- CN110387954A CN110387954A CN201910714121.5A CN201910714121A CN110387954A CN 110387954 A CN110387954 A CN 110387954A CN 201910714121 A CN201910714121 A CN 201910714121A CN 110387954 A CN110387954 A CN 110387954A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- prefabricated panel
- panel
- foundation plate
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000002360 preparation method Methods 0.000 title abstract description 5
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 58
- 239000010959 steel Substances 0.000 claims abstract description 58
- 238000009413 insulation Methods 0.000 claims abstract description 30
- 238000010276 construction Methods 0.000 claims abstract description 24
- 239000004567 concrete Substances 0.000 claims abstract description 23
- 239000011490 mineral wool Substances 0.000 claims abstract description 16
- 239000004568 cement Substances 0.000 claims abstract description 14
- 229910052918 calcium silicate Inorganic materials 0.000 claims abstract description 13
- 239000000378 calcium silicate Substances 0.000 claims abstract description 13
- OYACROKNLOSFPA-UHFFFAOYSA-N calcium;dioxido(oxo)silane Chemical compound [Ca+2].[O-][Si]([O-])=O OYACROKNLOSFPA-UHFFFAOYSA-N 0.000 claims abstract description 13
- 238000009434 installation Methods 0.000 claims description 18
- 238000005034 decoration Methods 0.000 claims description 12
- 238000000465 moulding Methods 0.000 claims description 11
- 238000004519 manufacturing process Methods 0.000 claims description 8
- 239000002689 soil Substances 0.000 claims description 6
- 239000011178 precast concrete Substances 0.000 claims description 5
- 238000005266 casting Methods 0.000 claims description 4
- 238000003032 molecular docking Methods 0.000 claims description 4
- 230000015271 coagulation Effects 0.000 claims description 2
- 238000005345 coagulation Methods 0.000 claims description 2
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 210000000988 bone and bone Anatomy 0.000 claims 1
- 239000007787 solid Substances 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 4
- 239000000203 mixture Substances 0.000 abstract description 3
- 238000009417 prefabrication Methods 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 5
- 238000004321 preservation Methods 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- OYPRJOBELJOOCE-UHFFFAOYSA-N Calcium Chemical compound [Ca] OYPRJOBELJOOCE-UHFFFAOYSA-N 0.000 description 1
- 241000238586 Cirripedia Species 0.000 description 1
- XUIMIQQOPSSXEZ-UHFFFAOYSA-N Silicon Chemical compound [Si] XUIMIQQOPSSXEZ-UHFFFAOYSA-N 0.000 description 1
- 239000011449 brick Substances 0.000 description 1
- 229910052791 calcium Inorganic materials 0.000 description 1
- 239000011575 calcium Substances 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 238000009877 rendering Methods 0.000 description 1
- 229910052710 silicon Inorganic materials 0.000 description 1
- 239000010703 silicon Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/02—Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/74—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
- E04B1/76—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/92—Protection against other undesired influences or dangers
- E04B1/94—Protection against other undesired influences or dangers against fire
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/24—Structural elements or technologies for improving thermal insulation
- Y02A30/244—Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B30/00—Energy efficient heating, ventilation or air conditioning [HVAC]
- Y02B30/90—Passive houses; Double facade technology
Abstract
The present invention relates to a kind of assembled energy-saving New Residence structures and preparation method thereof, are characterized in that, including prefabricated profiled prefabricated foundation plate, prefabricated panel, integral roofing, floor panels and exterior-wall heat insulation integrated board;Pass through reserved bayonet slot and concrete connection between the prefabricated foundation plate and prefabricated panel;Pass through reserved opening and pre-embedded steel slab between adjacent prefabricated panel and is bolted fixation;Integral roofing successively includes lightgage steel joist, calcium silicate board, waterproof layer, batten, rock-wool heat insulation plate and prefabricated anti-ancient cement tile from inside to outside;Fixation is bolted between the lightgage steel joist of the integral roofing and the pre-embedded steel slab of prefabricated panel.The present invention uses precast construction independent, the prefabrication process of each component is produced in factory, then it is transported to construction site to be assembled, assembly node design substantially shortens construction period rationally and with a certain amount of non-deformability, composition easy operation between each component.
