CN111594231A - Grouting reinforcement method for deep surrounding rock broken water erosion roadway - Google Patents

Grouting reinforcement method for deep surrounding rock broken water erosion roadway Download PDF

Info

Publication number
CN111594231A
CN111594231A CN202010494881.2A CN202010494881A CN111594231A CN 111594231 A CN111594231 A CN 111594231A CN 202010494881 A CN202010494881 A CN 202010494881A CN 111594231 A CN111594231 A CN 111594231A
Authority
CN
China
Prior art keywords
grouting
surrounding rock
long
drill hole
roof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010494881.2A
Other languages
Chinese (zh)
Inventor
秦振东
余富佳
李宏伟
曾勇
李伟
尚松芳
党兴国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Panjiang Refined Coal Co Ltd
Original Assignee
Guizhou Panjiang Refined Coal Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Panjiang Refined Coal Co Ltd filed Critical Guizhou Panjiang Refined Coal Co Ltd
Priority to CN202010494881.2A priority Critical patent/CN111594231A/en
Publication of CN111594231A publication Critical patent/CN111594231A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/06Filling-up mechanically

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

The invention discloses a deep surrounding rock broken water erosion roadway grouting reinforcement method, which comprises the following steps: firstly, filling and plugging a roof fall area of a head-on roof; secondly, grouting and water plugging reinforcement are carried out on the broken surrounding rock of the head-on top plate; and thirdly, performing advanced grouting and water plugging reinforcement on the crushing top plate of the pre-excavation region. Through pouring into polymer chemical material, will originally broken rock mass condense, pass through polymer material's hydrophobicity and expansibility with the crack, with the crack closure to the country rock that has restrained the tunnel roof is not hard up and slides, strengthens the internal friction of country rock, and polymer material's cohesive force effect in addition, thereby the effect of strutting in reinforcing tunnel has promoted the tunnel safety in utilization for the tunnelling speed in tunnel.

Description

Grouting reinforcement method for deep surrounding rock broken water erosion roadway
Technical Field
The invention relates to a roadway support reinforcing method, in particular to a deep surrounding rock crushing water erosion roadway grouting reinforcing method, and belongs to the technical field of coal mine support.
Background
Aiming at the technical requirements that a working face goaf is pre-penetrated during the air return inclined roadway tunneling period of a coal mine, roadway surrounding rocks are broken during the penetration period, the top plate of a roadway is easy to leak, a top caving area and a water burst channel are formed, and great difficulty is brought to roadway supporting, a gold U-shaped shed is mostly adopted for reinforcing and supporting a water spraying roadway in the mine in the past under the condition, and the anchor rope density and the anchor rope driving depth are mostly increased for reinforcing and supporting the position without water spraying at a fork. One problem with these supports is that they fail in the case of drenched or heavily crushed roadways, which results in the need to repeatedly repair the roadway, resulting in increased repair costs and less safety.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: the grouting reinforcement method for the deep surrounding rock broken water erosion roadway is characterized in that a high polymer chemical material is injected, an originally broken rock body is condensed, and cracks are closed through the hydrophobicity and the expansibility of the high polymer material, so that the looseness and the slippage of the surrounding rock of a roadway top plate are inhibited, the internal friction force of the surrounding rock is enhanced, the cohesive force action of the high polymer material is added, the supporting effect of the roadway is enhanced, and the existing problems are solved.
The technical scheme of the invention is as follows: a deep surrounding rock broken water erosion roadway grouting reinforcement method comprises the following steps: firstly, filling and plugging a roof fall area of a head-on roof; secondly, grouting and water plugging reinforcement are carried out on the broken surrounding rock of the head-on top plate; and thirdly, performing advanced grouting and water plugging reinforcement on the crushing top plate of the pre-excavation region.
In the first step, 4 minutes of seamless steel pipes are uniformly inserted into the roof-fall area according to the field condition in the roof-fall area, and the inserting pipe grout outlet is positioned at the top of the roof-fall area.
And in the second step, a row of fan-shaped grouting drill holes with length matched with each other are arranged for crushing the surrounding rock close to the head-on top plate, wherein the length of each long drill hole is 3 meters, the length of each short drill hole is 1.5 meters, and the drilling angle is perpendicular to the roadway surface.
In the third step, aiming at the roof crushing surrounding rock in front of the head-on pre-digging area, multiple rows of fan-shaped advanced long-short matched grouting drill holes are arranged until the roof is transited to the complete area of the roof, wherein the long drill holes are 3 or 4.5 meters, and the short drill holes are 1.5 meters.
The construction sequence of the second step is as follows:
(1) constructing short drill holes, grouting after the construction of six short drill holes of the surrounding rock is finished, and sequentially setting the grouting first and then setting up the grouting;
(2) the grouting amount of each grouting hole is determined according to the field condition, and the reference grouting amount or grouting pressure is increased;
(3) after the short drill hole grouting is finished, waiting for half an hour, and then constructing the long drill hole;
(4) and the grouting sequence and the grouting amount of the long drill hole are determined according to the field condition.
The construction sequence of the third step is as follows:
(1) constructing advanced short drill holes, grouting after the construction of six short drill holes of the surrounding rock is finished, and sequentially setting the grouting first and then setting up the grouting;
(2) the grouting amount of each grouting hole is determined according to the field condition, and the reference grouting amount or grouting pressure is increased;
(3) after the short drill hole grouting is finished, waiting for half an hour, constructing a long-ahead drill hole, testing the length of the long-ahead drill hole to be 3-4.5m, testing the length of the long-ahead drill hole to be 4.5m, if the reinforcing effect is better, adjusting the length to be 3m for testing, and if the reinforcing effect is also better, adjusting the length of the long drill hole to be 3.0 m;
(4) the grouting sequence and grouting amount of the long drill hole are determined according to the field condition;
(5) after grouting of the long drill hole, the long drill hole needs to wait for more than 8 hours, and then tunneling construction is carried out;
(6) the row spacing for long and short drilling construction is about 0.6m (flexibly adjusted according to the row spacing of the shed).
(7) The number of rows of advanced drilling construction needs to be determined according to actual needs.
The invention has the beneficial effects that: compared with the prior art, by adopting the technical scheme of the invention, the originally broken rock mass is condensed by injecting the high polymer chemical material, and the cracks are closed by the hydrophobicity and the expansibility of the high polymer material, so that the looseness and the slippage of the surrounding rock of the top plate of the roadway are inhibited, the internal friction force of the surrounding rock is enhanced, and the cohesive force action of the high polymer material is added, so that the supporting effect of the roadway is enhanced.
Drawings
FIG. 1 is a schematic view of a cannula according to the present invention;
FIG. 2 is a schematic view of the filling effect of the cannula according to the present invention;
FIG. 3 is a cross-sectional view of a fan-shaped head-on borehole of the present invention;
FIG. 4 is a schematic view of a head-on fan-shaped borehole of the present invention;
FIG. 5 is a cross-sectional view of a head-on advanced fan-shaped borehole according to the present invention;
FIG. 6 is a schematic view of a head-on advanced fan drill of the present invention;
FIG. 7 is a schematic diagram of the effect of the advanced drilling hole of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in further detail with reference to the accompanying drawings.
Example 1: as shown in the attached drawings 1-7, the deep surrounding rock crushing water erosion roadway grouting reinforcement method comprises the following steps: firstly, filling and plugging a roof fall area of a head-on roof; secondly, grouting and water plugging reinforcement are carried out on the broken surrounding rock of the head-on top plate; and thirdly, performing advanced grouting and water plugging reinforcement on the crushing top plate of the pre-excavation region.
In the first step, 4-minute seamless steel pipes are uniformly inserted into the roof-fall area according to the field condition in the roof-fall area, and the inserting pipe grout outlet is positioned at the top of the roof-fall area. The cannula is schematically shown in figure 1 and the filling effect is schematically shown in figure 2.
And in the second step, crushing the surrounding rock close to the head-on top plate, and arranging a row of fan-shaped grouting drill holes in length matching, wherein the length of each long drill hole is 3 meters, the length of each short drill hole is 1.5 meters, and the drilling angle is perpendicular to the roadway surface.
The drilling parameters are listed in table 1. The head-on fan-shaped drilling design is schematically shown in the attached figures 3-4.
Table 1 design parameter table for grouting reinforcement drilling of broken surrounding rock of head-on top plate
Figure DEST_PATH_IMAGE002
In the third step, aiming at the roof crushing surrounding rock in front of the head-on pre-digging area, multiple rows of fan-shaped advanced long-short matched grouting drill holes are arranged until the roof is transited to the complete area of the roof, wherein the long drill holes are 3 or 4.5 meters, and the short drill holes are 1.5 meters.
The construction sequence of the second step is as follows:
(1) constructing short drill holes, grouting after the construction of six short drill holes of the surrounding rock is finished, and sequentially setting the grouting first and then setting up the grouting;
(2) the grouting amount of each grouting hole is determined according to the field condition, and the reference grouting amount or grouting pressure is increased;
(3) after the short drill hole grouting is finished, waiting for half an hour, and then constructing the long drill hole;
(4) and the grouting sequence and the grouting amount of the long drill hole are determined according to the field condition.
The construction sequence of the third step is as follows:
(1) constructing advanced short drill holes, grouting after the construction of six short drill holes of the surrounding rock is finished, and sequentially setting the grouting first and then setting up the grouting;
(2) the grouting amount of each grouting hole is determined according to the field condition, and the reference grouting amount or grouting pressure is increased;
(3) after the short drill hole grouting is finished, waiting for half an hour, constructing a long-ahead drill hole, testing the length of the long-ahead drill hole to be 3-4.5m, testing the length of the long-ahead drill hole to be 4.5m, if the reinforcing effect is better, adjusting the length to be 3m for testing, and if the reinforcing effect is also better, adjusting the length of the long drill hole to be 3.0 m;
(4) the grouting sequence and grouting amount of the long drill hole are determined according to the field condition;
(5) after grouting of the long drill hole, the long drill hole needs to wait for more than 8 hours, and then tunneling construction is carried out;
(6) the row spacing for long and short drilling construction is about 0.6m (flexibly adjusted according to the row spacing of the shed).
(7) The number of rows of advanced drilling construction needs to be determined according to actual needs.
The drilling parameters are listed in table 2. The drilling design is schematically shown in figures 5-6.
Table 2 table of design parameters for head-on top plate crushing surrounding rock advanced grouting reinforcement drilling
Figure DEST_PATH_IMAGE004
Through injecting into polymer chemical material, will originally broken rock mass condense, pass through polymer material's hydrophobicity and expansibility with the crack, with the crack closure to the country rock of having restrained the tunnel roof is not hard up and has slided, strengthens the internal friction of country rock, and polymer material's cohesion effect in addition, thereby the effect of strutting in reinforcing tunnel.
The present invention is not described in detail, but is known to those skilled in the art. Finally, the above embodiments are only for illustrating the technical solutions of the present invention and not for limiting, although the present invention has been described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that modifications or equivalent substitutions may be made to the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention, and all of them should be covered in the claims of the present invention.

Claims (6)

1. A deep surrounding rock broken water erosion roadway grouting reinforcement method is characterized by comprising the following steps: the method comprises the following steps: firstly, filling and plugging a roof fall area of a head-on roof; secondly, grouting and water plugging reinforcement are carried out on the broken surrounding rock of the head-on top plate; and thirdly, performing advanced grouting and water plugging reinforcement on the crushing top plate of the pre-excavation region.
2. The deep surrounding rock crushing and water erosion roadway grouting reinforcement method according to claim 1, characterized in that: in the first step, 4 minutes of seamless steel pipes are uniformly inserted into the roof-fall area according to the field condition in the roof-fall area, and the inserting pipe grout outlet is positioned at the top of the roof-fall area.
3. The deep surrounding rock crushing and water erosion roadway grouting reinforcement method according to claim 1, characterized in that: and in the second step, a row of fan-shaped grouting drill holes with length matched with each other are arranged for crushing the surrounding rock close to the head-on top plate, wherein the length of each long drill hole is 3 meters, the length of each short drill hole is 1.5 meters, and the drilling angle is perpendicular to the roadway surface.
4. The deep surrounding rock crushing and water erosion roadway grouting reinforcement method according to claim 1, characterized in that: in the third step, aiming at the roof crushing surrounding rock in front of the head-on pre-digging area, multiple rows of fan-shaped advanced long-short matched grouting drill holes are arranged until the roof is transited to the complete area of the roof, wherein the long drill holes are 3 or 4.5 meters, and the short drill holes are 1.5 meters.
5. The deep surrounding rock crushing and water erosion roadway grouting reinforcement method according to claim 3, characterized in that: the construction sequence of the second step is as follows:
(1) constructing short drill holes, grouting after the construction of six short drill holes of the surrounding rock is finished, and sequentially setting the grouting first and then setting up the grouting;
(2) the grouting amount of each grouting hole is determined according to the field condition, and the reference grouting amount or grouting pressure is increased;
(3) after the short drill hole grouting is finished, waiting for half an hour, and then constructing the long drill hole;
(4) and the grouting sequence and the grouting amount of the long drill hole are determined according to the field condition.
6. The deep surrounding rock crushing and water erosion roadway grouting reinforcement method according to claim 4, characterized in that: the construction sequence of the third step is as follows:
(1) constructing advanced short drill holes, grouting after the construction of six short drill holes of the surrounding rock is finished, and sequentially setting the grouting first and then setting up the grouting;
(2) the grouting amount of each grouting hole is determined according to the field condition, and the reference grouting amount or grouting pressure is increased;
(3) after the short drill hole grouting is finished, waiting for half an hour, constructing a long-ahead drill hole, testing the length of the long-ahead drill hole to be 3-4.5m, testing the length of the long-ahead drill hole to be 4.5m, if the reinforcing effect is better, adjusting the length to be 3m for testing, and if the reinforcing effect is also better, adjusting the length of the long drill hole to be 3.0 m;
(4) the grouting sequence and grouting amount of the long drill hole are determined according to the field condition;
(5) after grouting of the long drill hole, the long drill hole needs to wait for more than 8 hours, and then tunneling construction is carried out;
(6) the row spacing of long and short drill hole construction is 0.6 m.
CN202010494881.2A 2020-06-03 2020-06-03 Grouting reinforcement method for deep surrounding rock broken water erosion roadway Pending CN111594231A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010494881.2A CN111594231A (en) 2020-06-03 2020-06-03 Grouting reinforcement method for deep surrounding rock broken water erosion roadway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010494881.2A CN111594231A (en) 2020-06-03 2020-06-03 Grouting reinforcement method for deep surrounding rock broken water erosion roadway

Publications (1)

Publication Number Publication Date
CN111594231A true CN111594231A (en) 2020-08-28

Family

ID=72180928

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010494881.2A Pending CN111594231A (en) 2020-06-03 2020-06-03 Grouting reinforcement method for deep surrounding rock broken water erosion roadway

Country Status (1)

Country Link
CN (1) CN111594231A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113027467A (en) * 2021-04-01 2021-06-25 宿州市金鼎安全技术股份有限公司 Advanced grouting reinforcement treatment method for fully mechanized mining face passing through structural broken zone
CN113153391A (en) * 2021-05-06 2021-07-23 中国科学院武汉岩土力学研究所 Anchor cable grouting combined supporting method for coal roadway inclined composite roof
CN114439505A (en) * 2021-11-29 2022-05-06 陕西彬长孟村矿业有限公司 Three-dimensional grouting method for roadway of roadway engineering
CN116517553A (en) * 2023-04-25 2023-08-01 安徽恒源煤电股份有限公司 Staggered high-low pressure complementary grouting method for broken rock mass long and short pipes

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105888683A (en) * 2016-06-28 2016-08-24 安徽理工大学 Roof-fall gangue cleaning method based on grouting technique
CN105927232A (en) * 2016-05-19 2016-09-07 安徽理工大学 Deep-blocking and shallow-grouting grouting method for no-blank area of mine and grouting safety protecting device
CN106121717A (en) * 2016-07-04 2016-11-16 河南理工大学 A kind of driving face in coal mine caving place injecting treatment method
CN109372555A (en) * 2018-12-26 2019-02-22 中国矿业大学 A kind of fault disruption zone area tunnel 3 D stereo grouting support method
CN109653749A (en) * 2018-11-30 2019-04-19 中铁二局第五工程有限公司 A kind of loose slide rock rubble soil section tunnel excavation construction method of high altitude localities shallow embedding
CN109763861A (en) * 2019-01-16 2019-05-17 中国矿业大学 One kind cutting intraocular fault belt treatment of roof collapse method
CN110067573A (en) * 2019-04-26 2019-07-30 西和县中宝矿业有限公司 A kind of quick improvement and the construction method for passing through the crushed zone that caved in
CN110206569A (en) * 2019-05-05 2019-09-06 西安科技大学 A method of administering large-mining-height working surface roof fall wall caving

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105927232A (en) * 2016-05-19 2016-09-07 安徽理工大学 Deep-blocking and shallow-grouting grouting method for no-blank area of mine and grouting safety protecting device
CN105888683A (en) * 2016-06-28 2016-08-24 安徽理工大学 Roof-fall gangue cleaning method based on grouting technique
CN106121717A (en) * 2016-07-04 2016-11-16 河南理工大学 A kind of driving face in coal mine caving place injecting treatment method
CN109653749A (en) * 2018-11-30 2019-04-19 中铁二局第五工程有限公司 A kind of loose slide rock rubble soil section tunnel excavation construction method of high altitude localities shallow embedding
CN109372555A (en) * 2018-12-26 2019-02-22 中国矿业大学 A kind of fault disruption zone area tunnel 3 D stereo grouting support method
CN109763861A (en) * 2019-01-16 2019-05-17 中国矿业大学 One kind cutting intraocular fault belt treatment of roof collapse method
CN110067573A (en) * 2019-04-26 2019-07-30 西和县中宝矿业有限公司 A kind of quick improvement and the construction method for passing through the crushed zone that caved in
CN110206569A (en) * 2019-05-05 2019-09-06 西安科技大学 A method of administering large-mining-height working surface roof fall wall caving

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113027467A (en) * 2021-04-01 2021-06-25 宿州市金鼎安全技术股份有限公司 Advanced grouting reinforcement treatment method for fully mechanized mining face passing through structural broken zone
CN113153391A (en) * 2021-05-06 2021-07-23 中国科学院武汉岩土力学研究所 Anchor cable grouting combined supporting method for coal roadway inclined composite roof
CN114439505A (en) * 2021-11-29 2022-05-06 陕西彬长孟村矿业有限公司 Three-dimensional grouting method for roadway of roadway engineering
CN116517553A (en) * 2023-04-25 2023-08-01 安徽恒源煤电股份有限公司 Staggered high-low pressure complementary grouting method for broken rock mass long and short pipes
CN116517553B (en) * 2023-04-25 2024-02-06 安徽恒源煤电股份有限公司 Staggered high-low pressure complementary grouting method for broken rock mass long and short pipes

Similar Documents

Publication Publication Date Title
CN111594231A (en) Grouting reinforcement method for deep surrounding rock broken water erosion roadway
CN104790978B (en) The tunnel ring-shaped base tunnel construction method of small interval crossings on different level
CN106194244B (en) Lower permeability seam liquid phase CO2Phase transformation fracturing is anti-reflection grid type gas pumping method
CN102877858B (en) Reinforcing method for crushed top plate of coal face
CN105804767B (en) A kind of the surrounding rock supporting construction method and surrounding rock supporting structure in the aqueous tunnel of coal mine
CN103821538B (en) J-type horizontal assistant branched hole surface advance grouting paste-making method
CN105041344B (en) High-pressure gas seam-expanding, grouting and water-plugging method for precutting trough of microfissure surrounding rock
CN107143338B (en) A kind of coal mine roadway driving and method for protecting support
CN109372556A (en) A kind of sandwich arch and construction method suitable for high stressed soft rock tunnel supporting roadway surrounding rock
CN103334770A (en) Construction method of superhigh water pressure water-affluent crushed zones of long-large counter-slope tunnels
CN103485808B (en) Electro-osmosis home position modified roadway anchoring method of underground swelling soft rock
CN102777185A (en) Inclined well shaft construction technology
CN113187486A (en) Gob-side entry driving method for deep well without coal pillar and formed entry
CN113622913A (en) Deformation control method for mining tunnel surrounding rock integrated with underground and up-down tunnel by full-caving method
CN105673014A (en) Method for controlling rock burst of hard roof jump mining working face
CN110529150A (en) A kind of coal mine fault belt grouting strengthening method based on tracer technique
CN109779663A (en) Gob side entry retaining multi-zone cascade-control method
CN109488329A (en) A kind of broken water drenching country rock administering method of Deep Soft Rock Tunnel large deformation
CN111764863A (en) Method for blocking water gushing of high-pressure drilling hole in underground fault fracture zone
CN112177623A (en) TBM (Tunnel boring machine) grading construction method for stratum tunnels with different water-rich crushing degrees
CN109057802A (en) Shallow tunnel with big cross-section underpass of freeways construction method
CN101358529A (en) Short tube and short tube sand consolidation agent strengthening construction process
CN112943306A (en) Roadway fault zone supporting method and step based on instability deformation research
Tian et al. Study on the deformation failure mechanism and coupling support technology of soft rock roadways in strong wind oxidation zones
CN102235151A (en) Advanced hole-forming method of sand gravel boulder layer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200828