CN110778123A - 一种混凝土钢筋绑扎施工方法 - Google Patents

一种混凝土钢筋绑扎施工方法 Download PDF

Info

Publication number
CN110778123A
CN110778123A CN201911096748.5A CN201911096748A CN110778123A CN 110778123 A CN110778123 A CN 110778123A CN 201911096748 A CN201911096748 A CN 201911096748A CN 110778123 A CN110778123 A CN 110778123A
Authority
CN
China
Prior art keywords
stirrups
construction method
install
formwork
fixing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911096748.5A
Other languages
English (en)
Other versions
CN110778123B (zh
Inventor
王云莺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Fuqian Construction Development Co Ltd
Original Assignee
Fujian Fuqian Construction Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Fuqian Construction Development Co Ltd filed Critical Fujian Fuqian Construction Development Co Ltd
Priority to CN201911096748.5A priority Critical patent/CN110778123B/zh
Publication of CN110778123A publication Critical patent/CN110778123A/zh
Application granted granted Critical
Publication of CN110778123B publication Critical patent/CN110778123B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12—Mounting of reinforcing inserts; Prestressing
    • E04G21/122—Machines for joining reinforcing bars
    • E04G21/123—Wire twisting tools

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

本发明公开了一种混凝土钢筋绑扎施工方法,包括以下步骤:(1)、搭建底座模板并固定;(2)、在底座模板的顶部固定横担,在横担上安装立柱模板;(3)、在立柱模板顶端安装弯钩,在弯钩的一侧安装箍筋,在箍筋四角处固定主筋,并在主筋表面按照图纸依次安装箍筋;(4)、在靠近立柱模板的两侧上下箍筋之间按照图纸依次安装辅筋;(5)、在箍筋剩下的两侧安装辅筋,并安装剩余的立柱模板。本发明涉及建筑领域。该种混凝土钢筋绑扎施工方法通过,通过在立柱模板上通过弯钩固定箍筋,随后进行主筋和辅筋的固定,避免了钢筋需要在底部支撑的问题,无需焊接和底部垫块,将绑扎钢筋和固定模板同步进行,提高了施工效率。

Description

一种混凝土钢筋绑扎施工方法
技术领域
本发明涉及建筑领域,具体为一种混凝土钢筋绑扎施工方法。
背景技术
建筑行业就是一个围绕建筑的设计、施工、装修、管理而展开的行业。在电力建筑中,铁塔的基础建设是重要的一项工程,在基础建设中,通常设计的立柱支撑钢筋通常悬空设计,底部不延伸到底座底部,在绑扎钢筋过程中,施工方只好延长主筋的长度进行绑扎,但对于根据图纸加工好的钢筋,一种是对主筋进行焊接延长,耗时耗力,效率低;另一种是在主筋底部垫上石块,石块过大不满足混凝土的要求,石块较小难以支撑钢筋重量,在施工中极为不便。
发明内容
为了解决上述缺陷,本发明提供了一种混凝土钢筋绑扎施工方法,解决了立柱钢筋悬空设计带来的绑扎不方便问题,提高了工作效率。
为了实现上述目的,本发明提供的技术方案为,一种混凝土钢筋绑扎施工方法,包括以下步骤:
(1)、搭建底座模板并固定;
(2)、在底座模板的顶部固定横担,在横担上安装立柱模板;
(3)、在立柱模板顶端安装弯钩,在弯钩的一侧安装箍筋,在箍筋四角处固定主筋,并在主筋表面按照图纸依次安装箍筋;
(4)、在靠近立柱模板的两侧上下箍筋之间按照图纸依次安装辅筋;
(5)、在箍筋剩下的两侧安装辅筋,并安装剩余的立柱模板。
优选的,在步骤(2)中实用的横担为角钢,角钢两侧设置有木块,且木块固定在底座模板顶部。
优选的,在步骤(3)中立柱模板顶端设置有防磨铁片,每一侧的立柱模板至少有三个弯钩。
优选的,在步骤(3)中箍筋与主筋之间通过扎丝固定。
优选的,在步骤(4)和步骤(5)中箍筋与辅筋之间通过扎丝固定。
优选的,在步骤(3)中底部的箍筋与立柱模板之间设置有木块。
优选的,在步骤(4)中每一根与辅筋与每层箍筋之间通过扎丝固定。
本发明采用上述技术方案,有益效果包括:该种混凝土钢筋绑扎施工方法通过,通过在立柱模板上通过弯钩固定箍筋,随后进行主筋和辅筋的固定,避免了钢筋需要在底部支撑的问题,无需焊接和底部垫块,将绑扎钢筋和固定模板同步进行,提高了施工效率。
附图说明
图1为本发明绑扎钢筋示意图;
图2为本发明图1中A处放大图。
图中:1-底座模板、2-横担、3-立柱模板、4-弯钩、5-箍筋、6-主筋、7-辅筋。
具体实施方式
以下结合附图对本发明作出进一步的说明。
实施例一:请参阅图1-2,本发明提供一种技术方案:一种混凝土钢筋绑扎施工方法,包括以下步骤:
(1)、搭建底座模板1并固定;
(2)、在底座模板的顶部固定横担2,在横担2上安装立柱模板3,立柱模板3的侧面可通过支撑杆固定;
(3)、在立柱模板3顶端安装弯钩4,在弯钩4的一侧安装箍筋5,在箍筋5四角处固定主筋6,并在主筋6表面按照图纸依次安装箍筋5;
(4)、在靠近立柱模板3的两侧上下箍筋5之间按照图纸依次安装辅筋7,便于绑扎操作;
(5)、在箍筋5剩下的两侧安装辅筋7,并安装剩余的立柱模板3,所有的立柱模板3组成矩形立柱,可在立柱模板3组成矩形立柱内浇筑混凝土。
在步骤(2)中实用的横担2为角钢,角钢的一侧便于对立柱模板支撑,角钢两侧设置有木块,且木块固定在底座模板顶部,通过木块将角钢固定,避免角钢滑动。
在步骤(3)中立柱模板顶端设置有防磨铁片,避免钢筋过重,弯钩4对立柱模板3边缘造成损坏,每一侧的立柱模板至少有三个弯钩4,保证了钢筋的稳定。
在步骤(3)中箍筋与主筋之间通过扎丝固定,采用常规方法绑扎,便于施工。
在步骤(4)和步骤(5)中箍筋与辅筋之间通过扎丝固定,采用常规方法绑扎,便于施工。
在步骤(3)中底部的箍筋5与立柱模板3之间设置有木块,避免钢筋悬挂晃动。
在步骤(4)中每一根与辅筋与每层箍筋之间通过扎丝固定,提高了整体的稳定。
该种混凝土钢筋绑扎施工方法通过,通过在立柱模板上通过弯钩固定箍筋,随后进行主筋和辅筋的固定,避免了钢筋需要在底部支撑的问题,将绑扎钢筋和固定模板同步进行,提高了施工效率。
需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下。由语句“包括一个......限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素”。
以上所述仅为本发明的固定、安装现有技术型的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。

Claims (7)

1.一种混凝土钢筋绑扎施工方法,其特征在于:包括以下步骤:(1)、搭建底座模板并固定;
(2)、在底座模板的顶部固定横担,在横担上安装立柱模板;
(3)、在立柱模板顶端安装弯钩,在弯钩的一侧安装箍筋,在箍筋四角处固定主筋,并在主筋表面按照图纸依次安装箍筋;
(4)、在靠近立柱模板的两侧上下箍筋之间按照图纸依次安装辅筋;
(5)、在箍筋剩下的两侧安装辅筋,并安装剩余的立柱模板。
2.根据权利要求1所述的一种混凝土钢筋绑扎施工方法,其特征在于:在步骤(2)中实用的横担为角钢,角钢两侧设置有木块,且木块固定在底座模板顶部。
3.根据权利要求1所述的一种混凝土钢筋绑扎施工方法,其特征在于:在步骤(3)中立柱模板顶端设置有防磨铁片,每一侧的立柱模板至少有三个弯钩。
4.根据权利要求1所述的一种混凝土钢筋绑扎施工方法,其特征在于:在步骤(3)中箍筋与主筋之间通过扎丝固定。
5.根据权利要求1所述的一种混凝土钢筋绑扎施工方法,其特征在于:在步骤(4)和步骤(5)中箍筋与辅筋之间通过扎丝固定。
6.根据权利要求1所述的一种混凝土钢筋绑扎施工方法,其特征在于:在步骤(3)中底部的箍筋与立柱模板之间设置有木块。
7.根据权利要求1所述的一种混凝土钢筋绑扎施工方法,其特征在于:在步骤(4)中每一根与辅筋与每层箍筋之间通过扎丝固定。
CN201911096748.5A 2019-11-11 2019-11-11 一种混凝土钢筋绑扎施工方法 Expired - Fee Related CN110778123B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911096748.5A CN110778123B (zh) 2019-11-11 2019-11-11 一种混凝土钢筋绑扎施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911096748.5A CN110778123B (zh) 2019-11-11 2019-11-11 一种混凝土钢筋绑扎施工方法

Publications (2)

Publication Number Publication Date
CN110778123A true CN110778123A (zh) 2020-02-11
CN110778123B CN110778123B (zh) 2021-08-27

Family

ID=69391667

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911096748.5A Expired - Fee Related CN110778123B (zh) 2019-11-11 2019-11-11 一种混凝土钢筋绑扎施工方法

Country Status (1)

Country Link
CN (1) CN110778123B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111779193A (zh) * 2020-08-07 2020-10-16 中交路桥华东工程有限公司 一种抗滑桩钢筋笼的绑扎方法
CN114991387A (zh) * 2022-06-16 2022-09-02 甘肃省安装建设集团有限公司 一种平单轴支护装置及其使用方法
CN115613763A (zh) * 2022-10-20 2023-01-17 通州建总集团有限公司 一种建筑箍筋布置固定机构

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2378149A1 (en) * 1977-01-25 1978-08-18 Diteco Sl Rectangular section reinforced concrete girder - consists of base with bottom ends of clamps embedded underneath stretched metal cables
CN104499501A (zh) * 2014-12-08 2015-04-08 国家电网公司 一种输电线路窄基塔单桩墩式自稳基础
CN106150085A (zh) * 2015-04-07 2016-11-23 五冶集团上海有限公司 一种劲性柱模板安装方法
CN206053358U (zh) * 2016-07-12 2017-03-29 河北晶通建筑科技股份有限公司 一种独立基础柱墩钢筋绑扎架
CN206267425U (zh) * 2016-11-22 2017-06-20 中建四局第五建筑工程有限公司 一种可周转使用钢筋马凳的装置
CN207160046U (zh) * 2017-08-11 2018-03-30 广东南方电信规划咨询设计院有限公司 一种通过锥形基础有效控制无线杆塔的塔基
CN109537810A (zh) * 2019-01-17 2019-03-29 中建科技有限公司深圳分公司 钢结构节点、预制柱及其制作方法、柱梁的装配方法
CN109707104A (zh) * 2018-12-27 2019-05-03 中南大学 一种带拉筋钢管混凝土浇筑体及施工方法
CN209353732U (zh) * 2018-11-29 2019-09-06 中国建筑第八工程局有限公司 用于绑扎柱箍筋的临时固定装置
CN110331780A (zh) * 2019-07-02 2019-10-15 中国建筑第八工程局有限公司 风洞洞体结构施工用钢筋布置方法

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2378149A1 (en) * 1977-01-25 1978-08-18 Diteco Sl Rectangular section reinforced concrete girder - consists of base with bottom ends of clamps embedded underneath stretched metal cables
CN104499501A (zh) * 2014-12-08 2015-04-08 国家电网公司 一种输电线路窄基塔单桩墩式自稳基础
CN106150085A (zh) * 2015-04-07 2016-11-23 五冶集团上海有限公司 一种劲性柱模板安装方法
CN206053358U (zh) * 2016-07-12 2017-03-29 河北晶通建筑科技股份有限公司 一种独立基础柱墩钢筋绑扎架
CN206267425U (zh) * 2016-11-22 2017-06-20 中建四局第五建筑工程有限公司 一种可周转使用钢筋马凳的装置
CN207160046U (zh) * 2017-08-11 2018-03-30 广东南方电信规划咨询设计院有限公司 一种通过锥形基础有效控制无线杆塔的塔基
CN209353732U (zh) * 2018-11-29 2019-09-06 中国建筑第八工程局有限公司 用于绑扎柱箍筋的临时固定装置
CN109707104A (zh) * 2018-12-27 2019-05-03 中南大学 一种带拉筋钢管混凝土浇筑体及施工方法
CN109537810A (zh) * 2019-01-17 2019-03-29 中建科技有限公司深圳分公司 钢结构节点、预制柱及其制作方法、柱梁的装配方法
CN110331780A (zh) * 2019-07-02 2019-10-15 中国建筑第八工程局有限公司 风洞洞体结构施工用钢筋布置方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111779193A (zh) * 2020-08-07 2020-10-16 中交路桥华东工程有限公司 一种抗滑桩钢筋笼的绑扎方法
CN114991387A (zh) * 2022-06-16 2022-09-02 甘肃省安装建设集团有限公司 一种平单轴支护装置及其使用方法
CN115613763A (zh) * 2022-10-20 2023-01-17 通州建总集团有限公司 一种建筑箍筋布置固定机构

Also Published As

Publication number Publication date
CN110778123B (zh) 2021-08-27

Similar Documents

Publication Publication Date Title
CN106276577B (zh) 一种框架独立基础的吊架及操作方法
CN110778123B (zh) 一种混凝土钢筋绑扎施工方法
CN109610739B (zh) 一种可周转装配式马镫及高平整度楼板的施工方法
CN106192607B (zh) 地铁道床钢筋笼悬吊式绑扎胎具及其应用
CN104533015A (zh) 现浇混凝土梁板中梁钢筋保护层的施工方法
CN110042988A (zh) 一种可循环利用的多功能马镫及其施工方法
CN101570999A (zh) 一种保证楼板保护层厚度的支撑架及其施工方法
CN117230924A (zh) 一种架空层预铺挂钩式一体化浇筑保温施工方法
CN205223864U (zh) 一种移动模架用钢筋绑扎胎具
CN207436503U (zh) 高效预制楼板施工的吊模组件
CN106760528A (zh) 一种混凝土免拆模施工新工艺
CN206554500U (zh) 钢结构混凝土浇筑用可调横向支撑杆
CN105463996A (zh) 一种用于预制立柱单机吊装的翻转装置和方法
CN104878926A (zh) 一种悬挂模板体系施工方法及可周转支托
CN204385626U (zh) 箱梁钢筋绑扎胎膜支架
CN203285056U (zh) 楼梯模板支撑底座
CN104005564B (zh) 一种大型钢管斜立柱的安装工艺
CN214462700U (zh) 水平钢筋绑扎平台
CN207538506U (zh) 高效预制楼板施工的独立支撑架
CN207211767U (zh) 一种用于楼板浇筑施工的板厚控制工具
CN204212302U (zh) 一种空心板轻质管抗浮结构
CN210659296U (zh) 浇筑漏斗
CN209653442U (zh) 用于预埋套管的支架
CN216840669U (zh) 一种悬挂法控制砼板厚度的方管架支撑装置
CN211597384U (zh) 钢筋马凳

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210827