Description
Technical field
The present invention relates to technical field of buildings, are a kind of assembled energy-saving New Residence structure and its production side specifically
Method.
Background technique
The more site operations of present countryside housing have long construction period, generate more waste material, style sheet one and construction quality hardly possible
The disadvantages of to guarantee.Especially north of china in winter is cold, and building wall, roof beam structure fabrication and installation, roofing tiling, exterior rendering etc. is wet in wall
Job execution difficulty is big, at high cost.And rural area tradition craftsman older and leave no successor, so that a set of traditional residence is built
There is a serious shortage in the supply by required carpenter, bricklayer, bricklayer's, electrician, Paste Up Man etc., causes the construction period at least in half a year to 1 year or so,
And the day and night temperature in the north is big, and masonry panel is caused to be easy cracking, the heat insulating ability, anti-of the brick, barnacle of tradition, local timber structure
Pinking is again not satisfactory.
The lightweight steel construction that existing market is being promoted+rock wool heat-preservation system, is difficult to be accepted in form and fire line and peace
Full property is poor;Timber structure or weight steel construction assembled New Residence, cost is again too high, is difficult to be received in cost.
Summary of the invention
The present invention is intended to provide a kind of assembled energy-saving New Residence structure and preparation method thereof, the structure is included in production
The various prefabricated components made in advance in workshop;The production method is to transport to the various prefabricated components completed in workshop to apply
Work on-site assembly assembles convenient and quick construction, and is not limited by external environment.
The technical solution adopted by the invention is as follows:
A kind of assembled energy-saving New Residence structure, is characterized in that, including prefabricated profiled prefabricated foundation plate 2, prefabricated panel
3, integral roofing 4, floor panels 5 and exterior-wall heat insulation integrated board 6;
Wherein, the prefabricated foundation plate 2 is poured the molding prefabricated foundation plate of concrete mold using in workshop;It is described prefabricated
Base plate 2 is paved on the top of blinding layer providing integral planar supporting framework, between adjacent prefabricated foundation plate 2
It is mutually butted;
Connecting node between the prefabricated foundation plate 2 and prefabricated panel 3 are as follows: bayonet slot 21, institute are reserved on prefabricated foundation plate 2
The bottom for stating prefabricated panel 3 is plugged in the bayonet slot 21, and tamps fixation by concrete;
The prefabricated panel 3 is poured the molding precast concrete wall panel of concrete mold using in workshop;
Connecting node between adjacent prefabricated panel 3 are as follows: the avris mold of prefabricated panel 3 forms reserved opening 31 and pre-buried
Steel plate 32, the pre-embedded steel slab 32 are located in the reserved opening 31, pass through 31 phase of reserved opening between adjacent prefabricated panel 3
Docking, and fixation is connect for be superimposed together two pieces pre-embedded steel slab 32 by wallboard bolt 33;
It can be for a word connects in parallel, T shape vertically connects and several connection types of Angle connection between the prefabricated panel 3;Root
According to the different connection types of installation of contiguous prefabricated wallboard 3, the pre-embedded steel slab 32 can use plain plate or gusset;
The integral roofing 4 is the straticulate structure of keel and prefabricated board, from inside to outside successively includes lightgage steel joist 41, silicon
Sour calcium plate 42, waterproof layer 43, batten 44, rock-wool heat insulation plate 45 and prefabricated anti-ancient cement tile 46;
Connecting node between the integral roofing 4 and prefabricated panel 3 are as follows: the facade keel and prefabricated panel 3 of lightgage steel joist 41
Pre-embedded steel slab 32 between fixation is bolted;
The floor panels 5 are poured the molding concrete soil floor of concrete mold using in workshop;It is described prefabricatedly
Plate 5 is to be layed in the upper surface of prefabricated foundation plate 2 by adjustment height feet 51;
It is by L-type pendant and to be bolted fixation between the prefabricated panel 3 and exterior-wall heat insulation integrated board 6;
Further, the assembled energy-saving New Residence structure can also include inner wall decoration integrated board, the inner wall decoration
It by L-type pendant and is bolted between integrated board and wallboard 3, can also directly paste fixation.
A kind of production method of assembled energy-saving New Residence, is characterized in that, comprising the following steps:
S1, shop-fabricated component
Shift to an earlier date pre-formed prefabricated foundation plate 2, prefabricated panel 3, floor panels 5 and exterior-wall heat insulation integrated board 6 in workshop;It is prefabricated complete
At lightgage steel joist 41, calcium silicate board 42, waterproof layer 43, batten 44, the rock-wool heat insulation plate 45 and prefabricated for assembling integral roofing 4
Anti- Gu cement tile 46;
The prefabricated foundation plate 2, prefabricated panel 3 and floor panels 5 are utilized in workshop casting concrete mold molding;
S2, site operation
Scene trench digging fluting, lay a good foundation;
S3, it is laid with prefabricated foundation plate
Prefabricated foundation plate 2 is laid in blinding layer, alignment is spliced between contiguous prefabricated base plate 2, completes prefabricated base after levelling
The laying construction of plinth plate 2;
S4, installation wallboard
Prefabricated panel 3 is lifted in place, the lower part of prefabricated panel 3 is plugged in the reserved bayonet slot 21 of prefabricated foundation plate 2, adjacent
Prefabricated panel 3 between 31 split of reserved opening docking after, 32 phase of pre-embedded steel slab in two 3 reserved openings 31 of prefabricated panel
Mutually overlapping, connects fixation for be superimposed together two pieces pre-embedded steel slab 32 by wallboard bolt 33, is sequentially completed adjacent prefabricated
After wallboard 3 connects, tamp concrete into the bayonet slot 21 of prefabricated foundation plate 2, complete prefabricated panel 3 and prefabricated foundation plate 2 it
Between connection;
S5, installation roofing
It will be connected and fixed between multiple lightgage steel joists 41, form roofing general frame;
The facade keel of lightgage steel joist 41 are plugged in 3 reserved opening 31 of prefabricated panel, by bolt by facade keel and in advance
Pre-embedded steel slab 32 in box out mouth 31 connect fixation, complete the connection between roofing lightgage steel joist and prefabricated panel 3;
Calcium silicate board 42, waterproof layer 43, batten 44, rock-wool heat insulation plate 45 and prefabricated anti-ancient cement tile 46 are successively layed in light steel
The upper surface of keel complete the construction of integral roofing 4;
The lightgage steel joist 41, calcium silicate board 42, waterproof layer 43, batten 44, rock-wool heat insulation plate 45 and prefabricated anti-ancient cement tile 46
Between pass through default wire hole and screw connection;
S6, installation floor panels
Adjustment height feet 51 is put at the upper surface of prefabricated foundation plate 2 interval, floor panels 5 are layed in adjustment height feet 51
On, split is docked between adjacent floor panels 5;
S7, installation exterior-wall heat insulation integrated board
Exterior-wall heat insulation integrated board is laid on to the outer surface of prefabricated panel 3 by L-type pendant;
S8, installation inner wall decoration integrated board
Inner wall decoration integrated board is laid on to the inner surface of prefabricated panel 3 by L-type pendant.
A kind of assembled energy-saving New Residence structure of the invention, using precast construction independent, each component it is prefabricated
Process is produced in factory, is then transported to construction site and is assembled, between each component assembly node design rationally and
With a certain amount of non-deformability, composition easy operation, substantially shorten construction period.Product waste material is few, precision is high, sample
Formula is more.Site-assembled production method prefabricated in advance is not by season and natural environment influence, even if in the winter of cryogenic conditions
It can produce, solve the problems, such as winter construction, while also can solve fabricated construction since temperature leads to the problem of crack.
Detailed description of the invention
A kind of Fig. 1: assembled energy-saving New Residence structure overall schematic of the present invention
Fig. 2: Fig. 1 right view;
Fig. 3: connecting node schematic diagram between prefabricated panel and prefabricated foundation plate;
Fig. 4: connecting node schematic diagram between prefabricated panel and prefabricated panel (to connection status);
Fig. 5: connecting node schematic diagram (connected status) between prefabricated panel and prefabricated panel;
Fig. 6: integral roofing structural schematic diagram;
Fig. 7: connecting node schematic diagram between integral roofing and prefabricated panel;
1, blinding layer in the figure, 2, prefabricated foundation plate, 21, bayonet slot, 3, prefabricated panel, 31, reserved opening, 32, pre-buried steel
Plate, 33, wallboard bolt, 4, integral roofing, 41, lightgage steel joist, 42, calcium silicate board, 43, waterproof layer, 44, batten, 45, rock wool guarantor
Warm plate, 46, prefabricated anti-ancient cement tile, 5, floor panels, 51, adjustment height feet, 6, exterior-wall heat insulation integrated board.
Specific embodiment
Provide a specific embodiment of the invention below in conjunction with attached drawing, for structure composition of the invention, design principle,
Work progress and main points are described in further detail.
Embodiment one
A kind of assembled energy-saving New Residence structure, including it is prefabricated profiled prefabricated foundation plate 2, prefabricated panel 3, integral roofing 4, pre-
Floor 5 processed and exterior-wall heat insulation integrated board 6;Wherein, the prefabricated foundation plate 2 is using in workshop casting concrete mold molding
Prefabricated foundation plate;The prefabricated foundation plate 2 is paved on the top of blinding layer providing integral planar supporting framework,
It is mutually butted between adjacent prefabricated foundation plate 2;Connecting node between the prefabricated foundation plate 2 and prefabricated panel 3 are as follows: prefabricated
Bayonet slot 21 is reserved on base plate 2, the bottom of the prefabricated panel 3 is plugged in the bayonet slot 21, and is filled out by concrete
It is real fixed;The prefabricated panel 3 is poured the molding precast concrete wall panel of concrete mold using in workshop;Adjacent is pre-
Connecting node between wallboard 3 processed are as follows: the avris mold of prefabricated panel 3 forms reserved opening 31 and pre-embedded steel slab 32, described
Pre-embedded steel slab 32 is located in the reserved opening 31, is connected to each other between adjacent prefabricated panel 3 by reserved opening 31, and pass through
Wallboard bolt 33 connects fixation for be superimposed together two pieces pre-embedded steel slab 32;It can be flat for a word between the prefabricated panel 3
Row connection, T shape vertically connects and several connection types of Angle connection;According to the different connection types of installation of contiguous prefabricated wallboard 3,
The pre-embedded steel slab 32 can use plain plate or gusset;The integral roofing 4 is the complex layered knot of keel and prefabricated board
Structure successively includes lightgage steel joist 41, calcium silicate board 42, waterproof layer 43, batten 44, rock-wool heat insulation plate 45 and prefabricated from inside to outside
Anti- Gu cement tile 46;Connecting node between the integral roofing 4 and prefabricated panel 3 are as follows: the facade keel of lightgage steel joist 41 with
Fixation is bolted between the pre-embedded steel slab 32 of prefabricated panel 3;The floor panels 5 are poured coagulation using in workshop
The formed in mould concrete soil floor of soil;The floor panels 5 are to be layed in prefabricated foundation plate 2 by adjustment height feet 51
The upper surface of;It is by L-type pendant and to be bolted fixation between the prefabricated panel 3 and exterior-wall heat insulation integrated board 6.
Embodiment two
The present embodiment and embodiment one the difference is that:
The assembled energy-saving New Residence structure, further includes inner wall decoration integrated board 7, the inner wall decoration integrated board 7 and wall
It by L-type pendant and is bolted between plate 3, can also directly paste fixation.
Embodiment three
A kind of production method of assembled energy-saving New Residence, comprising the following steps:
S1, shop-fabricated component
Shift to an earlier date pre-formed prefabricated foundation plate 2, prefabricated panel 3, floor panels 5 and exterior-wall heat insulation integrated board 6 in workshop;It is prefabricated complete
At lightgage steel joist 41, calcium silicate board 42, waterproof layer 43, batten 44, the rock-wool heat insulation plate 45 and prefabricated for assembling integral roofing 4
Anti- Gu cement tile 46;
The prefabricated foundation plate 2, prefabricated panel 3 and floor panels 5 are utilized in workshop casting concrete mold molding;
S2, site operation
Scene trench digging fluting, lay a good foundation;
S3, it is laid with prefabricated foundation plate
Prefabricated foundation plate 2 is laid in blinding layer, alignment is spliced between contiguous prefabricated base plate 2, completes prefabricated base after levelling
The laying construction of plinth plate 2;
S4, installation wallboard
Prefabricated panel 3 is lifted in place, the lower part of prefabricated panel 3 is plugged in the reserved bayonet slot 21 of prefabricated foundation plate 2, adjacent
Prefabricated panel 3 between 31 split of reserved opening docking after, 32 phase of pre-embedded steel slab in two 3 reserved openings 31 of prefabricated panel
Mutually overlapping, connects fixation for be superimposed together two pieces pre-embedded steel slab 32 by wallboard bolt 33, is sequentially completed adjacent prefabricated
After wallboard 3 connects, tamp concrete into the bayonet slot 21 of prefabricated foundation plate 2, complete prefabricated panel 3 and prefabricated foundation plate 2 it
Between connection;
S5, installation roofing
It will be connected and fixed between multiple lightgage steel joists 41, form roofing general frame;
The facade keel of lightgage steel joist 41 are plugged in 3 reserved opening 31 of prefabricated panel, by bolt by facade keel and in advance
Pre-embedded steel slab 32 in box out mouth 31 connect fixation, complete the connection between roofing lightgage steel joist and prefabricated panel 3;
Calcium silicate board 42, waterproof layer 43, batten 44, rock-wool heat insulation plate 45 and prefabricated anti-ancient cement tile 46 are successively layed in light steel
The upper surface of keel complete the construction of integral roofing 4;
The lightgage steel joist 41, calcium silicate board 42, waterproof layer 43, batten 44, rock-wool heat insulation plate 45 and prefabricated anti-ancient cement tile 46
Between pass through default wire hole and screw connection;
S6, installation floor panels
Adjustment height feet 51 is put at the upper surface of prefabricated foundation plate 2 interval, floor panels 5 are layed in adjustment height feet 51
On, split is docked between adjacent floor panels 5;
S7, installation exterior-wall heat insulation integrated board
Exterior-wall heat insulation integrated board is laid on to the outer surface of prefabricated panel 3 by L-type pendant;
S8, installation inner wall decoration integrated board
Inner wall decoration integrated board is laid on to the inner surface of prefabricated panel 3 by L-type pendant.
A kind of assembled energy-saving New Residence structure of the invention and preparation method thereof is built for new rural village New Residence and is set
Meter proposes, solves the problems, such as that current rural area tradition craftsman is older and leave no successor, using pre-formed in factory floor
The mode of various prefabricated members solves outdoor environment and climate change to many influences of site operation bring, scene dress
With efficient and convenient, it can substantially shorten construction period.By base plate, wallboard and floor factory floor inner concrete mold at
It is molding to obtain precast concrete foundation plate, precast concrete wall panel and concrete soil floor, concrete mold respectively for type
Various plates compare traditional lightweight steel construction+rock wool heat-preservation system, have better fire line and higher safety, compare the wooden knot
For structure or weight steel construction assembled New Residence, cost is cheaper.At the scene in work progress, pass through prefabricated components
Between connecting node carry out effective assembly connection, all have a certain amount of non-deformability between each assembly node, therefrom
Solve the problems, such as that fabricated construction generates crack due to the temperature difference.
Claims (8)
1. a kind of assembled energy-saving New Residence structure, is characterized in that, including prefabricated profiled prefabricated foundation plate (2), prefabricated panel
(3), integral roofing (4), floor panels (5) and exterior-wall heat insulation integrated board (6);
Connecting node between the prefabricated foundation plate (2) and prefabricated panel (3) are as follows: prefabricated foundation plate is reserved with bayonet on (2)
Slot (21), the bottom of the prefabricated panel (3) is plugged in the bayonet slot (21), and tamps fixation by concrete;
Connecting node between adjacent prefabricated panel (3) are as follows: the avris mold of prefabricated panel (3) forms reserved opening (31)
With pre-embedded steel slab (32), the pre-embedded steel slab (32) is located in the reserved opening (31), leads between adjacent prefabricated panel (3)
It crosses reserved opening (31) to be connected to each other, and by wallboard bolt (33) that be superimposed together two pieces of pre-embedded steel slabs (32) are solid connecing
It is fixed;
The integral roofing (4) is the straticulate structure of keel and prefabricated board, from inside to outside successively includes lightgage steel joist
(41), calcium silicate board (42), waterproof layer (43), batten (44), rock-wool heat insulation plate (45) and prefabricated anti-ancient cement tile (46);
Connecting node between the integral roofing (4) and prefabricated panel (3) are as follows: the facade keel of lightgage steel joist (41) with it is prefabricated
Fixation is bolted between the pre-embedded steel slab (32) of wallboard (3).
2. a kind of assembled energy-saving New Residence structure as described in claim 1, is characterized in that,
Wherein, the prefabricated foundation plate (2) is poured the molding prefabricated foundation plate of concrete mold using in workshop;It is mated formation
It is mutually butted between the top of blinding layer, adjacent prefabricated foundation plate (2).
3. a kind of assembled energy-saving New Residence structure as described in claim 1, is characterized in that,
The prefabricated panel (3) is poured the molding precast concrete wall panel of concrete mold using in workshop.
4. a kind of assembled energy-saving New Residence structure as described in claim 1, is characterized in that,
For a word connects in parallel, T shape vertically connects or Angle connection between the prefabricated panel (3);According to contiguous prefabricated wallboard
(3) different connection types, the pre-embedded steel slab (32) use plain plate or gusset.
5. a kind of assembled energy-saving New Residence structure as described in claim 1, is characterized in that,
The floor panels (5) are poured the molding concrete soil floor of concrete mold using in workshop;It is described prefabricated
Floor (5) is to be layed in the upper surface of prefabricated foundation plate (2) by adjustment height feet (51).
6. a kind of assembled energy-saving New Residence structure as described in claim 1, is characterized in that,
It is by L-type pendant and to be bolted fixation between the prefabricated panel (3) and exterior-wall heat insulation integrated board (6).
7. a kind of assembled energy-saving New Residence structure as described in claim 1, is characterized in that,
Further include inner wall decoration integrated board, is by L-type pendant and spiral shell between the inner wall decoration integrated board and prefabricated panel (3)
Bolt is connected and fixed.
8. a kind of production method of assembled energy-saving New Residence, is characterized in that, comprising the following steps:
S1, shop-fabricated component
Shift to an earlier date pre-formed prefabricated foundation plate (2), prefabricated panel (3), floor panels (5) and exterior-wall heat insulation integrated board in workshop
(6);The prefabricated lightgage steel joist (41), calcium silicate board (42), waterproof layer (43), batten completed for assembling integral roofing (4)
(44), rock-wool heat insulation plate (45) and prefabricated anti-ancient cement tile (46);
The prefabricated foundation plate (2), prefabricated panel (3) and floor panels (5) be utilized in workshop casting concrete mold at
Type;
S2, site operation
Scene trench digging fluting, lay a good foundation;
S3, it is laid with prefabricated foundation plate
Prefabricated foundation plate (2) is laid in blinding layer, alignment is spliced between contiguous prefabricated base plate (2), is completed after levelling pre-
The laying construction of base plate (2) processed;
S4, installation wallboard
Prefabricated panel (3) lifting is in place, and the lower part of prefabricated panel (3) is plugged in prefabricated foundation plate (2) reserved bayonet slot
(21) in, after reserved opening (31) the split docking between adjacent prefabricated panel (3), two prefabricated panel (3) reserved openings
(31) pre-embedded steel slab (32) in is superimposed with each other, by wallboard bolt (33) by be superimposed together two pieces of pre-embedded steel slabs (32)
Fixation is connect, after being sequentially completed adjacent prefabricated panel (3) connection, tamps coagulation into the bayonet slot (21) of prefabricated foundation plate (2)
Soil completes the connection between prefabricated panel (3) and prefabricated foundation plate (2);
S5, installation roofing
It will be connected and fixed between multiple lightgage steel joists (41), form roofing general frame;
The facade keel of lightgage steel joist (41) are plugged in prefabricated panel (3) reserved opening (31), it is by bolt that facade is imperial
Pre-embedded steel slab (32) in bone and reserved opening (31) is completed between roofing lightgage steel joist and prefabricated panel (3) fixation is connect
Connection;
Successively by calcium silicate board (42), waterproof layer (43), batten (44), rock-wool heat insulation plate (45) and prefabricated anti-ancient cement tile (46)
It is layed in the upper surface of lightgage steel joist, completes the construction of integral roofing (4);
The lightgage steel joist (41), calcium silicate board (42), waterproof layer (43), batten (44), rock-wool heat insulation plate (45) and prefabricated anti-
Pass through default wire hole and screw connection between ancient cement tile (46);
S6, installation floor panels
Adjustment height feet (51) are put at the upper surface of prefabricated foundation plate (2) interval, floor panels (5) are layed in adjustment height
In feet (51), split is docked between adjacent floor panels (5);
S7, installation exterior-wall heat insulation integrated board
Exterior-wall heat insulation integrated board is laid on to the outer surface of prefabricated panel (3) by L-type pendant;
S8, installation inner wall decoration integrated board
Inner wall decoration integrated board is laid on to the inner surface of prefabricated panel (3) by L-type pendant.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910714121.5A CN110387954A (en) | 2019-08-03 | 2019-08-03 | A kind of assembled energy-saving New Residence structure and preparation method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910714121.5A CN110387954A (en) | 2019-08-03 | 2019-08-03 | A kind of assembled energy-saving New Residence structure and preparation method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110387954A true CN110387954A (en) | 2019-10-29 |
Family
ID=68288250
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910714121.5A Pending CN110387954A (en) | 2019-08-03 | 2019-08-03 | A kind of assembled energy-saving New Residence structure and preparation method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110387954A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113582613A (en) * | 2021-07-23 | 2021-11-02 | 广东海龙建筑科技有限公司 | Conductive inorganic artificial stone and preparation method thereof |
CN114908978A (en) * | 2022-05-27 | 2022-08-16 | 中建八局第三建设有限公司 | Design and construction method of assembled antique building steel structure board house system |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104563288A (en) * | 2014-10-30 | 2015-04-29 | 徐曼 | Reinforced concrete frame gridding slab prefabricated energy-saving house |
WO2015135440A1 (en) * | 2014-03-10 | 2015-09-17 | 初明进 | Prefabricated concrete wall |
CN205530671U (en) * | 2016-02-17 | 2016-08-31 | 杨雪梅 | Light steel house with energy -conserving environmental protection |
CN206581283U (en) * | 2016-06-22 | 2017-10-24 | 上海建工七建集团有限公司 | The prefabricated assembled basis of hoarding |
CN108824648A (en) * | 2018-06-13 | 2018-11-16 | 北京乡墅科技有限公司 | Space module house |
CN210658664U (en) * | 2019-08-03 | 2020-06-02 | 山东惠晟建筑科技有限公司 | Assembled energy-saving new residential structure |
-
2019
- 2019-08-03 CN CN201910714121.5A patent/CN110387954A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2015135440A1 (en) * | 2014-03-10 | 2015-09-17 | 初明进 | Prefabricated concrete wall |
CN104563288A (en) * | 2014-10-30 | 2015-04-29 | 徐曼 | Reinforced concrete frame gridding slab prefabricated energy-saving house |
CN205530671U (en) * | 2016-02-17 | 2016-08-31 | 杨雪梅 | Light steel house with energy -conserving environmental protection |
CN206581283U (en) * | 2016-06-22 | 2017-10-24 | 上海建工七建集团有限公司 | The prefabricated assembled basis of hoarding |
CN108824648A (en) * | 2018-06-13 | 2018-11-16 | 北京乡墅科技有限公司 | Space module house |
CN210658664U (en) * | 2019-08-03 | 2020-06-02 | 山东惠晟建筑科技有限公司 | Assembled energy-saving new residential structure |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113582613A (en) * | 2021-07-23 | 2021-11-02 | 广东海龙建筑科技有限公司 | Conductive inorganic artificial stone and preparation method thereof |
CN114908978A (en) * | 2022-05-27 | 2022-08-16 | 中建八局第三建设有限公司 | Design and construction method of assembled antique building steel structure board house system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106013811B (en) | A kind of installation method of assembled architecture | |
CN109072604B (en) | Method for constructing multi-storey building using stacked structural steel wall truss | |
CN104358341B (en) | Building brickwork and masonry construction method of building brickwork | |
CN103821276B (en) | A kind of assembled, modular architectural system | |
EP1992750A1 (en) | Prefabricated reinforced-concrete single-family dwelling and method for erecting said dwelling | |
US8429876B2 (en) | Concrete rib construction method | |
CN109322392B (en) | Light steel house and construction method thereof | |
CN101139849A (en) | Modular building component and on-site hoisting building method | |
CN107130684A (en) | A kind of fabricated structure and its construction method | |
CN105672664A (en) | Integral heat insulation wallboard building system | |
CN210658664U (en) | Assembled energy-saving new residential structure | |
CN106522359A (en) | Total-prefabricated rural residential class composite wall structure system and construction method thereof | |
CN101413300A (en) | Gypsum reinforced concrete construction system | |
CN107419801A (en) | A kind of assembled individual layer ALC wood connecting building and its construction method and ALC board manufacturing methods | |
US20070039265A1 (en) | Prefabricated masonry covered structural wall panel | |
CN110387954A (en) | A kind of assembled energy-saving New Residence structure and preparation method thereof | |
CN109707111B (en) | Assembled concrete archaized roof and construction method thereof | |
CN206681418U (en) | The industrialization commercial residential buildings of energy-conserving and environment-protective | |
CN113585541A (en) | Fast-assembling type indoor partition wall and construction method thereof | |
US3955332A (en) | Method of building a structure from bricks and mortar | |
RU2678750C1 (en) | Buildings and structures with bearing monolithic reinforced concrete structures construction method using the reinforced concrete wall panels | |
CN206396997U (en) | Precast wall body, prefabricated unit body and building system | |
RU2812973C1 (en) | Method of construction of buildings | |
CA1225234A (en) | Prefabricated plastered panels for housing | |
CN206245606U (en) | A kind of EPS composite heat-insulation roofs |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |