CN114439505A - Three-dimensional grouting method for roadway of roadway engineering - Google Patents

Three-dimensional grouting method for roadway of roadway engineering Download PDF

Info

Publication number
CN114439505A
CN114439505A CN202111429517.9A CN202111429517A CN114439505A CN 114439505 A CN114439505 A CN 114439505A CN 202111429517 A CN202111429517 A CN 202111429517A CN 114439505 A CN114439505 A CN 114439505A
Authority
CN
China
Prior art keywords
grouting
roadway
pipe
hole
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111429517.9A
Other languages
Chinese (zh)
Inventor
贺海鸿
马小辉
胡沛
程洪涛
李晶昆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Binchangmengcun Mining Co ltd
Original Assignee
Shaanxi Binchangmengcun Mining Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Binchangmengcun Mining Co ltd filed Critical Shaanxi Binchangmengcun Mining Co ltd
Priority to CN202111429517.9A priority Critical patent/CN114439505A/en
Publication of CN114439505A publication Critical patent/CN114439505A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Abstract

The invention discloses a three-dimensional grouting method for a roadway of a roadway engineering, which comprises the following steps: step 1, determining a construction area, performing shallow grouting construction on the top plate construction of the construction area, then adopting composite polymer double-liquid slurry to quickly grout and reinforce surrounding rocks, and plugging a water spraying path; step 2, selecting the position of a deep grouting hole, performing deep grouting construction, and adopting an inorganic reinforcing material to perform grouting reinforcement on surrounding rock; and 3, after the construction of the step 1 and the step 2 is finished and the top plate still has a large amount of water, reducing the distance between grouting holes in the step 1 and the step 2, and then circulating the step 1 and the step 2 until the water of the top plate disappears. The invention combines the grouting in the deep and shallow areas to consolidate the laneway in the area with poor laneway molding, difficult support and serious water spraying into a whole, thereby realizing the three-dimensional grouting of the laneway and quickly realizing the purposes of molding control, strengthening support and grouting water plugging.

