CN110700842A - An advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end - Google Patents
An advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end Download PDFInfo
- Publication number
- CN110700842A CN110700842A CN201911095271.9A CN201911095271A CN110700842A CN 110700842 A CN110700842 A CN 110700842A CN 201911095271 A CN201911095271 A CN 201911095271A CN 110700842 A CN110700842 A CN 110700842A
- Authority
- CN
- China
- Prior art keywords
- grouting
- water
- shield
- rich sand
- slurry
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000002787 reinforcement Effects 0.000 title claims abstract description 73
- 238000000034 method Methods 0.000 title claims abstract description 48
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 46
- 239000004576 sand Substances 0.000 title claims abstract description 37
- 239000002002 slurry Substances 0.000 claims abstract description 59
- 238000006073 displacement reaction Methods 0.000 claims abstract description 45
- 238000012544 monitoring process Methods 0.000 claims abstract description 45
- 238000013461 design Methods 0.000 claims abstract description 41
- 239000004746 geotextile Substances 0.000 claims abstract description 36
- 230000000694 effects Effects 0.000 claims abstract description 20
- 239000004568 cement Substances 0.000 claims abstract description 16
- 230000008569 process Effects 0.000 claims abstract description 15
- 239000000463 material Substances 0.000 claims abstract description 12
- 238000007689 inspection Methods 0.000 claims abstract description 11
- 239000011435 rock Substances 0.000 claims abstract description 10
- 238000005553 drilling Methods 0.000 claims description 9
- 239000007788 liquid Substances 0.000 claims description 7
- 238000012360 testing method Methods 0.000 claims description 5
- 235000019353 potassium silicate Nutrition 0.000 claims description 4
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 claims description 4
- 239000004744 fabric Substances 0.000 claims description 2
- 238000005728 strengthening Methods 0.000 claims 1
- 238000010276 construction Methods 0.000 description 7
- 238000009412 basement excavation Methods 0.000 description 5
- 238000005056 compaction Methods 0.000 description 5
- 238000009792 diffusion process Methods 0.000 description 5
- 230000014759 maintenance of location Effects 0.000 description 5
- 230000015572 biosynthetic process Effects 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 230000035699 permeability Effects 0.000 description 3
- 238000001556 precipitation Methods 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 230000005641 tunneling Effects 0.000 description 3
- 230000009471 action Effects 0.000 description 2
- 230000002411 adverse Effects 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000000717 retained effect Effects 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 239000004115 Sodium Silicate Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000001125 extrusion Methods 0.000 description 1
- 238000001879 gelation Methods 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
- 238000007712 rapid solidification Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000005204 segregation Methods 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 229910052911 sodium silicate Inorganic materials 0.000 description 1
- 239000007921 spray Substances 0.000 description 1
- 230000007480 spreading Effects 0.000 description 1
- 238000003756 stirring Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/001—Improving soil or rock, e.g. by freezing; Injections
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/06—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
- E21D9/08—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Environmental & Geological Engineering (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Soil Sciences (AREA)
- Civil Engineering (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
本发明公开了一种适用于盾构端头富水砂层段的超前注浆加固方法,它解决了现有技术中水泥浆液难以在富水砂层中有效留存、注浆过程中容易存在浆液上返跑浆等问题,能够实现盾构端头富水砂层段有效加固。其技术方案为:包括以下步骤:确定目标加固区域并设计注浆钻孔;布置地表变形监测点及车站结构位移监测点;制作带有土工布袋的孔口管;打设注浆钻孔并在注浆钻孔中下入孔口管;对土工布袋实施注浆,压密周围地层,构造止浆岩盘;采用速凝注浆材料对目标加固区域实施前进式分段注浆,注浆过程中实时监测地表变形及车站结构位移;通过地表变形及车站结构位移监测数据对注浆设计进行反馈调整;完成所有注浆钻孔的注浆工作,进行注浆效果检查。
The invention discloses an advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end, which solves the problem that the cement slurry in the prior art is difficult to effectively retain in the water-rich sand layer, and the slurry is easy to exist in the grouting process. Problems such as the upper back and running of the slurry can effectively strengthen the water-rich sand layer at the end of the shield. The technical scheme includes the following steps: determining the target reinforcement area and designing grouting holes; arranging surface deformation monitoring points and station structure displacement monitoring points; making orifice pipes with geotextile bags; The orifice pipe is placed in the grouting hole; the geotextile bag is grouted, the surrounding stratum is compacted, and the grouting rock plate is constructed; the fast-setting grouting material is used to carry out forward segment grouting in the target reinforcement area, and the grouting process Real-time monitoring of surface deformation and displacement of station structure; feedback adjustment of grouting design through monitoring data of surface deformation and displacement of station structure; completion of grouting work for all grouting holes and inspection of grouting effect.
Description
技术领域technical field
本发明涉及隧道及地下工程领域,尤其涉及一种适用于盾构端头富水砂层段的超前注浆加固方法。The invention relates to the field of tunnels and underground engineering, in particular to an advanced grouting reinforcement method suitable for a water-rich sand layer section at the end of a shield.
背景技术Background technique
盾构在盾构端头区域进行始发或接收掘进施工时,地层受力状态发生突变,地层稳定性较差,尤其当盾构端头区域位于富水砂层段时,由于富水砂层具有结构松散、富水性强、自稳能力差等特性,极易发生溃砂塌方事故,导致盾构无法掘进。When the shield starts or receives tunneling at the shield end area, the stress state of the stratum changes abruptly, and the stability of the stratum is poor, especially when the shield end area is located in the water-rich sand layer, due to the water-rich sand layer. It has the characteristics of loose structure, strong water richness and poor self-stabilizing ability, which is very prone to sand collapse and landslide accidents, resulting in the inability of shield tunneling.
现有盾构端头的加固方法主要有旋喷法、降水法及袖阀管注浆法等,旋喷法主要采用高压射流技术将地层与水泥浆液进行强制切割搅拌混合以形成旋喷桩体,然后通过不同旋喷桩之间的咬合形成连续加固体,最终实现地层加固止水的目的。发明人发现,在富水砂层旋喷施工过程中,水泥浆液难以在富水砂层中有效留存,导致成桩效果差、旋喷桩咬合度不高,地层加固效果难以满足盾构端头的加固要求。The existing reinforcement methods for shield ends mainly include rotary jetting method, precipitation method and sleeve valve grouting method, etc. The rotary jetting method mainly uses high-pressure jet technology to forcibly cut, stir and mix the stratum and cement slurry to form a rotary jetted pile body. , and then form continuous reinforcement through the occlusion between different jetting piles, and finally achieve the purpose of stratum reinforcement and water-stopping. The inventor found that in the process of rotary jetting construction of the water-rich sand layer, it is difficult for the cement slurry to be effectively retained in the water-rich sand layer, resulting in poor pile forming effect, low occlusion of the rotary jet pile, and difficulty in stratum reinforcement effect meeting the shield end. reinforcement requirements.
降水法主要是对目标地层进行抽水以降低地层含水率进而达到改善地层性能的目的,然而由于降水会导致周围地层的沉降,因此难以在建筑物、市政管线密集分布的城市环境中应用。袖阀管注浆法通过对地层实施由地层深部到地层浅部的后退式注浆,达到抗渗加固的目的。但是该方法在富水砂层中应用存在三方面弊端,一是由于袖阀管注浆法的止浆措施较弱,注浆过程中容易存在浆液上返跑浆的问题,导致目标加固区域内浆液留存率及注浆压力均较低,加固效果难以保证;二是浆液容易在地层浅部扩散,造成地表显著隆起,若地表存在市政管线,会严重威胁市政管线安全;三是富水砂层钻进困难,钻孔塌孔严重,导致袖阀管难以安装到位,施工效率较低。The precipitation method is mainly to pump water to the target stratum to reduce the water content of the stratum and improve the stratum performance. However, since precipitation will cause the subsidence of the surrounding strata, it is difficult to apply in the urban environment where buildings and municipal pipelines are densely distributed. The sleeve valve grouting method achieves the purpose of impermeability and reinforcement by implementing the backward grouting from the deep part of the stratum to the shallow part of the stratum. However, the application of this method in water-rich sand layers has three disadvantages. First, due to the weak grouting measures of the sleeve valve pipe grouting method, the grouting process is prone to the problem of back-running of the grouting, which leads to the problem of grouting in the target reinforcement area. The retention rate of the slurry and the grouting pressure are low, and the reinforcement effect is difficult to guarantee; the second is that the slurry is easy to spread in the shallow part of the formation, causing the surface to rise significantly. If there is a municipal pipeline on the surface, it will seriously threaten the safety of the municipal pipeline; the third is the water-rich sand layer Difficulty in drilling and serious hole collapse in the drilled hole make it difficult to install the sleeve valve tube in place and the construction efficiency is low.
发明内容SUMMARY OF THE INVENTION
为了克服现有技术的不足,本发明提供了一种适用于盾构端头富水砂层段的超前注浆加固方法,其具有能够实现盾构端头富水砂层段有效加固的效果。In order to overcome the deficiencies of the prior art, the present invention provides an advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end, which has the effect of effectively reinforcing the water-rich sand layer at the shield end.
本发明采用下述技术方案:The present invention adopts following technical scheme:
一种适用于盾构端头富水砂层段的超前注浆加固方法,包括以下步骤:An advanced grouting reinforcement method suitable for a water-rich sand layer at a shield end, comprising the following steps:
步骤一:确定目标加固区域并设计注浆钻孔;Step 1: Determine the target reinforcement area and design grouting holes;
步骤二:布置地表变形监测点及车站结构位移监测点;Step 2: Arrange surface deformation monitoring points and station structure displacement monitoring points;
步骤三:制作带有可膨胀土工布袋的孔口管;Step 3: Make an orifice tube with an expandable geotextile bag;
步骤四:打设注浆钻孔并在注浆钻孔中下入孔口管;Step 4: Set up a grouting hole and lower the orifice pipe in the grouting hole;
步骤五:对位于注浆钻孔中的土工布袋实施注浆,压密周围地层,构造止浆岩盘;Step 5: Carry out grouting to the geotextile bag located in the grouting hole, compact the surrounding stratum, and construct a grouting rock plate;
步骤六:采用速凝注浆材料对目标加固区域实施前进式分段注浆,注浆过程中实时监测地表变形及车站结构位移;Step 6: Use rapid-setting grouting material to implement forward segmented grouting to the target reinforcement area, and monitor the surface deformation and the displacement of the station structure in real time during the grouting process;
步骤七:通过地表变形及车站结构位移监测数据对注浆设计进行反馈调整;Step 7: Feedback and adjust the grouting design through the monitoring data of the surface deformation and the displacement of the station structure;
步骤八:完成所有注浆钻孔的注浆工作,并进行注浆效果检查。Step 8: Complete the grouting work of all grouting holes, and check the grouting effect.
进一步的,所述步骤一中,目标加固区域的平面范围在垂直于盾构隧道轴线方向上由盾构隧道轮廓线外扩3~4m,在平行于盾构隧道轴线方向上由车站围护结构边界平移6~8m;目标加固区域的竖向范围为盾构隧道拱顶高度线上移3~4m,盾构隧道拱底高度线下移1~1.5m。Further, in the
进一步的,所述步骤二中,地表变形监测点布置范围为目标加固区域的平面范围外扩设定距离,相邻地表变形监测点的间距为3~5m;Further, in the second step, the arrangement range of the surface deformation monitoring points is the set distance of the expansion of the plane range of the target reinforcement area, and the distance between the adjacent surface deformation monitoring points is 3-5m;
车站结构位移监测点布置于车站围护结构上,相邻车站结构位移监测点的间距为3~5m,且位移监测方向为水平方向。The displacement monitoring points of the station structure are arranged on the station envelope. The distance between the displacement monitoring points of the adjacent station structures is 3-5m, and the displacement monitoring direction is the horizontal direction.
进一步的,所述孔口管的顶部安装法兰盘,所述法兰盘上方设有注浆阀门;所述孔口管的末端与目标加固区域上边界平齐。Further, a flange plate is installed on the top of the orifice pipe, and a grouting valve is arranged above the flange plate; the end of the orifice pipe is flush with the upper boundary of the target reinforcement area.
进一步的,所述土工布袋固定于孔口管的外侧,孔口管一侧设有注浆管,所述注浆管的末端伸入土工布袋内部。Further, the geotextile bag is fixed on the outer side of the orifice pipe, a grouting pipe is arranged on one side of the orifice pipe, and the end of the grouting pipe extends into the interior of the geotextile bag.
进一步的,所述步骤五中,采用速凝类浆液通过注浆管对土工布袋实施注浆,速凝类浆液的凝胶时间小于20s。Further, in the fifth step, the geotextile bag is grouted with a quick-setting type slurry through a grouting pipe, and the gel time of the quick-setting type slurry is less than 20s.
进一步的,所述步骤六中,速凝注浆材料采用水泥-水玻璃双液浆,水泥浆液水灰质量比控制在W/C=0.8~1之间,水泥浆液与水玻璃浆液的双液体积比控制在C:S=3~4:1之间。Further, in the
进一步的,所述步骤六中,当注浆压力达到设计注浆终压而注浆量达到设计注浆量80%时停止注浆,当注浆量达到设计注浆量的1.5倍而注浆压力未达到设计注浆终压时停止注浆,当注浆压力未达到设计注浆终压、注浆量未达到设计注浆量,但地表变形或车站结构位移超过预警值时停止注浆。Further, in the sixth step, when the grouting pressure reaches the design grouting final pressure and the grouting amount reaches 80% of the design grouting amount, the grouting is stopped, and when the grouting amount reaches 1.5 times the design grouting amount, the grouting is stopped. Stop grouting when the pressure does not reach the design final grouting pressure, and stop grouting when the grouting pressure does not reach the design final grouting pressure and the grouting amount does not reach the design grouting amount, but the surface deformation or the displacement of the station structure exceeds the warning value.
进一步的,所述步骤七中,当单次注浆导致的最大地表隆起变形量超过0.3cm或车站结构位移超过0.2cm时,降低设计注浆量。Further, in the seventh step, when the maximum surface uplift deformation caused by a single grouting exceeds 0.3 cm or the displacement of the station structure exceeds 0.2 cm, the design grouting amount is reduced.
进一步的,所述步骤八中,注浆效果检查包括压水试验、钻孔取芯及钻孔电视探查。Further, in the eighth step, the inspection of the grouting effect includes a water pressure test, a drilling core and a drilling video inspection.
与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:
(1)本发明利用可膨胀土工布袋对目标加固区域上方地层施加挤压力,挤密土工布袋周围的地层形成地层挤密区,提高地层抵抗浆液劈裂破坏的能力,通过多个地层挤密区的搭接,在目标加固区域上方形成止浆岩盘,防止注浆过程中浆液上返;(1) The present invention uses the expandable geotextile bag to apply a squeezing force to the stratum above the target reinforcement area, and the stratum around the geotextile bag is compacted to form a stratum compaction area, and the ability of the stratum to resist the splitting damage of the slurry is improved. The lap joint of the grouting area forms a stop rock disk above the target reinforcement area to prevent the slurry from returning during the grouting process;
(2)本发明采用速凝浆液,利用其快速凝胶特性有效限制其浆液扩散范围,最终极大提高目标加固区域内的浆液留存率,使得注浆加固效果大幅度提高,满足盾构始发与接收对盾构端头地层力学性能的要求;(2) The present invention adopts the fast-setting slurry, and uses its fast-gel properties to effectively limit the diffusion range of the slurry, and finally greatly improves the slurry retention rate in the target reinforcement area, so that the grouting reinforcement effect is greatly improved, and it meets the requirements of shield tunneling. And accept the requirements for the mechanical properties of the shield end formation;
(3)本发明相比旋喷法与袖阀管注浆法,可以达到更好的富水砂层加固效果,有效保证盾构始发与接收过程的施工安全;相比袖阀管注浆法,可防止浆液在地层浅部扩散,避免地表隆起值超限;相比旋喷法,本方法设备简单、施工效率高、缩短了整个作业时间,成本较低。(3) Compared with the rotary jet method and the sleeve valve pipe grouting method, the present invention can achieve a better reinforcement effect of the water-rich sand layer, effectively ensuring the construction safety of the shield starting and receiving process; compared with the sleeve valve pipe grouting The method can prevent the slurry from spreading in the shallow part of the stratum and avoid the surface uplift value exceeding the limit; compared with the rotary spray method, this method has simple equipment, high construction efficiency, shortens the entire operation time and lower cost.
附图说明Description of drawings
构成本申请的一部分的说明书附图用来提供对本申请的进一步理解,本申请的示意性实施例及其说明用于解释本申请,并不构成对本申请的不当限定。The accompanying drawings that form a part of the present application are used to provide further understanding of the present application, and the schematic embodiments and descriptions of the present application are used to explain the present application and do not constitute improper limitations on the present application.
