CN110344743A - A kind of construction site can be used in turn standardization gate posts and its installation method - Google Patents

A kind of construction site can be used in turn standardization gate posts and its installation method Download PDF

Info

Publication number
CN110344743A
CN110344743A CN201910531525.0A CN201910531525A CN110344743A CN 110344743 A CN110344743 A CN 110344743A CN 201910531525 A CN201910531525 A CN 201910531525A CN 110344743 A CN110344743 A CN 110344743A
Authority
CN
China
Prior art keywords
column
turn
gate posts
standardization
construction site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910531525.0A
Other languages
Chinese (zh)
Inventor
梁广远
汪从
董健
汪铮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201910531525.0A priority Critical patent/CN110344743A/en
Publication of CN110344743A publication Critical patent/CN110344743A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B11/00Means for allowing passage through fences, barriers or the like, e.g. stiles
    • E06B11/02Gates; Doors
    • E06B11/028Gates; Doors with posts connected underground

Abstract

A kind of construction site can be used in turn standardization gate posts, including column coxopodite, column middle node, capital section, it is characterized by: the column coxopodite is the cuboid framework welded by angle steel, including four upright bars, four upright bar upper and lower ends respectively set the square end faces frame welded by four horizon bar angle steel, the structure of the column middle node is identical as column coxopodite in addition to bottom end steel plate and door-hinge connecting rod, the structure of the capital section is identical as column middle node, wherein: the upper and lower ends of column middle node are bolted connection with column coxopodite and capital section respectively, the bottom end steel plate of column coxopodite is fastenedly connected by pre-buried concrete ground foot bolt, reach gate posts.Construction site of the invention, which can be used in turn standardization gate posts and its installation method, has pillar structure simple, easy to make, door pillar is connected by screw bolts with basis, detachably, can be used in turn with multiple building sites, door pillar is handsome in appearance, it is economical and practical and reduce engineering cost the advantages of.

