CN107143338B - A kind of coal mine roadway driving and method for protecting support - Google Patents

A kind of coal mine roadway driving and method for protecting support Download PDF

Info

Publication number
CN107143338B
CN107143338B CN201710512244.1A CN201710512244A CN107143338B CN 107143338 B CN107143338 B CN 107143338B CN 201710512244 A CN201710512244 A CN 201710512244A CN 107143338 B CN107143338 B CN 107143338B
Authority
CN
China
Prior art keywords
channel
passage
supporting
top plate
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710512244.1A
Other languages
Chinese (zh)
Other versions
CN107143338A (en
Inventor
丁国峰
陈通
黄克军
沈会初
乔懿麟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Coal and Chemical Technology Institute Co Ltd
Original Assignee
Shaanxi Coal and Chemical Technology Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Coal and Chemical Technology Institute Co Ltd filed Critical Shaanxi Coal and Chemical Technology Institute Co Ltd
Priority to CN201710512244.1A priority Critical patent/CN107143338B/en
Publication of CN107143338A publication Critical patent/CN107143338A/en
Application granted granted Critical
Publication of CN107143338B publication Critical patent/CN107143338B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/155Laggings made of strips, slats, slabs or sheet piles
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Abstract

The invention discloses a kind of coal mine down-hole tunnel driving and method for protecting support, primarily to roof rock soft broken, laneway molding is difficult when three soft high seam stopes of solution cut eye driving, and then influence the driving problems such as safety and speed.The method of the present invention is will entirely to cut space and excavate to be divided into broken that top forms first passage, planted agent forms second channel and expand to help to form third channel to side to be mined to be total to three phases, the present invention can be good at adapt to top plate extremely the high seam working face large section open*.off top plate weak broken of soft broken the characteristics of, effectively prevent the generation of top plate roof fall accident.

Description

A kind of coal mine roadway driving and method for protecting support
Technical field
The present invention relates to a kind of coal mine roadway driving and method for protecting support, adapt to the high seam work of top plate extremely soft broken Face large section open*.off driving and supporting.
Background technique
China's coal-mine mining machines degree and application range step up, and working face open-off cut eye height and width constantly increase Greatly, general use leads the tunneling method that cave expands side secondary tunneling, easily causes in the secondary lane Kuo Bangcheng and cuts a roof fall accident, especially Roof fall accident takes place frequently in the high seam working face open-off cut eye of top plate extremely soft broken.Thus it is guaranteed that top plate extremely soft broken High seam working face open-off cut eye safety driving and adjoining rock stability have great economy meaning and social effect.
Currently, the main method that driving face cuts eye is to lead cave to expand side secondary tunneling method, eye is cut using this method driving When, although first tunneling, a section is lesser to lead cave, and the expansion for then carrying out big depth again, which is helped to be formed, cuts eye, thoroughly eliminates yet Cut the security risk of a roof fall.One of main cause is: often larger due to cutting a width, width is steady as a country rock is cut Fixed Dominated Factors, current cave of leading expand the time that side secondary tunneling method has only postponed big width formation, do not account for eliminating Big width cuts the flexure and buckling effect of eye, and secondary expansions helps to cut eye-shaped at rear, causes to cut a top plate weak broken coal and rock inbreak. Coal and rock grouting and reinforcing be solve one of back coal and rock effective means, but be confined to cut a pre-pouring grout project amount it is big, Top plate slip casting effect is poor, the factors such as at high cost, fails to promote and apply on a large scale.To sum up, an existing driving method of cutting is shown Following problem: 1) an existing driving technology of cutting cannot reach the mesh for preventing top plate weak broken coal and rock roof fall well 's;2) existing to cut that a pre-pouring grout engineering amount is big, security risk is big, top plate slip casting effect is poor, at high cost;3) secondary expansion was helped Cheng Zhong, roof timbering difficulty is big, and security risk is serious, and it is slow to cut a driving speed;4) can not eliminate cut a top plate flexure effect and Always there is the hidden danger of roof fall in large span buckling effect.
Summary of the invention
The purpose of the present invention is to provide a kind of coal mine roadway driving and method for protecting support, to overcome in the prior art ask Topic, the present invention can be good at adapting to the top plate extremely high seam working face large section open*.off top plate weak broken of soft broken Feature effectively prevent the generation of top plate roof fall accident.
In order to achieve the above objectives, the present invention adopts the following technical scheme:
A kind of coal mine roadway driving and method for protecting support, by entire incisor canal be divided into broken top form first passage, shape of acting as a planted agent Third channel three phases are formed at second channel and to side to be mined expansion side, specifically includes the following steps:
Step 1: using the channel interface apart from seat earth height H as the bottom surface of first passage basis, part coal of backbreaking Layer top plate, driving form first passage, carry out supporting to first passage in tunneling process, wherein H is the height of second channel;
Step 2: the tunnel portion of side on coal mining side, which carries out grouting and reinforcing and strengthening supporting, to be waited for first passage;
Step 3: being top surface boundary driving second channel using channel interface, and to the using seat earth as bottom surface basis It helps to carry out supporting in two channels two;
Step 4: waiting for that coal mining side carries out expansion side to second channel, i.e., driving forms third channel, and to third channel into Row combined supporting forms and cuts eye by what first passage, second channel and third channel formed.
Further, it backbreaks in step 1 part roof specifically: the false roof of preservation above coal seam and weakness is straight It connects top to excavate, to stablize the top plate directly pushed up as first passage.
Further, in step 1 to first passage carry out supporting specifically: to first passage top plate totally use anchor pole, Anchor cable, metal mesh and steel band Combined Support Technology;First passage two is helped overall using anchor pole, anchor cable, metal mesh and steel Muscle ladder beam Combined Support Technology, stream line are constructed immediately following boring head.
Further, injecting paste material is super poly- concrete in step 2, and strengthening supporting mode is that complement anchor cable is reinforced Supporting.
Further, second channel two is helped in step 3 to carry out bolting with wire mesh, wherein side use in side to be mined can return Half davit carries out supporting.
Further, before carrying out combined supporting to third channel in step 4, slip casting first is carried out to the top plate of third channel It reinforces, and side and lower section progress cable supplement support to third channel.
Further, joint branch is carried out using anchor pole and dual anti-net to side the to be mined side of third channel in step 4 The top plate of shield, third channel carries out combined supporting using anchor pole, anchor cable, metal mesh and steel band, and stream line is met immediately following driving Head construction.
Compared with prior art, the invention has the following beneficial technical effects:
The present invention can poor, carrying for the high seam working face large section open*.off top plate self-stability of top plate extremely soft broken The features such as ability difference and big span, using a kind of new tunnelling and method for protecting support.This method can substantially reduce unstable The flexure effect and buckling effect of large span top plate, fundamentally improve the stress of top plate;The tunnelling technology edge Seat earth driving cuts a mode compared with along roof arrangement, and solving working face in exploitation process needs under multiple recycle gradually The process of bundle and two heading heads and the different supporting problem of working face absolute altitude, coal trigonum of not keeping on file improve coal extraction Rate;Compare and cut front pre-grouting technology before eye is dug, the technology each process intersect influence it is small, multi-process can parallel operations, Speed of application is fast and safe and reliable.The present invention has rational design, safe and reliable, speed of application is fast, it is extensive to push through application prospect, can be with Increase substantially the level of security and technical economic benefit of the high seam working face large section open*.off of top plate extremely soft broken.
Further, slip casting effect can be significantly improved to third channel roof reinforcement in side using note chemical grout, Enhance the overall stability of broken coal rock layer, provide molding basis and safety guarantee for working face extraction equipment installation space, With significant consolidation effect;Carry out cable supplement support to it on the basis of third channel top plate bolting with wire mesh, while Also there is cable supplement support in one side, and integral reinforcing effect is good, and Surrounding Rock Strength is high.
Detailed description of the invention
Fig. 1 is first passage supporting cross-section diagram;
Fig. 2 is grouted anchor bar structural schematic diagram;
Fig. 3 is grouting system equipment arrangement schematic diagram;
Fig. 4 is grouting construction process flow chart;
Fig. 5 is second channel supporting cross-section diagram;
Fig. 6 is spin anchor structure schematic diagram;
Fig. 7 is third channel supporting cross-section diagram;
In figure: 1-first passage;2-second channels;3-third channels;4-channel interfaces;5-seat earths; 6-roofs;7-twisted steel anchor rods;8-anchor cables;9-grouted anchor bars;10-conical ends;11-grouted anchor bar bars Body;12-slurry outlets;13-retaining rings;14-A group materials;15-B group materials;16-grouting pumps;17-high-pressure rubber hoses;18— Filling gun;19-sealers;20-recoverable anchor rods;21-squeeze precession conehead;22-spin anchor rod bodies;23-rotation silks; 24-pre-load nuts;25-butterfly pallets;26-country rock surfaces;27-glass fibre reinforced plastics rockbolts.
Specific embodiment
Present invention is further described in detail with reference to the accompanying drawing:
Referring to Fig. 1 to Fig. 7, a kind of coal mine down-hole tunnel driving of the invention and method for protecting support, primarily to solving three When soft high seam stope cuts eye driving, roof rock soft broken, laneway molding is difficult, so influence driving safety and The problems such as speed.The method of the present invention is will entirely to cut space and excavate to be divided into broken that top forms first passage 1, planted agent's formation second is led to Road 2 and expands side to side to be mined and forms third channel 3 and be total to three phases, comprising the following steps:
Step 1: with the channel interface apart from 5 certain distance of seat earth (height that certain distance refers to second channel 2) 4 is basic for the bottom surface of first passage 1, and part roof 6 of backbreaking abolishes false roof, and driving forms first passage 1, i.e., by coal seam The false roof of top preservation is excavated with weak directly top, and the top plate for first passage 1, tunneling process are preferably directly pushed up with stability In in time to first passage 1 carry out supporting, top plate use anchor pole+anchor cable+metal mesh+steel band Combined Support Technology, two help to use Anchor pole+anchor cable+metal mesh+reinforcing bar ladder beam Combined Support Technology implements combined supporting step by step, and stream line is immediately following driving It meets head on to construct;
Step 2: carrying out grouting and reinforcing and strengthening supporting to the tunnel portion of side of the advance of the face direction side of first passage 1, Injecting paste material is super poly- concrete, and super poly- concrete is made of A group material 14 and B group material 15, A group material 14 and B group material 15 using inorganic material as aggregate, using various kinds of resin as binding material, the characteristics of having both inorganic and high-molecular organic material, has The advantages that cohesiveness is good, early strength is high, curing time is adjustable, security performance is high, at low cost, is detailed in patent CNCN201110207625.1, strengthening supporting mode are 8 strengthening supporting of complement anchor cable;Wherein chemical grouting using theoretical calculation and The method that numerical simulation combines primarily determines out the parameters of slip casting, and depth, grouting pressure, slip casting including injected hole expand Array pitch, grouting sequence and grouted anchor bar single hole grouting amount etc. between radius, slip casting time, injected hole are dissipated, then according to field engineering Practice effect carries out feedback analysis, can optimize to every grouting parameter;
Step 3: being bottom surface basis with seat earth 5, is top surface boundary driving second channel 2 with channel interface 4, and It helps to carry out bolting with wire mesh to two in time, wherein side to be mined side selects recoverable anchor rod 10 to carry out supporting;
Step 4: carrying out expansion side to the side to be mined of second channel 2, i.e., driving forms third channel 3, to third channel On the basis of 3 top plates carry out grouting and reinforcing, cable supplement support is carried out to it from side and lower section, then to third channel 3 and Shi Jinhang combined supporting, wherein side to be mined side carries out supporting using anchor pole+dual anti-net, top plate uses anchor pole+anchor cable+metal Net+steel band carries out supporting, and stream line is constructed immediately following boring head, and second channel 2 and third channel 3 together constitute and cut eye time The space for adopting equipment installation, so far cuts eye and has been formed, i.e., be made of first passage 1, second channel 2 and third channel 3.
The present invention preferentially tunnels the pole weak broken wall rock that first passage 1 is working face extraction equipment installation space top plate and infuses Slurry provides condition, in the side slip casting of above-mentioned pole weak broken wall rock, on the one hand ensure that the safety in Grouting engineering space, separately On the one hand it is more preferable slip casting surrounding rock consolidation effect to be carried out in weak surrounding rock lower space compared with directly.
The diameter of the grouted anchor bar 9 used when slip casting is Φ 20mm~Φ 25mm.The determination of drilling depth is using numerical value Simulate determine first passage 1 formed after plastic zone of surrounding rock range as determination slip casting hole depth reference frame.When slip casting Between determination be obtained by numerical simulation working face with slip casting time change slurry infiltration areal map and pore pressure spread Cloud atlas, slurries diffusion velocity is very slow and as suitable slip casting time when tending towards stability.Grouting sequence is from bottom to top, i.e., first to infuse Help foot, then intermediate and side top is infused, the grouting mode in hole is jumped using interval.
The stability of top plate when working face open-off cut Yan Kuo lane secondary tunneling is to influence incisor canal speed and guarantee that safety digs lane Key factor.The present invention excavates working face open-off cut eye spatial decomposition at three channels stage by stage, logical by driving first Road 1 provides space for top plate coal rock layer Grouting engineering, while side portion's Anchor reinforced support of constructing, and further enhances its stabilization Property.It, can be in lag 1 suitable distance of first passage construction second channel 2 when the conditions permits such as worker's technical level, construction organization; If equipment equipment allows, can also construct second channel 2 and third channel 3 simultaneously.
Operating process of the invention is described in detail below with reference to embodiment:
A kind of coal mine roadway driving and method for protecting support of the present invention, are divided into brokenly top for entire incisor canal and form first Channel 1, planted agent, which form second channel 2 and expand side, forms 3 three phases of third channel, comprising steps of
Step 1: any end being connected to using two lanes with working face open-off cut eye is starting point, apart from 5 certain distance of seat earth Channel interface 4 be first passage 1 base plinth, part roof 6 of backbreaking abolishes false roof, using development machine or quick-fried Broken mode tunnels first passage 1, which is the tunnel for being connected to air return lane and air inlet.
Step 2: carrying out anchor pole+anchor cable+metal mesh+steel band branch to top plate for the stability for guaranteeing 1 country rock of first passage Shield, stream line arrangement alternate with anchor pole, anchor cable are constructed immediately following boring head.7 length of twisted steel anchor rod is 2.4m, and an array pitch is 900×800mm;Anchor cable 8 select seven strands of prestress wires, specification be 17.8 × 6000mm of Φ, array pitch be 1400 × 1600mm, anchor pole cooperate 300 × 300 × 10mm drum type pallet, and anchor cable cooperates steel band cushioning 400 × 400 × 12mm flat pallet.
Two help to carry out supporting with anchor pole+metal+reinforcing bar ladder beam+anchor cable, to avoid the later period to 3 roof timbering of third channel It impacts, anchor cable and anchor pole are arranged on same section, and anchor cable lag boring head 30m construction.Bolt interval is 800 × 800mm, array pitch is 1600 × 1600mm between anchor cable, and help foot anchor pole is not more than 300mm away from bottom plate distance, lags first passage 1 On boring head certain distance to 1 working face lateral wall of first passage carry out 8 reinforcement supporting of anchor cable, array pitch be 1600 × 1600mm, the same roof timbering of the parameters such as pallet, supporting cross-section diagram are as shown in Figure 1.Twisted steel anchor rod pretightning force in coal seam and rock stratum Square is not less than 200Nm and 250Nm, and anchor cable pretightning force is not less than 8T, and to anchor pole, rope pretightning force after having constructed 7 days (square) carries out secondary preload, to eliminate the springback influence of pretightning force (square).
Step 3: carrying out slip casting to the work of first passage 1 surface side tunnel portion of side.Grouting parameter should be according to theoretical calculation, number Value simulation primarily determines, and is advanced optimized according to field conduct effect, and major parameter includes grouting pressure, slurries diffusion half Array pitch, grouting sequence etc. between diameter, slip casting time, injected hole.
Grouted anchor bar 9 is mounted on the portion of side side to be mined of first passage 1.9 protruded length 100mm of grouted anchor bar is used 26 bit bore of Φ is to projected depth, hole depth 2.2m.Grouted anchor bar 9 is put into drilling, is then put into along anchor pole bar diameter hollow Annular cement volume is blocked with the gauze of dipping cement slurry.It is that a kind of dual liquid type changes that injecting paste material, which selects Bo Leiyin, Bo Leiyin, Property polyurethane injecting paste material, be made of 15 two kinds of liquid components of A group material 14 and B group material, carried out by weight 1:1 when construction Mixing.Slip casting from bottom to top in same section, i.e., first infuse help foot, then infuse in side, finally note side top;Different section class interval note Slurry, every 8 row are one group, i.e., first carry out 1,3,5,7 single slip castings, then carry out 2,4,6,8 double rows slip castings, successively alternately.Note It starches pressure and is not more than 3Mpa.The single hole slip casting time is 10~13min.To guarantee that slip casting can be closely knit by fracture filling, answer in principle Infuse to it is unobvious eat slurry until.After the completion of slip casting, in grouted anchor bar exposed junction cushioning pallet, and pre-tightened with nut, pre-fastening moment Not less than 150Nm.
9 structural schematic diagram of grouted anchor bar is as shown in Figure 2.9 front end of grouted anchor bar is conical end 10, and length K is 200mm, and firm welding.The grouted anchor bar body of rod 11 arranges that Φ 8mm slurry outlet 12, pitch-row d=200mm are in five flower-shaped arrangements, bar Outer diameter D=22mm, wall thickness 3mm, do not set slurry outlet in the L=500mm of body of rod rear end, thread segment S=100mm, and retaining ring 13 is high 5mm.As country rock extremely it is broken cause drilling can not pore-forming, then Self-propelled grouting anchoring-bolt can be selected.Grouting system equipment arrangement is shown It is intended to as shown in Figure 3.
Grouting construction process flow chart is as shown in Figure 4.Drilling → installation grouted anchor bar 9 → installation 19 → high pressure of hole packer Rubber tube 17 connects filling gun 18 and grouting pump 16 → two root canals are respectively connected in A group material 14 and B group material 15 → is opened Open grouting pump 16 → reach slip casting requirement → closing grouting pump 16 → disassembly filling gun 18.
Before each slip casting class uses grouting pump, should all check whether equipment is normal by way of with pump suction clear water Work, including grouting pipeline, pressure gauge etc..
Step 4: driving second channel 2.It is acted as a planted agent first passage 1 to seat earth 5 using development machine or big gun pick mode Between driving form second channel 2, and help to carry out anchor pole+metal mesh+reinforcing bar ladder beam supporting to two, array pitch is 800 × 800mm, side side to be mined carry out supporting with recoverable prestressed anchor pole 20, and recoverable anchor rod 20 selects spirally recyclable anchor Bar carries out supporting to country rock using the frictional force and pretightning force of rotation silk 23 and fastener offer on spin anchor rod body 22. For remaining parameter with the requirement of first passage 1, supporting section is as shown in Figure 5.
Recoverable anchor rod 20, i.e., recyclable prestressed anchor structural schematic diagram are as shown in Figure 6.20 front end of recoverable anchor rod is Precession conehead 21, length N=50mm are squeezed, spin 22 diameter of anchor rod body is 20mm, is covered with rotation silk on the anchor rod body 22 that spins 23, rotation silk spacing M are 30~40mm, and rotation silk height is 4~7mm.Dish is held in the palm by applying torque to pre-load nut 24 rear end Disk 25 is close to country rock surface 26, has the function that apply pretightning force to recoverable anchor rod 20.The anchor pole is to bore anchoring integrated anchor rod, I.e. without using Anchor Agent, the initial deformation of dependence and weak surrounding rock is fast and boring aperture and body of rod nominal diameter similar in Feature realizes pretightning force and guarantees anchor force.
Step 5: driving third channel 3.Using development machine or big gun pick mode to the side to be mined of second channel 2 help into Row expands side and forms third channel 3, carries out anchor pole+anchor cable+metal mesh+steel band combined supporting, roofbolt and anchor cable cloth to top plate It sets in same section, and helps portion's support anchor rod, section where rope to be staggered half of array pitch, i.e. 400mm with first passage 1, wherein Anchor cable is constructed immediately following boring head.Array pitch is 1500 × 1600mm between three anchor cables of top plate, remaining parameter is the same as 1 top plate of first passage Supporting requirement.
Side side to be mined anchor pole+dual anti-net supporting, anchor pole select glass fibre reinforced plastics rockbolts 27, and glass steel tray selects spherical shell Thickness and height are respectively the pallet of 7mm and 18mm.Supporting section is as shown in Figure 7.
Step 6: checking Grouting engineering consolidation effect, it can be used that 3 roof strata of third channel drill and peep The method that inspection is looked into observes roof strata fracture filling situation;Analysis is optimized to supporting parameter, mainly by top plate Rock stratum absciss layer is monitored, and checks the stability of top plate entirety, adjusts supporting parameter.
The above is only presently preferred embodiments of the present invention, not any limitation of the invention, it is all according to the present invention Technical spirit any simple modification change and equivalent structural changes made to the above embodiment, belong to of the invention In the protection scope of technical solution.

Claims (7)

1. a kind of coal mine roadway driving and method for protecting support, which is characterized in that entire incisor canal is divided into brokenly top formation first and is led to Road (1), planted agent, which form second channel (2) and expand side to side to be mined, forms third channel (3) three phases, specifically includes Following steps:
Step 1: it with the bottom surface basis that the channel interface (4) apart from seat earth (5) height H is first passage (1), backbreaks Part roof (6), driving are formed first passage (1), carry out supporting to first passage (1) in tunneling process, and wherein H is the The height in two channels (2);
Step 2: grouting and reinforcing and strengthening supporting are carried out to the tunnel portion of side on first passage (1) side to be mined;
Step 3: being bottom surface basis with seat earth (5), is that second channel (2) are tunneled on top surface boundary with channel interface (4), And second channel (2) two is helped to carry out supporting;
Step 4: carrying out expansion side to second channel (2) side to be mined, i.e., driving forms third channel (3), and to third channel (3) combined supporting is carried out, that is, is formed and cuts eye by what first passage (1), second channel (2) and third channel (3) formed.
2. a kind of coal mine roadway driving according to claim 1 and method for protecting support, which is characterized in that portion of backbreaking in step 1 Divide roof (6) specifically: the false roof of preservation above coal seam and weak directly push up are excavated, directly pushed up using stablizing as first The top plate in channel (1).
3. a kind of coal mine roadway driving according to claim 1 and method for protecting support, which is characterized in that first in step 1 Channel (1) carries out supporting specifically: totally uses anchor pole, anchor cable, metal mesh and steel band joint branch to first passage (1) top plate Shield;First passage (1) two is helped totally using anchor pole, anchor cable, metal mesh and reinforcing bar ladder beam combined supporting, wherein to first Channel (1) top plate is overall and helps overall anchor cable to closely follow boring head construction first passage (1) two.
4. a kind of coal mine roadway driving according to claim 1 and method for protecting support, which is characterized in that slip casting material in step 2 Material is super poly- concrete, and strengthening supporting mode is that complement anchor cable (8) carry out strengthening supporting.
5. a kind of coal mine roadway driving according to claim 1 and method for protecting support, which is characterized in that second in step 3 Channel (2) two is helped to carry out bolting with wire mesh, wherein side to be mined side carries out supporting using recoverable anchor rod (20).
6. a kind of coal mine roadway driving according to claim 1 and method for protecting support, which is characterized in that third in step 4 Before channel (3) carries out combined supporting, grouting and reinforcing first is carried out to the top plate of third channel (3), and to the side of third channel (3) Cable supplement support is carried out with lower section.
7. a kind of coal mine roadway driving according to claim 1 and method for protecting support, which is characterized in that third in step 4 Side the to be mined side in channel (3) carries out combined supporting using anchor pole and dual anti-net, the top plate of third channel (3) using anchor pole, Anchor cable, metal mesh and steel band carry out combined supporting, and stream line is constructed immediately following boring head.
CN201710512244.1A 2017-06-28 2017-06-28 A kind of coal mine roadway driving and method for protecting support Active CN107143338B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710512244.1A CN107143338B (en) 2017-06-28 2017-06-28 A kind of coal mine roadway driving and method for protecting support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710512244.1A CN107143338B (en) 2017-06-28 2017-06-28 A kind of coal mine roadway driving and method for protecting support

Publications (2)

Publication Number Publication Date
CN107143338A CN107143338A (en) 2017-09-08
CN107143338B true CN107143338B (en) 2018-12-25

Family

ID=59784334

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710512244.1A Active CN107143338B (en) 2017-06-28 2017-06-28 A kind of coal mine roadway driving and method for protecting support

Country Status (1)

Country Link
CN (1) CN107143338B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107654247B (en) * 2017-09-22 2019-04-16 中国矿业大学 A kind of sliding structure area pole loose thick coal layer coal roadway tunneling is met head on anti-top coal leakage method for leakage
CN108035742B (en) * 2017-11-16 2023-04-14 河南理工大学 Active and passive harmonious support method for extremely soft coal seam roadway
CN109958459B (en) * 2019-03-05 2021-07-23 辽宁工程技术大学 Soft thick coal seam bottom tunneling method
CN111663945A (en) * 2020-05-27 2020-09-15 山东黄金矿业(莱州)有限公司三山岛金矿 Open roof cutting roadway type upward wide drift filling mining method
CN112664248A (en) * 2020-12-25 2021-04-16 国家能源集团宁夏煤业有限责任公司 Soft rock water spraying roadway supporting method
CN113153315A (en) * 2021-04-26 2021-07-23 中国矿业大学 Deep large-section hole-cutting roadway-forming mode and method for determining supporting time
CN113914867A (en) * 2021-10-12 2022-01-11 国能神东煤炭集团有限责任公司 Top plate reinforcing method for tunneling lower layering cut hole under upper layering goaf

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001023711A1 (en) * 1998-07-16 2001-04-05 Kfc Ltd. Ground reinforcing method
CN102305074A (en) * 2011-08-15 2012-01-04 鞍钢集团矿业公司 Flat-bottomed pillar sublevel caving method of reinforced concrete structure artificial roof
CN102390952A (en) * 2011-07-22 2012-03-28 安徽佳泰矿业科技有限公司 Super-polymerized concrete composite material and preparation method thereof
CN104141496A (en) * 2014-06-21 2014-11-12 西安科技大学 Rectangular roadway surrounding rock deformation and failure control method
CN105525919A (en) * 2014-09-29 2016-04-27 四川省华蓥山煤业股份有限公司绿水洞煤矿 Steeply inclined fully-mechanized mining face open-off cut enlarging and equipment installation crossing operation method
CN105781597A (en) * 2014-12-16 2016-07-20 淮南矿业(集团)有限责任公司 Method for performing anchoring and grouting reinforcement inside deep well soft rock gob-side entry retaining
CN106351663A (en) * 2016-09-29 2017-01-25 淮南矿业(集团)有限责任公司 Retrograde brush expansion process for cut construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001023711A1 (en) * 1998-07-16 2001-04-05 Kfc Ltd. Ground reinforcing method
CN102390952A (en) * 2011-07-22 2012-03-28 安徽佳泰矿业科技有限公司 Super-polymerized concrete composite material and preparation method thereof
CN102305074A (en) * 2011-08-15 2012-01-04 鞍钢集团矿业公司 Flat-bottomed pillar sublevel caving method of reinforced concrete structure artificial roof
CN104141496A (en) * 2014-06-21 2014-11-12 西安科技大学 Rectangular roadway surrounding rock deformation and failure control method
CN105525919A (en) * 2014-09-29 2016-04-27 四川省华蓥山煤业股份有限公司绿水洞煤矿 Steeply inclined fully-mechanized mining face open-off cut enlarging and equipment installation crossing operation method
CN105781597A (en) * 2014-12-16 2016-07-20 淮南矿业(集团)有限责任公司 Method for performing anchoring and grouting reinforcement inside deep well soft rock gob-side entry retaining
CN106351663A (en) * 2016-09-29 2017-01-25 淮南矿业(集团)有限责任公司 Retrograde brush expansion process for cut construction

Also Published As

Publication number Publication date
CN107143338A (en) 2017-09-08

Similar Documents

Publication Publication Date Title
CN107143338B (en) A kind of coal mine roadway driving and method for protecting support
CN105041325B (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN104790978B (en) The tunnel ring-shaped base tunnel construction method of small interval crossings on different level
CN103306687B (en) Soft rock tunnel long cantilever horizontal jet grouting Deformation control construction method
CN102493821B (en) Support method for high stress roadway coal-rock mass
CN109372555A (en) A kind of fault disruption zone area tunnel 3 D stereo grouting support method
CN103615250B (en) The full Open stope mining afterwards filling of itemize studding works in coordination with mining codes
CN102877858B (en) Reinforcing method for crushed top plate of coal face
CN103032086B (en) Method for filling resin explosive cartridge in drilled hole of tunnel roof anchor rod
CN105781571A (en) Construction method for soft rock deformation tunnel lining support dismantling-replacing arch
CN106884655B (en) A kind of two-way reinforcement means of gob side entry driving coal column
CN104533446A (en) Construction method and structure of two-layer preliminary support for preventing geological disaster of large-section weak surrounding rock tunnel
CN106481343A (en) A kind of Soft Rock Tunnel Excavation and preliminary bracing method
CN110374600A (en) A kind of ultra close distance coal seam group stope drift active workings are error-free away from formula method for arranging
CN105971640A (en) Strengthening method for gob-side entrydriving narrow coal pillar
CN103306713A (en) Networking reinforcement method for cross drilling holes of outburst coal seam
CN110656951A (en) Disaster safety control method for full-face tunnel boring machine excavation extrusion deformation card machine
CN109681248A (en) A kind of grouting cable anchor advanced support method
CN103195467A (en) Hydraulic fracturing and grouting solidification combined rock cross-cut coal uncovering method
CN105927243B (en) A kind of underground country rock tomography suspension device and method for protecting support
CN111535817A (en) Working face double-lane tunneling small coal pillar reinforcement construction method
CN102704965A (en) Method for preventing tunnel top plate collapse risk caused by severe mining
CN102966359A (en) Working face ventilation oxidization zone roof control method
CN108487924B (en) A kind of reinforcement means of soft coal level gob side entry driving thin coal pillar
CN102425428A (en) Method for controlling extreme broken roof in roadway head

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant