CN108035754A - A kind of roadway bolt anchor cable combination supporting method - Google Patents

A kind of roadway bolt anchor cable combination supporting method Download PDF

Info

Publication number
CN108035754A
CN108035754A CN201711106842.5A CN201711106842A CN108035754A CN 108035754 A CN108035754 A CN 108035754A CN 201711106842 A CN201711106842 A CN 201711106842A CN 108035754 A CN108035754 A CN 108035754A
Authority
CN
China
Prior art keywords
anchor cable
anchor
hole
floor
bolthole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711106842.5A
Other languages
Chinese (zh)
Inventor
张蓓
张蕾
胡少轩
许佳林
赵万亮
武威
林冬
杨耀君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201711106842.5A priority Critical patent/CN108035754A/en
Publication of CN108035754A publication Critical patent/CN108035754A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of roadway bolt anchor cable combination supporting method, including gib layer, forms slurries in the bottom hole portion slip casting of bolthole and anchor cable hole and reinforces group;Form superficial part supporting and deep supporting;Seal orifice, the mounting base grouting anchor pile in floor grouting hole, and inject cement mortar to the floor grouting anchor tube.The present invention solves the problems, such as that roadway support country rock is broken in the prior art, deforms or even collapse, bottom distension is strong, it is necessary to repair repeatedly.

Description

A kind of roadway bolt anchor cable combination supporting method
Technical field
The present invention relates to Roadway Support Technology field, is specially a kind of roadway bolt anchor cable combination supporting method.
Background technology
At present, as the expansion of coal mining scope, the increase of mining depth, the tunnel of supporting difficulty are more and more.It is real Proof is trampled, has been difficult to prove effective using the strong strong supporting mode such as metallic support.In recent years, grouting support is come into being.It is relatively golden Belong to for stent, grouting support is a kind of active support mode, it is started with transforming coffer mechanics performance, country rock (or coal body) Extraneous pressure is resisted as supporting main body, the reliability and support speed of supporting is greatly improved, reduces support cost.But It is this support pattern in the case where mining influence is larger, stress is complicated, still can produces destruction, supporting rock crusher, become Shape so collapse, bottom distension is strong, it is necessary to repair repeatedly, influence production efficiency, increase cost of winning.
The content of the invention
It is an object of the invention to provide a kind of roadway bolt anchor cable combination supporting method, solves tunnel in the prior art Supporting country rock is broken, deform or even collapse, bottom distension is strong, it is necessary to the problem of repairing repeatedly.
To achieve the above object, the present invention provides following technical solution:
A kind of roadway bolt anchor cable combination supporting method, includes the following steps:
Step a, after driling explosion excavates tunnel, exposed balkstones all to work surface and two help country rock surface injection 30~ 50mm concrete forms gib layer, with temporary enclosed country rock;
Step b, bolthole is bored at the top of roadway surrounding rock and on lane side, armature boring depth is 3m;In the bottom hole of the bolthole Portion's slip casting forms slurries and reinforces group;And the rod end of anchor pole is anchored at the slurries and is reinforced in group, the rod end of anchor pole After the completion of anchoring, cement mortar is injected in the bolthole, grouting pressure is 5MPa in bolthole, forms superficial part supporting;In lane Anchor cable hole, drilling depth 6m are bored at the center of top and both sides spandrel of road country rock;Formed in the bottom hole portion slip casting of the anchor cable hole Slurries reinforce group;And reinforce the cable body end anchorage of anchor cable in group in the slurries, after the completion of the cable body end anchorage of anchor cable, Cement mortar is injected in the anchor cable hole, grouting pressure is 10Mpa in anchor cable hole, forms deep supporting;
Step c, prestressed anchor cable supplement support is carried out in the bolthole and anchor cable hole.
Step d, described bolthole and anchor cable hole are reacted to each other sealing of hole by staple and chemical pulp, staple and chemical pulp reaction Volumetric expansion afterwards, seal orifice, closing length are 280-300mm;
Step e, in Floor water plane, the thickness of 800mm is excavated downwards, the floor rock surface injection 150mm after excavation Thick concrete layer, which is formed, stops pulp layer;The construction floor grouting hole on the floor rock for stopping pulp layer is formed, in floor grouting hole Mounting base grouting anchor pile, and cement mortar is injected to the floor grouting anchor tube, finally roadway floor is formed with concrete backfill On smooth concrete backfill layer.
Preferably, after step d, tracking drilling, radius of the bore position centered on anchor pole, anchor cable are carried out to roadway surrounding rock Start arrangement expansion at 0.2-0.3 meters, drill 0.4-0.8 meters of distance between borehole;At old 1 meter of the top of drilling depth distance, so neither The deformation of top plate can effectively be suppressed again by influencing the anchoring strength of anchor cable;Bore angle is parallel with adjacent anchor shaft anchor cable;Drilling is straight Footpath is identical with anchor cable diameter.
Preferably, after step d, steel wire rope is hung on anchor pole and arranges steel basketry net in tunnel inner wall, anchor pole anchor disk is installed, is made Steel wire rope and steel basketry net are close to tunnel inner wall, small using the second layer concrete of 50~70mm of pulp shooting machine even application, maintenance 24 When, prevent concrete to be cracked because of dehydration.
Compared with prior art, beneficial effects of the present invention are as follows:
1st, in roadway support structure of the present invention, due to the bottom hole portion of bolthole and anchor cable hole have slurries reinforce group, anchor pole and The end anchorage of anchor cable is reinforced in group in the slurries.The reliability of anchor pole and the anchor cable grappling in rock stratum can so be strengthened, Decline the pretightning force of anchor pole and anchor cable to prevent grappling loosely, so that the occurrence of reducing rock stratum roadway deformation.
2nd, control effect of the present invention is good, preferably solves deep tunnel deformation especially severe, bottom distension is strong, safeguards very The problem of difficult, effectively prevent the reclamation work in tunnel, reduce roadway support cost.
Brief description of the drawings
Fig. 1 is the structure diagram of the present invention.
In figure:1 gib layer, 2 anchor poles, 3 anchor cables, 4 slurries reinforce group, 5 only pulp layer, 6 grouting anchor piles, 7 backfill layers, 8 Second layer concrete.
Embodiment
The preferred embodiment of the present invention is illustrated below in conjunction with attached drawing, it will be appreciated that described herein preferred real Apply example to be merely to illustrate and explain the present invention, be not intended to limit the present invention.
Referring to Fig. 1, a kind of roadway bolt anchor cable combination supporting method, includes the following steps:
Step a, after driling explosion excavates tunnel, exposed balkstones all to work surface and two help country rock surface injection 30~ 50mm concrete forms gib layer 1, with temporary enclosed country rock;Broken arch body surface face is formed into an entirety, prevents from noting The outflow of slurries during slurry.
When the driling explosion excavates tunnel, periphery hole is smaller than 2R2, periphery hole contour line retraction data for R2~ 1.1R2, wherein, R2 represents the radius of Rock Fragmentation by Blasting relaxation zone;Alternatively, using the method every eye powder charge, and periphery hole fills Dose is no more than 200g.
Step b, bolthole is bored at the top of roadway surrounding rock and on lane side, armature boring depth is 3m;In the bolthole The slip casting of bottom hole portion forms slurries and reinforces group 4;And the rod end of anchor pole 2 is anchored at the slurries and is reinforced in group 4, anchor pole 2 After the completion of rod end anchoring, cement mortar is injected in the bolthole, grouting pressure is 5MPa in bolthole, forms superficial part branch Shield;Anchor cable hole, drilling depth 6m are bored at the center of top of roadway surrounding rock and both sides spandrel;Noted in the bottom hole portion of the anchor cable hole Slurry forms slurries and reinforces group 4;And the cable body end anchorage of anchor cable 3 is reinforced in group 4 in the slurries, the cable body end of anchor cable 3 After the completion of anchoring, cement mortar is injected in the anchor cable hole, grouting pressure is 10Mpa in anchor cable hole, forms deep supporting.
In a preferred embodiment, the cross-sectional area that the slurries reinforce group 4 is that 3 cable body of anchor cable and 2 body of rod of anchor pole are transversal 11-14 times of area.The cross-sectional area that the slurries reinforce group 4 is too small, is unfavorable for the reliable grappling of anchor cable 3 and anchor pole 2, slurries The cross-sectional area of the group of reinforcing 4 is as too greatly, not only increased difficulty of construction, and can increase the production costs such as slurry.
Step c, prestressed anchor cable supplement support is carried out in the bolthole and anchor cable hole;
Step d, described bolthole and anchor cable hole are reacted to each other sealing of hole by staple and chemical pulp, body after staple and chemical pulp reaction Product expansion, seal orifice, closing length is 280-300mm;
Step e, in Floor water plane, the thickness of 800mm is excavated downwards, the floor rock surface injection 150mm after excavation Thick concrete layer, which is formed, stops pulp layer 5;The construction floor grouting hole on the floor rock for stopping pulp layer 5 is formed, in floor grouting hole Middle mounting base grouting anchor pile 6, and cement mortar is injected into the floor grouting anchor tube 6, finally lane is formed with concrete backfill Smooth concrete backfill layer 7 on road bottom plate.
The concrete used by moisture 2~5% mix and stir material and water is made, wherein mix and stir material be by each component according to Following weight proportion is made:1 part of cement, 2 parts of sand, 2 parts of stone, during gunning concrete, will make the Spray gun nozzle and rock of pulp shooting machine The angle in face is 75~90 °, and distance of the nozzle away from scar is 0.9m~1.2m, control pulp shooting machine wind pressure of work be more than 5Mpa, Hydraulic pressure is maintained at 1~4Mpa.
The cement mortar is composed of the following components:Portland cement slurry, account for the Portland cement slurries matter The hydrophilic nano-silicon dioxide of amount 0.5%~1.5%, account for the Portland cement grind slurries quality 0.2%~3% UNF-5 type naphthalene water reducers.
In a preferred embodiment, after step d, tracking drilling is carried out to roadway surrounding rock, bore position is with anchor pole 2, anchor cable 3 Centered on 0.2-0.3 meters of radius at start arrangement expansion, drill 0.4-0.8 meters of distance between borehole;Old 1 meter of the top of drilling depth distance Place, so neither influence anchor pole 2, the anchoring strength of anchor cable 3 can effectively suppress the deformation of top plate again;Bore angle and adjacent anchor Bar 2, anchor cable 3 are parallel;Bore diameter is identical with anchor pole 2,3 diameter of anchor cable.
In a preferred embodiment, after step d, steel wire rope is hung on anchor pole and arranges steel basketry net, installation in tunnel inner wall Anchor pole anchor disk, makes steel wire rope and steel basketry net be close to tunnel inner wall, using the second layer coagulation of 50~70mm of pulp shooting machine even application Soil 8, when maintenance 24 is small, prevents concrete to be cracked because of dehydration.
Finally it should be noted that:The foregoing is merely the preferred embodiment of the present invention, it is not intended to limit the invention, to the greatest extent Pipe is with reference to the foregoing embodiments described in detail the present invention, and for those skilled in the art, it still can be with Modify to the technical solution described in foregoing embodiments, or equivalent substitution is carried out to which part technical characteristic.It is all Within the spirit and principles in the present invention, any modification, equivalent replacement, improvement and so on, should be included in the guarantor of the present invention Within the scope of shield.

Claims (3)

1. a kind of roadway bolt anchor cable combination supporting method, it is characterised in that include the following steps:
Step a, after driling explosion excavates tunnel, exposed balkstones all to work surface and two help country rock surface injection 30~ 50mm concrete forms gib layer, with temporary enclosed country rock;
Step b, bolthole is bored at the top of roadway surrounding rock and on lane side, armature boring depth is 3m;In the bottom hole of the bolthole Portion's slip casting forms slurries and reinforces group;And the rod end of anchor pole is anchored at the slurries and is reinforced in group, the rod end of anchor pole After the completion of anchoring, cement mortar is injected in the bolthole, grouting pressure is 5MPa in bolthole, forms superficial part supporting;In lane Anchor cable hole, drilling depth 6m are bored at the center of top and both sides spandrel of road country rock;Formed in the bottom hole portion slip casting of the anchor cable hole Slurries reinforce group;And reinforce the cable body end anchorage of anchor cable in group in the slurries, after the completion of the cable body end anchorage of anchor cable, Cement mortar is injected in the anchor cable hole, grouting pressure is 10Mpa in anchor cable hole, forms deep supporting;
Step c, prestressed anchor cable supplement support is carried out in the bolthole and anchor cable hole.
Step d, described bolthole and anchor cable hole are reacted to each other sealing of hole by staple and chemical pulp, body after staple and chemical pulp reaction Product expansion, seal orifice, closing length is 280-300mm;
Step e, in Floor water plane, the thickness of 800mm is excavated downwards, the floor rock surface injection 150mm after excavation Thick concrete layer, which is formed, stops pulp layer;The construction floor grouting hole on the floor rock for stopping pulp layer is formed, in floor grouting hole Mounting base grouting anchor pile, and cement mortar is injected to the floor grouting anchor tube, finally roadway floor is formed with concrete backfill On smooth concrete backfill layer.
A kind of 2. roadway bolt anchor cable combination supporting method according to claim 1, it is characterised in that:After the step d, Tracking drilling is carried out to roadway surrounding rock, starts arrangement exhibition at 0.2-0.3 meters of radius of the bore position centered on anchor pole, anchor cable Open, drill 0.4-0.8 meters of distance between borehole;At old 1 meter of the top of drilling depth distance, the anchoring strength for so neither influencing anchor cable again can The effective deformation for suppressing top plate;Bore angle is parallel with adjacent anchor shaft anchor cable;Bore diameter is identical with anchor cable diameter.
A kind of 3. roadway bolt anchor cable combination supporting method according to claim 1, it is characterised in that:After the step d, Steel wire rope is hung on anchor pole and arranges steel basketry net in tunnel inner wall, anchor pole anchor disk is installed, steel wire rope and steel basketry net is close to tunnel Inner wall, using the second layer concrete of 50~70mm of pulp shooting machine even application, when maintenance 24 is small, prevent concrete because of dehydration tortoise Split.
CN201711106842.5A 2017-11-10 2017-11-10 A kind of roadway bolt anchor cable combination supporting method Pending CN108035754A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711106842.5A CN108035754A (en) 2017-11-10 2017-11-10 A kind of roadway bolt anchor cable combination supporting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711106842.5A CN108035754A (en) 2017-11-10 2017-11-10 A kind of roadway bolt anchor cable combination supporting method

Publications (1)

Publication Number Publication Date
CN108035754A true CN108035754A (en) 2018-05-15

Family

ID=62093835

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711106842.5A Pending CN108035754A (en) 2017-11-10 2017-11-10 A kind of roadway bolt anchor cable combination supporting method

Country Status (1)

Country Link
CN (1) CN108035754A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109372555A (en) * 2018-12-26 2019-02-22 中国矿业大学 A kind of fault disruption zone area tunnel 3 D stereo grouting support method
CN109763821A (en) * 2019-03-15 2019-05-17 山西潞安矿业(集团)有限责任公司 A kind of compound shield lane method of dynamic pressure exploiting field main entry
CN110566226A (en) * 2019-08-30 2019-12-13 河南理工大学 shallow-consolidation deep-injection supporting method for rapid excavation of broken roof large-section roadway
CN110593903A (en) * 2019-09-27 2019-12-20 中国矿业大学 Novel grouting anchor cable supporting method and grouting anchor cable
CN112576276A (en) * 2020-11-18 2021-03-30 彬县水帘洞煤炭有限责任公司 Rock coal supporting method based on loose rock coal seam grouting reinforcement
CN113356904A (en) * 2021-07-14 2021-09-07 宿州市金鼎安全技术股份有限公司 Three-anchor combined dynamic support method for deep well high-stress soft rock roadway
CN113586109A (en) * 2021-07-09 2021-11-02 山东黄金矿业(莱州)有限公司三山岛金矿 Hanging wall rock mass supporting method for underground mining ore body of metal mine
WO2022063326A1 (en) * 2020-09-28 2022-03-31 中煤科工开采研究院有限公司 Spraying temporary support and bolt permanent support method and system
CN114294034A (en) * 2021-12-29 2022-04-08 国家能源集团宁夏煤业有限责任公司 Roadway support system and roadway support method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4052860A (en) * 1974-12-09 1977-10-11 Environmental Engineering Dr. Ing. Alterman Ltd. Construction of underground tunnels and rock chambers
CN101493011A (en) * 2008-12-30 2009-07-29 中国科学院武汉岩土力学研究所 Soft expansion type wall rock tunnel support method
CN101906977A (en) * 2010-07-21 2010-12-08 中国矿业大学(北京) Method for preventing and treating large deformation and collapse of softrock tunnel
CN102337903A (en) * 2011-08-25 2012-02-01 安徽理工大学 Method of active coupling support in time and space for control of minimum deformation of surrounding rock of deep well roadway
CN103174444A (en) * 2013-02-26 2013-06-26 中国矿业大学(北京) Support method and support structure for soft coal/ rock stratum alley
CN104074529A (en) * 2013-08-02 2014-10-01 河北工程大学 A continuous double-shell reinforcement method for deep roadways and chambers
CN104533453A (en) * 2014-12-12 2015-04-22 山东科技大学 Substep dynamic coupling support method for roadway fault fracture zone
CN105178981A (en) * 2015-09-30 2015-12-23 中国矿业大学 Total-section closed type deep-shallow coupling yielding, bolting-grouting and supporting method for incompact and fractured soft-rock roadway

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4052860A (en) * 1974-12-09 1977-10-11 Environmental Engineering Dr. Ing. Alterman Ltd. Construction of underground tunnels and rock chambers
CN101493011A (en) * 2008-12-30 2009-07-29 中国科学院武汉岩土力学研究所 Soft expansion type wall rock tunnel support method
CN101906977A (en) * 2010-07-21 2010-12-08 中国矿业大学(北京) Method for preventing and treating large deformation and collapse of softrock tunnel
CN102337903A (en) * 2011-08-25 2012-02-01 安徽理工大学 Method of active coupling support in time and space for control of minimum deformation of surrounding rock of deep well roadway
CN103174444A (en) * 2013-02-26 2013-06-26 中国矿业大学(北京) Support method and support structure for soft coal/ rock stratum alley
CN104074529A (en) * 2013-08-02 2014-10-01 河北工程大学 A continuous double-shell reinforcement method for deep roadways and chambers
CN104533453A (en) * 2014-12-12 2015-04-22 山东科技大学 Substep dynamic coupling support method for roadway fault fracture zone
CN105178981A (en) * 2015-09-30 2015-12-23 中国矿业大学 Total-section closed type deep-shallow coupling yielding, bolting-grouting and supporting method for incompact and fractured soft-rock roadway

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109372555A (en) * 2018-12-26 2019-02-22 中国矿业大学 A kind of fault disruption zone area tunnel 3 D stereo grouting support method
CN109763821A (en) * 2019-03-15 2019-05-17 山西潞安矿业(集团)有限责任公司 A kind of compound shield lane method of dynamic pressure exploiting field main entry
CN109763821B (en) * 2019-03-15 2024-02-09 山西潞安矿业(集团)有限责任公司 Dynamic pressure mining area large roadway composite roadway protection method
CN110566226A (en) * 2019-08-30 2019-12-13 河南理工大学 shallow-consolidation deep-injection supporting method for rapid excavation of broken roof large-section roadway
CN110593903A (en) * 2019-09-27 2019-12-20 中国矿业大学 Novel grouting anchor cable supporting method and grouting anchor cable
CN110593903B (en) * 2019-09-27 2020-08-25 中国矿业大学 Novel grouting anchor cable supporting method and grouting anchor cable
WO2022063326A1 (en) * 2020-09-28 2022-03-31 中煤科工开采研究院有限公司 Spraying temporary support and bolt permanent support method and system
CN112576276A (en) * 2020-11-18 2021-03-30 彬县水帘洞煤炭有限责任公司 Rock coal supporting method based on loose rock coal seam grouting reinforcement
CN113586109A (en) * 2021-07-09 2021-11-02 山东黄金矿业(莱州)有限公司三山岛金矿 Hanging wall rock mass supporting method for underground mining ore body of metal mine
CN113356904A (en) * 2021-07-14 2021-09-07 宿州市金鼎安全技术股份有限公司 Three-anchor combined dynamic support method for deep well high-stress soft rock roadway
CN114294034A (en) * 2021-12-29 2022-04-08 国家能源集团宁夏煤业有限责任公司 Roadway support system and roadway support method

Similar Documents

Publication Publication Date Title
CN108035754A (en) A kind of roadway bolt anchor cable combination supporting method
CN103195441B (en) A kind of supporting and reinforcing structure of coal mine tunnel and construction technology thereof
CN111119935B (en) Multi-layer grouting reinforcement method for surrounding rock of soft and broken roadway structure
CN102996149B (en) Support method for bolt-grouting composite crushing dynamic-pressure roadway soft rock roof by high-pre-stressed anchor cable
CN204098049U (en) A kind of protective reinforcing structure of broken rock mass slope
CN108087008B (en) A kind of three-soft seam gob side entry method for protecting support
CN204000901U (en) The vertical high slope prestressing anchor support of a kind of massif device
CN104481560A (en) Roadway roof aquifer treatment method
CN104895073B (en) Can being dismounted for multiple times anchor cable construction system and its construction method
CN105040712A (en) High-pressure washing anchor planting and recharging comprehensive biological protection structure of soft and hard smashing interbedding type composite rock slope and construction method of structure
CN208533540U (en) Soil Nailing Wall sloping timbering structure
CN112145203A (en) Full-face advancing type sectional grouting construction method and overlapped tunnel construction method
CN114673527B (en) Progressive roadway and tunnel broken surrounding rock reinforcing method
CN112177635A (en) Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel
CN109209443A (en) A kind of construction method of breaking surrounding rock tunnel structure
CN110645018B (en) Mine underground strong dynamic pressure roadway prestress anchor-charging integrated supporting structure and method
CN204875812U (en) Broken alternating layers formula composite rock matter side slope high pressure of soft or hard washes plants anchor and recharges and synthesize ecological protective structure
CN109403321A (en) Construction method of filling slope prestressed anchor cable
CN109763852B (en) Advanced support structure suitable for unconsolidated formation and construction method thereof
CN205400758U (en) Temporary support system convenient to undercut tunnel passes through fast and invades limit pipeline region
CN102286979A (en) Construction method for deep foundation pit supporting by adopting steel pipe piles-self-drilling prestressed anchor bars
CN115717397A (en) Larsen steel sheet pile and prestressed anchor cable combined supporting construction method
CN110714770A (en) Support method for releasing high ground stress of hard horizontal surrounding rock through buffer layer
CN113882425B (en) Hole digging foundation structure for high and steep slope and construction method
CN113982033B (en) Method for repairing hydraulic retaining wall with inclination trend by using water in post-construction structure without damage to wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180515

RJ01 Rejection of invention patent application after publication