CN102777185A - Inclined well shaft construction technology - Google Patents

Inclined well shaft construction technology Download PDF

Info

Publication number
CN102777185A
CN102777185A CN2012101592924A CN201210159292A CN102777185A CN 102777185 A CN102777185 A CN 102777185A CN 2012101592924 A CN2012101592924 A CN 2012101592924A CN 201210159292 A CN201210159292 A CN 201210159292A CN 102777185 A CN102777185 A CN 102777185A
Authority
CN
China
Prior art keywords
freezing
shaft
construction technology
construction
inclined well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012101592924A
Other languages
Chinese (zh)
Inventor
张晓岩
张辉
张青霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2012101592924A priority Critical patent/CN102777185A/en
Publication of CN102777185A publication Critical patent/CN102777185A/en
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention relates to an inclined well shaft construction technology. The construction technology comprises a freezing step and is characterized in that the freezing is block freezing, namely a shaft and an arch part are vertically inserted into a freezing pipe to be frozen. The construction technology also comprises a drilling and digging freezing of a shaft bottom-plate, the shaft bottom-plate is put down from a wellhead section to drill, and the direction of drill holes are parallel with the central line direction of a shaft, namely obliquely drilling; and a freezing station is established at a wellhead and is specially used for freezing of the shaft bottom-plate. The inclined well shaft construction technology adopting the technical scheme has the following beneficial effects that through the improved freezing process, the frozen soil quantity at the excavated section of the inclined well shaft can be greatly reduced, and even the excavated section of the shaft cannot generate frozen soil; the construction difficulty, the manpower and the material resources can be greatly reduced; and the construction progress of an inclined well can be greatly speeded up.

Description

A kind of inclines construction technology
Technical field:
The present invention relates to colliery inclines construction technology, relate in particular to a kind of inclines construction technology.
Background technology:
China is the extremely abundant country of coal reserves, and mine construction is the basic premise of coal resources in China exploitation, and good shaft building technology is the input of the minimizing construction fund of degree greatly, can accelerate the paces of mine construction again.
The inclined shaft freezing engineering is meant in the inclines process of construction; For making things convenient for shaft excavation borehole wall surrounding soil or rock are carried out freezing of certain limit; To reduce or to stop that roof and floor in the shaft excavation process caves in or the generation of accident such as permeable, ensure that pit shaft safety passes through caving ground.
China's large-scale capital construction mine main slant pit shaft is adopting existing inclines to freeze technology when showing soil and weathered rocks section; Though this method can ensure shaft construction safety to greatest extent; But a very big drawback is arranged also; It is excessive that is exactly the frozen soil area, caused very big obstacle to shaft excavation.Waste lot of manpower and material resources, caused the pit shaft cost too high, the situation that driving speed is slow excessively.
Summary of the invention:
Goal of the invention: for a kind of technology that reduces the frozen soil amount of inclines excavated section dramatically is provided.
In order to reach as above purpose, the present invention takes following technical scheme: comprise and freeze step, it is characterized in that: said freezing for piecemeal freezes, promptly pit shaft wall, arch are vertically inserted freezing pipe and are freezed.
Further technical scheme of the present invention is: the brill that also comprises the pit shaft base plate digs freezing; It is transferred from the well head section for the employing of pit shaft base plate and drills, and bore direction is parallel with wellbore centre line direction, promptly makes oblique brill; Set up a Freezing Station again at the well head place, specialize in the pit shaft base plate and freeze to use.
Adopt as above the present invention of technical scheme; Have following beneficial effect: so improved freezes technology; Just can reduce the frozen soil amount of inclines excavated section dramatically; Even make the excavated section of pit shaft frozen soil not occur, greatly degree reduces the construction speed of difficulty of construction and manpower and materials, quickening inclined shaft.
Description of drawings:
In order to further specify the present invention, further describe below in conjunction with accompanying drawing:
Fig. 1 is the constructing structure sketch map of background technology:
Fig. 2 is the constructing structure sketch map of invention:
The specific embodiment:
Below in conjunction with accompanying drawing embodiments of the invention are described, embodiment is not construed as limiting the invention:
In conjunction with Fig. 1;
It is that whole pit shaft freeze all is as a whole that original inclines freeze technology; Comprising the pit shaft part of needs driving, is frozen soil all thereby cause the shaft excavation section, blows out and explodes not open; Excavator digs motionless situation; Greatly influence the driving progress of mine, greatly wasted manpower and materials, extremely be unfavorable for the construction of inclines.
In conjunction with Fig. 2;
This measure improves on original freezing method basis, be to reduce the frozen soil area in the tunneling process, and we adopt piecemeal to freeze, and promptly pit shaft wall, arch are vertically inserted freezing pipe and freezed; The pit shaft base plate then adopts transfers (being that the pit shaft base plate is transferred) from the well head section and drills, and bore direction is parallel with wellbore centre line direction, promptly makes oblique brill.So, just need again the well head place to set up a Freezing Station again, specialize in the pit shaft base plate and freeze to use.
This corrective measure is freezed at original inclines to improve on the basis of technology; The technology of freezing after the improvement divides two parts that inclines are freezed; Freezing efficiency can not change; But can farthest reduce the frozen soil amount of shaft excavation section, improve drivage efficiency, reduce drain on manpower and material resources.
Can effectively improve the inclines efficiency of construction, reduce the inclines cost.
More than show and described basic principle of the present invention, principal character and advantage of the present invention.The technician of the industry should understand; The present invention is not restricted to the described embodiments; That describes in the foregoing description and the manual just explains principle of the present invention; The present invention also has various changes and modifications under the prerequisite that does not break away from spirit and scope of the invention, and these variations and improvement all fall in the scope of the invention that requires protection.The present invention requires protection domain to be defined by appending claims and equivalent thereof.

Claims (2)

1. an inclines construction technology comprises and freezes step, it is characterized in that: said freezing for piecemeal freezes, promptly pit shaft wall, arch are vertically inserted freezing pipe and are freezed.
2. a kind of inclines construction technology as claimed in claim 1; It is characterized in that: the brill that also comprises the pit shaft base plate digs freezing; It is transferred from the well head section for the employing of pit shaft base plate and drills, and bore direction is parallel with wellbore centre line direction, promptly makes oblique brill; Set up a Freezing Station again at the well head place, specialize in the pit shaft base plate and freeze to use.
CN2012101592924A 2012-05-15 2012-05-15 Inclined well shaft construction technology Pending CN102777185A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012101592924A CN102777185A (en) 2012-05-15 2012-05-15 Inclined well shaft construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012101592924A CN102777185A (en) 2012-05-15 2012-05-15 Inclined well shaft construction technology

Publications (1)

Publication Number Publication Date
CN102777185A true CN102777185A (en) 2012-11-14

Family

ID=47122274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012101592924A Pending CN102777185A (en) 2012-05-15 2012-05-15 Inclined well shaft construction technology

Country Status (1)

Country Link
CN (1) CN102777185A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103321239A (en) * 2013-06-26 2013-09-25 中煤邯郸特殊凿井有限公司 Drilling machine foundation
CN103726852A (en) * 2013-12-17 2014-04-16 北京中煤矿山工程有限公司 Incline step-wise freezing construction process
CN104632225A (en) * 2014-12-24 2015-05-20 陕西煤业化工建设(集团)有限公司 Annular frozen pipeline
CN108386228A (en) * 2018-02-09 2018-08-10 西安科技大学 A kind of method of inclined shaft freezing method construction long term monitoring lane wall stress
CN108457306A (en) * 2018-06-20 2018-08-28 北京城建集团有限责任公司 A kind of pile pipe collaboration upright side walls level being used for 4/6 pilot tunnel PBA engineering methods makes bottom basin shape and freezes sealing engineering method
CN108457307A (en) * 2018-06-20 2018-08-28 北京城建集团有限责任公司 A kind of leading pilot tunnel upright side walls level being used for 4/6/8 pilot tunnel PBA engineering methods makes bottom basin shape and freezes sealing engineering method
CN109441453A (en) * 2018-11-28 2019-03-08 中煤邯郸特殊凿井有限公司 Partial freezing's construction method in inclines
CN109751052A (en) * 2018-11-30 2019-05-14 陕西中能煤田有限公司 The big height difference brine recycling decompressor of inclined shaft freezing
CN111852483A (en) * 2020-07-30 2020-10-30 中煤第一建设有限公司 Inclined shaft freezing construction process and inclined shaft freezing system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4107455A1 (en) * 1991-03-08 1992-09-10 Messer Griesheim Gmbh METHOD FOR THE ACCELERATED FREEZING OF EARTH
KR20050079973A (en) * 2005-06-24 2005-08-11 김기수 Process for reinforcing the ground on the upper part of a tunnel for excavating
TW200742785A (en) * 2006-05-09 2007-11-16 Yang-Yuan Chen The method of liquid nitrogen ground freezing for underground sewer jack-piping
CN101158268A (en) * 2007-11-15 2008-04-09 中铁二局股份有限公司 Construction method for super-long high-precision horizontal drilling

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4107455A1 (en) * 1991-03-08 1992-09-10 Messer Griesheim Gmbh METHOD FOR THE ACCELERATED FREEZING OF EARTH
KR20050079973A (en) * 2005-06-24 2005-08-11 김기수 Process for reinforcing the ground on the upper part of a tunnel for excavating
TW200742785A (en) * 2006-05-09 2007-11-16 Yang-Yuan Chen The method of liquid nitrogen ground freezing for underground sewer jack-piping
CN101158268A (en) * 2007-11-15 2008-04-09 中铁二局股份有限公司 Construction method for super-long high-precision horizontal drilling

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周晓敏: "斜井井筒的冻结法施工", 《建井技术》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103321239A (en) * 2013-06-26 2013-09-25 中煤邯郸特殊凿井有限公司 Drilling machine foundation
CN103321239B (en) * 2013-06-26 2015-09-30 中煤邯郸特殊凿井有限公司 A kind of rig basis
CN103726852A (en) * 2013-12-17 2014-04-16 北京中煤矿山工程有限公司 Incline step-wise freezing construction process
CN103726852B (en) * 2013-12-17 2016-01-13 北京中煤矿山工程有限公司 A kind of inclined shaft step-by-step movement frozen construction technique
CN104632225A (en) * 2014-12-24 2015-05-20 陕西煤业化工建设(集团)有限公司 Annular frozen pipeline
CN108386228A (en) * 2018-02-09 2018-08-10 西安科技大学 A kind of method of inclined shaft freezing method construction long term monitoring lane wall stress
CN108457306A (en) * 2018-06-20 2018-08-28 北京城建集团有限责任公司 A kind of pile pipe collaboration upright side walls level being used for 4/6 pilot tunnel PBA engineering methods makes bottom basin shape and freezes sealing engineering method
CN108457307A (en) * 2018-06-20 2018-08-28 北京城建集团有限责任公司 A kind of leading pilot tunnel upright side walls level being used for 4/6/8 pilot tunnel PBA engineering methods makes bottom basin shape and freezes sealing engineering method
CN109441453A (en) * 2018-11-28 2019-03-08 中煤邯郸特殊凿井有限公司 Partial freezing's construction method in inclines
CN109751052A (en) * 2018-11-30 2019-05-14 陕西中能煤田有限公司 The big height difference brine recycling decompressor of inclined shaft freezing
CN109751052B (en) * 2018-11-30 2024-05-24 陕西中能煤田有限公司 Brine circulation pressure reducing device with large height difference for inclined shaft freezing
CN111852483A (en) * 2020-07-30 2020-10-30 中煤第一建设有限公司 Inclined shaft freezing construction process and inclined shaft freezing system

Similar Documents

Publication Publication Date Title
CN102777185A (en) Inclined well shaft construction technology
CN104694746B (en) A kind of method of ion adsorption type re in_situ leaching and leaching ore deposit system thereof
CN103590831B (en) A kind of gentle dip is thin-the novel mining methods of middle thickness orebody
CN105952475B (en) A kind of residual exploiting field inbreak abandoned working grouting and reinforcing technology of coal mine and method
CN110242301A (en) A kind of modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer
CN103498696B (en) A kind of method from roadway in the roof grouting filling compacting goaf filling body
CN104863629A (en) Method for extracting gas from separation layer below overlying strata, draining water and grouting through combined drill hole
CN103835651B (en) A kind of single hole directional drilling local slip casting mine shaft rising boring technique
CN102392678A (en) Gas drainage method combining surface and underground fracturing and permeability improvement
CN111335944B (en) Coal face gangue slurry pipeline collaborative filling method
CN103046931B (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN103498680B (en) Improve the method for fully mechanized coal face period of beginning mining top-coal recovery rate
CN105464700B (en) Fully mechanized mining filling mixed mining working face filling segment length determines method
CN102877857B (en) Deep hole pre-grouting top plate reinforcement method for large-mining height working face under special geological conditions
CN104481540A (en) Method for controlling multiple coal mining hazards by high level borehole grouting
CN102777180A (en) Method for actively and regionally preventing and controlling rock burst in coal mines
CN103953386A (en) Upstream-blocking and downstream-seepage method for extracting gas in mining area
CN103306713A (en) Networked reinforcement method for cross-layer drilling of outburst coal seam
CN104895531A (en) Single thick coal seam ground mining well extraction process
CN104975868A (en) Top plate high-position boring large-diameter long-drill-hole gas extraction method based on directional drilling
CN107091091A (en) A kind of steeply-inclined seam mining gob-side entry retaining method of prefabricated arc support
CN103557001B (en) A kind of low section high oper cylinler shrink afterwards filling mining method
CN109973095A (en) A kind of method of coal mine solid filling exploitation reconstruction groundwater storage space
CN103114854B (en) Pillar robbing method of reconstructed artificial stud
CN110173295A (en) A method of utilizing concordant directional drilling mash gas extraction and fire extinguishing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121114