Description

Three-dimensional grouting method for roadway of roadway engineering
Technical Field
The invention belongs to the technical field of a three-dimensional grouting method, and particularly relates to a three-dimensional grouting method for a roadway of a roadway engineering.
Background
The surrounding rock of the roadway engineering is influenced by geology and self conditions, so that the roadway is formed in various ways, water leakage phenomenon occurs in partial roadways, supporting is difficult, and high caving points occur. Therefore, how to avoid poor tunnel forming, difficult supporting and water plugging caused by surrounding rock crushing and crack development of the tunnel becomes a main research direction of the industry.
Disclosure of Invention
The invention aims to provide a three-dimensional grouting method for a roadway of a roadway engineering, which solves the problem of poor roadway molding caused by surrounding rock crushing and crack development of the conventional roadway.
The technical scheme adopted by the invention is as follows: the three-dimensional grouting method for the roadway of the roadway engineering comprises the following steps:
step 1, determining a construction area, performing shallow grouting construction on the top plate construction of the construction area, then adopting composite polymer double-liquid slurry to quickly grout and reinforce surrounding rocks, and plugging a water spraying path;
step 2, selecting the position of a deep grouting hole, performing deep grouting construction, and adopting an inorganic reinforcing material to perform grouting reinforcement on surrounding rock;
and 3, after the construction of the step 1 and the step 2 is finished and the top plate still has a large amount of water, reducing the distance between grouting holes in the step 1 and the step 2, and then circulating the step 1 and the step 2 until the water of the top plate disappears.
The present invention is also characterized in that,
step 1 shallow grouting specifically comprises the following steps: and constructing grouting holes by using anchor rods and a cable drilling machine, embedding a steel pipe in each hole to form a shallow grouting pipe, arranging a through hole close to the pipe orifice, and welding and directly connecting the pipe orifice of the shallow grouting pipe with a rubber head of a high-pressure rubber pipe of a grouting pump.
The length of the shallow grouting pipe is 2m, and the diameter of the through hole is 6 mm.
And winding the woven bag at a position away from the pipe opening, fastening the woven bag by using binding wires, coating hole sealing glue on the woven bag, and inserting the shallow grouting pipe into the grouting drill hole.
In the step 1, a double-liquid grouting pump is selected during grouting, the pressure of a grouting final hole is not less than 4MPa, and the grouting amount of each grouting hole is not more than 1 ton.
The deep grouting in the step 2 specifically comprises the following steps: and (3) making a deep grouting pipe by embedding a steel pipe in the hole, wherein the length of the deep grouting pipe is 3.5-5m, a through hole is formed at a distance from the pipe orifice, and the deep grouting pipe orifice is welded and directly communicated with a rubber head of a high-pressure rubber pipe of a grouting pump.
The invention has the beneficial effects that:
1. based on the space effect and the characteristics of grout, the roadway in the area with poor roadway molding, difficult support and serious water spraying is consolidated into a whole by combining grouting in the depth area, so that the three-dimensional grouting of the roadway is realized, and the purposes of molding control, support reinforcement and grouting water plugging can be quickly realized.
2. The composite polymer material is adopted for grouting the shallow part of the roadway, the material can quickly bond coal bodies, the effects of reinforcing surrounding rocks and strengthening anchor bolt support are achieved, and the influence time of tunneling circulation can be reduced.
3. Through deep slip casting, shallow slip casting and the mutual cooperation of macromolecular material, inorganic reinforcement material, can reach reduction in production cost, reach the purpose of firm tunnel, slip casting water shutoff fast, can reduce the tunnel and reprocess the frequency, provide the guarantee for the safety in production.
Drawings
FIG. 1 is a schematic diagram of deep and shallow three-dimensional grouting of a roadway three-dimensional grouting method for roadway engineering according to the invention;
FIG. 2 is a schematic view of shallow grouting hole sealing in a roadway of roadway engineering according to the three-dimensional grouting method of the invention;
fig. 3 is a schematic diagram of deep grouting hole sealing of the roadway three-dimensional grouting method for roadway engineering.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments.
The invention provides a three-dimensional grouting method for a roadway of a roadway engineering, which comprises the following steps:
step 1, determining a construction area, performing shallow grouting construction on the top plate construction of the construction area, then adopting composite polymer double-liquid slurry to quickly grout and reinforce surrounding rocks, and plugging a water spraying path;
step 1 shallow grouting specifically comprises the following steps: constructing grouting holes by using an anchor rod and a cable drilling machine, wherein a steel pipe embedded in the holes is used as a shallow grouting pipe, a through hole is formed in a position close to and away from the pipe orifice, the pipe orifice of the shallow grouting pipe is welded and directly communicated, the through hole is connected with a rubber head of a high-pressure rubber pipe of a grouting pump, the length of the shallow grouting pipe is 2m, the diameter of the through hole is 6mm, a woven bag is wound at a position away from the pipe orifice and is tightly bound by a binding wire, hole sealing rubber is coated on the woven bag, the shallow grouting pipe is inserted into a grouting drill hole, a double-liquid grouting pump is selected in step 1 during grouting, the pressure of a final grouting hole is not less than 4MPa, and the grouting amount of each grouting hole is not more than 1 ton;
step 2, selecting the position of a deep grouting hole, performing deep grouting construction, and adopting an inorganic reinforcing material to perform grouting reinforcement on surrounding rock;
in the step 2, deep grouting specifically comprises the following steps: and (3) making a deep grouting pipe by embedding a steel pipe in the hole, wherein the length of the deep grouting pipe is 3.5-5m, a through hole is formed at a distance from the pipe orifice, and the deep grouting pipe orifice is welded and directly communicated with a rubber head of a high-pressure rubber pipe of a grouting pump.
And 3, after the construction of the step 1 and the step 2 is finished and the top plate still has a large amount of water, reducing the distance between grouting holes in the step 1 and the step 2, and then circulating the step 1 and the step 2 until the water on the top plate disappears.
Example 1
The invention provides a three-dimensional grouting method for a roadway of a roadway engineering, which comprises the following steps of 1, determining a construction area according to roadway forming control, supporting difficulty and whether water leakage occurs, performing shallow grouting construction on a top plate of the construction area, then adopting composite polymer double-liquid slurry to quickly perform grouting to reinforce surrounding rock, and plugging a water spraying path;
step 1 shallow grouting specifically comprises the following steps: constructing grouting holes by using an anchor rod and a cable drilling machine, wherein the aperture of each shallow grouting hole is 32mm, the hole spacing is 1500-3000mm, the hole depth is 2.5-3.5m, the inclination angle of a drilled hole is 60-90 degrees, 4' steel pipes are pre-embedded in the holes to form shallow grouting pipes, a through hole is drilled at intervals of 300mm within the range of 1-2 m from the pipe orifice to serve as a grout outlet, the pipe orifice of each shallow grouting pipe is welded directly and connected with a glue head of a high-pressure rubber pipe of a grouting pump, the length of each shallow grouting pipe is 2m, the diameter of each through hole is 6mm, a woven bag is wound within the range of 1m from the pipe orifice and is tied tightly by three binding wires, the woven bag is coated with hole sealing glue, the shallow grouting pipes are inserted into the grouting drilled holes, the thickness of the woven bag wound by the grouting pipes is matched with the aperture of the grouting holes, a double-fluid grouting pump is selected in the step 1 during grouting, the final hole pressure is not less than 4MPa and the grouting amount of each grouting hole is not more than 1 ton, after the whole work of shallow grouting construction is finished, staying for 15 minutes, and then performing the step 2;
step 2, selecting the position of a deep grouting hole, wherein the hole interval is 1500-3000mm, constructing the grouting hole by using an anchor rod, a cable drilling machine and a hydraulic drilling machine, the hole diameter is 32mm, the hole depth is 2.5-3.5m, the inclination angle of a drilling hole is 60-90 degrees, performing deep grouting construction, and adopting an inorganic reinforcing material for grouting and reinforcing surrounding rock;
in the step 2, deep grouting specifically comprises the following steps: 4' steel pipes are pre-buried in the holes to be used as deep grouting pipes, the length of each deep grouting pipe is 3.5-5m, and the deep grouting pipes are arranged at intervals of 500mm within the range of 1-4 m from the pipe orifice
Figure BDA0003379729570000041
The through hole is used as a grout outlet, and the deep grouting pipe orifice is welded
Figure BDA0003379729570000051
The straight-through is connected with a rubber head of a high-pressure rubber pipe of a grouting pump.
And 3, after the construction of the step 1 and the step 2 is finished and the top plate still has a large amount of water, reducing the distance between grouting holes in the step 1 and the step 2, and then circulating the step 1 and the step 2 until the water of the top plate disappears.
By the mode, the three-dimensional grouting method for the roadway of the roadway engineering is based on the space effect and the characteristics of grout, and the roadway in the area with poor roadway molding, difficult supporting and serious water spraying is consolidated into a whole by combining grouting in the deep and shallow areas, so that three-dimensional grouting of the roadway is realized, and the purposes of molding control, supporting reinforcement, grouting and water plugging can be quickly realized.

Claims (6)

1. The three-dimensional grouting method for the roadway of the roadway engineering is characterized by comprising the following steps of:
step 1, determining a construction area, performing shallow grouting construction on the top plate construction of the construction area, then adopting composite polymer double-liquid slurry to quickly grout and reinforce surrounding rocks, and plugging a water spraying path;
step 2, selecting the position of a deep grouting hole, performing deep grouting construction, and adopting an inorganic reinforcing material to perform grouting reinforcement on surrounding rock;
and 3, after the construction of the step 1 and the step 2 is finished and the top plate still has a large amount of water, reducing the distance between grouting holes in the step 1 and the step 2, and then circulating the step 1 and the step 2 until the water of the top plate disappears.
2. The three-dimensional grouting method for the roadway of the roadway engineering according to claim 1, wherein the shallow grouting in the step 1 is specifically: and constructing grouting holes by using anchor rods and a cable drilling machine, embedding a steel pipe in each hole to form a shallow grouting pipe, arranging a through hole close to the pipe orifice, and welding and directly connecting the pipe orifice of the shallow grouting pipe with a rubber head of a high-pressure rubber pipe of a grouting pump.
3. The three-dimensional grouting method for the roadway engineering roadway according to claim 2, wherein the length of the shallow grouting pipe is 2m, and the diameter of the through hole is 6 mm.
4. The method as claimed in claim 2, wherein woven bags are wound around the pipe opening and tightened with binding wires, sealing glue is applied to the woven bags, and the shallow grouting pipe is inserted into the grouting hole.
5. The three-dimensional grouting method for the roadway engineering roadway of claim 1, wherein a double-liquid grouting pump is selected in the grouting in the step 4, the pressure of a grouting final hole is not less than 4MPa, and the grouting amount of each grouting hole is not more than 1 ton.
6. The three-dimensional grouting method for the roadway of the roadway engineering according to claim 1, wherein the deep grouting in the step 2 specifically comprises: and (3) making a deep grouting pipe by embedding a steel pipe in the hole, wherein the length of the deep grouting pipe is 3.5-5m, a through hole is formed at a distance from the pipe orifice, and the deep grouting pipe orifice is welded and directly communicated with a rubber head of a high-pressure rubber pipe of a grouting pump.
CN202111429517.9A 2021-11-29 2021-11-29 Three-dimensional grouting method for roadway of roadway engineering Pending CN114439505A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111429517.9A CN114439505A (en) 2021-11-29 2021-11-29 Three-dimensional grouting method for roadway of roadway engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111429517.9A CN114439505A (en) 2021-11-29 2021-11-29 Three-dimensional grouting method for roadway of roadway engineering

Publications (1)

Publication Number Publication Date
CN114439505A true CN114439505A (en) 2022-05-06

Family

ID=81362965

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111429517.9A Pending CN114439505A (en) 2021-11-29 2021-11-29 Three-dimensional grouting method for roadway of roadway engineering

Country Status (1)

Country Link
CN (1) CN114439505A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102322273A (en) * 2011-05-20 2012-01-18 中国矿业大学 A kind of roadway floor anchor is annotated integrated reinforcement means
CN103061785A (en) * 2012-12-28 2013-04-24 山东大学 Borehole casing pressure-proof seepage sealing grouting device and process for roadway breaking water burst surrounding rock
CN104481560A (en) * 2014-12-09 2015-04-01 中煤第一建设有限公司 Roadway roof aquifer treatment method
CN106089252A (en) * 2016-08-09 2016-11-09 北京矿冶研究总院 Grouting reinforcement method for inhomogeneous loose bodies
KR20170087786A (en) * 2016-01-21 2017-07-31 이평우 Reinforcement method of Tunnel
CN109372555A (en) * 2018-12-26 2019-02-22 中国矿业大学 A kind of fault disruption zone area tunnel 3 D stereo grouting support method
CN111119935A (en) * 2019-12-04 2020-05-08 太原理工大学 Multi-layer grouting reinforcement method for surrounding rock of soft and broken roadway structure
CN111594231A (en) * 2020-06-03 2020-08-28 贵州盘江精煤股份有限公司 Grouting reinforcement method for deep surrounding rock broken water erosion roadway
CN113153396A (en) * 2021-04-19 2021-07-23 华北科技学院 Hole sealing, grouting and water plugging reinforcing method for anchor cable holes in roadway water spraying area
CN113217031A (en) * 2021-05-31 2021-08-06 山东固立特新材料科技有限公司 Water plugging treatment method for tunneling roadway fault

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102322273A (en) * 2011-05-20 2012-01-18 中国矿业大学 A kind of roadway floor anchor is annotated integrated reinforcement means
CN103061785A (en) * 2012-12-28 2013-04-24 山东大学 Borehole casing pressure-proof seepage sealing grouting device and process for roadway breaking water burst surrounding rock
CN104481560A (en) * 2014-12-09 2015-04-01 中煤第一建设有限公司 Roadway roof aquifer treatment method
KR20170087786A (en) * 2016-01-21 2017-07-31 이평우 Reinforcement method of Tunnel
CN106089252A (en) * 2016-08-09 2016-11-09 北京矿冶研究总院 Grouting reinforcement method for inhomogeneous loose bodies
CN109372555A (en) * 2018-12-26 2019-02-22 中国矿业大学 A kind of fault disruption zone area tunnel 3 D stereo grouting support method
CN111119935A (en) * 2019-12-04 2020-05-08 太原理工大学 Multi-layer grouting reinforcement method for surrounding rock of soft and broken roadway structure
CN111594231A (en) * 2020-06-03 2020-08-28 贵州盘江精煤股份有限公司 Grouting reinforcement method for deep surrounding rock broken water erosion roadway
CN113153396A (en) * 2021-04-19 2021-07-23 华北科技学院 Hole sealing, grouting and water plugging reinforcing method for anchor cable holes in roadway water spraying area
CN113217031A (en) * 2021-05-31 2021-08-06 山东固立特新材料科技有限公司 Water plugging treatment method for tunneling roadway fault

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
魏强;: "开拓巷道顶板淋水封堵技术实践", 能源与节能, no. 08, 24 August 2020 (2020-08-24), pages 162 - 165 *

Similar Documents

Publication Publication Date Title
CN110230309B (en) Karst area bridge karst cave pile foundation construction method
CN101644160B (en) High ground stress soft rock stress-relief construction method
CN105715296B (en) Sand blowing, backfilling and grouting construction method for tunnel to penetrate through coal mine goaf
CN111119935B (en) Multi-layer grouting reinforcement method for surrounding rock of soft and broken roadway structure
CN105041325A (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN111287759B (en) Shallow-buried close-connection underground excavation tunnel construction method
CN202543906U (en) Precast pile with reserved grouting pipes
CN101748741A (en) Construction method of concrete supporting structure
CN107725056A (en) One kind passes through silly stratum tunnel loopful quick grouting construction method in advance
CN108035754A (en) A kind of roadway bolt anchor cable combination supporting method
CN109083682A (en) A kind of construction method of mine working antiseepage high intensity fire dam
CN108678772A (en) A kind of multilevel hierarchy suspension device and its construction method for rich water sandy gravel stratum tunnel
Jiang et al. Failure mechanism analysis and support design for deep composite soft rock roadway: a case study of the Yangcheng coal mine in China
CN110700842A (en) Advanced grouting reinforcement method suitable for water-rich sand layer section of shield end
CN111501781A (en) Supporting method and structure combining consolidation grouting of hybrid filling ultra-deep foundation pit with double rows of steel pipe piles
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN105134254B (en) A kind of tunnel surface drilling sleeve pipe sealing device and its operating procedure
CN100535262C (en) Method for reinforcing and increasing foundation pit passive earth pressure
CN106014443A (en) Method for preventing roadway floor heaving and wall sliding of gob-side entry retaining
CN114109442A (en) Tunnel karst broken zone collapse half-section curtain forward grouting reinforcement treatment method
CN110241837A (en) A kind of construction method for preventing basement bottom board from cracking under high artesian geological conditions
CN108914911A (en) A kind of stratum prestress advanced excavation stability control method
CN113309526A (en) Construction method for excavation and support of subway station buckling arch
CN105114099A (en) Poorly consolidated formation roadway support method and system
CN105840209B (en) Construction method for controlling deformation of anchor pile in tunnel body section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination