CN101929340A - Pre-grouting advance support construction process for pipe shed of underground flat inclined roadway of coal mine - Google Patents
Pre-grouting advance support construction process for pipe shed of underground flat inclined roadway of coal mine Download PDFInfo
- Publication number
- CN101929340A CN101929340A CN2009102277906A CN200910227790A CN101929340A CN 101929340 A CN101929340 A CN 101929340A CN 2009102277906 A CN2009102277906 A CN 2009102277906A CN 200910227790 A CN200910227790 A CN 200910227790A CN 101929340 A CN101929340 A CN 101929340A
- Authority
- CN
- China
- Prior art keywords
- grouting
- hole
- pipe
- construction
- pipe shed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 63
- 238000000034 method Methods 0.000 title claims abstract description 28
- 239000003245 coal Substances 0.000 title claims abstract description 25
- 230000008569 process Effects 0.000 title claims abstract description 18
- 238000005553 drilling Methods 0.000 claims abstract description 31
- 238000009434 installation Methods 0.000 claims abstract description 5
- 239000002002 slurry Substances 0.000 claims description 24
- 239000011435 rock Substances 0.000 claims description 17
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 15
- 239000002689 soil Substances 0.000 claims description 13
- 239000011148 porous material Substances 0.000 claims description 6
- 230000002787 reinforcement Effects 0.000 claims description 6
- 238000002347 injection Methods 0.000 claims description 5
- 239000007924 injection Substances 0.000 claims description 5
- 230000002093 peripheral effect Effects 0.000 claims description 5
- 229920001971 elastomer Polymers 0.000 claims description 4
- 238000005520 cutting process Methods 0.000 claims description 3
- 239000004575 stone Substances 0.000 claims description 3
- 239000004115 Sodium Silicate Substances 0.000 claims description 2
- 229910052911 sodium silicate Inorganic materials 0.000 claims description 2
- 238000007569 slipcasting Methods 0.000 claims 10
- 239000002699 waste material Substances 0.000 claims 4
- 229910000712 Boron steel Inorganic materials 0.000 claims 2
- 239000004744 fabric Substances 0.000 claims 2
- 238000011010 flushing procedure Methods 0.000 claims 2
- 238000004140 cleaning Methods 0.000 claims 1
- 239000012467 final product Substances 0.000 claims 1
- 239000012530 fluid Substances 0.000 claims 1
- 238000009740 moulding (composite fabrication) Methods 0.000 claims 1
- 230000003014 reinforcing effect Effects 0.000 claims 1
- 239000011440 grout Substances 0.000 abstract description 42
- 238000009412 basement excavation Methods 0.000 abstract description 16
- 238000005516 engineering process Methods 0.000 abstract description 8
- 238000005406 washing Methods 0.000 abstract description 7
- 230000008901 benefit Effects 0.000 abstract description 5
- 239000007787 solid Substances 0.000 description 9
- 239000004568 cement Substances 0.000 description 7
- 239000007788 liquid Substances 0.000 description 7
- 239000000463 material Substances 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 5
- 238000009792 diffusion process Methods 0.000 description 5
- 238000005065 mining Methods 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 239000007921 spray Substances 0.000 description 4
- 230000000903 blocking effect Effects 0.000 description 3
- 239000003795 chemical substances by application Substances 0.000 description 3
- 235000019353 potassium silicate Nutrition 0.000 description 3
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 description 3
- 238000007711 solidification Methods 0.000 description 3
- 230000008023 solidification Effects 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 230000008859 change Effects 0.000 description 2
- 238000005755 formation reaction Methods 0.000 description 2
- 230000006872 improvement Effects 0.000 description 2
- 210000001503 joint Anatomy 0.000 description 2
- 238000005507 spraying Methods 0.000 description 2
- 238000010408 sweeping Methods 0.000 description 2
- 238000004078 waterproofing Methods 0.000 description 2
- 239000011398 Portland cement Substances 0.000 description 1
- 239000000654 additive Substances 0.000 description 1
- 230000000996 additive effect Effects 0.000 description 1
- 238000004873 anchoring Methods 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 230000002706 hydrostatic effect Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 229920006395 saturated elastomer Polymers 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
煤矿井下平斜巷管棚预注浆超前支护施工工艺,包括以下步骤:(1)止浆墙的施工;(2)管棚钻孔施工包括布孔,造孔;(3)管棚钻孔洗孔施工;(4)管棚安装施工;(5)管棚预注浆施工;(6)然后按照步骤(2)~(5)循环,施工一个管棚孔,安装一个孔,注浆一个孔,直至注浆结束;工作面管棚预注浆9m,掘进6m、预留3m超前距或者掘进7m、预留2m超前距;向前掘进后,再次管棚预注浆时,按步骤(2)~(5)施工时,不再施工止浆墙,在工作面迎头直接喷射混凝土即可,直至巷道施工完该区段为止。本发明工艺结构简单,施工速度快,成本低,安全可靠,风险小,还能确保巷道质量,经济效益极为明显。The construction technology of pre-grouting and advanced support for pipe sheds in horizontal and inclined lanes in coal mines includes the following steps: (1) construction of grout-stop walls; (2) pipe shed drilling construction including hole layout and hole making; (3) pipe shed drilling Hole washing construction; (4) Pipe shed installation and construction; (5) Pipe shed pre-grouting construction; (6) Then follow the steps (2) to (5) cycle to construct a pipe shed hole, install a hole, and grout One hole until the grouting is completed; pre-grouting of the pipe shed on the working face is 9m, excavation is 6m, and a 3m advance distance is reserved; or excavation is 7m, and a 2m advance distance is reserved; (2)~(5) During the construction, the grout stop wall is no longer constructed, and the concrete can be sprayed directly on the working face until the section of the roadway is completed. The invention has the advantages of simple process structure, fast construction speed, low cost, safety and reliability, low risk, and can ensure the quality of the roadway, and the economic benefit is extremely obvious.
Description
技术领域technical field
本发明涉及一种煤矿井下平斜巷穿过煤层、急倾斜煤层、软岩层、构造破碎带以及地表土层明斜井穿过大型建筑物、主要铁路运输线及河床段,使用工作面管棚预注浆超前支护施工工艺。 The invention relates to a coal mine underground level inclined roadway which passes through coal seams, steeply inclined coal seams, soft rock layers, structural fracture zones and surface soil layers. Pre-grouting advanced support construction technology. the
背景技术Background technique
煤炭是我国工业和国民经济发展的主要能源。目前我国浅部煤炭资源因持续开采已大量减少,矿井的开采深度越来越深。我国的煤炭资源埋深在1000m以下的为2.95万亿吨,占煤炭资源总量的53%。目前煤矿开采深度以每年8-12m的速度增加。目前很多已有多个工作面进入到1000m到1500m的深度。深部矿井与地面“三下工程”(地面表土层过建筑群、过铁路段及过河床段等。)的开发和利用是我国矿业今后的发展趋势。矿井深部施工过程中遇到的煤层、急倾斜煤层、软岩层、构造破碎带以及表土层明斜井过大型建筑物、铁路段、河床段等,一旦发生顶板冒顶事故,非常危险。如何快速、安全通过等一系列科学和技术问题,已成为矿业界的重大理论和技术课题。 Coal is the main energy source for the development of my country's industry and national economy. At present, my country's shallow coal resources have been greatly reduced due to continuous mining, and the mining depth of mines is getting deeper and deeper. my country's coal resources buried below 1000m are 2.95 trillion tons, accounting for 53% of the total coal resources. At present, the mining depth of coal mines is increasing at a rate of 8-12m per year. At present, many working faces have entered the depth of 1000m to 1500m. The development and utilization of deep mines and the "three lower projects" on the ground (ground topsoil passing through building groups, crossing railway sections and riverbed sections, etc.) is the future development trend of my country's mining industry. Coal seams, steeply inclined coal seams, soft rock strata, structural fracture zones, and topsoil exposed inclined shafts passing through large buildings, railway sections, riverbed sections, etc. encountered during deep mine construction will be very dangerous in the event of a roof fall accident. A series of scientific and technical issues such as how to pass through quickly and safely have become major theoretical and technical issues in the mining industry. the
发明内容Contents of the invention
本发明目的在于提供一种煤矿井下平斜巷管棚预注浆超前支护施工工艺,在揭过煤层、急倾斜煤层、软岩层、构造破碎带及表土层明斜井等,通过工作面管棚式预注浆,可以有效防止巷道坍塌、大面积冒顶、片帮,杜绝事故发生;施工工艺结构简单,施工速度快,成本低,安全可靠,风险小,还能确保巷道质量。 The purpose of the present invention is to provide a construction technology of pre-grouting and advanced support for pipe sheds in flat inclined roadways in coal mines. Shed-type pre-grouting can effectively prevent roadway collapse, large-area roof caving, and sidewalls, and prevent accidents; the construction process is simple in structure, fast in construction speed, low in cost, safe and reliable, with low risk, and can also ensure the quality of the roadway. the
为了实现上述目的,本发明采用如下技术方案:。煤矿井下平斜巷管棚预注浆超前支护施工工艺,包括以下步骤: In order to achieve the above object, the present invention adopts the following technical solutions:. The construction technology of pre-grouting and advanced support of pipe shed in horizontal inclined roadway in coal mine includes the following steps:
(1)止浆墙的施工:把掘进工作面前做钻场,按设计尺寸向巷道轮廓线外扩挖沟槽,垒砌一道止浆墙,止浆墙两边用料石垒砌,中间空槽浇筑混凝土;垒砌前,将巷道出水的地方,安装引水管将水导出;止浆墙垒砌过程中,根据设计方位、倾角,在巷道荒断面外250~400mm之间预埋孔口管,孔口管外露150mm,距法兰盘100mm处,事先焊接一个带有丝扣的接头,止浆墙垒砌好后喷射砼把巷道与止浆墙周边衔接的处填平,凝固24小时后,先把预埋导水的引水管注浆封堵,加固止浆墙。 (1) Construction of the slurry wall: use the front of the excavation work as a drilling site, expand the trench to the outside of the roadway outline according to the design size, and build a slurry wall. The two sides of the slurry wall are built with material stones, and the middle is empty Concrete pouring; before building, install water diversion pipes at the water outlet of the roadway to lead the water out; during the construction of the grout wall, according to the design orientation and inclination angle, the orifice pipe is pre-buried between 250-400mm outside the barren section of the roadway, The orifice pipe is exposed 150mm, 100mm away from the flange, and a joint with a screw is welded in advance. After the grout wall is built, spray concrete to fill the joint between the roadway and the grout wall. After 24 hours of solidification, First, grout the pre-embedded water diversion pipe to seal, and strengthen the grout-stop wall. the
(2)管棚钻孔施工:在掘进工作面拱部荒断面外300~500mm周边均匀布置管棚钻孔,管棚孔间距为250~400mm,深度为9m; (2) Pipe shed drilling construction: uniformly arrange pipe shed drilling holes around 300-500mm outside the barren section of the arch of the excavation face, the spacing of the pipe shed holes is 250-400mm, and the depth is 9m;
布孔:管棚预注浆采用“周边孔与中部孔”相结合的布孔法,“周边孔”使巷道净断面外5m范围内固结成整体,“中部孔”对整体进行补强注浆加固;将地表土层破碎带岩层裂隙用浆液充填饱满固结成坚固整体,把管棚与巷道周边围岩固结成坚固整体; Hole layout: The pre-grouting of the pipe shed adopts the hole layout method combining "peripheral holes and middle holes". Slurry reinforcement: fill the cracks in the broken surface soil layer with grout and consolidate them into a solid whole, and consolidate the pipe shed and the surrounding rock around the roadway into a solid whole;
造孔:施工止浆墙的同时,按设计方位、倾角预埋好“周边孔”的孔口管;“中部孔”不预埋孔口管,直接在墙上施工;搭好工作台,把钻机吊运到工作台上固定牢固;施工钻孔,遇到破碎泥土层不进时,反复扫孔,反复注浆,直至施工至设计深度; Hole making: While constructing the slurry wall, the orifice pipes of the "peripheral holes" are pre-embedded according to the design orientation and inclination angle; the "middle hole" does not pre-embed the orifice pipes, and is directly constructed on the wall; the workbench is set up, and the The drilling rig is hoisted to the workbench and fixed firmly; when the construction drilling fails to enter the broken soil layer, the hole is repeatedly swept and grouted repeatedly until the construction reaches the design depth;
(3)管棚钻孔洗孔施工:造孔达到设计深度后,连接洗孔管路,用高压水把钻孔内泥浆及钻屑清洗干净; (3) Drilling and washing construction of the pipe shed: After the hole reaches the design depth, connect the washing pipeline, and clean the mud and drilling cuttings in the drilling with high-pressure water;
(4)管棚安装施工:把管棚钢管慢慢下到孔底,把预埋孔口管上的法兰盘与管棚钢管上的子母扣法兰盘对接严实,用螺栓固定;其余注浆钻孔成孔后, 安装伸缩型封孔器,并把封孔器上的大螺母拧紧,使胶垫与钻孔周边充分啮合密实,把管固定牢固; (4) Pipe shed installation and construction: Slowly lower the pipe shed steel pipe to the bottom of the hole, connect the flange plate on the pre-buried orifice pipe with the snap button flange plate on the pipe shed steel pipe tightly, and fix it with bolts; the rest After the hole is drilled by grouting, install the telescopic hole sealer, and tighten the big nut on the hole sealer, so that the rubber pad and the periphery of the drilled hole are fully meshed and dense, and the pipe is fixed firmly;
(5)管棚预注浆施工:安装注浆管路,根据注浆情况随时调整流量、浆液浓度,注浆时让管棚孔中浆液顺着钻孔向外回浆,使管棚管周围充满浆液与注浆后土层或破碎带形成坚固的整体,注浆压力达到设计注浆压力,即可停止注浆; (5) Pre-grouting construction of the pipe shed: install the grouting pipeline, adjust the flow rate and the concentration of the slurry at any time according to the grouting situation, and let the grout in the pipe shed hole return to the outside along the drill hole during grouting, so that the surrounding area of the pipe shed pipe Filled with grout and the soil layer or broken zone after grouting forms a solid whole, and the grouting pressure can reach the design grouting pressure, and the grouting can be stopped;
(6)然后按照步骤(2)~(5)循环,施工一个管棚孔,安装一个孔,注浆一个孔,直至注浆结束;工作面管棚预注浆9m,掘进6m、预留3m超前距或者掘进7m、预留2m超前距;向前掘进后,再次管棚预注浆时,按步骤(2)~(5)施工时,不再施工止浆墙,在工作面迎头直接喷射混凝土即可,直至巷道施工完该区段为止。 (6) Then cycle according to steps (2) to (5), construct a pipe shed hole, install a hole, and grout a hole until the grouting is completed; the working surface pipe shed pre-grouting 9m, excavation 6m, reserve 3m Advance distance or excavation 7m, reserve 2m advance distance; after forward excavation, when pipe shed pre-grouting again, when constructing according to steps (2) to (5), do not construct grout stop wall, and spray directly on the working face Concrete will suffice until the section of the roadway is completed. the
所述的步骤(5)出现跑、漏浆的处理:在注浆过程中,发现跑、漏浆现象,可根据现场跑、漏浆情况采取糊、停、点注的方法处理,以减少浆液损失。 The treatment of grout running and leaking in the step (5): in the process of grouting, if grout running and leaking are found, the methods of paste, stop and spot injection can be adopted according to the on-site running and grout leakage, so as to reduce the amount of grout loss. the
所述的步骤(5)中设计的注浆压力为8~10MPa。 The designed grouting pressure in the step (5) is 8-10 MPa. the
所述的步骤(2)中在掘进工作面拱部荒断面外400~500mm周边均匀布置管棚钻孔,管棚孔间距为300~400mm。 In the step (2), pipe shed drilling holes are evenly arranged around 400-500 mm outside the barren section of the arch of the excavation face, and the distance between the pipe shed holes is 300-400 mm. the
所述的步骤(2)中在掘进工作面拱部荒断面外300~400mm周边均匀布置管棚钻孔,管棚孔间距为250~300mm。 In the step (2), pipe shed drilling holes are evenly arranged around 300-400 mm outside the barren section of the arch of the excavation face, and the distance between the pipe shed holes is 250-300 mm. the
所述的步骤(5)中的注浆利用双液注浆原理采用水泥-水玻璃浆液把巷道周边5m范围内孔隙充填饱满。 The grouting in the step (5) utilizes the principle of two-liquid grouting and uses cement-sodium silicate grout to fill the pores within 5m around the roadway. the
本发明具有以下优点: The present invention has the following advantages:
1.本发明的煤矿井下平斜巷工作面管棚式预注浆超前支护,在揭过煤层、急倾斜煤层、软岩层、构造破碎带及地表土层明斜井通过大型建筑物、主要铁路 干线与河床段。在掘进施工中,预防巷道顶板大面积坍塌及严重抽帮、抽顶,管棚孔间距按250~400mm控制,深度按9m施工,安装9m管棚管,注双液浆加固,把巷道周边的裂隙、孔隙充填饱满,并与周边固结成整体,增大了巷道的承载能力,提高围岩稳定性。避免了巷道掘进过程中,整体坍塌、大面积冒顶及片帮。 1. The pipe shed type pre-grouting advanced support of the working face of the horizontal inclined roadway in the coal mine of the present invention can pass through large buildings, main Railway trunk line and riverbed section. During the excavation construction, to prevent large-scale collapse of the roof of the roadway and serious side and roof withdrawal, the distance between the pipe shed holes is controlled at 250-400mm, the depth is 9m, the 9m pipe shed pipe is installed, and double slurry is injected for reinforcement. The fissures and pores are fully filled and consolidated with the surrounding area as a whole, which increases the bearing capacity of the roadway and improves the stability of the surrounding rock. It avoids the overall collapse, large-area roof caving and sidewalls during the roadway excavation process. the
2.煤矿井下平斜巷工作面管棚式预注浆超前支护施工工艺结构简单,施工速度快,成本低,安全可靠,风险小,还能确保巷道质量。经济效益极为明显,由此带来的安全所实现的社会效益则更加可观。 2. The construction process of tube shed type pre-grouting advance support on the working face of horizontal and inclined roadways in coal mines is simple in structure, fast in construction speed, low in cost, safe and reliable, with low risk, and can also ensure the quality of the roadway. The economic benefit is extremely obvious, and the social benefit realized by the security brought about by it is even more considerable. the
步骤(1)中,法兰盘用途:与管棚管焊接的同等直径对接固定,封闭孔口管。预埋孔口管作用:防止注浆时管棚管窜出。带丝扣的接头用途:上面有直径25mm的阀门,注浆刚开始时起排气作用,空气排完后出浆时关闭上面阀门。 In the step (1), the purpose of the flange plate is to butt joint and fix with the same diameter welded with the pipe shed pipe, and to close the orifice pipe. Function of pre-buried orifice pipe: to prevent the pipe shed pipe from escaping during grouting. The purpose of the joint with threaded buckle: there is a valve with a diameter of 25mm on it, which acts as an exhaust gas at the beginning of the grouting, and closes the upper valve when the grout is discharged after the air is exhausted. the
步骤(5)中,注浆过程中,压力小进浆顺畅,说明烈、空隙大,可注单液浆,增大液浆浓度,逐渐升压,增大注浆流量,尽快用高压稠浆液将裂隙中的含水量换出去,随着浆液源源不断注入注浆体。压力上升快说明注浆体大裂隙已基本注实,为了注浆体内充满浆液达到饱和状态,可减小浆液浓度,减小流量,提高压力,使注浆体内细小空裂隙充满浆液。 In step (5), during the grouting process, if the pressure is low and the grout enters smoothly, it means that the grout is strong and the gap is large. You can inject a single grout, increase the grout concentration, gradually increase the pressure, increase the grouting flow rate, and use high-pressure thick grout as soon as possible. Change the water content in the cracks, and inject the grouting body continuously with the grout. The rapid pressure rise indicates that the large fissures of the grouting body have been basically filled. In order to fill the grouting body with grout and reach a saturated state, the concentration of the grout can be reduced, the flow rate can be reduced, and the pressure can be increased to fill the small empty fissures in the grouting body with grout. the
具体实施方式Detailed ways
本发明的煤矿井下平斜巷工作面管棚式预注浆超前支护施工工艺包括止浆墙施工,管棚钻孔施工,管棚钻孔洗孔施工,管棚制作安装施工及管棚预注浆施工。 The pipe shed type pre-grouting advanced support construction technology of the working face of the flat and inclined roadway in the coal mine of the present invention includes the construction of the grout stop wall, the drilling construction of the pipe shed, the drilling and washing construction of the pipe shed, the fabrication and installation of the pipe shed and the prefabrication of the pipe shed. Grouting construction. the
作为本发明专利技术的一种改进,在揭过煤层、急倾斜煤层、软岩层、构造破碎带巷道工作面拱部荒断面外400~500mm周边布孔,管棚孔间距300~400mm。管棚钻孔方位、倾角与巷道方位、倾角保持一致,用ZDY1200S型(或SGZ150 型)全液压钻机配¢89mm螺旋钻杆或¢50mm圆形钻杆,造¢90mm钻孔,安装¢75mm×9m管棚管,双液注浆加固,利用双液注浆原理把巷道周边5m范围内裂隙充填饱满,并固结成一体,增大巷道围岩的承载能力,把管棚管与巷道周边围岩固结成坚固整体,增强了围岩的支撑系数,提高了围岩稳定性。掘进7m,留2m超前距。第二次施工管棚孔预注浆时,在2m超前距断面上,喷射300mm厚混凝土,直接布孔施工,依次循环。撇开了传统的打超前锚杆->掘进->锚网喷临时支护->抽顶(或抽帮)->用圆木刹顶->架U型金属棚子->复喷至设计厚度(或立模、浇筑砼)等施工工艺。 As an improvement of the patented technology of the present invention, holes are arranged around 400-500mm outside the barren section of the arch section of the roadway working face that exposes the coal seam, steeply inclined coal seam, soft rock layer, and structural fracture zone, and the hole spacing of the pipe shed is 300-400mm. The azimuth and inclination of the pipe shed are consistent with the azimuth and inclination of the roadway. Use a ZDY1200S (or SGZ150) full hydraulic drilling rig with a ¢89mm helical drill pipe or a ¢50mm round drill pipe to make a ¢90mm hole and install a ¢75mm× The 9m pipe shed pipe is strengthened by double-liquid grouting. The principle of double-liquid grouting is used to fill the cracks within 5m around the roadway and consolidate them into one body to increase the bearing capacity of the surrounding rock of the roadway. The rock is consolidated into a solid whole, which enhances the support coefficient of the surrounding rock and improves the stability of the surrounding rock. Excavate 7m, leave 2m advance distance. During the second construction of the pre-grouting of the pipe shed holes, spray 300mm thick concrete on the 2m advanced section, directly lay the holes for construction, and cycle in turn. Leaving aside the traditional way of laying ahead bolts -> excavation -> anchor net spraying temporary support -> pulling out the roof (or side) -> using a log to brake the roof -> erecting a U-shaped metal shed -> re-spraying to the design thickness ( Or vertical formwork, pouring concrete) and other construction techniques. the
作为本发明专利技术的进一步改进,明斜井通过地表土层过大型建筑物、主要铁路干线及河床段等,在掘进工作面拱部荒断面外300~400mm周边均匀布置一排管棚钻孔,孔间距250~300mm,管棚方位、倾角与巷道方位、倾角保持一致。用全液压钻机配¢89mm的螺旋钻杆钻头,造¢90mm管棚孔,安装¢75mm×9m管棚管,双液注浆加固,利用双液注浆原理采用水泥-水玻璃浆液把巷道周边5m范围内孔隙充填饱满,并固结成一体,增大巷道周围的承载能力,把管棚管与巷道周边固结成坚固整体,提高周边的稳定性。掘进6m,留3m超前距,依次循环。克服了传统的大量开挖明槽,施工中片帮修大量的边坡,投入过多的支护形式,耗费大量的人力、物力、财力,施工复杂,风险大。 As a further improvement of the patented technology of the present invention, the open inclined shaft passes through the surface soil layer to pass through large buildings, main railway lines and riverbed sections, etc., and a row of pipe shed drilling holes is evenly arranged around the 300-400mm of the barren section of the arch of the excavation face , the hole spacing is 250-300mm, and the orientation and inclination of the pipe shed are consistent with the azimuth and inclination of the roadway. Use a full hydraulic drilling rig with a ¢89mm auger drill bit to make ¢90mm pipe shed holes, install ¢75mm×9m pipe shed pipes, double-liquid grouting for reinforcement, and use the principle of double-liquid grouting to use cement-water glass grout to seal the roadway surroundings. The pores within the range of 5m are fully filled and consolidated into one body, which increases the bearing capacity around the roadway, consolidates the pipe shed pipe and the surrounding roadway into a solid whole, and improves the stability of the surrounding area. Excavate 6m, leave 3m advance distance, and cycle in turn. It overcomes the traditional method of excavating a large number of open trenches, helping to repair a large number of slopes during construction, and investing too many support forms, which consumes a lot of manpower, material resources, and financial resources. The construction is complicated and the risk is high. the
具体实施的时候,将巷道掘进工作面清理干净,迎面墙扩刷平整,荒断面向外扩刷达到设计尺寸,用料石砌筑一道止浆墙,按设计方位、倾角预埋¢108mm孔口管。工作面第二次管棚施工前,要求已施工的巷道进行永久支护及分段进行壁后注浆加固后,方可进行第二次管棚施工。 During specific implementation, the roadway excavation working face is cleaned, the facing wall is expanded to be smooth, the barren section is expanded outward to reach the design size, a slurry wall is built with material stones, and a ¢108mm orifice is pre-buried according to the design orientation and inclination angle Tube. Before the construction of the second pipe shed on the working face, it is required that the constructed roadway be permanently supported and reinforced by grouting behind the wall in sections before the second pipe shed construction can be carried out. the
1.止浆墙的施工 1. Construction of grout stop wall
把掘进工作面前3m做钻场,按设计尺寸向巷道轮廓线外扩挖200mm的沟槽, 垒砌一道止浆墙,止浆墙厚度1.0m,两边用料石垒砌厚度各300mm,中间空槽400mm浇筑标号为C25混凝土。垒砌前,将巷道出水的地方,安装引水管将水导出。止浆墙垒砌过程中,根据设计方位、倾角,在巷道荒断面外300~400mm之间预埋¢108mm×1.5m孔口管,孔口管外露150mm,距法兰盘100mm处,事先焊接一个带有丝扣(¢25mm×60mm)的接头,止浆墙垒砌好后喷射砼把巷道与止浆墙周边衔接的处填平。凝固24小时后,先把预埋导水的引水管注浆封堵,加固止浆墙。 Use the 3m in front of the excavation work as a drilling site, expand and dig a 200mm trench to the outside of the roadway outline according to the design size, and build a grout-stop wall with a thickness of 1.0m. Groove 400mm pouring grade is C 25 concrete. Before laying the foundations, install water diversion pipes to guide the water out of the roadway where the water comes out. In the process of building the grout-stop wall, according to the design orientation and inclination angle, ¢108mm×1.5m orifice tubes are pre-buried between 300-400mm outside the barren section of the roadway, and the orifice tubes are exposed 150mm and 100mm away from the flange. A joint with a screw (¢25mm×60mm), after the grout-stop wall is built, spray concrete to fill the connection between the roadway and the grout-stop wall. After 24 hours of solidification, the pre-embedded diversion pipe for water conduction shall be grouted and blocked to strengthen the grout-stop wall.
2.施工方法 2. Construction method
把工作台在工作面搭设牢固。将液压钻机起吊到工作台上固定好,校对好钻孔方位及倾角,紧固钻架,开钻慢速推进200mm后,重新校准钻孔的方位及倾角,方可继续钻进。如果钻进施工过程中,遇到粘泥土层塌孔或破碎带不进尺时起钻,盖上¢108mm子母扣法兰堵盘(堵盘上焊接有¢25mm×50mm带丝扣接头),用螺栓拧紧,连接注浆管路进行注浆,当注浆压力达到5~8MPa时停止注浆,进行扫孔钻进,反复(扫孔)钻进,反复注浆,直至施工到设计深度。收钻后,在管棚孔内,安装¢75mm×9m管棚钢管(管棚管一头用电钻钻有花孔,长度1m;另一头焊有¢108mm法兰堵盘,堵盘中间焊接¢25mm×60mm带丝接头)。连接注浆管路,开始注浆加固。注浆前,把预埋孔口管上距法兰盘100mm处焊接的¢25mm×60mm接头上的¢25mm球阀打开,注浆时让管棚孔中浆液顺着钻孔向外回浆,使管棚管周围充满浆液与注浆后土层或破碎带形成坚固的整体。封孔压力控制到10MPa左右。施工一个管棚孔,安装一个孔,注浆一个孔,直至注浆结束。工作面管棚预注浆9m,掘进6m,预留3m超前距。向前掘进6m后,再次管棚预注浆时,按原施工工序施工(不再施工止浆墙,在工作面迎头直接喷射300mm厚混凝土即可),直至巷道施工完该区段为止。 Set up the workbench firmly on the work surface. Lift the hydraulic drilling rig to the workbench and fix it, calibrate the drilling azimuth and inclination, fasten the drill frame, spud and advance 200mm at a slow speed, recalibrate the azimuth and inclination of the drilling, and continue drilling. If during the drilling construction process, when the hole in the clay layer collapses or the broken zone does not advance, the drill should be pulled out, and the ¢108mm snap-in flange plugging plate (¢25mm×50mm threaded joints are welded on the blocking plate), Tighten the bolts, connect the grouting pipeline for grouting, stop grouting when the grouting pressure reaches 5-8MPa, carry out sweeping drilling, repeat (sweeping) drilling, and repeat grouting until the construction reaches the design depth. After closing the drill, install a ¢75mm×9m pipe shed steel pipe in the pipe shed hole (one end of the pipe shed pipe has a flower hole drilled with an electric drill, and the length is 1m; the other end is welded with a ¢108mm flange blocking plate, and the middle of the blocking plate is welded ¢25mm ×60mm with wire connector). Connect the grouting pipeline and start grouting reinforcement. Before grouting, open the ¢25mm ball valve on the ¢25mm×60mm joint welded 100mm away from the flange on the pre-buried orifice pipe. The surroundings of the pipe shed pipe are filled with grout and form a solid whole with the soil layer or broken zone after grouting. The sealing pressure is controlled to about 10MPa. Construct one pipe shed hole, install one hole, and grout one hole until the grouting is finished. 9m pre-grouting for the pipe shed on the working face, 6m excavation, 3m advance distance reserved. After digging 6m forward, when pre-grouting the pipe shed again, the construction shall be carried out according to the original construction procedure (the grout stop wall shall not be constructed, and the 300mm thick concrete shall be sprayed directly on the working face) until the section of the roadway is completed. the
3、施工工艺 3. Construction technology
(1).布孔:管棚预注浆采用“周边与中部”相结合的布孔法。“周边孔”使巷道净断面外5m范围内固结成整体,“中部孔”对整体进行补强注浆加固。将地表土层破碎带岩层裂隙用浆液充填饱满固结成坚固整体,增大巷道围岩岩体的承载能力,把管棚与巷道周边围岩固结成坚固整体,提高围岩整体稳定性。 (1). Hole layout: The pre-grouting of the pipe shed adopts the hole layout method combining "periphery and middle". The "peripheral holes" consolidate the roadway within 5m outside the net section into a whole, and the "middle holes" reinforce the whole by grouting. Fill the cracks in the broken surface soil layer with grout to form a solid whole, increase the bearing capacity of the surrounding rock mass of the roadway, consolidate the pipe shed and the surrounding rock around the roadway into a solid whole, and improve the overall stability of the surrounding rock. the
(2).造孔:施工止浆墙的同时,按设计方位、倾角预埋好“周边孔”的孔口管;“中部孔”不预埋孔口管,直接在墙上施工。搭好工作台,把钻机吊运到工作台上固定牢固。施工钻孔,遇到破碎泥土层不进时,反复扫孔,反复注浆,直至施工至设计深度。 (2). Hole making: While constructing the slurry wall, the orifice pipes of the "peripheral holes" are pre-embedded according to the design orientation and inclination angle; the "middle holes" do not pre-embed the orifice pipes, and are directly constructed on the wall. Set up the workbench, hoist the drilling rig to the workbench and fix it firmly. Construction drilling, when the broken soil layer cannot be penetrated, the hole is repeatedly swept and the grouting is repeated until the construction reaches the design depth. the
(3).洗孔:造孔达到设计深度后,连接洗孔管路,用高压水把钻孔内泥浆及钻屑清洗干净。 (3). Hole washing: After the hole reaches the design depth, connect the hole washing pipeline, and clean the mud and drilling cuttings in the drilling hole with high-pressure water. the
(3).安装管棚:洗孔结束后,人工把管棚钢管慢慢下到孔底,把预埋孔口管上的法兰盘与管棚钢管上的子母扣法兰盘对接严实,用螺栓固定;其余注浆钻孔(补强注浆孔)成孔后,安装¢80mm×3m伸缩型专用封孔器,用扳手把封孔器上的大螺母拧紧,使胶垫与钻孔周边充分啮合密实,让胶垫充分起到作用,把管固定牢固。 (3). Install the pipe shed: after the hole washing is completed, slowly lower the pipe shed steel pipe to the bottom of the hole manually, and connect the flange plate on the pre-buried orifice pipe with the buckle flange on the pipe shed steel pipe tightly , fixed with bolts; after the remaining grouting holes (reinforced grouting holes) are formed, install a ¢80mm×3m telescopic special hole sealer, and tighten the big nut on the hole sealer with a wrench to make the rubber pad and the drill The periphery of the hole is fully meshed and dense, so that the rubber pad can fully play a role and fix the tube firmly. the
(4).注浆管路的安装:管棚管安装好后,先安球型阀,连接双液高压注浆管、三通混合器、四通及卸压阀。 (4).Installation of the grouting pipeline: After the pipe shed pipe is installed, install the ball valve first, connect the double-liquid high-pressure grouting pipe, the three-way mixer, the four-way and the pressure relief valve. the
(5).管棚注浆:根据注浆情况进行配比,随时调整流量、浆液浓度,注意注浆压力,随变化而变化,达到设计注浆压力(8~10MPa),即可停止注浆。 (5). Pipe shed grouting: Proportion according to the grouting situation, adjust the flow rate and slurry concentration at any time, pay attention to the grouting pressure, which changes with the change, and stop the grouting when the design grouting pressure (8 ~ 10MPa) is reached. . the
(6).跑、漏浆的处理:在注浆过程中,如发现跑、漏浆现象,可根据现场跑、漏浆情况采取糊、停、点注等方法处理,以减少浆液损失,达到注浆预期目的。 (6). Treatment of grout running and leaking: in the process of grouting, if grout running and leaking are found, methods such as pasting, stopping, and point injection can be adopted according to the on-site running and grout leakage, so as to reduce the loss of grout and achieve Intended purpose of grouting. the
4、注浆参数的选择 4. Selection of grouting parameters
(1).水泥浆液的配制:水泥浆液的水灰比为1∶1(重量比)。 (1). Preparation of cement slurry: the water-cement ratio of the cement slurry is 1:1 (weight ratio). the
(2).水泥浆液与水玻璃浆液的体积比为1∶0.6~0.8。 (2). The volume ratio of cement slurry to water glass slurry is 1:0.6-0.8. the
(3).QBZ-BI型防水剂加量是水泥重量的3%。 (3). The dosage of QBZ-BI waterproofing agent is 3% of the cement weight. the
(4).注浆压力:根据岩层、表土层的发育情况及抗压能力,终孔压力按8~10MPa控制。注浆压力是浆液扩散充填的能量,注浆压力的大小,取决于注浆钻孔静水压力的大小、表土层空隙程度。 (4). Grouting pressure: according to the development of rock formations and surface soil layers and the compressive capacity, the final hole pressure is controlled at 8-10MPa. The grouting pressure is the energy for the grout to diffuse and fill, and the size of the grouting pressure depends on the hydrostatic pressure of the grouting borehole and the porosity of the surface soil layer. the
(5).扩散半径:浆液的扩散半径在压力不变的情况下,是随表土层、岩层空隙不同而不同,浆液的扩散半径有较大差异。因此,合理确定浆液的扩散半径,对节约材料、缩短工期、保证质量具有重大意义。结合以往注浆经验,浆液扩散半径按5m控制。 (5). Diffusion radius: Under the condition of constant pressure, the diffusion radius of the slurry varies with the surface soil layer and the voids of the rock layer, and the diffusion radius of the slurry has a large difference. Therefore, reasonably determining the diffusion radius of the slurry is of great significance for saving materials, shortening the construction period, and ensuring quality. Combined with previous grouting experience, the grout diffusion radius is controlled at 5m. the
(6).注浆量:正常注浆量是根据注浆的加固体积、孔隙率、浆液凝固时间、岩层的孔隙和裂隙的连通情况来确定的。在注浆不跑浆的情况下,尽可能使双液浆在巷道内外形成帷幕,把孔隙充填饱满固结成坚固整体,提高注浆整体性效果。 (6). Grouting amount: The normal grouting amount is determined according to the grouting reinforcement volume, porosity, grout solidification time, and the connectivity of pores and fissures in the rock formation. In the case of grouting without running out of grout, try to make the double-liquid grout form a curtain inside and outside the roadway, fill the pores fully and consolidate them into a solid whole, and improve the overall effect of grouting. the
帷幕注浆注入量计算如下:Q=V·n·a Curtain grouting injection volume is calculated as follows: Q=V·n·a
式中Q-注浆量m3、V-需充填注浆体积m3 In the formula, Q- grouting amount m3, V- grouting volume to be filled m3
n-孔隙率取6%、a-浆液损失系数(1.2~1.5)取1.4 n-porosity is taken as 6%, a-slurry loss coefficient (1.2~1.5) is taken as 1.4
5.注浆设备与材料选择: 5. Grouting equipment and material selection:
管棚预注浆设备计划一览表1 Pipe shed pre-grouting equipment plan list 1
管棚预注浆材料计划一览表2 Pipe shed pre-grouting material plan list 2
(1).水泥:选用标号P.O 42.5级的普通硅酸盐水泥。 (1). Cement: Choose ordinary Portland cement with the label P.O 42.5. the
(2).水玻璃:模数为2.8~3.2、浓度为38~42波美度的水玻璃。 (2). Water glass: water glass with a modulus of 2.8-3.2 and a concentration of 38-42 degrees Baume. the
(3).添加剂:确必治QBZ-BI型防水剂。 (3). Additive: Quebec QBZ-BI type waterproofing agent. the
(4).其他:I型水泥锚固剂(固管用)。 (4). Others: Type I cement anchoring agent (for fixing pipes). the
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN200910227790A CN101929340B (en) | 2009-12-31 | 2009-12-31 | Pre-grouting advance support construction process for pipe shed of underground flat inclined roadway of coal mine |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN200910227790A CN101929340B (en) | 2009-12-31 | 2009-12-31 | Pre-grouting advance support construction process for pipe shed of underground flat inclined roadway of coal mine |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101929340A true CN101929340A (en) | 2010-12-29 |
| CN101929340B CN101929340B (en) | 2012-08-29 |
Family
ID=43368730
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN200910227790A Expired - Fee Related CN101929340B (en) | 2009-12-31 | 2009-12-31 | Pre-grouting advance support construction process for pipe shed of underground flat inclined roadway of coal mine |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101929340B (en) |
Cited By (25)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102128038A (en) * | 2011-01-26 | 2011-07-20 | 北京中铁瑞威基础工程有限公司 | Quick construction method for tunnel pipe shed |
| CN102182471A (en) * | 2011-03-23 | 2011-09-14 | 彬县水帘洞煤炭有限责任公司 | Advance support method for coal mine tunnel high-risk area |
| CN102182498A (en) * | 2011-03-23 | 2011-09-14 | 彬县水帘洞煤炭有限责任公司 | Comprehensive laneway-supporting method for cracked area in coal mine |
| CN102226406A (en) * | 2011-05-10 | 2011-10-26 | 中铁十二局集团第一工程有限公司 | Construction method of ultra-long advanced bolt |
| CN102493822A (en) * | 2011-12-29 | 2012-06-13 | 中铁二十三局集团有限公司 | Method for performing curtain grouting construction on tunnel by water rich fault influence zone |
| CN102704950A (en) * | 2012-06-21 | 2012-10-03 | 山东黄金矿业(莱州)有限公司三山岛金矿 | Support method used in passing water guide fracture structure in mine exploration |
| CN102808627A (en) * | 2012-09-07 | 2012-12-05 | 中国建筑第八工程局有限公司 | Underground excavation construction method of steel pipe shed |
| CN102966359A (en) * | 2012-11-09 | 2013-03-13 | 山西潞安环保能源开发股份有限公司 | Working face ventilation oxidization zone roof control method |
| CN103821538A (en) * | 2013-12-26 | 2014-05-28 | 安徽理工大学 | Ground preliminary grouting method for J-shaped horizontal wing-shaped branch holes |
| CN104790971A (en) * | 2015-04-03 | 2015-07-22 | 核工业井巷建设公司 | Large pipe shed advanced pre-reinforcement method for shallow buried small-spacing rock soil tunnel construction |
| CN105484753A (en) * | 2015-12-29 | 2016-04-13 | 龙口矿业集团有限公司 | Tunneling support method for high-water-pressure high-flow fracture zone |
| CN105587321A (en) * | 2015-12-22 | 2016-05-18 | 大同煤矿集团有限责任公司 | Collapse column bypassing extraction process |
| CN106368709A (en) * | 2016-09-30 | 2017-02-01 | 首钢总公司 | Construction method of vertical shaft |
| CN106968677A (en) * | 2017-03-28 | 2017-07-21 | 中国五冶集团有限公司 | Method for tunnel construction based on pipe shed support |
| CN107339108A (en) * | 2017-06-26 | 2017-11-10 | 中铁十二局集团有限公司 | The layer of sand location subway pipe shed construction method of underground water enrichment |
| CN108035738A (en) * | 2017-12-08 | 2018-05-15 | 中国矿业大学 | The anchoring process of more anchor pole simultaneous quantitative slip castings |
| CN108104840A (en) * | 2017-12-14 | 2018-06-01 | 中铁四局集团有限公司 | Hole-forming method and application of grouting hole-by-hole drilling in advanced tube shed of pebble-accumulated layer tunnel |
| CN108678666A (en) * | 2018-07-28 | 2018-10-19 | 徐工集团工程机械有限公司 | A kind of multifunctional drill and pipe canopy mounting device |
| CN108756898A (en) * | 2018-06-06 | 2018-11-06 | 中铁六局集团有限公司 | Using the front pre-grouting construction method of HSC grouting materials |
| CN111042820A (en) * | 2019-12-27 | 2020-04-21 | 中南大学 | Construction method for sand layer with oversized pilot hole by vertical shaft raise-shaft method |
| CN112855223A (en) * | 2021-04-06 | 2021-05-28 | 中国矿业大学 | Integrated grouting method for coal roadway penetrating through goaf wall rear-advance curtain space |
| CN114635727A (en) * | 2022-02-25 | 2022-06-17 | 华亭煤业集团有限责任公司 | Method for improving anchoring effect through outlet water anchoring drilling hole pre-treatment |
| CN116006184A (en) * | 2022-10-29 | 2023-04-25 | 中铁广州工程局集团有限公司 | A static pressure construction method for a tunnel-type large pipe shed |
| CN116752974A (en) * | 2023-07-07 | 2023-09-15 | 紫金(长沙)工程技术有限公司 | A method for tunneling vertical shafts through mudstone aquifers |
| CN117145523A (en) * | 2023-10-31 | 2023-12-01 | 煤炭工业太原设计研究院集团有限公司 | A reinforcement structure and method for roof caving treatment in the mudstone section of an inclined shaft in a potash salt mine |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4193715A (en) * | 1978-05-12 | 1980-03-18 | The Eastern Company | Mine roof support method and apparatus |
| CN101235719A (en) * | 2008-02-29 | 2008-08-06 | 李明远 | Prevacuated decompressed soft rock laneway support technology |
| CN101285385B (en) * | 2008-05-29 | 2010-06-02 | 中交第二公路勘察设计研究院有限公司 | Three-dimensional pipe screen underground excavation method |
-
2009
- 2009-12-31 CN CN200910227790A patent/CN101929340B/en not_active Expired - Fee Related
Cited By (34)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102128038A (en) * | 2011-01-26 | 2011-07-20 | 北京中铁瑞威基础工程有限公司 | Quick construction method for tunnel pipe shed |
| CN102128038B (en) * | 2011-01-26 | 2013-11-13 | 北京中铁瑞威基础工程有限公司 | Quick construction method for tunnel pipe shed |
| CN102182471A (en) * | 2011-03-23 | 2011-09-14 | 彬县水帘洞煤炭有限责任公司 | Advance support method for coal mine tunnel high-risk area |
| CN102182498A (en) * | 2011-03-23 | 2011-09-14 | 彬县水帘洞煤炭有限责任公司 | Comprehensive laneway-supporting method for cracked area in coal mine |
| CN102226406B (en) * | 2011-05-10 | 2013-09-18 | 中铁十二局集团第一工程有限公司 | Construction method of super-long advanced anchor bars |
| CN102226406A (en) * | 2011-05-10 | 2011-10-26 | 中铁十二局集团第一工程有限公司 | Construction method of ultra-long advanced bolt |
| CN102493822A (en) * | 2011-12-29 | 2012-06-13 | 中铁二十三局集团有限公司 | Method for performing curtain grouting construction on tunnel by water rich fault influence zone |
| CN102704950A (en) * | 2012-06-21 | 2012-10-03 | 山东黄金矿业(莱州)有限公司三山岛金矿 | Support method used in passing water guide fracture structure in mine exploration |
| CN102704950B (en) * | 2012-06-21 | 2014-06-11 | 山东黄金矿业(莱州)有限公司三山岛金矿 | Support method used in passing water guide fracture structure in mine exploration |
| CN102808627A (en) * | 2012-09-07 | 2012-12-05 | 中国建筑第八工程局有限公司 | Underground excavation construction method of steel pipe shed |
| CN102966359A (en) * | 2012-11-09 | 2013-03-13 | 山西潞安环保能源开发股份有限公司 | Working face ventilation oxidization zone roof control method |
| CN103821538A (en) * | 2013-12-26 | 2014-05-28 | 安徽理工大学 | Ground preliminary grouting method for J-shaped horizontal wing-shaped branch holes |
| CN103821538B (en) * | 2013-12-26 | 2016-09-07 | 安徽理工大学 | J-type horizontal assistant branched hole surface advance grouting paste-making method |
| CN104790971A (en) * | 2015-04-03 | 2015-07-22 | 核工业井巷建设公司 | Large pipe shed advanced pre-reinforcement method for shallow buried small-spacing rock soil tunnel construction |
| CN105587321A (en) * | 2015-12-22 | 2016-05-18 | 大同煤矿集团有限责任公司 | Collapse column bypassing extraction process |
| CN105484753A (en) * | 2015-12-29 | 2016-04-13 | 龙口矿业集团有限公司 | Tunneling support method for high-water-pressure high-flow fracture zone |
| CN105484753B (en) * | 2015-12-29 | 2018-01-23 | 龙口矿业集团有限公司 | The Supporting Method for Drifting of high hydraulic pressure big flow crushed zone |
| CN106368709A (en) * | 2016-09-30 | 2017-02-01 | 首钢总公司 | Construction method of vertical shaft |
| CN106968677A (en) * | 2017-03-28 | 2017-07-21 | 中国五冶集团有限公司 | Method for tunnel construction based on pipe shed support |
| CN107339108A (en) * | 2017-06-26 | 2017-11-10 | 中铁十二局集团有限公司 | The layer of sand location subway pipe shed construction method of underground water enrichment |
| CN108035738A (en) * | 2017-12-08 | 2018-05-15 | 中国矿业大学 | The anchoring process of more anchor pole simultaneous quantitative slip castings |
| CN108104840A (en) * | 2017-12-14 | 2018-06-01 | 中铁四局集团有限公司 | Hole-forming method and application of grouting hole-by-hole drilling in advanced tube shed of pebble-accumulated layer tunnel |
| CN108756898A (en) * | 2018-06-06 | 2018-11-06 | 中铁六局集团有限公司 | Using the front pre-grouting construction method of HSC grouting materials |
| CN108678666A (en) * | 2018-07-28 | 2018-10-19 | 徐工集团工程机械有限公司 | A kind of multifunctional drill and pipe canopy mounting device |
| CN108678666B (en) * | 2018-07-28 | 2024-02-02 | 江苏徐工工程机械研究院有限公司 | A multifunctional drilling rig and pipe shed installation device |
| CN111042820B (en) * | 2019-12-27 | 2021-06-15 | 中南大学 | Construction method for sand layer with oversized pilot hole by vertical shaft raise-shaft method |
| CN111042820A (en) * | 2019-12-27 | 2020-04-21 | 中南大学 | Construction method for sand layer with oversized pilot hole by vertical shaft raise-shaft method |
| CN112855223A (en) * | 2021-04-06 | 2021-05-28 | 中国矿业大学 | Integrated grouting method for coal roadway penetrating through goaf wall rear-advance curtain space |
| CN112855223B (en) * | 2021-04-06 | 2024-05-10 | 中国矿业大学 | Coal roadway-advanced curtain space integrated grouting method after penetrating goaf wall |
| CN114635727A (en) * | 2022-02-25 | 2022-06-17 | 华亭煤业集团有限责任公司 | Method for improving anchoring effect through outlet water anchoring drilling hole pre-treatment |
| CN116006184A (en) * | 2022-10-29 | 2023-04-25 | 中铁广州工程局集团有限公司 | A static pressure construction method for a tunnel-type large pipe shed |
| CN116752974A (en) * | 2023-07-07 | 2023-09-15 | 紫金(长沙)工程技术有限公司 | A method for tunneling vertical shafts through mudstone aquifers |
| CN117145523A (en) * | 2023-10-31 | 2023-12-01 | 煤炭工业太原设计研究院集团有限公司 | A reinforcement structure and method for roof caving treatment in the mudstone section of an inclined shaft in a potash salt mine |
| CN117145523B (en) * | 2023-10-31 | 2023-12-26 | 煤炭工业太原设计研究院集团有限公司 | Sylvite inclined shaft mudstone section roof-falling treatment reinforcing structure and method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN101929340B (en) | 2012-08-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101929340B (en) | Pre-grouting advance support construction process for pipe shed of underground flat inclined roadway of coal mine | |
| CN104818991B (en) | A kind of construction method in Shallow-buried residual soil slope tunnel | |
| CN103410527B (en) | Preliminary bracing construction method for tunnel with surrounding rocks containing collapsible loess and soft rocks | |
| WO2020259059A1 (en) | Tbm parallel heading tunnel trunk construction method | |
| CN105041325B (en) | Construction method of high-tension water-rich extra-large-section weak breccia tunnel | |
| CN112855223B (en) | Coal roadway-advanced curtain space integrated grouting method after penetrating goaf wall | |
| WO2021223573A1 (en) | Construction structure for communication and connection between newly added mined channel and existing station hall layer | |
| CN113107501B (en) | A Construction Method of Excavation Excavation by Extending the Steel Ring of the Portal | |
| CN111997624A (en) | A construction method for shallowly buried large-section undercut rectangular tunnel | |
| CN111119935B (en) | A multi-layer grouting reinforcement method for surrounding rock of soft and broken structure of roadway | |
| CN112663625A (en) | Construction and protection method for shallow-buried bias-pressure weak surrounding rock tunnel portal in alpine region | |
| CN205172598U (en) | Pipe curtain spouts a supporting construction soon | |
| CN110195604B (en) | Construction method for tunnel main tunnel TBM (tunnel boring machine) tunneling section | |
| CN111677520A (en) | Construction method of excavating station structure by tunnel first and then station pipe curtain hole pile method | |
| CN111287759A (en) | A kind of construction method of shallow buried close-cut tunnel | |
| CN112963156A (en) | Composite reinforcing method and composite reinforcing structure for shallow tunnel in soil-rock composite stratum | |
| CN217028947U (en) | Construction structure of shield tunnel lower-passing water pipeline | |
| CN114737979B (en) | Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region | |
| CN107339108A (en) | The layer of sand location subway pipe shed construction method of underground water enrichment | |
| CN106013078A (en) | A construction method for strengthening curtain structure in highly permeable ground | |
| CN119435012B (en) | A method for concealed excavation of a three-layer six-hole subway station | |
| CN108952727B (en) | A method of grouting and water plugging in vertically fractured strata with large dip angle | |
| CN114086968A (en) | Construction method for underground excavation tunnel penetrating existing building | |
| CN106437796A (en) | Rock stratum shield tunnel end reinforcing structure and reinforcing method | |
| CN115539048A (en) | A construction method for shallow-buried bias-pressure tunnel entrance |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120829 |