CN110242301A - A kind of modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer - Google Patents
A kind of modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer Download PDFInfo
- Publication number
- CN110242301A CN110242301A CN201910225492.7A CN201910225492A CN110242301A CN 110242301 A CN110242301 A CN 110242301A CN 201910225492 A CN201910225492 A CN 201910225492A CN 110242301 A CN110242301 A CN 110242301A
- Authority
- CN
- China
- Prior art keywords
- water
- bearing layer
- slip casting
- coal
- slurries
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 155
- 238000007569 slipcasting Methods 0.000 title claims abstract description 46
- 238000005065 mining Methods 0.000 title claims abstract description 38
- 238000000034 method Methods 0.000 title claims abstract description 37
- 239000003245 coal Substances 0.000 claims abstract description 51
- 239000002002 slurry Substances 0.000 claims abstract description 48
- 238000004519 manufacturing process Methods 0.000 claims abstract description 15
- 238000002347 injection Methods 0.000 claims abstract description 14
- 239000007924 injection Substances 0.000 claims abstract description 14
- 238000005553 drilling Methods 0.000 claims description 29
- 230000004888 barrier function Effects 0.000 claims description 14
- 239000011440 grout Substances 0.000 claims description 8
- 239000004568 cement Substances 0.000 claims description 7
- 239000004927 clay Substances 0.000 claims description 7
- 235000019353 potassium silicate Nutrition 0.000 claims description 7
- 238000005086 pumping Methods 0.000 claims description 7
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 claims description 7
- 230000009466 transformation Effects 0.000 claims description 7
- 230000000694 effects Effects 0.000 claims description 6
- 230000004048 modification Effects 0.000 claims description 6
- 238000012986 modification Methods 0.000 claims description 6
- 230000009471 action Effects 0.000 claims description 4
- 238000007711 solidification Methods 0.000 claims description 4
- 230000008023 solidification Effects 0.000 claims description 4
- 239000000463 material Substances 0.000 abstract description 3
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 238000011160 research Methods 0.000 description 4
- 239000011435 rock Substances 0.000 description 4
- PPTYJKAXVCCBDU-UHFFFAOYSA-N Rohypnol Chemical compound N=1CC(=O)N(C)C2=CC=C([N+]([O-])=O)C=C2C=1C1=CC=CC=C1F PPTYJKAXVCCBDU-UHFFFAOYSA-N 0.000 description 2
- 238000011084 recovery Methods 0.000 description 2
- 210000004911 serous fluid Anatomy 0.000 description 2
- 239000013589 supplement Substances 0.000 description 2
- FGUUSXIOTUKUDN-IBGZPJMESA-N C1(=CC=CC=C1)N1C2=C(NC([C@H](C1)NC=1OC(=NN=1)C1=CC=CC=C1)=O)C=CC=C2 Chemical compound C1(=CC=CC=C1)N1C2=C(NC([C@H](C1)NC=1OC(=NN=1)C1=CC=CC=C1)=O)C=CC=C2 FGUUSXIOTUKUDN-IBGZPJMESA-N 0.000 description 1
- 238000006424 Flood reaction Methods 0.000 description 1
- 208000036119 Frailty Diseases 0.000 description 1
- 230000003466 anti-cipated effect Effects 0.000 description 1
- 206010003549 asthenia Diseases 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 230000000994 depressogenic effect Effects 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000009792 diffusion process Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 239000011521 glass Substances 0.000 description 1
- 238000011017 operating method Methods 0.000 description 1
- 230000001151 other effect Effects 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 230000035699 permeability Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000003672 processing method Methods 0.000 description 1
- 210000002966 serum Anatomy 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Remote Sensing (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
The invention discloses a kind of modified water-protection coal-mining methods of two step slip casting of top plate water-bearing layer, the water-bearing layer including coal seam and above coal seam, specific implementation step are as follows: get parms;By the way that the first spatial dimension is calculated;Arrange several the first inlet wells;First slurries are injected water-bearing layer bottom, carry out normal back production;The second space range of the second slurries of injection is calculated with parameter;Drill out the second inlet well;Reinject the second slurries with high-intensitive and low-permeability.Beneficial effect is: this method before adopting, after adopting to top plate water-bearing layer by being injected separately into the slurries of different materials, on the one hand increase impermeable layer thickness before adopting, weaken disturbance of the Seam Mining to top plate water-bearing layer, on the other hand prevented also from rear water producing fractures conducting water-bearing layer and goaf is adopted, to realize water-retaining production.
Description
Technical field
The present invention relates to a kind of water-protection coal-mining method in mine field, specially a kind of two step slip casting of top plate water-bearing layer changes
Property water-protection coal-mining method.
Background technique
During pit mining, overlying strata occur movement and deformation and form conduit pipe, make top plate water-bearing layer and goaf
Perforation, causes water resource to be largely lost, or even constitutes security risk to the diggings space such as working face of coal seam and tunnel, particularly with
China western water resources are deficient, for ecological environment frailty mine, and these problems are more serious.How Seam Mining pair is reduced
The disturbance in top plate water-bearing layer prevents water-bearing layer and goaf from penetrating through, and is that realize that safety, water-retaining production must solve key is asked
One of topic.
Currently, having more research and practice in relation to the processing method to water-bearing layer, and achieve good results.Example
Such as, unrestrained top plate water-bearing layer water body is shifted to an earlier date by construction drill, to reduce the watery in water-bearing layer;The water guide that Xiang Caidong is formed is split
Slip casting blocks water producing fractures and pours in prevent water-stop body in gap.
However, there are following several respects in these methods: (1) angle that from mine water disaster prevents and treats, it is unrestrained aqueous
Layer causes water resource to be largely lost to reduce exploitation security risk;(2) it is mainly used for preventing and treating bottom plate to water-bearing layer slip casting at present
Pressure-bearing floods disaster, and for top plate water-bearing layer using less;(3) previous research is that crack occurs in top plate after adopting mostly
After blocked to administer top plate water damage, however water resource has occurred at this time and has been largely lost;(4) it is directed to the protection in top plate water-bearing layer
It is mostly realized with sacrificing resource recovery and back production efficiency, such as increases the thickness of reserved coal pillar, limits mining height, using filling mining side
Method etc..
Therefore, for the limitation of existing research, a kind of modified water protection mining side of two step slip casting of top plate water-bearing layer is proposed
Method.
Summary of the invention
The purpose of the present invention is to provide a kind of modified water-protection coal-mining methods of two step slip casting of top plate water-bearing layer, on solving
State the problem of proposing in background technique.
To achieve the above object, the invention provides the following technical scheme:
A kind of modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer, it is aqueous including coal seam and above coal seam
Layer, further comprising the steps of:
A, the Basic Geological parameter and production technique parameter in place of working are obtained;By calculating, obtains and need modification before adopting
First spatial dimension of aquifer and aquifuge;
B, the first spatial dimension described in step a arranges several the first slip castings from earth's surface to water-bearing layer bottom interval
Drilling, the first inlet well include vertical drilling hole, drilling kick-off section and the horizontal drilling for being bonded water-bearing layer bottom;
C, the first slurries with soft plasticity and water-resisting property are injected by the first inlet well by b step by surface grout injection pumping plant
In water-bearing layer bottom in rapid, so that water-bearing layer is modified;
D, after the completion of slip casting is modified, normal back production is carried out to the working face in coal seam;
E, after working face of coal seam exploitation, the second sky of the second slurries of injection is calculated according to the parameter in step a
Between range;
F, the second inlet well is drilled out from earth's surface toward the second space range, then the second note is passed through by surface grout injection pumping plant
Slurry drilling and/or the first inlet well are adopted in the new water producing fractures that rear unstable overlying strata activity may cause to due to step d
Inject second slurries with high-intensitive and low-permeability.
One embodiment of the present of invention: Basic Geological parameter described in step a and production technique parameter include: water-bearing layer away from
Coal seam distance H, seam inclination α, δ is moved towards to mining face mining height m, strike length l, tendency length l ', travelling limit angle, is gone up a hill
β, γ of going down the hill, crush coefficient q, and further, calculating the modified water-bearing layer bulk of needs is: along the working face side of trend
To, thickness d=qm cos α, length L=l+2H cot δ from the bottom of water-bearing layer, along working face tendency direction length B=l '+
H (cot β+cot γ), then slip casting modified range in water-bearing layer is right above working face from water-bearing layer bottom L × B × d size sky
Between region.
One embodiment of the present of invention: the first inlet well further includes several separated from horizontal drilling in step b
Horizontal branch drilling.
One embodiment of the present of invention: as the first slurries are clay plasmoid humors in step c.
One embodiment of the present of invention: the slip casting step as injected the first slurries in step c is:
The solidification of the plugging action and lower part water in water-bearing layer low portion crack is made 1. first being primarily served with dilute slurry
With;
2. reinjecting underflow, by adjusting grouting pressure, guarantee that slurries are full of to slip casting region and are uniformly distributed, until reaching
To estimated transformation impermeable layer thickness.
One embodiment of the present of invention: the second slurries in step e are the height mixed by water, cement slurry, waterglass
Strong hypotonic slurries.
One embodiment of the present of invention: second space range described in step e is closed ring structure, and specific size is such as
Under: it is moved towards on direction in working face, is H cot δ from coal wall surface to entity coal side width, along working face tendency direction,
Upper and lower end, from right above coal wall to entity coal side width be respectively H cot γ, H cot β an annular region.
Compared with prior art, the beneficial effects of the present invention are: this method before adopting, after adopting to top plate water-bearing layer by dividing
Not Zhu Ru different materials slurry, increase impermeable layer thickness before on the one hand adopting, weaken disturbance of the Seam Mining to top plate water-bearing layer,
On the other hand prevented also from rear water producing fractures conducting water-bearing layer and goaf is adopted, to realize water-retaining production.
Detailed description of the invention
Fig. 1 is positive structure schematic of the present invention;
Fig. 2 is the top view of water-bearing layer of the present invention after modification;
Fig. 3 is the cross-sectional view in Fig. 2 at A-A.
In figure: 1, surface grout injection pumping plant, the 2, first inlet well, 3, topsoil, 4, water-bearing layer, 41 water barriers, 5, coal
Layer, 6, working face, the 7, first space, 8, goaf, 9, second space, the 91, second inlet well.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
Describe the application technical problems to be solved in detail in the background technology, it may be assumed that propose that one kind can be protected both
Water, and the coal-mining method of output capacity can be improved, specific embodiment can be such that
As shown in Figure 1, a kind of modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer, including coal seam 5 and it is located at coal
The water-bearing layer 4 of 5 top of layer after coal seam 5 is mined out, will result in the rock stratum of the water barrier 41 of 4 lower section of water-bearing layer under normal circumstances
There is damaged crack, when crack continued development and links up water-bearing layer and coal seam, gushing water will be formed.Using the present processes
Before, it needs first to implement according to following step:
Such as Fig. 1, a, the Basic Geological parameter and production technique parameter for obtaining place of working, there are many mode for obtaining parameter, can
With by field exploring or inquiry data etc., the parameter mainly obtained include water-bearing layer 4 away from coal seam distance H, seam inclination α,
δ is moved towards to the mining height m of mining face 6, strike length l, tendency length l ', travelling limit angle, the β that goes up a hill, γ of going down the hill, is crushed
Coefficient q obtains the first spatial dimension that modified water-bearing layer 4 and water barrier 41 are needed before adopting by the calculating of these data.This
In spatial dimension specifically need the modified water-bearing layer bulk to be: direction is moved towards along working face, from 4 bottom of water-bearing layer
Thickness d=qm cos α, the length L=l+2H cot δ that portion rises are inclined to direction length B=l '+H (cot β+cot along working face
γ), then the modified range of 4 slip casting of water-bearing layer is right above working face from water-bearing layer bottom L × B × d size area of space.
In Fig. 1,2, b, 7 range of the first space described in step a are arranged several from earth's surface to water-bearing layer bottom interval
A first inlet well 2, the first inlet well include that vertical drilling hole, drilling kick-off section and the horizontal of fitting water-bearing layer bottom are bored
Hole.Here it in order to ensure being all modified by the first slurries in bottom L × B × d size area of space in entire water-bearing layer 4, needs
First inlet well 2 is just drilled out every a distance in earth's surface, specific spacing distance can be according to live water-bearing layer 4
Water penetration calculating is learnt.
And the first inlet well 2 in step b is to make the first slurries stronger comprehensively modified to water-bearing layer 4, it can be with
The first inlet well 2 is allowed to include several horizontal branch drilling separated from horizontal drilling.Here horizontal branch, which drills, to be belonged to
In the prior art of drilling field, just it is not described in detail here.
C, the first slurries with soft plasticity and water-resisting property are injected by the first inlet well 2 by b by surface grout injection pumping plant
In 4 bottom of water-bearing layer in step, so that making water-bearing layer 4 modified.
Clay plasmoid humor can be for the first slurries specific formula used, can be the first slurries in more detail
Formula is clay: water: cement=5:10:1.
It, can be according to following operating method also, in order to allow the first slurries preferably to inject in the rock stratum in water-bearing layer 4:
The solidification of the plugging action and lower part water in 4 low portion crack of water-bearing layer is made 1. first being primarily served with dilute slurry
With;
2. reinjecting underflow, by adjusting grouting pressure, guarantee that slurries are full of to slip casting region and are uniformly distributed, until reaching
To estimated transformation 41 thickness of water barrier.
According to capillary theory, diluter first slurries can utilize this expansion quickly to the capillary diffusion inside water-bearing layer 4
The capillary in water-bearing layer 4 can all be blocked by dissipating, thus covert that water-bearing layer 4 is modified as water barrier 41.It infuses again
Enter underflow, so again can clogging thicker capillary achieved the purpose that modified to water-bearing layer 4 by above-mentioned method.
In Fig. 3, after the completion of d, slip casting are modified, normal back production is carried out to the working face 6 in coal seam 5, but due to water-bearing layer 4
It has been to be modified with certain anti-interference ability, thereby it can be assured that entire water-bearing layer 4 is not in the feelings of gushing water
Condition.
In Fig. 3, the present invention consider face roof deflection, modified water-bearing layer 4 also want one it is prior
Effect: the height in modified water-bearing layer 4 can just supplement sink caused by depressed area.
In Fig. 2 and 3, although there is not the case where gushing water in water-bearing layer 4 in step d, due to face roof
Sinking, there is new stretching slight crack in the edge that will lead to modified aqueous layer 4.Therefore, in order to remove a hidden danger, in step e, coal
After layer working face mining, 9 range of second space of the second slurries of injection is calculated according to the parameter in step a, specifically
Range it is as follows:
9 range of second space is closed ring structure, and specific size is as follows: being moved towards on direction in working face, from coal wall
Surface to entity coal side width be H cot δ, along working face tendency direction along, upper and lower end, from right above coal wall to entity
Coal side width is respectively an annular region of H cot γ, H cot β.The specific course of work such as step f: from earth's surface toward described the
Two spatial dimensions drill out the second inlet well 91, then pass through the second inlet well 91 and/or the first slip casting by surface grout injection pumping plant 1
Drilling 2 is injected to since step d is adopted in the issuable new water producing fractures of rear unstable overlying strata activity with high-intensitive and low
Second slurries of permeability.
Second slurries can be to be mixed by water, cement slurry, waterglass, specifically their ratio, water: water
Mud: the proportion of waterglass is 2:2:3.
The principle of the present invention is roughly divided into 2 steps: first step is that the bottom in water-bearing layer 4 is modified to water barrier.By
In 4 bottom of water-bearing layer inherently in the top of septum primum water layer 41, and because using clay plasmoid humor, Ability of Resisting Disturbance is stronger, therefore
For modified latter aspect after septum primum water layer 41 is broken, the first slurries used can play impermeable role;On the other hand, modified
After water-bearing layer 4 afterwards is superimposed upon water barrier 41, the thickness of water barrier is increased, it is mined out that this extra thickness can be used as supplement
The difference in height that area sinks.
And the effect of second step of the present invention is that the emerging crack in modified 4 edge of water-bearing layer is blocked in slip casting again, the
The effect of two steps is in addition to blocking crack, there are also an other effect: to a pulling force at modified 4 edge of water-bearing layer,
Both modified water-bearing layer 4 and second slurries are allowed to constitute an entirety, it can be ensured that the water source of entire water layer will not be exhausted, and
And the coal full extraction of entire working face 6 can also be fallen using this method, improve output efficiency.
Illustrate practice of the invention below with reference to a specific case study on implementation.
Northwest China portion mine surface environment is severe, shortage of water resources.It can be obtained according to mine side's data, research coal seam is
Flat seam, 7 ° of seam inclination, coal seam buried depth 260m, minable coal seam thickness 8m, advance of the face length 1800m, working face
Length 200m, using the exploitation of longwall full-mechanized mining technique coal caving mining method is moved towards, whole caving methods manage top plate.Through geological prospecting, coal seam
There are the water-bearing layers of a thickness 15m or so at the 165m of top, under the conditions of data shows one's respective area, adopt subsidence factor 0.6, rock
Layer traveling angle, which is respectively as follows:, moves towards 65 ° of traveling angle, goes down the hill 55 ° of traveling angle, goes up a hill 60 ° of traveling angle.Under original recovery method, water
Resource loss is serious.
1) working face Basic Geological parameter and production technique parameter are obtained.By consult mine basic document, water-bearing layer away from
Coal seam distance H=165m, water-bearing layer thickness 15m, seam inclination α=7 °, coal seam buried depth 260m, minable coal seam thickness m=8m, work
Make face and promotes length l=1800m, face length l'=200m.Subsidence factor q=0.6 is adopted, travelling limit angle is respectively as follows:
Traveling angle δ=65 ° are moved towards, traveling angle β=55 ° of going down the hill, traveling angle γ=60 ° of going up a hill.
2) modified to slip casting is carried out from water-bearing layer bottom a certain range before working face mining.Specific steps are as follows:
(1) before working face mining, first according to the basic parameter, the modified range of slip casting before adopting is determined by calculation: from
Water-bearing layer bottom thickness d=qmcos α moves towards direction length L=l+2Hcot δ along working face, is inclined to direction length along working face
B=l'+H (cot β+cot γ).By relevant parameter substitution formula can be calculated, from water-bearing layer bottom thickness d=0.6 × 8 ×
Cos7 °=4.8m, direction length L=1800+2 × 165 × cot65 °=1954m is moved towards along working face, along working face tendency side
To length B=200+165 × (cot55 °+cot65 °)=411m, then the range for needing slip casting is right above working face from aqueous
Layer bottom 1954m × 411m × 4.8m size region, forms the first space 7 as shown in figure 1.
(2) according to 1) in the obtained water-bearing layer position of detection and the modified range of the slip casting being calculated, pumped by surface grout injection
It stands and arranges inlet well into water-bearing layer, inlet well is bored by vertical drilling hole, drilling kick-off section, horizontal drilling and horizontal branch
Four part of hole is constituted.As shown in figure 1 shown in (2), vertical drilling hole is drilled at buried depth 55m, away from water-bearing layer vertical range 20m~30m, is
Drilling kick-off provides enough curved spaces later;Drilling kick-off is carried out later, and enable main borehole level squeezes into water-bearing layer
Lower part;Horizontal drilling is arranged in the transformation water barrier position being calculated, and strike length 1980m is moved towards slightly larger than water barrier
Length L, above entire working face;Finally by no magnetic drilling rod adjusting position, arranged in water-bearing layer slip casting modification area
Several branch holes, branch hole length are 420m, using equally distributed arrangement, guarantee that injection slurries can be in determination
Region in be uniformly distributed, form the water barrier of anticipated thickness.
(3) grouting serous fluid uses clay hardening slurry, and match as clay: water: cement=5:10:1 can according to circumstances be added
Appropriate waterglass properly increases rate of set.Grouting sequence is primarily served using first dilute rear dense grouting mode, dilute thick slurry
The solidification of plugging action and lower part water to water-bearing layer low portion crack, is then injected into underflow, by adjusting slip casting pressure
Power guarantees that slurries are full of to slip casting region and are uniformly distributed, until reaching estimated transformation impermeable layer thickness.
3) after the completion of slip casting is modified before adopting, working face carries out normal back production.
4) after working face mining, the mining influence that transformation water barrier is subject to, especially overlying rock deformation cause to exploit side
Boundary top plate upper section region generates tensioning crack, needs to block these issuable water producing fractures by slip casting epistasis.Tool
Body step are as follows:
(1) after working face mining, firstly, 9 model of second space for adopting grouting behind shaft or drift lining is calculated according to the basic parameter
Enclose: working face moves towards on direction, is Hcot δ from coal wall surface to entity coal side width, along working face tendency direction, upper
Lower end is respectively Hcot γ, Hcot β from coal wall surface to entity coal side width.Relevant parameter is substituted into formula calculating can
, it is moved towards on direction along working face, it is δ=165 Hcot × cot65 °=77m, edge that entity coal two sides, which need the width in slip casting region,
Working face is inclined on direction, and upper end entity coal side width is γ=165 Hcot × cot60 °=95m, lower end entity coal side
Width is β=165 Hcot × cot55 °=116m.Range of grouting is an annular region.
(2) need the region of slip casting as shown in figure 3, being directly arranged into drilling from ground, the whole hole that drills pierce transformation every
Water layer bottom, drilling depth 95m are located at range of grouting center, inlet well every 50m arrangement on trend, tendency direction
One.It is 411m that the working face, which is inclined to slip casting length, and moving towards slip casting length is 1954m, therefore is inclined to the every side arrangement note in direction
Slurry drilling 8 moves towards the every side in direction and arranges inlet well 40.
(3) injecting paste material suggestion uses high-intensitive, low-permeability slurries.In this example, grouting serous fluid selects water glass
Glass, cement slurry mixed serum, match as water: cement: waterglass=2:2:3.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding
And modification, the scope of the present invention is defined by the appended.
Claims (8)
1. a kind of modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer, including coal seam (5) and is located above coal seam (5)
Water-bearing layer (4), it is characterised in that:
A, the Basic Geological parameter and production technique parameter in place of working are obtained;By calculating, obtains and need the aqueous of modification before adopting
The first space (7) range of layer (4) and water barrier (41);
B, the first space (7) range described in step a arranges that several first slip castings are bored from earth's surface to water-bearing layer bottom interval
Hole (2), the first inlet well (2) include vertical drilling hole, drilling kick-off section and the horizontal drilling for being bonded water-bearing layer (4) bottom;
C, the first slurries with soft plasticity and water-resisting property are injected b step by the first inlet well (2) by surface grout injection pumping plant
In water-bearing layer (4) bottom in rapid, so that water-bearing layer (4) are modified;
D, after the completion of slip casting is modified, normal back production is carried out to the working face (6) in coal seam;
E, after working face of coal seam (6) exploitation, the second space of the second slurries of injection is calculated according to the parameter in step a
(9) range;
F, it drills out the second inlet well (91) from earth's surface toward the second space (9) range, then is passed through by surface grout injection pumping plant (1)
Second inlet well (91) and/or the first inlet well (2) to due to step d adopt rear unstable overlying strata activity may cause it is new
Water producing fractures in injection there are high-intensitive and low-permeability the second slurries.
2. the modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer according to claim 1, it is characterised in that: step
Basic Geological parameter described in a and production technique parameter include: water-bearing layer (4) away from coal seam (5) distance H, coal seam (5) inclination alpha, to
Mining face (6) mining height m, strike length l, tendency length l, travelling limit angle (moving towards δ, the β that goes up a hill, γ of going down the hill), crush
Coefficient q.
3. the modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer according to claim 2, it is characterised in that: need
Modified water-bearing layer bulk is: direction is moved towards along working face (6), thickness d=qmcos α from water-bearing layer (4) bottom,
Length L=l+2Hcot δ is inclined to direction length B=l '+H (cot β+cot γ) along working face (6), then water-bearing layer (4) slip casting changes
Property range be right above working face (6) from the area of space of water-bearing layer (4) bottom L × B × d size.
4. the modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer according to claim 1, it is characterised in that: step
The first inlet well (2) further includes several horizontal branch drilling separated from horizontal drilling in b.
5. the modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer according to claim 1, it is characterised in that: step
The first slurries are clay plasmoid humors in c.
6. the modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer according to claim 1, it is characterised in that: step
The slip casting step that the first slurries are injected in c is:
The solidification of the plugging action and lower part water in water-bearing layer (4) low portion crack is made 1. first being primarily served with dilute slurry
With;
2. reinjecting underflow, by adjusting grouting pressure, guarantee that slurries are full of to slip casting region and are uniformly distributed, until reaching pre-
Meter transformation water barrier (41) thickness.
7. the modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer according to claim 1, it is characterised in that: step
The second slurries in e are the high-strength hypotonic slurries mixed by water, cement slurry, waterglass.