图1为本发明实施例一的盾构隧道富水砂层段目标加固区域平面图;Fig. 1 is the plan view of the target reinforcement area of the water-rich sand section of the shield tunnel according to the first embodiment of the present invention;
图2为本发明实施例一的盾构隧道富水砂层段目标加固区域纵剖面图;Fig. 2 is the longitudinal sectional view of the target reinforcement area of the water-rich sand section of the shield tunnel according to the first embodiment of the present invention;
图3为本发明实施例一的盾构隧道富水砂层段目标加固区域横剖面图;3 is a cross-sectional view of the target reinforcement area of the water-rich sand section of the shield tunnel according to
图4为本发明实施例一的构造止浆岩盘及前进式注浆原理图;FIG. 4 is a schematic diagram of the construction of the igneous stop rock plate and the progressive grouting according to the first embodiment of the present invention;
其中,1、盾构隧道,2、富水砂层,3、目标加固区域,4、注浆钻孔,5、车站围护结构,6、地表变形监测点,7、车站结构位移监测点,8、地表变形监测点布置范围;9、地表,10、土工布袋,11、孔口管,12、法兰盘,13、注浆阀门,14、注浆管,15、止浆岩盘,16、地层挤密区,17、第一注浆段,18、第二注浆段,19、第三注浆段。Among them, 1. Shield tunnel, 2. Water-rich sand layer, 3. Target reinforcement area, 4. Grouting drilling, 5. Station envelope structure, 6. Surface deformation monitoring point, 7. Station structure displacement monitoring point, 8. Layout range of surface deformation monitoring points; 9. Surface, 10, Geotextile bag, 11, Orifice pipe, 12, Flange plate, 13, Grouting valve, 14, Grouting pipe, 15, Stopping rock plate, 16 , stratum compaction area, 17, the first grouting section, 18, the second grouting section, 19, the third grouting section.
具体实施方式Detailed ways
应该指出,以下详细说明都是例示性的,旨在对本申请提供进一步的说明。除非另有指明,本文使用的所有技术和科学术语具有与本申请所属技术领域的普通技术人员通常理解的相同含义。It should be noted that the following detailed description is exemplary and intended to provide further explanation of the application. Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.
需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合;It should be noted that the terminology used herein is for the purpose of describing specific embodiments only, and is not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly dictates otherwise, the singular is intended to include the plural as well, furthermore, it is to be understood that when the terms "comprising" and/or "including" are used in this specification, it indicates that the presence of features, steps, operations, devices, components and/or combinations thereof;
为了方便叙述,本申请中如果出现“上”、“下”、“左”“右”字样,仅表示与附图本身的上、下、左、右方向一致,并不对结构起限定作用,仅仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的设备或元件必须具有特定的方位,以特定的方位构造和操作,因此不能理解为对本申请的限制。For the convenience of description, if the words "up", "down", "left" and "right" appear in this application, it only means that the directions of up, down, left and right are consistent with the drawings themselves, and do not limit the structure. It is to facilitate the description of the present invention and to simplify the description, rather than indicating or implying that the device or element referred to must have a particular orientation, be constructed and operate in a particular orientation, and therefore should not be construed as a limitation on the application.
术语解释部分:本申请中的术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或为一体;可以是机械连接,也可以是电连接,可以是直接连接,也可以是通过中间媒介间接相连,可以是两个元件内部连接,或者两个元件的相互作用关系,对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明的具体含义。Terminology explanation part: Terms such as "installation", "connection", "connection", "fixation" in this application should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integrated; It can be a mechanical connection, it can also be an electrical connection, it can be a direct connection, it can also be indirectly connected through an intermediate medium, it can be an internal connection between two elements, or an interaction relationship between two elements, for those of ordinary skill in the art. , the specific meanings of the above terms in the present invention can be understood according to specific situations.
正如背景技术所介绍的,现有技术中存在水泥浆液难以在富水砂层中有效留存、注浆过程中容易存在浆液上返跑浆等问题,为了解决如上的技术问题,本发明提出了一种适用于盾构端头富水砂层段的超前注浆加固方法。As described in the background art, in the prior art, it is difficult for the cement slurry to be effectively retained in the water-rich sand layer, and the slurry tends to run back and forth during the grouting process. In order to solve the above technical problems, the present invention proposes a An advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end.
实施例一:Example 1:
下面结合附图1-图4对本发明进行详细说明,具体的,结构如下:The present invention will be described in detail below in conjunction with accompanying drawings 1-4. Specifically, the structure is as follows:
本实施例提供了一种适用于盾构端头富水砂层段的超前注浆加固方法,能够实现盾构端头富水砂层2的有效加固,包括以下步骤:This embodiment provides an advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end, which can effectively reinforce the water-
步骤一:确定目标加固区域3并设计注浆钻孔4;Step 1: Determine the
为了保证隧道的开挖稳定性,目标加固区域的范围要大于某一限值,而从工程经济性考虑,目标加固区域的范围不能过大,因此,目标加固区域3的平面范围在垂直于盾构隧道1轴线方向上由盾构隧道1轮廓线外扩3~4m,在平行于盾构隧道1轴线方向上由车站围护结构5的边界平移6~8m。In order to ensure the excavation stability of the tunnel, the scope of the target reinforcement area should be larger than a certain limit, and considering the engineering economy, the scope of the target reinforcement area should not be too large. Therefore, the plane range of the