Description

A kind of construction site can be used in turn standardization gate posts and its installation method
Technical field
The present invention relates to a kind of and extraneous separation interim gates in construction site construction site, specifically, being that one kind is built Standardization gate posts and its installation method can be used in turn by building building site.
Background technique
Before construction site goes into operation, construction site temporary construction fence and gate first separate construction site with the external world, So that the construction in scene is normally carried out.Interim gate quality represents the image of a company, since the civilized construction at scene ceases Manner of breathing closes, therefore construction enterprises all compare the installation for paying attention to the interim gate in scene.But the interim gate in present construction site is Fixed concrete door pillar gate, a project complete transition and just complete mission dismounting, rebuild to a new building site, take a lot of work, is time-consuming, Waste construction material.
Therefore the known interim door construction mode in construction site there are problems that it is above-mentioned various inconvenient and.
Summary of the invention
The purpose of the present invention is to propose that a kind of safe and reliable construction site can be used in turn standardization gate posts.
It is another object of the present invention to propose that a kind of safe and reliable construction site can be used in turn standardization gate door Column installation method.
To achieve the above object, the technical solution of the invention is as follows:
A kind of construction site can be used in turn standardization gate posts, including column coxopodite, column middle node, capital section, feature exist In:
The column coxopodite is the cuboid framework welded by angle steel, including four upright bars, and four upright bar upper and lower ends respectively set one The square end faces frame welded by four horizon bar angle steel;The upright bar of bottom end four of column coxopodite is respectively vertical with one block of steel plate to weld admittedly, Each side of the top square end faces frame of column coxopodite is used for bolted through-hole there are three being all provided with;The side of cuboid framework is each If a side brace enhancing, butt face brace enhancing is respectively set on the inside of square end faces frame;Also at one of cuboid framework A door-hinge connecting rod for door-hinge connection is arranged in side;
The structure of the column middle node is identical as column coxopodite in addition to bottom end steel plate and door-hinge connecting rod;
The structure of the capital section is identical as column middle node;
Wherein: the upper and lower ends of column middle node are bolted connection with column coxopodite and capital section respectively, the bottom end steel of column coxopodite Plate is fastenedly connected by pre-buried concrete ground foot bolt, reaches gate posts.
Construction site of the invention can be used in turn standardization gate posts can also using technical measures below come into One step is realized.
Construction site above-mentioned can be used in turn standardization gate posts, wherein the upright bar specification is 70*70*6 angle steel.
Construction site above-mentioned can be used in turn standardization gate posts, wherein the horizon bar specification is the angle 50*50*5 Steel, length 1000mm.
Construction site above-mentioned can be used in turn standardization gate posts, wherein the steel plate specification is 300*300*15 steel Plate, steel plate quadrangle are equipped with the through-hole for connecting with foundation bolt.
Construction site above-mentioned can be used in turn standardization gate posts, wherein the column coxopodite and column middle node height point Not Wei 2000mm, capital section height be 1000mm.
A kind of construction site can be used in turn the installation method of standardization gate posts, it is characterised in that including following step It is rapid:
A, according to designing prefabricated gate posts concrete foundation, pre-embedded anchoring bolts in concrete foundation;
B, the gate posts steel plate through-hole being connected with is connected with foundation bolt through-hole, completes gate posts peace Dress.
The installation method that construction site of the invention can be used in turn standardization gate posts can also use skill below Art measure further realizes.
Method above-mentioned, wherein the pre-embedded anchoring bolts are J-shaped, hook length 60mm.
Method above-mentioned, wherein bolt is fastened using double nut in the step b.
After adopting the above technical scheme, construction site of the invention can be used in turn standardization gate posts and its installation side Method has the advantage that
1, pillar structure is simple, easy to make;
2, door pillar and basis are connected by screw bolts, and detachably, can be used in turn with multiple building sites;
3, door pillar is handsome in appearance, economical and practical, reduces engineering cost.
Detailed description of the invention
Fig. 1 is the column coxopodite structural schematic diagram of the embodiment of the present invention;
Fig. 2 is the square end faces mount structure schematic diagram of the embodiment of the present invention;
Fig. 3 is the upright bar and pre-embedded anchoring bolts connection schematic diagram of the embodiment of the present invention;
Fig. 4 is the gate posts structural schematic diagram of the embodiment of the present invention.
In figure: 1 upright bar, 2 horizon bars, 3 end face braces, 4 side braces, 5 bottom plates, 6 door-hinge connecting rods, 7 column coxopodites, in 8 columns Segmentum intercalaris, 9 capitals section, 10 nuts, 11 through-holes.
Specific embodiment
With reference to embodiments and its attached drawing further explains the present invention.
Embodiment 1
Construction site of the invention can be used in turn standardization gate posts, including column coxopodite 7, column middle node 8, capital section 9.
It is the column coxopodite structural schematic diagram of the embodiment of the present invention referring now to Fig. 1, Fig. 1.As shown, the column coxopodite is The cuboid framework welded by angle steel, including four upright bars 1, four upright bar upper and lower ends respectively set one by four 2 jiaos of horizon bar The square end faces frame of steel welding;The upright bar of bottom end four of column coxopodite respectively solid weldering vertical with one piece of steel sole plate 5, the top of column coxopodite Each side of square end faces frame is used for bolted through-hole there are three being all provided with;It is oblique that the side of cuboid framework respectively sets a side Bar 4 enhances, and a butt face brace 3 enhancing is respectively set on the inside of square end faces frame;Also it is arranged one in a side of cuboid framework Root is used for the door-hinge connecting rod 7 of door-hinge connection;The upright bar specification is 70*70*6 angle steel, and horizon bar specification is 50*50*5 angle steel, Length is 1000mm.The steel plate specification is 300*300*15 steel sole plate 5, and steel plate quadrangle is equipped with for connecting with foundation bolt Through-hole 11.
The structure of the column middle node is identical as column coxopodite in addition to bottom end steel plate and door-hinge connecting rod;
The structure of the capital section is identical as column middle node;The column coxopodite and column middle node height are respectively 2000mm, capital Section height is 1000mm.
Fig. 2 is the square end faces mount structure schematic diagram of the embodiment of the present invention.Wherein: the upper and lower ends difference of column middle node It is bolted connection with column coxopodite and capital section, the bottom end steel plate of column coxopodite is connected by pre-buried concrete fastening foundation bolt It connects, reaches gate posts.Fig. 3 is the upright bar and pre-embedded anchoring bolts connection schematic diagram of the embodiment of the present invention.
Embodiment 2
Fig. 4 is the gate posts structural schematic diagram of the embodiment of the present invention.It is big that construction site of the invention can be used in turn standardization The installation method of door post, comprising the following steps:
A, according to designing prefabricated gate posts concrete foundation, pre-embedded anchoring bolts in concrete foundation;
B, the gate posts steel plate through-hole being connected in embodiment 1 is connected with foundation bolt through-hole, bolt is adopted It is fastened with double nut 10, completes gate posts installation.The pre-embedded anchoring bolts are J-shaped, hook length 60mm.
The present invention has substantive distinguishing features and significant technological progress, and construction site of the invention can be used in turn standardization Gate posts and its installation method can compare the overall image at standard construction scene gate, and the height at gate can be high as needed Degree is adjusted, and door pillar is connected by screw bolts with basis, detachably, can be used in turn with multiple building sites, beautiful, economical.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field Member, without departing from the spirit and scope of the present invention, can also make various transformation or variation.Therefore, all equivalent Technical solution also should belong to scope of the invention, should be limited by each claim.

Claims (8)

1. a kind of construction site can be used in turn standardization gate posts, including column coxopodite, column middle node, capital section, feature It is:
The column coxopodite is the cuboid framework welded by angle steel, including four upright bars, and four upright bar upper and lower ends respectively set one The square end faces frame welded by four horizon bar angle steel;The upright bar of bottom end four of column coxopodite is respectively vertical with one block of steel plate to weld admittedly, Each side of the top square end faces frame of column coxopodite is used for bolted through-hole there are three being all provided with;The side of cuboid framework is each If a side brace enhancing, butt face brace enhancing is respectively set on the inside of square end faces frame;Also at one of cuboid framework A door-hinge connecting rod for door-hinge connection is arranged in side;
The structure of the column middle node is identical as column coxopodite in addition to bottom end steel plate and door-hinge connecting rod;
The structure of the capital section is identical as column middle node;
Wherein: the upper and lower ends of column middle node are bolted connection with column coxopodite and capital section respectively, the bottom end steel of column coxopodite Plate is fastenedly connected by pre-buried concrete ground foot bolt, reaches gate posts.
2. construction site as described in claim 1 can be used in turn standardization gate posts, which is characterized in that the upright bar rule Lattice are 70*70*6 angle steel.
3. construction site as described in claim 1 can be used in turn standardization gate posts, which is characterized in that the horizon bar Specification is 50*50*5 angle steel, length 1000mm.
4. construction site as described in claim 1 can be used in turn standardization gate posts, which is characterized in that the steel plate rule Lattice are 300*300*15 steel plate, and steel plate quadrangle is equipped with the through-hole for connecting with foundation bolt.
5. construction site as described in claim 1 can be used in turn standardization gate posts, which is characterized in that the column coxopodite It is respectively 2000mm with column middle node height, capital section height is 1000mm.
6. a kind of construction site as described in claim 1 can be used in turn the installation method of standardization gate posts, feature Be the following steps are included:
A, according to designing prefabricated gate posts concrete foundation, pre-embedded anchoring bolts in concrete foundation;
B, the gate posts steel plate through-hole being connected with is connected with foundation bolt through-hole, completes gate posts peace Dress.
7. the installation method that construction site as claimed in claim 6 can be used in turn standardization gate posts, which is characterized in that The pre-embedded anchoring bolts are J-shaped, hook length 60mm.
8. the installation method that construction site as claimed in claim 6 can be used in turn standardization gate posts, which is characterized in that In the step b, bolt is fastened using double nut.
CN201910531525.0A 2019-06-19 2019-06-19 A kind of construction site can be used in turn standardization gate posts and its installation method Pending CN110344743A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910531525.0A CN110344743A (en) 2019-06-19 2019-06-19 A kind of construction site can be used in turn standardization gate posts and its installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910531525.0A CN110344743A (en) 2019-06-19 2019-06-19 A kind of construction site can be used in turn standardization gate posts and its installation method

Publications (1)

Publication Number Publication Date
CN110344743A true CN110344743A (en) 2019-10-18

Family

ID=68182363

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910531525.0A Pending CN110344743A (en) 2019-06-19 2019-06-19 A kind of construction site can be used in turn standardization gate posts and its installation method

Country Status (1)

Country Link
CN (1) CN110344743A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203729852U (en) * 2013-12-30 2014-07-23 中建五局第三建设有限公司 Assembly type construction site door
CN204238830U (en) * 2014-11-21 2015-04-01 中国建筑第四工程局有限公司 A kind of gate, assembly type building site
JP2016141995A (en) * 2015-01-30 2016-08-08 三協立山株式会社 Panel body
CN205530675U (en) * 2016-03-23 2016-08-31 中国建筑第七工程局有限公司 Frame arch over a gate can be dismantled in concatenation
CN207794298U (en) * 2017-12-22 2018-08-31 武汉建工集团股份有限公司 A kind of standard cell mode building site bar that can be recycled

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203729852U (en) * 2013-12-30 2014-07-23 中建五局第三建设有限公司 Assembly type construction site door
CN204238830U (en) * 2014-11-21 2015-04-01 中国建筑第四工程局有限公司 A kind of gate, assembly type building site
JP2016141995A (en) * 2015-01-30 2016-08-08 三協立山株式会社 Panel body
CN205530675U (en) * 2016-03-23 2016-08-31 中国建筑第七工程局有限公司 Frame arch over a gate can be dismantled in concatenation
CN207794298U (en) * 2017-12-22 2018-08-31 武汉建工集团股份有限公司 A kind of standard cell mode building site bar that can be recycled

Similar Documents

Publication Publication Date Title
CN107090925A (en) Reinforced precast reinforced concrete shear wall, structural system and its construction method
CN107419824A (en) The full precast shear wall structural system of regenerative steel skeleton and construction method
CN107989447A (en) A kind of large-scale earthing concrete tank dome steel support structure and installation method
CN103104092A (en) Support composite structure of beam and slab
CN106351445B (en) A kind of strengthening concrete sloping core form assembly bracing reinforcement system and construction method of installation
CN107090909A (en) A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve and its assembly method
CN207017484U (en) Reinforced precast reinforced concrete shear wall and structural system
CN103758024A (en) Quick assembling and disassembling steel-structure pedestrian overpass
CN210067544U (en) Prefabricated steel structure protective shed frame for railway business line
CN103452350A (en) Fabricated electronic workshop and construction method thereof
CN102808511B (en) Steel box column-concrete girder connection construction method
CN204081478U (en) A kind of Novel steel structure cast-in-situ floor formwork erecting structure
US5259160A (en) Knot for the connection of pillars and girders in spatial frames in metallic carpentry
CN111535628B (en) Construction method for upper structure of C-shaped stock ground
CN212897482U (en) Construction platform for high-rise building overhanging structural layer
CN203684061U (en) Steel pedestrian overcrossing fast to disassemble or assemble
CN203475310U (en) Formwork for concrete slabs of composite steel-concrete box girders
CN205475250U (en) Pin -connected panel steel stair in foundation ditch
CN202369921U (en) Inverted trapezoidal truss
CN110344743A (en) A kind of construction site can be used in turn standardization gate posts and its installation method
CN206753043U (en) A kind of Structure Beam-column node Hou Jiao areas mould plate supporting device
RU128636U1 (en) BASE ASSEMBLY JOINT REINFORCED CONCRETE COLUMN WITH FOUNDATION
CN203729852U (en) Assembly type construction site door
CN212000638U (en) Overhead cover beam type steel supporting structure
CN203924047U (en) Antidetonation rural area sectionalized house foundation pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191018