8. the modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer according to claim 2, it is characterised in that: step
Second space described in e (9) range is closed ring structure, and specific size is as follows: it is moved towards on direction in working face (6),
To entity coal side width be Hcot δ right above the coal wall, along working face (6) tendency direction, upper and lower end, from coal wall just on
Direction entity coal side width is respectively an annular region of Hcot γ, Hcot β.
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910225492.7A CN110242301B (en) | 2019-03-25 | 2019-03-25 | Two-step grouting modification water-retention coal mining method for roof aquifer |
AU2019435042A AU2019435042B2 (en) | 2019-03-25 | 2019-09-27 | Two-step grouting modified coal mining method under water-preservation for roof aquifer |
PCT/CN2019/108508 WO2020192055A1 (en) | 2019-03-25 | 2019-09-27 | Two-step grouting modified water-protective coal mining method for roof aquifers |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910225492.7A CN110242301B (en) | 2019-03-25 | 2019-03-25 | Two-step grouting modification water-retention coal mining method for roof aquifer |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110242301A true CN110242301A (en) | 2019-09-17 |
CN110242301B CN110242301B (en) | 2020-05-05 |
Family
ID=67883081
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910225492.7A Active CN110242301B (en) | 2019-03-25 | 2019-03-25 | Two-step grouting modification water-retention coal mining method for roof aquifer |
Country Status (3)
Country | Link |
---|---|
CN (1) | CN110242301B (en) |
AU (1) | AU2019435042B2 (en) |
WO (1) | WO2020192055A1 (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2020192055A1 (en) * | 2019-03-25 | 2020-10-01 | 中国矿业大学 | Two-step grouting modified water-protective coal mining method for roof aquifers |
CN111764960A (en) * | 2020-08-17 | 2020-10-13 | 六盘水师范学院 | Coal mining separation layer water damage prevention and control method |
CN112483172A (en) * | 2020-11-25 | 2021-03-12 | 中国煤炭地质总局水文地质局 | Method for artificially reconstructing water blocking boundary |
CN112483040A (en) * | 2020-12-23 | 2021-03-12 | 莱芜莱新铁矿有限责任公司 | Mine water spraying treatment method |
CN112664192A (en) * | 2020-12-11 | 2021-04-16 | 中国矿业大学 | Method for improving coal mining upper limit in thin bedrock area |
CN112695739A (en) * | 2020-12-18 | 2021-04-23 | 中国矿业大学(北京) | Grouting reinforcement method for thick flowing sand layer under mining influence area building structure group |
CN112814737A (en) * | 2021-03-10 | 2021-05-18 | 淮南矿业(集团)有限责任公司 | Collapse column advanced treatment method and system based on laminated multi-branch horizontal well |
CN113006795A (en) * | 2021-04-09 | 2021-06-22 | 中国煤炭地质总局勘查研究总院 | Treatment method of sandstone water on top plate of Jurassic coal field |
CN113175325A (en) * | 2021-04-25 | 2021-07-27 | 中国矿业大学 | Coal and intergrown sandstone type uranium ore coordinated mining method based on key layer protection |
CN114017106A (en) * | 2021-11-03 | 2022-02-08 | 中煤能源研究院有限责任公司 | Calculation method for underground ortho-position grouting filling capacity of gangue |
CN114033382A (en) * | 2021-08-17 | 2022-02-11 | 国家能源投资集团有限责任公司 | Water retention and dew mining process based on aquifer transformation |
CN114934757A (en) * | 2022-05-31 | 2022-08-23 | 彬县水帘洞煤炭有限责任公司 | Water spraying treatment process for underground tunneling roadway of coal seam immediate roof aquifer |
CN115419434A (en) * | 2022-07-31 | 2022-12-02 | 陕西正通煤业有限责任公司 | Coal seam roof pulse type high-pressure grouting working face water inrush prevention technology |
Families Citing this family (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112377221B (en) * | 2020-10-30 | 2022-09-23 | 中煤科工集团西安研究院有限公司 | Method for inhibiting development of water guide crack belt by grouting before mining and building key layer of structure |
CN112746846B (en) * | 2021-02-05 | 2023-02-28 | 中煤科工集团西安研究院有限公司 | Non-settling coal mining method and device for mining and filling parallel with ground directional long drill hole |
CN113062739B (en) * | 2021-04-15 | 2023-04-25 | 神华神东煤炭集团有限责任公司 | Goaf water disaster and strong mine pressure disaster cooperative treatment method |
CN113982581B (en) * | 2021-10-26 | 2023-04-07 | 中国矿业大学 | Stability control method for overburden seepage isolation zone based on low-carbon mining |
CN114233392B (en) * | 2021-11-03 | 2023-07-14 | 河南理工大学 | Underground low ecological damage working face mining parameter optimization method |
CN114109454B (en) * | 2021-11-10 | 2024-06-18 | 北京国电水利电力工程有限公司 | Method for treating grotto rock mass microcrack water damage |
CN114218518B (en) * | 2021-12-16 | 2024-06-21 | 河南省地质局生态环境地质服务中心 | Method for measuring and calculating settling volume of goaf of coal mine |
CN114414438B (en) * | 2022-01-24 | 2024-01-26 | 中国矿业大学 | Identification method for detecting grouting diffusion range based on proton magnetometer |
CN114876403B (en) * | 2022-05-06 | 2023-04-21 | 河南理工大学 | Grouting repairing method for mining high-level fracture space |
CN115467639A (en) * | 2022-08-15 | 2022-12-13 | 中煤科工集团西安研究院有限公司 | Water interception and emission reduction method for directionally exploring and blocking ground |
CN115791524B (en) * | 2022-11-01 | 2024-02-27 | 山东科技大学 | Measuring device and measuring method for measuring goaf grouting slurry properties |
CN116147711B (en) * | 2023-04-17 | 2023-07-11 | 山西潞安环保能源开发股份有限公司 | Device and method for testing coal mine overburden stratum fracture space-time evolution law |
CN117758772B (en) * | 2023-12-21 | 2024-07-02 | 中国矿业大学(北京) | Post-mining aquifer grouting restoration water retention method based on one-hole multipurpose coal mine area |
CN117967277B (en) * | 2024-01-18 | 2024-08-02 | 中国矿业大学 | Measuring method for accurately measuring thickness of coal seam through bedding drilling |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3999617A (en) * | 1975-09-29 | 1976-12-28 | Exxon Production Research Company | Self-supported drilling riser |
CN108661644A (en) * | 2018-06-14 | 2018-10-16 | 陕西省地质环境监测总站 | A kind of water-protection coal-mining method reproducing clay pan using goaf negative pressure |
CN108798589A (en) * | 2018-04-28 | 2018-11-13 | 安徽建筑大学 | A kind of water-bearing layer method of modifying |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6158517A (en) * | 1997-05-07 | 2000-12-12 | Tarim Associates For Scientific Mineral And Oil Exploration | Artificial aquifers in hydrologic cells for primary and enhanced oil recoveries, for exploitation of heavy oil, tar sands and gas hydrates |
CN101608552A (en) * | 2008-06-18 | 2009-12-23 | 郭国政 | The seat earth aquifer reinforces and protects the method for water barrier in reinforcing process |
CN104481560B (en) * | 2014-12-09 | 2017-08-22 | 中煤第一建设有限公司 | Back water-bearing layer administering method |
CN104989403B (en) * | 2015-06-02 | 2017-05-10 | 国投新集能源股份有限公司 | Method for reconstructing floor limestone aquifer into natural-artificial composite integrated aquiclude |
CN106593445A (en) * | 2016-12-02 | 2017-04-26 | 淮北矿业(集团)有限责任公司 | Old goaf underlying close distance coal seam strata-overlying isolation grouting filling exploitation method |
CN106907152B (en) * | 2017-04-06 | 2019-01-25 | 安徽理工大学 | A kind of soil type inlet well arrangement and grouting method |
CN107740701A (en) * | 2017-11-27 | 2018-02-27 | 山东省邱集煤矿 | A kind of method of the accurate grout transformation of top plate thin layer limestone aquifer |
CN110242301B (en) * | 2019-03-25 | 2020-05-05 | 中国矿业大学 | Two-step grouting modification water-retention coal mining method for roof aquifer |
-
2019
- 2019-03-25 CN CN201910225492.7A patent/CN110242301B/en active Active
- 2019-09-27 AU AU2019435042A patent/AU2019435042B2/en active Active
- 2019-09-27 WO PCT/CN2019/108508 patent/WO2020192055A1/en active Application Filing
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3999617A (en) * | 1975-09-29 | 1976-12-28 | Exxon Production Research Company | Self-supported drilling riser |
CN108798589A (en) * | 2018-04-28 | 2018-11-13 | 安徽建筑大学 | A kind of water-bearing layer method of modifying |
CN108661644A (en) * | 2018-06-14 | 2018-10-16 | 陕西省地质环境监测总站 | A kind of water-protection coal-mining method reproducing clay pan using goaf negative pressure |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2020192055A1 (en) * | 2019-03-25 | 2020-10-01 | 中国矿业大学 | Two-step grouting modified water-protective coal mining method for roof aquifers |
CN111764960A (en) * | 2020-08-17 | 2020-10-13 | 六盘水师范学院 | Coal mining separation layer water damage prevention and control method |
CN111764960B (en) * | 2020-08-17 | 2021-11-12 | 六盘水师范学院 | Coal mining separation layer water damage prevention and control method |
CN112483172A (en) * | 2020-11-25 | 2021-03-12 | 中国煤炭地质总局水文地质局 | Method for artificially reconstructing water blocking boundary |
CN112664192A (en) * | 2020-12-11 | 2021-04-16 | 中国矿业大学 | Method for improving coal mining upper limit in thin bedrock area |
CN112695739A (en) * | 2020-12-18 | 2021-04-23 | 中国矿业大学(北京) | Grouting reinforcement method for thick flowing sand layer under mining influence area building structure group |
CN112483040A (en) * | 2020-12-23 | 2021-03-12 | 莱芜莱新铁矿有限责任公司 | Mine water spraying treatment method |
CN112814737B (en) * | 2021-03-10 | 2023-03-14 | 淮南矿业(集团)有限责任公司 | Collapse column advanced treatment method and system based on laminated multi-branch horizontal well |
CN112814737A (en) * | 2021-03-10 | 2021-05-18 | 淮南矿业(集团)有限责任公司 | Collapse column advanced treatment method and system based on laminated multi-branch horizontal well |
CN113006795A (en) * | 2021-04-09 | 2021-06-22 | 中国煤炭地质总局勘查研究总院 | Treatment method of sandstone water on top plate of Jurassic coal field |
CN113006795B (en) * | 2021-04-09 | 2023-10-20 | 中国煤炭地质总局勘查研究总院 | Treatment method of dwarf coal field roof sandstone water |
CN113175325A (en) * | 2021-04-25 | 2021-07-27 | 中国矿业大学 | Coal and intergrown sandstone type uranium ore coordinated mining method based on key layer protection |
CN113175325B (en) * | 2021-04-25 | 2022-03-08 | 中国矿业大学 | Coal and intergrown sandstone type uranium ore coordinated mining method based on key layer protection |
CN114033382A (en) * | 2021-08-17 | 2022-02-11 | 国家能源投资集团有限责任公司 | Water retention and dew mining process based on aquifer transformation |
CN114017106A (en) * | 2021-11-03 | 2022-02-08 | 中煤能源研究院有限责任公司 | Calculation method for underground ortho-position grouting filling capacity of gangue |
CN114017106B (en) * | 2021-11-03 | 2023-10-27 | 中煤能源研究院有限责任公司 | Method for calculating filling capacity of underground ortho grouting of gangue |
CN114934757A (en) * | 2022-05-31 | 2022-08-23 | 彬县水帘洞煤炭有限责任公司 | Water spraying treatment process for underground tunneling roadway of coal seam immediate roof aquifer |
CN115419434A (en) * | 2022-07-31 | 2022-12-02 | 陕西正通煤业有限责任公司 | Coal seam roof pulse type high-pressure grouting working face water inrush prevention technology |
Also Published As
Publication number | Publication date |
---|---|
WO2020192055A1 (en) | 2020-10-01 |
AU2019435042B2 (en) | 2021-10-07 |
AU2019435042A1 (en) | 2020-10-15 |
CN110242301B (en) | 2020-05-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110242301A (en) | A kind of modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer | |
CN104863629B (en) | A kind of method taking out absciss layer gas and draining slip casting under overlying strata using combined drilling and counterboring | |
CN105422170B (en) | Middle deep goaf grouting reinforcing and processing method under a kind of building foundation | |
CA2614569C (en) | Method of increasing reservoir permeability | |
CN113175325B (en) | Coal and intergrown sandstone type uranium ore coordinated mining method based on key layer protection | |
CN102979498B (en) | Coal bed gas multi-branch horizontal well system | |
CN102337919B (en) | A four-period-five-purpose hole-drilling high-efficiency gas extracting process | |
CN108894727A (en) | The water-retaining method of ground level directional drilling slip casting closure overlying strata water producing fractures main channel | |
CN103867229B (en) | A kind of coal mine large-mining is dark prevents and treats comprehensive treatment method for water with lower group of coal mining | |
CN102877884B (en) | The difficult to understand grey top transformation of a kind of mine based on km directional drilling technology and construction method | |
CN102392677A (en) | Permeability improvement technology for coal bed gas reservoir cap by using three-dimensional fracture network modification | |
AU2021106168A4 (en) | High-gas Coal Seam Group Pressure Relief Mining Method Based on Gob-side Entry Retaining in the First Mining Whole Rock Pressure Relief Working Face | |
CN110671145A (en) | Large-mining-width thick coal seam mining composite grouting method | |
CN112879011B (en) | Method for controlling height of water guide crack zone by hard overburden rock pre-cracking weakening under aquifer | |
CN108343418B (en) | Method for controlling mining influence range from surface directional hydraulic fracturing pre-cracked bedrock | |
CN104775816A (en) | Isolated grouting-filling mining method for overburden rock without village migration under cut-side local pressed-coal conditions | |
CN106089291A (en) | A kind of collaborative extraction is caving the old dead zone of formula and the method for lower coal seam coal bed gas | |
CN110030013B (en) | Gob-side entry retaining method for three-seam periodic roof cutting self-entry side of transition support area | |
CN103306713A (en) | Networked reinforcement method for cross-layer drilling of outburst coal seam | |
CN103643918A (en) | Method for searching for and preventing mine water seepage of Ordovician limestone mine field | |
CN104370508A (en) | Coal mine floor rock mass grouting reinforcement method and grouting slurry | |
CN105804754A (en) | Coal uncovering method for mining shaft with coal seam as main water-bearing layer | |
CN107152309B (en) | A kind of coal seam is the high water level and high-speed drainage water damage control method of Main aquifer | |
CN110778317A (en) | Construction method for ground grouting filling drilling structure in caving zone in mining process | |
CN104088637A (en) | Method for second mining of upper-group shallow residual coal under coal seam group conditions |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |