,按先上后下顺序进行,再赶光压实,然后用铁抹子压一遍,然后压光,搓平、压光工作要在净浆终凝前完成,随后用毛刷蘸水将罩面灰污染处清刷于净,抹灰厚度小于5mm的可以直接使用面层型粉刷石膏,抹灰厚度为5~20mm的,可以先用底层型粉刷石膏打底,再用面层型粉刷石膏罩面,抹时,用灰板和抹子将料浆抹在墙面上,用靠尺或刮板紧贴标筋上下刮平压实,达到墙面平整垂直,抹灰层厚度超过8mm时,分层施抹,每层厚度控制在8mm以内,待上一层料浆终凝后再抹下一层。
2.根据权利要求1所述的建筑工程内墙装修免抹灰系统施工方法,其特征在于:所述步骤S2b中水泥砂浆的比例为1∶2~2.5。
3.根据权利要求1所述的建筑工程内墙装修免抹灰系统施工方法,其特征在于:所述步骤S2c中细石混凝土添加有微膨胀剂。
4.根据权利要求1所述的建筑工程内墙装修免抹灰系统施工方法,其特征在于:所述步骤S2c中素水泥浆添加有砼界面剂。
5.根据权利要求1所述的建筑工程内墙装修免抹灰系统施工方法,其特征在于:所述步骤S2c中固定镀锌钢丝网时,砼墙面采用保温钉,砌体墙面采用钢钉,钉距为250mm并在交界面的两侧交错布置呈梅花形,钢钉、保温钉距钢丝网的网边为6cm,钢丝网搭接重叠处,四角用钢钉、保温钉固定牢固且距钢丝网的网边为6cm。
6.根据权利要求1所述的建筑工程内墙装修免抹灰系统施工方法,其特征在于:所述步骤S5中水泥细砂与砼界面剂的比例为1:0.25。
7.根据权利要求1所述的建筑工程内墙装修免抹灰系统施工方法,其特征在于:所述步骤S8a步骤(2)中石膏粉料与水的比例为1:0.3-0.4。
CN202011110636.3A 2020-10-16 2020-10-16 建筑工程内墙装修免抹灰系统施工方法 Pending CN112267628A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011110636.3A CN112267628A (zh) 2020-10-16 2020-10-16 建筑工程内墙装修免抹灰系统施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011110636.3A CN112267628A (zh) 2020-10-16 2020-10-16 建筑工程内墙装修免抹灰系统施工方法

Publications (1)

Publication Number Publication Date
CN112267628A true CN112267628A (zh) 2021-01-26

Family

ID=74337406

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011110636.3A Pending CN112267628A (zh) 2020-10-16 2020-10-16 建筑工程内墙装修免抹灰系统施工方法

Country Status (1)

Country Link
CN (1) CN112267628A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113006397A (zh) * 2021-02-22 2021-06-22 北京梵客家居科技有限公司 一种厨卫空间规方找平的施工方法
CN114135068A (zh) * 2021-12-09 2022-03-04 上海隆振建筑工程股份有限公司 一种抹面砂浆的施工工艺
CN114775961A (zh) * 2022-04-28 2022-07-22 重庆渝能建筑安装工程有限公司 一种抹灰施工方法及抹灰装置
CN117589626A (zh) * 2024-01-18 2024-02-23 陕西榆能青青源环保材料有限责任公司 测试抹灰石膏涂布率的方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046709A (zh) * 2013-01-14 2013-04-17 山西省第二建筑工程公司 一种内墙面的建筑施工方法
CN103195218A (zh) * 2013-03-29 2013-07-10 浙江万华建设有限公司 一种墙体陶砂砂浆外抹灰施工工法
CN103643769A (zh) * 2013-12-26 2014-03-19 中建八局第四建设有限公司 墙壁抹灰施工工艺和墙体
JP2014062422A (ja) * 2012-09-22 2014-04-10 Jyukankyo-Innovation Co Ltd 塗り壁の施工方法及び塗り壁構造
CN104088416A (zh) * 2014-07-16 2014-10-08 上海隆振建筑工程有限公司 石膏保温粉刷砂浆施工工艺

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014062422A (ja) * 2012-09-22 2014-04-10 Jyukankyo-Innovation Co Ltd 塗り壁の施工方法及び塗り壁構造
CN103046709A (zh) * 2013-01-14 2013-04-17 山西省第二建筑工程公司 一种内墙面的建筑施工方法
CN103195218A (zh) * 2013-03-29 2013-07-10 浙江万华建设有限公司 一种墙体陶砂砂浆外抹灰施工工法
CN103643769A (zh) * 2013-12-26 2014-03-19 中建八局第四建设有限公司 墙壁抹灰施工工艺和墙体
CN104088416A (zh) * 2014-07-16 2014-10-08 上海隆振建筑工程有限公司 石膏保温粉刷砂浆施工工艺

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
吴潮玮,郭红兵: "《建筑材料》", 31 January 2018 *
江苏省建设工程质量监督总站: "《城市轨道交通工程质量监督实务》", 30 November 2017 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113006397A (zh) * 2021-02-22 2021-06-22 北京梵客家居科技有限公司 一种厨卫空间规方找平的施工方法
CN114135068A (zh) * 2021-12-09 2022-03-04 上海隆振建筑工程股份有限公司 一种抹面砂浆的施工工艺
WO2023103406A1 (zh) * 2021-12-09 2023-06-15 上海隆振建筑工程股份有限公司 一种抹面砂浆的施工工艺
CN114775961A (zh) * 2022-04-28 2022-07-22 重庆渝能建筑安装工程有限公司 一种抹灰施工方法及抹灰装置
CN117589626A (zh) * 2024-01-18 2024-02-23 陕西榆能青青源环保材料有限责任公司 测试抹灰石膏涂布率的方法
CN117589626B (zh) * 2024-01-18 2024-05-03 陕西榆能青青源环保材料有限责任公司 测试抹灰石膏涂布率的方法

Similar Documents

Publication Publication Date Title
CN112267628A (zh) 建筑工程内墙装修免抹灰系统施工方法
CN103046709B (zh) 一种内墙面的建筑施工方法
CN101363269A (zh) 免抹灰混凝土结构墙体腻子施工方法
CN104018598A (zh) 一种外墙结构及施工安装方法
CN101565997A (zh) 大面积不规则地面砖施工方法
CN109797920B (zh) 一种室内涂饰施工方法
CN103572845A (zh) 一种保温胶泥反射隔热涂料外墙保温系统及其施工工艺
CN101886460A (zh) 内墙抹灰网格布压光施工方法
CN102400525A (zh) 蒸压加气砼砌块墙体薄层抹灰方法
CN102587527A (zh) 一种钢柱包覆的防火施工方法
CN113006397A (zh) 一种厨卫空间规方找平的施工方法
CN106284998A (zh) 内墙抹灰满铺玻璃纤维网格布施工方法
CN110761507A (zh) 一种外墙斩假石的施工方法
CN108130992A (zh) 毛石板、聚苯板及多孔砖复合保温装饰外墙施工工法
CN107761968A (zh) 外墙内保温砂浆交接部位施工方法
CN103291024A (zh) 一种新型水泥基抹灰砂浆的施工方法
CN105888084A (zh) 加强型复合保温材料整体外墙内保温体系施工工法
CN102182323A (zh) 低纬度高原蒸压加气砼砌块干法砌筑施工工艺
CN207553357U (zh) 毛石板、聚苯板及多孔砖复合保温装饰外墙
CN113530124B (zh) 一种墙面火山石内防外阻水湿贴施工方法
CN211949245U (zh) 一种屋面石材泛水结构
CN112127752A (zh) 外齐式外窗安装防渗漏施工工艺
CN109610764B (zh) 一种花岗岩立面铺贴施工工艺
CN111677210A (zh) 一种石膏砂浆施工工艺
CN112031341A (zh) 一种有利于环保的建筑工程施工方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210126