CN110144834A - 一种盖板涵施工工艺 - Google Patents
一种盖板涵施工工艺 Download PDFInfo
- Publication number
- CN110144834A CN110144834A CN201910344851.0A CN201910344851A CN110144834A CN 110144834 A CN110144834 A CN 110144834A CN 201910344851 A CN201910344851 A CN 201910344851A CN 110144834 A CN110144834 A CN 110144834A
- Authority
- CN
- China
- Prior art keywords
- platform cap
- cover board
- mortar
- culvert
- construction technology
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01F—ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
- E01F5/00—Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
- E01F5/005—Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
本发明公开了一种盖板涵施工工艺,其特征在于包括以下步骤:测量放样、基槽开挖、基础及台身砌筑、台帽施工、盖板安装、做防水层、回填,通过本发明的实施,使用盖板涵作为涵洞,施工过程中没有大的预制件,便于在施工现场进行预制,适合在一些崎岖的山区施工,同时盖板涵的泄洪能力强,在多雨的季节,可以保证洪水的正常通过,避免洪水漫过路面,影响道路和行车安全。
Description
技术领域
本发明属于道路施工工艺领域,尤其涉及一种盖板涵施工工艺。
背景技术
在山区的道路建设中,常使用圆管涵来跨越一些小的沟谷,但是圆管涵需要预制,在一些崎岖的山区施工时,现场没有预制条件,而且运输不便,限制了圆管涵的使用条件,同时圆管涵的泄洪能力差,在多雨季节,容易在导致洪水漫过路面,影响道路和行车的安全,因此需要一种盖板涵施工工艺,通过盖板涵替代圆管涵,便于在山区中进行道路建设。
发明内容
为解决上述技术问题,本发明提供了一种盖板涵施工工艺,可以解决现有技术施工困难的问题。
本发明通过以下技术方案得以实现。
本发明提供的一种盖板涵施工工艺,其特征在于包括以下步骤:
S1,测量放样,根据设计图纸要求,使用全站仪放样出中线,再根据中线用白石灰洒出基础线,确定开挖边线,并注明高程及开挖深度,同时对其位置、方向、基底尺寸、高程等定位放线;
S2,基槽开挖,基槽开挖采用挖掘机挖方,自卸汽车配合运转,基槽开挖时需预留150mm厚作为人工修理,并清除沟底的松土、虚土,并将沟底夯实;
S3,基础及台身砌筑,基础、进口、出口及台身均采用M7.5砂浆和MU30块石,通过座浆法,分层、分段砌筑,并设置沉降缝,各砌块的砌缝互相错开,砌筑时缝宽不得大于3cm;
S4,台帽施工,台帽通过混凝土浇注制成,浇注前,对钢模板进行拼装,模板拼缝要求高差小于2mm,混凝土浇注前需将模板内的杂物等清除干净,浇筑过程中,应随时对混凝土进行振捣并保证使其均匀密实,混凝土浇筑完成后,需覆盖保护和定期洒水;
S5,盖板安装,安装前,先在台帽上用砂浆找平,并在台帽上垫双层油毛毡作为支座后,通过吊车将预制的盖板安装在台帽上,盖板安装完毕后,使用M10水泥砂浆紧密填塞盖板之间缝隙,盖板与台帽背墙之间的缝隙用石子和M15水泥砂浆填塞;
S6,做防水层,板缝填塞完毕后,在板缝和盖板与台帽背墙的缝隙上各刷一道2mm至3mm沥青防水层;
S7,回填,填土选用沙砾石或砂性土,且应保证填料内摩擦角不小于35°,回填时使用振动打夯机进行压实。
在步骤S2中,若发生超挖,不得用土回填,必须以相同圬工回填再砌筑,施工中如检测到地基承载力小于0.25Mpa,应使用浆砌片石或抛石挤淤的方法进行处理。
在步骤S3中,涵身在顺水方向每隔4m至6m设置一道沉降缝,沉降缝贯穿整个涵洞断面,缝宽2cm,沉降缝内使用沥青和麻絮填充。
在步骤S3中,石料间的砌缝应互相交错、咬搭,石料间不得无砂浆直接接触,也不得先干填石料,而后铺灌砂浆。
在步骤S4中,台帽上设有沉降缝,且台帽上的沉降缝与涵身上的沉降缝相对应。
本发明的有益效果在于:通过本发明的实施,使用盖板涵作为涵洞,施工过程中没有大的预制件,便于在施工现场进行预制,适合在一些崎岖的山区施工,同时盖板涵的泄洪能力强,在多雨的季节,可以保证洪水的正常通过,避免洪水漫过路面,影响道路和行车安全。
附图说明
图1是盖板涵施工工艺流程;
具体实施方式
下面进一步描述本发明的技术方案,但要求保护的范围并不局限于所述。
如图1所示,一种盖板涵施工工艺,其特征在于包括以下步骤:
S1,测量放样,根据设计图纸要求,使用全站仪放样出中线,再根据中线用白石灰洒出基础线,确定开挖边线,并注明高程及开挖深度,同时对其位置、方向、基底尺寸、高程等定位放线,以便于施工时,施工人员可以快速识别位置。
S2,基槽开挖,基槽开挖采用挖掘机挖方,自卸汽车配合运转,基槽开挖时需预留150mm厚作为人工修理,并清除沟底的松土、虚土,并将沟底夯实,预留150mm厚作为人工修理,以便于准确控制基槽开挖的尺寸,开挖后的沟槽要及时排水,保证槽底干燥、无滞水。
S3,基础及台身砌筑,基础、进口、出口及台身均采用M7.5砂浆和MU30块石,通过座浆法,分层、分段砌筑,并设置沉降缝,各砌块的砌缝互相错开,砌筑时缝宽不得大于3cm,通过M7.5砂浆和MU30块石,砌筑出基础及台身,砌筑时,定位石块的表面砌缝的宽度不得超过3cm,砌体表面与三块相邻石料相切的内切圆直径,不得大于7cm,两层间的竖向错缝不得小于8cm,用块石填腹时,水平砌缝宽度不得大于3cm,竖向砌缝不得大于4cm,以保证基础及台身的砌筑质量的强度。
S4,台帽施工,台帽通过混凝土浇注制成,浇注前,对钢模板进行拼装,模板拼缝要求高差小于2mm,混凝土浇注前需将模板内的杂物等清除干净,浇筑过程中,应随时对混凝土进行振捣并保证使其均匀密实,混凝土浇筑完成后,需覆盖保护和定期洒水,通过钢模板制作浇注模具,可以保证台帽的平整度,台帽施工完成后,通过覆盖保护和定期洒水,保证台帽混凝土的凝固强度和质量,提高台帽的结构强度。
S5,盖板安装,安装前,先在台帽上用砂浆找平,并在台帽上垫双层油毛毡作为支座后,通过吊车将预制的盖板安装在台帽上,盖板安装完毕后,使用M10水泥砂浆紧密填塞盖板之间缝隙,盖板与台帽背墙之间的缝隙用石子和M15水泥砂浆填塞,油毛毡将盖板与台帽间的缝隙填满,启动防水的作用,盖板有多块,通过盖板的相互拼接,组成盖板涵的上部分,盖板的宽度为1m至2m,体积小,可以在工地现场进行预制,且搬运方便,适合在狭小的区域进行施工,同时当地面发生沉降时。盖板之间还可以发生相对位移,避免了盖板的断裂,适合在山区等易沉降的地区使用,在盖板与台帽之间、盖板与盖板之间用水泥砂浆填塞可以提盖连接强度,同时防止漏水。
S6,做防水层,板缝填塞完毕后,在板缝和盖板与台帽背墙的缝隙上各刷一道2mm至3mm沥青防水层,通过沥青进行防水,提高盖板涵的防水性能。
S7,回填,填土选用沙砾石或砂性土,且应保证填料内摩擦角不小于35°,回填时使用振动打夯机进行压实。
在步骤S2中,若发生超挖,不得用土回填,必须以相同圬工回填再砌筑,施工中如检测到地基承载力小于0.25Mpa,应使用浆砌片石或抛石挤淤的方法进行处理,以保证基槽有足够的承载力,减少沉降,提高使用寿命。
在步骤S3中,涵身在顺水方向每隔4m至6m设置一道沉降缝,沉降缝贯穿整个涵洞断面,缝宽2cm,沉降缝内使用沥青和麻絮填充,山区容易发生沉降,通过设置沉降缝,在地基沉降时,涵身可以发生相对位移,防止涵身内产生裂缝。
在步骤S3中,石料间的砌缝应互相交错、咬搭,石料间不得无砂浆直接接触,也不得先干填石料,而后铺灌砂浆,以保证基础及台身的强度。
在步骤S4中,台帽上设有沉降缝,且台帽上的沉降缝与涵身上的沉降缝相对应,在地基沉降时,台帽可以配合涵身发生位移。
Claims (5)
1.一种盖板涵施工工艺,其特征在于包括以下步骤:
S1,测量放样,根据设计图纸要求,使用全站仪放样出中线,再根据中线用白石灰洒出基础线,确定开挖边线,并注明高程及开挖深度,同时对其位置、方向、基底尺寸、高程等定位放线;
S2,基槽开挖,基槽开挖采用挖掘机挖方,自卸汽车配合运转,基槽开挖时需预留150mm厚作为人工修理,并清除沟底的松土、虚土,并将沟底夯实;
S3,基础及台身砌筑,基础、进口、出口及台身均采用M7.5砂浆和MU30块石,通过座浆法,分层、分段砌筑,并设置沉降缝,各砌块的砌缝互相错开,砌筑时缝宽不得大于3cm;
S4,台帽施工,台帽通过混凝土浇注制成,浇注前,对钢模板进行拼装,模板拼缝要求高差小于2mm,混凝土浇注前需将模板内的杂物等清除干净,浇筑过程中,应随时对混凝土进行振捣并保证使其均匀密实,混凝土浇筑完成后,需覆盖保护和定期洒水;
S5,盖板安装,安装前,先在台帽上用砂浆找平,并在台帽上垫双层油毛毡作为支座后,通过吊车将预制的盖板安装在台帽上,盖板安装完毕后,使用M10水泥砂浆紧密填塞盖板之间缝隙,盖板与台帽背墙之间的缝隙用石子和M15水泥砂浆填塞;
S6,做防水层,板缝填塞完毕后,在板缝和盖板与台帽背墙的缝隙上各刷一道2mm至3mm沥青防水层;
S7,回填,填土选用沙砾石或砂性土,且应保证填料内摩擦角不小于35°,回填时使用振动打夯机进行压实。
2.如权利要求1所述的一种盖板涵施工工艺,其特征在于:在步骤S2中,若发生超挖,不得用土回填,必须以相同圬工回填再砌筑,施工中如检测到地基承载力小于0.25Mpa,应使用浆砌片石或抛石挤淤的方法进行处理。
3.如权利要求1所述的一种盖板涵施工工艺,其特征在于:在步骤S3中,涵身在顺水方向每隔4m至6m设置一道沉降缝,沉降缝贯穿整个涵洞断面,缝宽2cm,沉降缝内使用沥青和麻絮填充。
4.如权利要求1所述的一种盖板涵施工工艺,其特征在于:在步骤S3中,石料间的砌缝应互相交错、咬搭,石料间不得无砂浆直接接触,也不得先干填石料,而后铺灌砂浆。
5.如权利要求1所述的一种盖板涵施工工艺,其特征在于:在步骤S4中,台帽上设有沉降缝,且台帽上的沉降缝与涵身上的沉降缝相对应。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910344851.0A CN110144834A (zh) | 2019-04-26 | 2019-04-26 | 一种盖板涵施工工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910344851.0A CN110144834A (zh) | 2019-04-26 | 2019-04-26 | 一种盖板涵施工工艺 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110144834A true CN110144834A (zh) | 2019-08-20 |
Family
ID=67594651
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910344851.0A Pending CN110144834A (zh) | 2019-04-26 | 2019-04-26 | 一种盖板涵施工工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110144834A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112031120A (zh) * | 2020-07-15 | 2020-12-04 | 中交第一航务工程局有限公司 | 一种内模法浆砌开敞式排水沟工艺 |
CN112832149A (zh) * | 2020-12-31 | 2021-05-25 | 山东省公路桥梁建设有限公司 | 一种涵洞施工设备及施工方法 |
CN115369786A (zh) * | 2022-09-06 | 2022-11-22 | 中国二十二冶集团有限公司 | 盖板涵施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2104566A (en) * | 1981-06-17 | 1983-03-09 | Carl William Peterson | Roof beam structures for culverts or underpasses |
CA1313956C (en) * | 1988-11-21 | 1993-03-02 | Hyun-Ho Hwang | Prefabricated culvert system |
CN2321810Y (zh) * | 1997-04-17 | 1999-06-02 | 韩建泰 | 箱体组装式盖板涵 |
US6017166A (en) * | 1996-12-06 | 2000-01-25 | Mossburg, Jr.; William H. | Catch basin guard and filter |
CN202031040U (zh) * | 2010-12-16 | 2011-11-09 | 神华集团有限责任公司 | 一种高寒地区干硬性可装配式涵洞结构 |
-
2019
- 2019-04-26 CN CN201910344851.0A patent/CN110144834A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2104566A (en) * | 1981-06-17 | 1983-03-09 | Carl William Peterson | Roof beam structures for culverts or underpasses |
CA1313956C (en) * | 1988-11-21 | 1993-03-02 | Hyun-Ho Hwang | Prefabricated culvert system |
US6017166A (en) * | 1996-12-06 | 2000-01-25 | Mossburg, Jr.; William H. | Catch basin guard and filter |
CN2321810Y (zh) * | 1997-04-17 | 1999-06-02 | 韩建泰 | 箱体组装式盖板涵 |
CN202031040U (zh) * | 2010-12-16 | 2011-11-09 | 神华集团有限责任公司 | 一种高寒地区干硬性可装配式涵洞结构 |
Non-Patent Citations (5)
Title |
---|
张帅: "《高速公路钢筋混凝土盖板涵施工要点》", 《山西建筑》 * |
徐先芦等: "《浅谈涵洞施工方法》", 《今日科苑》 * |
本书编委会: "《砌筑工》", 31 December 2008 * |
靳晓燕等: "《铁路桥涵施工及维修》", 31 March 2014, 中国铁道出版社 * |
黄志安: "《小城镇建设实用施工技术指南》", 31 December 2015 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112031120A (zh) * | 2020-07-15 | 2020-12-04 | 中交第一航务工程局有限公司 | 一种内模法浆砌开敞式排水沟工艺 |
CN112832149A (zh) * | 2020-12-31 | 2021-05-25 | 山东省公路桥梁建设有限公司 | 一种涵洞施工设备及施工方法 |
CN115369786A (zh) * | 2022-09-06 | 2022-11-22 | 中国二十二冶集团有限公司 | 盖板涵施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100535254C (zh) | 混凝土面板堆石坝垫层料及固坡砂浆一次成形施工方法 | |
CN111893827A (zh) | 一种城市主干道路的施工工艺 | |
CN108797249A (zh) | 软土路基高填方陡坡路段泡沫轻质土的施工方法 | |
CN110144834A (zh) | 一种盖板涵施工工艺 | |
CN110485377A (zh) | 一种小断面渠道衬砌施工方法 | |
CN102677661A (zh) | 一种淤泥质软基现浇箱梁支架基础加固方法 | |
CN101597888B (zh) | 市政排水涵洞沉槽施工方法 | |
CN110295628A (zh) | 一种带有检查井的路面施工方法 | |
CN111778941A (zh) | 高标准农田渠道施工方法及结构 | |
CN110004842A (zh) | 一种基于离心成型法的装配式涵洞管节整体制备与安装方法 | |
CN109706952A (zh) | 大型沉井施工方法 | |
CN108252176A (zh) | 一种设有检查井的路面工程施工方法 | |
CN110230272A (zh) | 一种圆管涵施工方法 | |
CN105332382B (zh) | 邻河基坑筑岛围堰粘土止水施工方法 | |
CN115418908B (zh) | 一种人行道海绵渗排系统及施工方法 | |
CN102535493B (zh) | 一种倒置式基础梁的施工方法 | |
CN205975653U (zh) | 一种土胎模施工的独立承台结构 | |
CN108316237A (zh) | 驳岸挡墙 | |
CN210797245U (zh) | 一种桥头台背回填结构 | |
CN106192645A (zh) | 一种风场道路施工方法 | |
CN110258625A (zh) | 一种填方路基挡土墙的施工方法 | |
CN111472359A (zh) | 一种用于泥炭土软基箱涵基础换填施工的方法 | |
CN109723043A (zh) | 灌溉排水渠道施工方法 | |
CN217479998U (zh) | 一种涵洞结构 | |
CN215829262U (zh) | 一种用于高水位地区低矮现浇箱梁的模板支撑装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190820 |