CN112064955A - Paving construction method applied to floor tiles - Google Patents

Paving construction method applied to floor tiles Download PDF

Info

Publication number
CN112064955A
CN112064955A CN202010898704.0A CN202010898704A CN112064955A CN 112064955 A CN112064955 A CN 112064955A CN 202010898704 A CN202010898704 A CN 202010898704A CN 112064955 A CN112064955 A CN 112064955A
Authority
CN
China
Prior art keywords
floor
paving
ground
floor tile
tile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010898704.0A
Other languages
Chinese (zh)
Inventor
高兴良
李永刚
温雯
张坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
China Railway 12th Bureau Group Construction and Installation Engineering Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
China Railway 12th Bureau Group Construction and Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, China Railway 12th Bureau Group Construction and Installation Engineering Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN202010898704.0A priority Critical patent/CN112064955A/en
Publication of CN112064955A publication Critical patent/CN112064955A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/02005Construction of joints, e.g. dividing strips
    • E04F15/02011Construction of joints, e.g. dividing strips with joint fillings integrated in the flooring elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/0215Flooring or floor layers composed of a number of similar elements specially adapted for being adhesively fixed to an underlayer; Fastening means therefor; Fixing by means of plastics materials hardening after application
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/08Flooring or floor layers composed of a number of similar elements only of stone or stone-like material, e.g. ceramics, concrete; of glass or with a top layer of stone or stone-like material, e.g. ceramics, concrete or glass

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Road Repair (AREA)

Abstract

The invention discloses a paving construction method applied to floor tiles, relating to the technical field of building construction and comprising the following steps: s1, ground cleaning: firstly, leveling a ground base layer needing to be paved with the floor tiles, removing sundries on the ground, and then sprinkling water on the ground for maintenance; s2, horizontal line positioning: according to the horizontal standard line and the selected thickness of the floor tile, the horizontal marking line is calibrated on the inner wall, and the horizontal line is positioned, so that the floor tile paving construction method is applied.

Description

Paving construction method applied to floor tiles
Technical Field
The invention relates to the technical field of building construction, in particular to a paving construction method applied to floor tiles.
Background
The floor tile is also called floor tile, it is a ground decorative material, the floor tile is fired with clay, it has advantages of firm quality, pressure-resistant wear-resistant, moisture-proof, etc., some floor tiles are glazed, it has decorative effect, utilize self colour, texture to build the room environment with different styles, the floor tile is used in the ground and floor of public building and civil building mostly, along with the social development, people's requirement for life is higher and higher, the requirement for laying the floor tile is higher and higher too.
In the process of using the floor tile ground paving construction method in the prior art, the process of the floor tile is not standard when the floor tile is paved, so that the paving quality is poor, and the phenomenon of swelling and falling frequently occurs, so that owners cannot be satisfied.
Disclosure of Invention
Aiming at the defects of the prior art, the invention provides a paving construction method applied to a floor tile ground, which aims to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: a paving construction method applied to a floor tile ground comprises the following steps:
s1, ground cleaning: firstly, leveling a ground base layer needing to be paved with the floor tiles, removing sundries on the ground, and then sprinkling water on the ground for maintenance;
s2, horizontal line positioning: according to the horizontal standard line and the selected thickness of the floor tiles, calibrating the horizontal marking line on the inner wall, and positioning the horizontal line;
s3, paving mud on the ground: paving cement mortar on the ground maintained in the step S1, and then carrying out sweeping and trowelling operations;
s4, operation before laying: paving dry and hard cement mortar on the ground after the slurry is swept in the step S3, and manually troweling the dry and hard cement mortar by using a trowel;
s5, laying a control line: performing tile flipping control lines according to the horizontal line positioned in the step S2, and determining the width of a tile paving gap according to design requirements;
s6, paving floor tiles: cement mortar is coated on the floor tiles to be laid in the step S2, the floor tiles are sequentially paved from left to right, and the rubber hammer is used for lightly knocking the floor tiles to fill the gaps between the ground and the floor tiles with cement;
s7, maintenance and seam beautifying: and (5) carrying out watering maintenance operation on the floor tile paved in the step (S8), and carrying out spot cleaning and seam beautifying operation on the surface of the floor tile when the strength of the surface layer of the floor tile reaches the strength for a worker to step on the floor tile to finish paving and pasting the floor tile.
Further optimizing the technical scheme, the curing time in the step S1 is 24-28H, and the proportion of water to the sand in the cement mortar in the steps S3 and S6 is 1: 2.
further optimizing the technical scheme, the coating thickness of the pure cement paste coated on the floor tile in the step S6 is 10-15 MM.
Further optimizing the technical scheme, in the step S7, the redundant seam beautifying agent on the floor tile is shoveled and removed by a scraper manually, so that the floor tile is laid.
Further optimizing the technical scheme, in the step S7, the surface of the floor tile is cleaned manually, and when the surface of the floor tile is seriously polluted, a 10% dilute hydrochloric acid solution is used to cooperate with the cleaning treatment.
Further optimizing the technical scheme, the watering and curing should be started within 24 hours after the floor tile surface layer in the step S7 is paved, and the curing time is 7-9 days.
Further optimizing the technical scheme, the cement for seam beautifying in the step S7 is the cement with the same variety, the same label and the same color.
Further optimizing the technical scheme, the proportion of the water and the sand in the dry and hard cement mortar in the step S4 is 1: 1.5-1: 2, after the preparation of the dry and hard cement mortar in the step S4, spreading the dry and hard cement mortar on the ground immediately, and quickly paving the floor tiles, wherein the dry and hard cement mortar is prepared and used according to the actual use amount of the engineering.
Advantageous effects
Compared with the prior art, the invention provides a paving construction method applied to floor tiles, which has the following beneficial effects:
1. the construction method for paving and pasting the floor tiles has the advantages that the dry and hard cement mortar is paved in front of the base layer, the adhesiveness in the paving and pasting process is improved, the paving and pasting effect is improved, the seam beautifying agent is injected into the seams of the floor tiles after paving and pasting, the seam beautifying agent is timely compacted, trowelled, dried and scraped to remove redundant parts, and the steps are repeated in this way, so that the device can continuously joint and beautify the seams of the floor tiles, the working efficiency is high, the manpower is saved, the flatness of the wall tiles and the floor tiles can be effectively improved, the construction method has the advantages that the construction requirements are met, the device can be quickly and conveniently mastered by workers, and the construction effect is obvious.
2. The construction method for paving and pasting the floor tiles is characterized in that the horizontal marking lines are calibrated on the inner wall in advance, so that when the leveling layer is paved, the elevation of the leveling layer is increased by taking the horizontal marking lines as a reference, the level of the leveling layer is ensured, then the leveling layer is paved, the paving control lines are flicked, and finally the paving is carried out according to the lines, so that the finally paved floor tiles can meet the quality requirement of construction.
Drawings
Fig. 1 is a schematic flow chart of a paving construction method applied to a floor tile according to the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The first embodiment is as follows: referring to fig. 1, the present invention discloses a paving construction method applied to a floor tile, including the following steps:
s1, ground cleaning: firstly, leveling a ground base layer needing to be paved with the floor tiles, removing impurities on the ground, and then sprinkling water on the ground for maintenance, wherein the maintenance time is 24H;
s2, horizontal line positioning: according to the horizontal standard line and the selected thickness of the floor tiles, calibrating the horizontal marking line on the inner wall, and positioning the horizontal line;
s3, paving mud on the ground: and (4) paving cement mortar on the ground after the maintenance in the step (S1), and then carrying out slurry sweeping and trowelling operations, wherein the proportion of water to the sand in the cement mortar is 1: 2;
s4, operation before laying: paving dry and hard cement mortar on the ground after the slurry is swept in the step S3, wherein the proportion of water to the sand in the dry and hard cement mortar is 1: 1.5, manually troweling the dry and hard cement mortar by a trowel, immediately paving the dry and hard cement mortar on the ground after the preparation of the dry and hard cement mortar is finished, quickly paving floor tiles, and preparing and using the dry and hard cement mortar according to the actual use amount of an engineering;
s5, laying a control line: performing tile flipping control lines according to the horizontal line positioned in the step S2, and determining the width of a tile paving gap according to design requirements;
s6, paving floor tiles: and (2) coating cement mortar on the floor tiles to be laid in the step S2, wherein the coating thickness of the pure cement mortar coated on the floor tiles is 10MM, the floor tiles are sequentially paved from left to right, the floor tiles are lightly knocked by using a rubber hammer, so that the cement is filled in the gaps between the ground and the floor tiles, and the proportion of water to the cement sand in the cement mortar is 1: 2;
s7, maintenance and seam beautifying: and (4) carrying out watering maintenance operation on the floor tile paved in the step S8, wherein the watering maintenance should be started within 24 hours after the floor tile surface layer is paved, the maintenance time is 7d, when the strength of the floor tile surface layer reaches the strength which can be stepped by an operator to walk, the stain cleaning and seam beautifying operation are carried out on the floor tile surface, the stain is cleaned on the floor tile surface manually, when the pollution on the floor tile surface is serious, a 10% dilute hydrochloric acid solution is used for cleaning, a scraper is used for shoveling and removing the redundant seam beautifying agent on the floor tile manually, and the cement for seam beautifying should be cement with the same type, the same label and the same color, so that the paving work of the floor tile is finished, and the paving and paving of the floor tile are finished.
Example two: referring to fig. 1, the present invention discloses a paving construction method applied to a floor tile, including the following steps:
s1, ground cleaning: firstly, leveling a ground base layer needing to be paved with the floor tiles, removing impurities on the ground, and then sprinkling water on the ground for maintenance, wherein the maintenance time is 26H;
s2, horizontal line positioning: according to the horizontal standard line and the selected thickness of the floor tiles, calibrating the horizontal marking line on the inner wall, and positioning the horizontal line;
s3, paving mud on the ground: and (4) paving cement mortar on the ground after the maintenance in the step (S1), and then carrying out slurry sweeping and trowelling operations, wherein the proportion of water to the sand in the cement mortar is 1: 2;
s4, operation before laying: paving dry and hard cement mortar on the ground after the slurry is swept in the step S3, wherein the proportion of water to the sand in the dry and hard cement mortar is 1: 1.7, manually troweling the dry and hard cement mortar by a trowel, immediately paving the dry and hard cement mortar on the ground after the preparation of the dry and hard cement mortar is finished, quickly paving floor tiles, and preparing and using the dry and hard cement mortar according to the actual use amount of an engineering;
s5, laying a control line: performing tile flipping control lines according to the horizontal line positioned in the step S2, and determining the width of a tile paving gap according to design requirements;
s6, paving floor tiles: and (2) coating cement mortar on the floor tiles to be laid in the step S2, wherein the coating thickness of the pure cement mortar coated on the floor tiles is 13MM, the floor tiles are sequentially paved from left to right, the floor tiles are lightly knocked by using a rubber hammer, so that the cement is filled in the gaps between the ground and the floor tiles, and the proportion of water to the cement sand in the cement mortar is 1: 2;
s7, maintenance and seam beautifying: and (4) carrying out watering maintenance operation on the floor tile paved in the step S8, wherein the watering maintenance should be started within 24 hours after the floor tile surface layer is paved, the maintenance time is 8d, when the strength of the floor tile surface layer reaches the strength which can be stepped by an operator to walk, the stain cleaning and seam beautifying operation are carried out on the floor tile surface, the stain is cleaned on the floor tile surface manually, when the pollution on the floor tile surface is serious, a 10% dilute hydrochloric acid solution is used for cleaning, a scraper is used for shoveling and removing the redundant seam beautifying agent on the floor tile manually, and the cement for seam beautifying should be cement with the same type, the same label and the same color, so that the paving work of the floor tile is finished, and the paving and paving of the floor tile are finished.
Example three: referring to fig. 1, the present invention discloses a paving construction method applied to a floor tile, including the following steps:
s1, ground cleaning: firstly, leveling a ground base layer needing to be paved with the floor tiles, removing impurities on the ground, and then sprinkling water on the ground for maintenance, wherein the maintenance time is 27H;
s2, horizontal line positioning: according to the horizontal standard line and the selected thickness of the floor tiles, calibrating the horizontal marking line on the inner wall, and positioning the horizontal line;
s3, paving mud on the ground: and (4) paving cement mortar on the ground after the maintenance in the step (S1), and then carrying out slurry sweeping and trowelling operations, wherein the proportion of water to the sand in the cement mortar is 1: 1.8;
s4, operation before laying: paving dry and hard cement mortar on the ground after the slurry is swept in the step S3, wherein the proportion of water to the sand in the dry and hard cement mortar is 1: 2, manually troweling the dry and hard cement mortar by using a trowel, immediately paving the dry and hard cement mortar on the ground after the preparation of the dry and hard cement mortar is finished, quickly paving floor tiles, and preparing and using the dry and hard cement mortar according to the actual use amount of the engineering;
s5, laying a control line: performing tile flipping control lines according to the horizontal line positioned in the step S2, and determining the width of a tile paving gap according to design requirements;
s6, paving floor tiles: and (2) coating cement mortar on the floor tiles to be laid in the step (S2), wherein the coating thickness of the pure cement mortar coated on the floor tiles is 14MM, the floor tiles are sequentially paved from left to right, the floor tiles are lightly knocked by a rubber hammer, so that the cement is filled in the gaps between the ground and the floor tiles, and the proportion of water to the cement sand in the cement mortar is 1: 2;
s7, maintenance and seam beautifying: and (4) carrying out watering maintenance operation on the floor tile paved in the step S8, wherein the watering maintenance should be started within 24 hours after the floor tile surface layer is paved, the maintenance time is 8d, when the strength of the floor tile surface layer reaches the strength which can be stepped by an operator to walk, the stain cleaning and seam beautifying operation are carried out on the floor tile surface, the stain is cleaned on the floor tile surface manually, when the pollution on the floor tile surface is serious, a 10% dilute hydrochloric acid solution is used for cleaning, a scraper is used for shoveling and removing the redundant seam beautifying agent on the floor tile manually, and the cement for seam beautifying should be cement with the same type, the same label and the same color, so that the paving work of the floor tile is finished, and the paving and paving of the floor tile are finished.
Example four: referring to fig. 1, the present invention discloses a paving construction method applied to a floor tile, including the following steps:
s1, ground cleaning: firstly, leveling a ground base layer needing to be paved with the floor tiles, removing impurities on the ground, and then sprinkling water on the ground for maintenance, wherein the maintenance time is 28H;
s2, horizontal line positioning: according to the horizontal standard line and the selected thickness of the floor tiles, calibrating the horizontal marking line on the inner wall, and positioning the horizontal line;
s3, paving mud on the ground: and (4) paving cement mortar on the ground after the maintenance in the step (S1), and then carrying out slurry sweeping and trowelling operations, wherein the proportion of water to the sand in the cement mortar is 1: 2;
s4, operation before laying: paving dry and hard cement mortar on the ground after the slurry is swept in the step S3, wherein the proportion of water to the sand in the dry and hard cement mortar is 1: 2, manually troweling the dry and hard cement mortar by using a trowel, immediately paving the dry and hard cement mortar on the ground after the preparation of the dry and hard cement mortar is finished, quickly paving floor tiles, and preparing and using the dry and hard cement mortar according to the actual use amount of the engineering;
s5, laying a control line: performing tile flipping control lines according to the horizontal line positioned in the step S2, and determining the width of a tile paving gap according to design requirements;
s6, paving floor tiles: cement mortar is coated on the floor tiles to be laid in the step S2, the coating thickness of the pure cement slurry coated on the floor tiles is 15MM, the floor tiles are sequentially paved from left to right, the rubber hammer is used for lightly knocking the floor tiles, so that the cement is filled in the gaps between the ground and the floor tiles, and the proportion of water to the cement sand in the cement mortar is 1: 2;
s7, maintenance and seam beautifying: and (4) carrying out watering maintenance operation on the floor tile paved in the step S8, wherein the watering maintenance should be started within 24 hours after the floor tile surface layer is paved, the maintenance time is 9d, when the strength of the floor tile surface layer reaches the strength which can be stepped by an operator to walk, the stain cleaning and seam beautifying operation are carried out on the floor tile surface, the stain is cleaned on the floor tile surface manually, when the pollution on the floor tile surface is serious, a 10% concentration dilute hydrochloric acid solution is used for cleaning, a scraper is used for shoveling and cleaning the redundant seam beautifying agent on the floor tile manually, and the cement for seam beautifying should be the same type, same label and same color cement, so that the paving work of the floor tile is finished, and the paving and paving of the floor tile are finished.
And (4) judging the standard: through comparison of the three embodiments, the best effect is the second embodiment, so that the second embodiment is selected as the best embodiment, and the specific change of the amount also belongs to the protection scope of the technical scheme.
The invention has the beneficial effects that: the construction method for paving and pasting the floor tiles has the advantages that the dry and hard cement mortar is paved in front of the base layer, the adhesiveness in the paving and pasting process is improved, the paving and pasting effect is improved, the seam beautifying agent is injected into the seams of the floor tiles after paving and pasting, the seam beautifying agent is timely compacted, trowelled, dried and scraped to remove redundant parts, and the steps are circularly carried out, so that the device can continuously joint and beautify the seams of the floor tiles, the working efficiency is high, the manpower is saved, the flatness of the wall tiles and the floor tiles can be effectively improved, the construction method has the advantages that the construction requirements are met, the device can be quickly and conveniently mastered by workers, and the construction effect is obvious; according to the invention, the horizontal marking line is calibrated on the inner wall in advance, so that when the leveling layer is laid, the elevation of the leveling layer is carried out by taking the horizontal marking line as a reference, the horizontal height of the leveling layer is ensured, then the laying and the brick-spreading control line are carried out, and finally brick-spreading is carried out according to the line, so that the finally laid floor tile can meet the quality requirement of construction.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. A paving construction method applied to a floor tile ground is characterized by comprising the following steps:
s1, ground cleaning: firstly, leveling a ground base layer needing to be paved with the floor tiles, removing sundries on the ground, and then sprinkling water on the ground for maintenance;
s2, horizontal line positioning: according to the horizontal standard line and the selected thickness of the floor tiles, calibrating the horizontal marking line on the inner wall, and positioning the horizontal line;
s3, paving mud on the ground: paving cement mortar on the ground maintained in the step S1, and then carrying out sweeping and trowelling operations;
s4, operation before laying: paving dry and hard cement mortar on the ground after the slurry is swept in the step S3, and manually troweling the dry and hard cement mortar by using a trowel;
s5, laying a control line: performing tile flipping control lines according to the horizontal line positioned in the step S2, and determining the width of a tile paving gap according to design requirements;
s6, paving floor tiles: cement mortar is coated on the floor tiles to be laid in the step S2, the floor tiles are sequentially paved from left to right, and the rubber hammer is used for lightly knocking the floor tiles to fill the gaps between the ground and the floor tiles with cement;
s7, maintenance and seam beautifying: and (5) carrying out watering maintenance operation on the floor tile paved in the step (S8), and carrying out spot cleaning and seam beautifying operation on the surface of the floor tile when the strength of the surface layer of the floor tile reaches the strength for a worker to step on the floor tile to finish paving and pasting the floor tile.
2. A floor tile floor covering method as claimed in claim 1, wherein the curing time in the step S1 is 24-28H, and the ratio of water to sand in the cement mortar in the steps S3 and S6 is 1: 2.
3. the floor tile floor covering method according to claim 1, wherein the thickness of the pure cement slurry applied to the floor tile in step S6 is 10MM to 15 MM.
4. The floor tile paving method according to claim 1, wherein in step S7, the excess jointing compound is scraped off by a scraper, thereby completing the paving of the floor tile.
5. A floor tile floor covering method as claimed in claim 1, wherein in S7, the floor tile surface is cleaned manually, and when the floor tile surface is contaminated seriously, a 10% diluted hydrochloric acid solution is used to cooperate with the cleaning process.
6. The method as claimed in claim 1, wherein the tile is applied for a period of 7-9 days after the tile is applied for 24 h.
7. A floor tile floor covering construction method according to claim 1, wherein: the cement for seam beautifying in the step S7 is the cement with the same variety, the same label and the same color.
8. A floor tile floor covering construction method according to claim 1, wherein: the proportion of water to the sand in the dry and hard cement mortar in the step S4 is 1: 1.5-1: 2, after the preparation of the dry and hard cement mortar in the step S4, spreading the dry and hard cement mortar on the ground immediately, and quickly paving the floor tiles, wherein the dry and hard cement mortar is prepared and used according to the actual use amount of the engineering.
CN202010898704.0A 2020-08-31 2020-08-31 Paving construction method applied to floor tiles Pending CN112064955A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010898704.0A CN112064955A (en) 2020-08-31 2020-08-31 Paving construction method applied to floor tiles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010898704.0A CN112064955A (en) 2020-08-31 2020-08-31 Paving construction method applied to floor tiles

Publications (1)

Publication Number Publication Date
CN112064955A true CN112064955A (en) 2020-12-11

Family

ID=73665907

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010898704.0A Pending CN112064955A (en) 2020-08-31 2020-08-31 Paving construction method applied to floor tiles

Country Status (1)

Country Link
CN (1) CN112064955A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113123547A (en) * 2021-03-03 2021-07-16 孙辉东 Method for mounting sound insulation ceramic tile
CN113482280A (en) * 2021-07-13 2021-10-08 广东包清贴装饰工程有限公司 Tile joint filling process
CN113833232A (en) * 2021-09-18 2021-12-24 广东贝林建筑设计有限公司 Marble ground construction process
CN114033135A (en) * 2021-12-17 2022-02-11 福建联创智业建设工程有限公司 Assembly type ground construction process
CN114250667A (en) * 2021-12-31 2022-03-29 临沂市政集团有限公司 Pavement brick paving process with high flatness and dense sedimentation
CN114293733A (en) * 2021-12-07 2022-04-08 苏州金螳螂文化发展股份有限公司 Surface wax baking treatment process for decorative floor
CN115059260A (en) * 2022-07-15 2022-09-16 菏泽德合建工集团有限公司开发区装饰分公司 Paving construction process for indoor floor decoration ceramic tile
CN115354543A (en) * 2022-01-05 2022-11-18 湖北理工学院 Automatic paving method for road floor tiles
CN115387569A (en) * 2022-08-23 2022-11-25 鑫源建设科技有限责任公司 Anti-hollowing construction method for floor tiles
CN115492334A (en) * 2022-09-15 2022-12-20 安徽山水空间装饰股份有限公司 Dry and wet mixed paving process for floor tiles

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2587443A1 (en) * 2015-04-22 2016-10-24 Universidad De Burgos Procedure for obtaining dry mortar from cement and cement and lime for construction, made with slate waste (Machine-translation by Google Translate, not legally binding)
CN109653469A (en) * 2019-01-31 2019-04-19 广东爱富兰建设有限公司 The levelling floor construction method of anti-hollowing essence
CN109736534A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 Flooring construction method
CN109838065A (en) * 2019-03-16 2019-06-04 北京金碧合力建筑设计工程有限公司 A kind of ground brick flooring paving construction method
CN110644723A (en) * 2019-10-18 2020-01-03 郭庆业 Construction method for laying floor tiles for building decoration

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2587443A1 (en) * 2015-04-22 2016-10-24 Universidad De Burgos Procedure for obtaining dry mortar from cement and cement and lime for construction, made with slate waste (Machine-translation by Google Translate, not legally binding)
CN109736534A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 Flooring construction method
CN109653469A (en) * 2019-01-31 2019-04-19 广东爱富兰建设有限公司 The levelling floor construction method of anti-hollowing essence
CN109838065A (en) * 2019-03-16 2019-06-04 北京金碧合力建筑设计工程有限公司 A kind of ground brick flooring paving construction method
CN110644723A (en) * 2019-10-18 2020-01-03 郭庆业 Construction method for laying floor tiles for building decoration

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113123547A (en) * 2021-03-03 2021-07-16 孙辉东 Method for mounting sound insulation ceramic tile
CN113482280A (en) * 2021-07-13 2021-10-08 广东包清贴装饰工程有限公司 Tile joint filling process
CN113833232A (en) * 2021-09-18 2021-12-24 广东贝林建筑设计有限公司 Marble ground construction process
CN114293733A (en) * 2021-12-07 2022-04-08 苏州金螳螂文化发展股份有限公司 Surface wax baking treatment process for decorative floor
CN114033135A (en) * 2021-12-17 2022-02-11 福建联创智业建设工程有限公司 Assembly type ground construction process
CN114250667A (en) * 2021-12-31 2022-03-29 临沂市政集团有限公司 Pavement brick paving process with high flatness and dense sedimentation
CN115354543A (en) * 2022-01-05 2022-11-18 湖北理工学院 Automatic paving method for road floor tiles
CN115354543B (en) * 2022-01-05 2023-05-02 湖北理工学院 Automatic road floor tile laying method
CN115059260A (en) * 2022-07-15 2022-09-16 菏泽德合建工集团有限公司开发区装饰分公司 Paving construction process for indoor floor decoration ceramic tile
CN115387569A (en) * 2022-08-23 2022-11-25 鑫源建设科技有限责任公司 Anti-hollowing construction method for floor tiles
CN115492334A (en) * 2022-09-15 2022-12-20 安徽山水空间装饰股份有限公司 Dry and wet mixed paving process for floor tiles

Similar Documents

Publication Publication Date Title
CN112064955A (en) Paving construction method applied to floor tiles
CN109838065B (en) Floor tile ground paving construction method
CN105587102B (en) A kind of wet construction method to the wet type high abrasion terrace that paves
CN107254954A (en) Ground paving ceramic tile construction technology
CN109653529A (en) Historical building clean water brick wall repairs construction method
CN103821296A (en) Wall plastering technique for aerated concrete block filler wall
CN101457581A (en) Construction method for auto-flowing floor
CN109797920B (en) Indoor decoration construction method
CN106884535A (en) A kind of construction technology of imitative stone material Self-leveling waterproof mortar
CN108468413A (en) A kind of air-entrained concrete building block exempts from anti-hollowing construction method of plastering
CN103821252A (en) Process for constructing aerated concrete building block infilled wall through membrane maintenance technology
CN110644723A (en) Construction method for laying floor tiles for building decoration
CN106284998A (en) Plastering on inner walls completely spreads fiberglass gridding cloth construction method
CN110306819B (en) Method for repairing red brick outer wall of historic building
CN112267628A (en) Construction method of plastering-free system for interior wall decoration of constructional engineering
CN103291024B (en) A kind of construction method of novel cement-based motar
CN107540329A (en) Quick-hardening cement based self-leveling mortar
CN110761507A (en) Construction method of external wall chopped false stone
CN110735493B (en) Anti-leakage composite waterproof method for flat roof
CN114876155A (en) Construction process for polishing ground by using non-ignition fine stone concrete
CN110005174A (en) Improve the construction method of Machine-blasting mortar plastering quality
CN214169786U (en) Terrazzo floor used in shopping center
CN211949245U (en) Roof stone flashing structure
CN113323314A (en) External wall paving construction method for sintered ceramic tiles in freeze-thaw environment
CN112627535A (en) Flatness control method for large-area carborundum wear-resistant terrace

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201211

RJ01 Rejection of invention patent application after publication