隧道开挖过程中拱顶部位的开挖安全风险要大于拱底部位的开挖安全风险,故目标加固区域的竖向范围由盾构隧道拱顶高度线上移的长度要大于由盾构隧道拱底高度线下移的长度。本实施例中,目标加固区域3的竖向范围为盾构隧道1拱顶高度线上移3~4m,盾构隧道1拱底高度线下移1~1.5m。注浆钻孔4采用梅花形布置,相邻注浆钻孔4间距一般为1.5~2.5m。In the process of tunnel excavation, the excavation safety risk at the top of the vault is greater than that at the bottom of the vault, so the vertical range of the target reinforcement area is moved from the height of the shield tunnel vault to the line longer than that of the shield tunnel. The length by which the base height line moves down. In this embodiment, the vertical range of the
步骤二:布置地表变形监测点6及车站结构位移监测点7;Step 2: Arrange surface deformation monitoring points 6 and station structure displacement monitoring points 7;
由于注浆过程导致的地表变形、车站结构位移在地表区域内是不均匀的,故地表变形监测点和车站结构位移监测点的布置要满足一定的密度要求,以达到监测精度要求。如图1所示,地表变形监测点布置范围8为目标加固区域3的平面范围外扩3m,相邻地表变形监测点6的间距为3~5m;车站结构位移监测点7布置于车站围护结构5上,相邻车站结构位移监测点7的间距为3~5m,且位移监测方向为水平方向。Because the surface deformation and station structure displacement caused by the grouting process are not uniform in the surface area, the layout of the surface deformation monitoring points and the station structure displacement monitoring points should meet certain density requirements to meet the monitoring accuracy requirements. As shown in Figure 1, the
步骤三:制作带有可膨胀土工布袋10的孔口管11;Step 3: making the
所述孔口管11的顶部安装法兰盘12,在本实施例中,法兰盘12与孔口管11焊接固定。孔口管11的直径可以根据实际情况选择,本实施例的孔口管11采用直径为108mm钢套管。所述法兰盘12上方安装有注浆阀门13。A
所述土工布袋10固定于孔口管11的外侧,孔口管11一侧焊接有注浆管14,所述注浆管14的末端伸入土工布袋10内部,注浆管14的顶端位于法兰盘12附近位置。注浆管14为钢制管,土工布袋10采用高强度土工布制成,土工布袋10两端绑扎固定在孔口管11上,其中一端绑扎在孔口管11末端位置。所述土工布袋长度为1.5~2.5m,周长为1~1.3m。The
步骤四:向地表9以下打设注浆钻孔4并在注浆钻孔4中下入孔口管11,使孔口管11的末端与目标加固区域3的上边界平齐。Step 4: Drill a
步骤五:对位于注浆钻孔4中的土工布袋10实施注浆,压密周围地层,构造止浆岩盘15。Step 5: Perform grouting on the
进一步的,采用速凝类浆液通过注浆管14对土工布袋10实施注浆,注浆压力2~3MPa,速凝类浆液的凝胶时间小于20s,浆液凝胶后体积稳定不收缩。采用速凝类浆液对土工布袋注浆的目的是减少土木布袋内浆液结石体的析水量,析水会导致浆液结石体的体积收缩,进而降低土工布袋对周围地层的挤压应力。采用速凝浆液就会有效缩短浆液凝胶时间,减少浆液析水量,保持浆液结石体体积稳定,维持土工布袋对周围地层的挤压应力。Further, the
通过土工布袋10的膨胀作用对周围地层施加挤压力,挤密周围地层形成地层挤密区16,地层被挤密后其强度远高于原始地层,进而抵抗浆液劈裂破坏的能力显著增强,当多个土工布袋10膨胀后,相邻地层挤密区互相搭接,会在目标加固区域3上方形成止浆岩盘15,起到防止浆液上返的作用,限制浆液扩散范围就位于目标加固区域3内,极大提高目标加固区域3内的浆液留存率。The expansive action of the
步骤六:采用速凝注浆材料对目标加固区域3实施前进式分段注浆,注浆过程中实时监测地表变形及车站结构位移;对地表变形进行实时监测目的是防止地表变形及市政管线变形超过规范允许值,对车站结构位移进行实时监测的目的是保证注浆对车站结构的不利影响控制在规范允许值范围内。Step 6: Use rapid-setting grouting material to implement forward segmented grouting in the
采用速凝类注浆材料的目的是利用其快速凝固特性,限制浆液扩散范围,将浆液尽可能多地留存在目标加固区域内,提高注浆加固效果。速凝注浆材料采用水泥-水玻璃双液浆,水泥浆液水灰质量比控制在W/C=0.8~1之间,水泥浆液与水玻璃浆液的双液体积比控制在C:S=3~4:1之间。The purpose of using the quick-setting grouting material is to use its rapid solidification characteristics to limit the diffusion range of the slurry, keep the slurry as much as possible in the target reinforcement area, and improve the grouting reinforcement effect. The quick-setting grouting material adopts cement-water glass double-liquid slurry, the water-cement mass ratio of cement slurry is controlled between W/C=0.8~1, and the double-liquid volume ratio of cement slurry and water glass slurry is controlled at C:S=3 ~4:1.
单次注浆的注浆结束标准采用“量、压、变形”三控的注浆结束标准,当注浆压力达到设计注浆终压而注浆量达到设计注浆量80%时停止注浆;当注浆量达到设计注浆量的1.5倍而注浆压力未达到设计注浆终压时停止注浆;当注浆压力未达到设计注浆终压、注浆量未达到设计注浆量,但地表变形或车站结构位移超过预警值时停止注浆。设计注浆终压可取1~1.5MPa,设计注浆量可取1.5~2.5m3,地表变形或车站结构位移预警值根据实际工程要求及当地规范要求确定。The grouting end standard of single grouting adopts the three-control grouting end standard of "quantity, pressure and deformation". When the grouting pressure reaches the design grouting final pressure and the grouting amount reaches 80% of the design grouting amount, the grouting is stopped. ; Stop grouting when the grouting amount reaches 1.5 times the design grouting amount and the grouting pressure does not reach the design grouting final pressure; when the grouting pressure does not reach the design grouting final pressure and the grouting amount does not reach the design grouting amount , but stop grouting when the surface deformation or the displacement of the station structure exceeds the warning value. Design grouting final pressure can be 1-1.5MPa, design grouting volume can be 1.5-2.5m 3 , surface deformation or station structure displacement early warning value is determined according to actual engineering requirements and local code requirements.
注浆钻孔4的注浆顺序为先外圈后内圈,先在外圈进行注浆,形成包围结构,限制后续注浆的浆液扩散范围,提高浆液在目标加固区域内的留存率。The grouting sequence of the
前进式分段注浆的分段长度为3~4m,通过前进式式注浆,先加固目标加固区3域的浅部地层,然后由浅入深,逐渐增加注浆深度,直至到达目标加固区域3底边界。如图4所示,先加固第一注浆段17,再依次加固第二注浆段18、第三注浆段19。由于前序注浆已将浅部富水砂层加固到位,因此后续注浆施工可避免富水砂层钻孔钻进困难、塌孔严重的问题。The segmental length of advance segmented grouting is 3-4m. Through advance type grouting, the shallow strata in the 3 areas of the target reinforcement area are first reinforced, and then the grouting depth is gradually increased from shallow to deep until the target reinforcement area is reached. 3 bottom borders. As shown in FIG. 4 , the
步骤七:通过地表变形及车站结构位移监测数据对注浆设计进行反馈调整。注浆全过程导致的地表隆起量总限值与车站结构位移总限值都是根据规范选取,单次注浆导致的地表隆起量限值与车站结构位移限值需要综合考虑注浆次数与地表隆起量总限值与车站结构位移总限值。当单次注浆导致的最大地表隆起变形量超过0.3cm或车站结构位移超过0.2cm时,适当降低设计注浆量。Step 7: Feedback and adjust the grouting design through the monitoring data of the surface deformation and the displacement of the station structure. The total limit of the surface uplift and the total displacement of the station structure caused by the whole grouting process are selected according to the specifications. The total limit of uplift and the total limit of station structure displacement. When the maximum surface uplift deformation caused by a single grouting exceeds 0.3 cm or the displacement of the station structure exceeds 0.2 cm, the design grouting amount should be appropriately reduced.
步骤八:完成所有注浆钻孔的注浆工作,并进行注浆效果检查。注浆效果检查包括压水试验、钻孔取芯及钻孔电视探查,当压水试验获得的加固后地层渗透系数<1×10-6cm/s,钻孔取芯率>50%,钻孔电视探查检查孔不存在塌孔时,认为注浆效果达到要求。Step 8: Complete the grouting work of all grouting holes, and check the grouting effect. The grouting effect inspection includes water pressure test, borehole coring and borehole video exploration. When the reinforced formation permeability coefficient obtained by the water pressure test is <1×10 -6 cm/s, the borehole coring rate is >50%, the drilling When there is no collapsed hole in the hole TV inspection inspection hole, it is considered that the grouting effect meets the requirements.
实施例二:Embodiment 2:
本实施例以某地铁工程区间隧道为例,采用盾构法开挖,盾构隧道1拱顶埋深10m,盾构隧道1开挖直径为6.5m,两条盾构隧道1净距为8m,在盾构端头部位,盾构隧道1全断面穿越富水砂层2,施工风险极高。In this example, an interval tunnel of a subway project is taken as an example. The shield tunnel method is used for excavation. The vault depth of
采用以下步骤进行加固:Use the following steps to reinforce:
步骤一:确定目标加固区域3并设计地表注浆钻孔4。目标加固区域3的平面范围在垂直于隧道轴线方向上由盾构隧道1轮廓线外扩4m,在平行于盾构隧道1轴线方向上由车站围护结构5边界平移8m,目标加固区域3的竖向范围为盾构隧道1拱顶高度线上移4m,盾构隧道1拱底高度线下移1m。地表注浆钻孔4采用梅花形布置,孔间距设计为2m。Step 1: Determine the
步骤二:布置地表变形监测点6及车站结构位移监测点7。地表变形监测点布置范围8为目标加固区域3的平面范围外扩3m,地表变形监测点6的间距为5m。车站结构位移监测点7布置于车站围护结构5上,车站结构位移监测点7的间距为5m,位移监测方向为水平方向。Step 2: Arrange surface deformation monitoring points 6 and station structure displacement monitoring points 7. The
步骤三:制作带土工布袋10的孔口管11,在孔口管11侧面焊接注浆管14,注浆管14的端部伸入土工布袋10内部。孔口管11采用直径108mm钢套管,孔口管11上部焊接有法兰盘12,法兰盘12连接注浆阀门13。土工布袋10采用高强度土工布制成,土工布袋10两端被绑扎固定在孔口管11上,其中一端绑扎在孔口管11端部(末端),土工布袋10的长度为2m,土工布袋10膨胀后的周长为1.2m。Step 3: Making the
步骤四:打设注浆钻孔4并下入孔口管11。孔口管11的深度直接到目标加固区域3上边界。Step 4: Drill the
步骤五:对所有注浆钻孔4的土工布袋10实施注浆,压密周围地层,构造止浆岩盘15。采用速凝类浆液通过注浆管14对所有注浆钻孔4的土工布袋10实施注浆,注浆压力2~3MPa,速凝类浆液要求凝胶时间<20s。本实施例中的速凝类浆液采用水泥-水玻璃浆液,水泥浆液水灰质量比为W/C=1,水泥浆液与水玻璃浆液的双液体积比为C:S=4:1。Step 5: Perform grouting on the
通过土工布袋10的膨胀作用对周围地层施加挤压力,挤密周围地层形成地层挤密区16,地层被挤密后其强度远高于原始地层,进而抵抗浆液劈裂破坏的能力显著增强,当多个土工布袋10膨胀后,相邻地层挤密区16互相搭接,会在目标加固区域3上方形成止浆岩盘15,起到防止浆液上返的作用,限制浆液扩散范围就位于目标加固区域3内,极大提高目标加固区域3内的浆液留存率。The expansive action of the
步骤六:采用速凝注浆材料对目标加固区域3实施前进式分段注浆,注浆过程中对地表变形及车站结构位移进行实时监测。Step 6: Use the fast-setting grouting material to implement forward segmented grouting to the
注浆所用材料为速凝类注浆材料,可采用水泥-水玻璃双液浆,水泥浆液水灰质量比为W/C=1,水泥浆液与水玻璃浆液的双液体积比为C:S=4:1。注浆过程中对地表变形及车站结构位移进行实时监测,防止地表变形及市政管线变形超过规范允许值,同时保证注浆对车站结构的不利影响控制在规范允许值范围内。The materials used for grouting are quick-setting grouting materials, and cement-water glass double-liquid slurry can be used. = 4:1. During the grouting process, the surface deformation and the displacement of the station structure are monitored in real time to prevent the surface deformation and the deformation of the municipal pipeline from exceeding the allowable value of the specification, and at the same time to ensure that the adverse effect of grouting on the station structure is controlled within the allowable value of the specification.
单次注浆的注浆结束标准采用“量、压、变形”三控的注浆结束标准,当注浆压力达到设计注浆终压而注浆量达到设计注浆量80%时停止注浆;当注浆量达到设计注浆量的1.5倍而注浆压力未达到设计注浆终压时停止注浆;当注浆压力未达到设计注浆终压、注浆量未达到设计注浆量,但地表变形或车站结构位移超过预警值时停止注浆。设计注浆终压为1.2MPa,设计注浆量取2.5m3,地表变形或车站结构位移预警值根据实际工程要求及当地规范要求确定,本实施例中地表变形位移预警值为1.5cm,车站结构位移预警值为0.5cm,前进式分段注浆的分段长度为4m。The grouting end standard of single grouting adopts the three-control grouting end standard of "quantity, pressure and deformation". When the grouting pressure reaches the design grouting final pressure and the grouting amount reaches 80% of the design grouting amount, the grouting is stopped. ; Stop grouting when the grouting amount reaches 1.5 times the design grouting amount and the grouting pressure does not reach the design grouting final pressure; when the grouting pressure does not reach the design grouting final pressure and the grouting amount does not reach the design grouting amount , but stop grouting when the surface deformation or the displacement of the station structure exceeds the warning value. The design final pressure of grouting is 1.2MPa, and the design grouting amount is 2.5m 3 . The early warning value of surface deformation or station structure displacement is determined according to actual engineering requirements and local code requirements. The early warning value of structural displacement is 0.5cm, and the segmental length of forward segmented grouting is 4m.
步骤七:通过地表变形监测数据及车站结构位移监测数据对注浆设计进行反馈调整。当单次注浆导致的最大地表隆起变形量超过0.3cm,或导致的车站结构位移超过0.2cm时,适当降低设计注浆量。Step 7: Feedback and adjust the grouting design based on the surface deformation monitoring data and the station structure displacement monitoring data. When the maximum surface uplift deformation caused by a single grouting exceeds 0.3 cm, or the resulting displacement of the station structure exceeds 0.2 cm, the design grouting amount should be appropriately reduced.
步骤八:完成所有注浆钻孔的注浆工作,并进行注浆效果检查。当压水试验获得的加固后地层渗透系数<1×10-6cm/s,钻孔取芯率>50%,钻孔电视探查检查孔不存在塌孔时,认为注浆效果达到要求。本实施例中,注浆加固结束后地层平均渗透系数为5.2×10-7cm/s,检查孔的钻孔取芯率普遍在65%以上,检查孔基本不存在塌孔现象,注浆效果达到目标要求。Step 8: Complete the grouting work of all grouting holes, and check the grouting effect. When the reinforced formation permeability coefficient obtained from the pressurized water test is less than 1×10 -6 cm/s, the drilling core rate is more than 50%, and there is no collapsed hole in the borehole TV inspection inspection hole, the grouting effect is considered to meet the requirements. In this embodiment, the average permeability coefficient of the stratum after grouting reinforcement is 5.2×10 -7 cm/s, the core rate of the inspection hole is generally above 65%, and the inspection hole basically does not have hole collapse phenomenon, and the grouting effect meet the target requirements.
以上所述仅为本申请的优选实施例而已,并不用于限制本申请,对于本领域的技术人员来说,本申请可以有各种更改和变化。凡在本申请的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本申请的保护范围之内。The above descriptions are only preferred embodiments of the present application, and are not intended to limit the present application. For those skilled in the art, the present application may have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of this application shall be included within the protection scope of this application.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911095271.9A CN110700842A (en) | 2019-11-11 | 2019-11-11 | An advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911095271.9A CN110700842A (en) | 2019-11-11 | 2019-11-11 | An advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110700842A true CN110700842A (en) | 2020-01-17 |
Family
ID=69205701
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911095271.9A Pending CN110700842A (en) | 2019-11-11 | 2019-11-11 | An advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110700842A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111878084A (en) * | 2020-07-15 | 2020-11-03 | 中铁十八局集团有限公司 | Rapid treatment method for controlling surface subsidence by using large-diameter shield construction in case of meeting stratum funnel |
CN112177620A (en) * | 2020-08-17 | 2021-01-05 | 山东大学 | A construction method for underground engineering TBM to cross complex soft and hard composite strata |
CN113417673A (en) * | 2021-07-22 | 2021-09-21 | 中交三航局第三工程有限公司 | Method for filling and grouting behind ground surface wall of tunnel or subway station |
CN116025367A (en) * | 2022-10-28 | 2023-04-28 | 中国海洋大学 | Pre-applied horizontal stress, induced splitting and localized combined grouting reinforcement device and process |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102011596A (en) * | 2010-11-29 | 2011-04-13 | 中铁三局集团有限公司 | Shield originating or receiving end tunnel portal maintenance process |
CN202866826U (en) * | 2012-10-25 | 2013-04-10 | 中铁二院工程集团有限责任公司 | Shield tunnel working well outer end socket stratum reinforced structure |
CN104453943A (en) * | 2014-10-27 | 2015-03-25 | 山东科技大学 | Method for controlling water-rich fractured rock mass comprehensive grouting under effective sealing batholite shortage condition |
CN105155563A (en) * | 2015-08-18 | 2015-12-16 | 山东大学 | Reinforcing and treating method for water burst of soft-flow muddy stratum of foundation pit |
CN106194218A (en) * | 2016-08-30 | 2016-12-07 | 中铁第四勘察设计院集团有限公司 | The shield end soil body reinforcement system in high water head deep and thick sand area |
CN106593470A (en) * | 2016-12-08 | 2017-04-26 | 中铁第勘察设计院集团有限公司 | High-permeability water-rich sand shield terminal reinforcing system and construction method thereof |
CN106640120A (en) * | 2016-10-31 | 2017-05-10 | 彭峰 | Ground-surface fixed-point deep hole layered grouting construction method |
CN107605498A (en) * | 2017-11-02 | 2018-01-19 | 中铁十局集团有限公司 | Rich water sand-pebble layer shield tunnel termination horizontal grouting ruggedized construction construction method |
CN108678781A (en) * | 2018-06-12 | 2018-10-19 | 中铁二十局集团轨道交通工程有限公司 | One kind closing on river shield launching end stratum consolidation method |
CN109083649A (en) * | 2018-10-11 | 2018-12-25 | 中国石油大学(华东) | It is applicable in the water-rich sand layer pre-grouting reinforcement means of complicated urban environment subway tunnel |
-
2019
- 2019-11-11 CN CN201911095271.9A patent/CN110700842A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102011596A (en) * | 2010-11-29 | 2011-04-13 | 中铁三局集团有限公司 | Shield originating or receiving end tunnel portal maintenance process |
CN202866826U (en) * | 2012-10-25 | 2013-04-10 | 中铁二院工程集团有限责任公司 | Shield tunnel working well outer end socket stratum reinforced structure |
CN104453943A (en) * | 2014-10-27 | 2015-03-25 | 山东科技大学 | Method for controlling water-rich fractured rock mass comprehensive grouting under effective sealing batholite shortage condition |
CN105155563A (en) * | 2015-08-18 | 2015-12-16 | 山东大学 | Reinforcing and treating method for water burst of soft-flow muddy stratum of foundation pit |
CN106194218A (en) * | 2016-08-30 | 2016-12-07 | 中铁第四勘察设计院集团有限公司 | The shield end soil body reinforcement system in high water head deep and thick sand area |
CN106640120A (en) * | 2016-10-31 | 2017-05-10 | 彭峰 | Ground-surface fixed-point deep hole layered grouting construction method |
CN106593470A (en) * | 2016-12-08 | 2017-04-26 | 中铁第勘察设计院集团有限公司 | High-permeability water-rich sand shield terminal reinforcing system and construction method thereof |
CN107605498A (en) * | 2017-11-02 | 2018-01-19 | 中铁十局集团有限公司 | Rich water sand-pebble layer shield tunnel termination horizontal grouting ruggedized construction construction method |
CN108678781A (en) * | 2018-06-12 | 2018-10-19 | 中铁二十局集团轨道交通工程有限公司 | One kind closing on river shield launching end stratum consolidation method |
CN109083649A (en) * | 2018-10-11 | 2018-12-25 | 中国石油大学(华东) | It is applicable in the water-rich sand layer pre-grouting reinforcement means of complicated urban environment subway tunnel |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111878084A (en) * | 2020-07-15 | 2020-11-03 | 中铁十八局集团有限公司 | Rapid treatment method for controlling surface subsidence by using large-diameter shield construction in case of meeting stratum funnel |
CN111878084B (en) * | 2020-07-15 | 2022-09-13 | 中铁十八局集团有限公司 | Rapid treatment method for controlling surface subsidence by using large-diameter shield construction in case of meeting stratum funnel |
CN112177620A (en) * | 2020-08-17 | 2021-01-05 | 山东大学 | A construction method for underground engineering TBM to cross complex soft and hard composite strata |
CN112177620B (en) * | 2020-08-17 | 2021-09-21 | 山东大学 | Construction method for underground engineering TBM to penetrate complex soft and hard composite stratum |
CN113417673A (en) * | 2021-07-22 | 2021-09-21 | 中交三航局第三工程有限公司 | Method for filling and grouting behind ground surface wall of tunnel or subway station |
CN116025367A (en) * | 2022-10-28 | 2023-04-28 | 中国海洋大学 | Pre-applied horizontal stress, induced splitting and localized combined grouting reinforcement device and process |
CN116025367B (en) * | 2022-10-28 | 2023-11-21 | 中国海洋大学 | Pre-applied horizontal stress, induced splitting and localized combined grouting reinforcement device and process |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110230309B (en) | Karst area bridge karst cave pile foundation construction method | |
CN109162722B (en) | Advanced compaction grouting reinforcement method for loose and weak strata suitable for shallow buried tunnels | |
CN105041325B (en) | Construction method of high-tension water-rich extra-large-section weak breccia tunnel | |
CN205172598U (en) | Pipe curtain spouts a supporting construction soon | |
CN110700842A (en) | An advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end | |
CN105155563A (en) | Reinforcing and treating method for water burst of soft-flow muddy stratum of foundation pit | |
CN109083649B (en) | It is applicable in the water-rich sand layer pre-grouting reinforcement means of complicated urban environment subway tunnel | |
CN105350519A (en) | Advanced pre-grouting device suitable for shallow-buried tunnel construction in sand soil layer and construction process | |
CN105200978B (en) | A forward-type localized double-fluid grouting device and construction method | |
CN101525881B (en) | Structure of karst strata pile holes protecting wall and method for constructing pile holes | |
CN104631480B (en) | Adopt the method that jet grouting pile driving machine carries out water seal for deep foundation pit curtain construction | |
CN101929340A (en) | Construction technology of pre-grouting and advance support for pipe shed in horizontal inclined roadway in coal mine | |
CN101560764B (en) | Method for calking exploratory hole by intermittent high-pressure rotary jet grouting | |
CN108119143A (en) | A kind of vertical shaft working surface cement soluble glass paste combines grouting method with chemical grout double-round curtain | |
CN106401600B (en) | Strengthen Treatment Methods and supporting construction in tunnel based on molten chamber position | |
CN103089276A (en) | Deep-shallow hole and high-low pressure coupling grouting technology | |
CN103696416B (en) | A kind of method for processing foundation | |
CN105731978B (en) | A kind of grouting serous fluid and grouting method for fine sand layer jacking culvert solidifying of the working face | |
CN110644539A (en) | Active seepage-proofing control method for subway station structure seepage diseases and underground seepage-proofing body | |
CN105443098A (en) | Coal mine underground borehole segmented fixed hydraulic fracturing fixation hole device and method | |
CN114108609B (en) | A construction method for multi-stage and segmental precise filling deep piles in goaf | |
CN112855225B (en) | Soft rock tunnel supporting construction method with high safety | |
CN112796807B (en) | A radial single-end double-expansion grouting bolt for broken rock tunnel | |
CN119122545A (en) | Quick construction method for urban large-section ultra-shallow buried underground tunnel proximity | |
CN108914911A (en) | A kind of stratum prestress advanced excavation stability control method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200117 |
|
RJ01 | Rejection of invention patent application after publication |