CN109853323A CN201811654608.0A CN201811654608A CN109853323A CN 109853323 A CN109853323 A CN 109853323A CN 201811654608 A CN201811654608 A CN 201811654608A CN 109853323 A CN109853323 A CN 109853323A
Authority
CN
China
Prior art keywords
filter layer
ground
kerbstone
base
laid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811654608.0A
Other languages
Chinese (zh)
Inventor
李昉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi City Into Design LLC
Original Assignee
Wuxi City Into Design LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi City Into Design LLC filed Critical Wuxi City Into Design LLC
Priority to CN201811654608.0A priority Critical patent/CN109853323A/en
Publication of CN109853323A publication Critical patent/CN109853323A/en
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of sponge urban ecology diafiltration ground structure and its construction methods, belong to urban construction environment protection field, its key points of the technical solution are that including the underlayment being arranged from bottom to up, base on underlayment is set, filter layer in base is set, water penetration ground on filter layer is set, it is arranged in base's two sides kerbstone, reinforcement assembly is equipped in the filter layer, the reinforcement assembly includes the bearing bar being vertically arranged, bearer network is set on carrier bar, the bearing bar extension is buried to underlayment and base, the bearer network vertical direction is equipped with multilayer and is fixedly connected with bearing bar, several reinforcing rods are equipped between bearer network described in adjacent two panels, the bearer network is fixedly connected with kerbstone.The present invention passes through the setting of filter layer and reinforcement assembly, can play the effect that ground intensity is also improved while ground sweat.

Description

A kind of sponge urban ecology diafiltration ground structure and its construction method
Technical field
The present invention relates to urban construction environment protection field, in particular to a kind of sponge urban ecology diafiltration ground structure and its structure Construction method.
Background technique
As urban construction develops rapidly, the construction of large amount of building and road etc. increases city hardened ground area quickly Add, currently, the paving design of the most of urban road in China, public square etc. is all made of and " coordinated development, ecology naturally The impermeable water type close-graded concrete and stone slab paving structure that benign cycle " theory is disagreed.The big face of this paving Product use can adversely affect urban ecological environment, destroy the normal circulation of water resource, prevent rain (snow) water Ground is directly infiltrated through, has blocked rain (snow) water to the supplement of urban groundwater resource;The negative climatic effect in city is exacerbated, is disliked Changed urban ecology, it is this it is fluid-tight mat formation and surrounding cities building collective effect, will increase city " tropical island effect " and City noise;Security risk is increased, with increasingly sharpening for city " rainwater disease ", the ground pavement of these surface compacts exists Rainy day prevents to cause large area ponding from draining in time at hypsography low-lying, generate " water drift phenomenon ", make rain due to hardened ground Its driving generates phenomena such as " drift is slided ", " splashing ", " Night Glare ", makes troubles and pacifies to pedestrian's trip and vehicle driving Full hidden danger.When the gradient is suitable for, due to the Quick drainage mode of hardened ground, urban water shortage phenomenon is aggravated, is unfavorable for adjusting Mesoclimate.With the proposition of sponge city concept, people prefer to can have a kind of ecotypic road surface existing hard to replace Change road surface, can solve these problems by ecological diafiltration techniques, is laid with ecology extensively using ecological diafiltration techniques in city Type pervious surface, this has become the common practice of many ecocities in the world.Environmental pervious surface can be reduced the heat in city Island effect adjusts mesoclimate, is also beneficial to the precipitation in city, and city can be helped to store more rainwater.This can mitigate city City's water resources crisis, and can increase the water content in soil, regulate the climate, so as to improve the ecological environment in city.
Notification number is that the Chinese patent of CN105887609A discloses a kind of building side on sponge urban ecology diafiltration ground Method, sponge urban ecology diafiltration ground are made of underlayment, base, filter layer, porous pavement, and construction method includes following Step: 1) it is percolated the preparation of material;2) underlayment and base are laid with;3) ground underlay is percolated material-paving filter layer;4) it installs Kerbstone and laying pervious surface.
The construction method on this sponge urban ecology diafiltration ground, although the advantages of inventing is: construction method ecology, ring It protects, green, there is preferable repeatability and showing property, the porosity and rain penetration rate on ground can be increased;Significantly improve road surface And the water storage performance and pollutant purification ability of surrounding soil, reduce the generation of water pollutant and road safety accident, appropriateness Adjust mesoclimate, hence it is evident that the problems such as slowing down city " rainwater disease ", " tropical island effect " and soil water shortage and city noise is solving Certainly while urban ecology, environmental and safety problems, building urban ecology road is played to use for reference well and is made, but in reality Due to the setting of filter layer in the use process of border, after water penetration ground is under pressure, pressure, which is transmitted to filter layer, can occur shape Become, from the case where will lead to the decline of road surface integral strength structure, road surface is caused to be damaged.
Summary of the invention
The object of the present invention is to provide a kind of sponge urban ecology diafiltration ground structure and its construction methods, have road surface tool There is the advantages of infiltration also ensures overall structural strength.
Above-mentioned technical purpose of the invention has the technical scheme that
A kind of sponge urban ecology diafiltration ground structure, including the underlayment being arranged from bottom to up, the base being arranged on underlayment Layer, the filter layer being arranged in base, the water penetration ground being arranged on filter layer, setting are described in base's two sides kerbstone Reinforcement assembly is equipped in filter layer, the reinforcement assembly includes the bearing bar being vertically arranged, bearer network, institute is arranged on carrier bar It states bearing bar extension to bury to underlayment and base, the bearer network vertical direction, which is equipped with multilayer and fixes with bearing bar, to be connected It connects, several reinforcing rods is equipped between bearer network described in adjacent two panels, the bearer network is fixedly connected with kerbstone.
By using above-mentioned technical proposal, whole ground structure is reinforced by reinforcement assembly, what can be seeped water Also ensure the structural strength on ground simultaneously, bearer network has certain tensile force, plays a supporting role to filter layer, bearing bar with Reinforcing rod has also shared the pressure on road surface, improves the intensity of the structure on ground.
Further, reinforcing rib is equipped between the adjacent bearing bar, reinforcing rib and curb at the kerbstone Stone is fixedly connected.
By using above-mentioned technical proposal, the stability of bearing bar positional structure is increased, improves road surface to reach Structural strength.
Further, tensioning chain, tensioning chain and curb at the kerbstone are equipped between the adjacent reinforcing rod Stone is fixedly connected.
By using above-mentioned technical proposal, the stability of reinforcing rod positional structure is increased, improves road surface to reach Structural strength.
Further, strainer is equipped between the adjacent bearer network, the strainer is woven by carbon fiber, the strainer On mesh be triangle.
By using above-mentioned technical proposal, carbon fiber has certain intensity, cooperates triangular mesh, increases strainer Structural strength, to reach the structural strength for improving road surface.
Further, the bearer network and strainer vertical direction are evenly distributed in filter layer.
By using above-mentioned technical proposal, the bearer network and strainer of multilayer setting, central filler filter layer reduces filter layer Being pressurized, deformation occurs, further improves the structural strength on ground.
Further, it is equipped with reinforcing network in the water penetration ground, if vertical direction is equipped in the water penetration ground Do hollow permeable column.
By using above-mentioned technical proposal, reinforcing network and hollow permeable column are combined, and further improve the intensity on ground, Hollow permeable column also increases the seepage of water on water penetration ground simultaneously.
Another object of the present invention is intended to provide a kind of construction method of sponge urban ecology diafiltration ground structure, including power Benefit requires sponge urban ecology described in 1-6 any one to be percolated ground structure, and specific implementation step is as follows:
S1, underlayment and base are laid with;
S2, embedded kerbstone;By the inside of one third the embedment underlayment and base of kerbstone height, kerbstone is prefabricated It is fabricated to bottom setting triangular in shape in the process;
S3, reinforcement assembly and filter layer are laid with;Filter layer is mixed by natural material;
A, carrier bar is uniformly fixed to the inside for being inserted into underlayment and base, is laid with a piece of bearer network contradicted with base, First of reinforcing rib connection is set on reinforcing rod, filter layer is laid on bearer network;
B, reinforcing rod is uniformly inserted into filter layer, reinforcing rod extends upward filter layer, the setting tensioning chain on reinforcing rod;
C, strainer is laid on filter layer, strainer is fixedly connected with reinforcing rod;
D, it is laid with filter layer again on strainer and thickness is lower than the top of reinforcing rod;
E, it is laid with bearer network again on filter layer;
S4, it is laid with water penetration ground;Several hollow permeable columns, permeable column and the fixed company of bearer network are first uniformly inserted into filter layer It connects, re-lays fixed net, then carry out the laying of water penetration ground;
S5, catch basin is opened up close to the side on road surface in kerbstone, the drainage hole extended transversely through is opened up in catch basin.
By using above-mentioned technical proposal, it may be implemented ground during constructing laying according to different ground demands Face structural strength increases and seepage of water guarantees.
Further, the requirement on ground is laid with according to reality, the b-d in step S3 is repeated as many times the paving for realizing filter layer If.
By using above-mentioned technical proposal, according to construction environment difference, the ruggedized construction multilayer in filter layer is arranged, so that Ground structure intensity increases.
Further, the thickness on the filter layer and water penetration ground and the height lower than kerbstone.
By using above-mentioned technical proposal, be conducive to kerbstone and realize the effect reinforced to ground, after reducing ground compression There is the case where collapsing to two sides.
Further, height of the integral thickness of the filter layer lower than the exposing base of bearing bar.
By using above-mentioned technical proposal, so that bearing bar has part that can extend into water penetration ground, and then improve The position of bearing bar is stablized, to achieve the effect that improve ground structure intensity.
In conclusion the invention has the following advantages:
1. passing through the setting of filter layer and reinforcement assembly, the effect that ground intensity is also improved while ground sweat can played Fruit;
2. the filter layer made of natural material can play the effect of environmental protection;
3. passing through the setting of filter layer and pervious surface, the surface water can be played and penetrate into soil, it not only can be with recharging groundwater, also City rain flood load can be mitigated, improve the effect of urban ecological environment.
Detailed description of the invention
Fig. 1 is the schematic diagram of sponge urban ecology diafiltration ground structure in embodiment.
In figure, 1, underlayment;2, base;3, filter layer;4, water penetration ground;41, reinforcing network;42, hollow permeable column;5, Kerbstone;51, catch basin;52, drainage hole;6, reinforcement assembly;61, bearing bar;611, reinforcing rib;62, bearer network;63, reinforce Bar;631, it is tensioned chain;7, strainer.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
Embodiment: a kind of sponge urban ecology diafiltration ground structure, as shown in Figure 1, including the base being arranged from bottom to up Layer 1, the base 2 being arranged on underlayment 1, the filter layer 3 being arranged in base 2, the water penetration ground being arranged on filter layer 3 4, setting plays the role of limit to the ground poured in 2 two sides kerbstone 5 of base, kerbstone 5, occurs after reducing road surface stress The case where collapsing to both sides, filter layer 3 and water penetration ground 4 combine, so that the effect of infiltration may be implemented in ground, not only may be used With recharging groundwater, city rain flood load can also be mitigated, improve the effect of urban ecological environment.
As shown in Figure 1, also to guarantee the structural strength on ground simultaneously in the case where guaranteeing that infiltration may be implemented in ground, So being equipped with reinforcement assembly 6 in filter layer 3, reinforcement assembly 6 includes the bearing bar 61 being vertically arranged, is arranged and holds on carrier bar Support grid 62, the extension of bearing bar 61 are buried to underlayment 1 and base 2, and 62 vertical direction of bearer network is equipped with multilayer and and bearing bar 61 are fixedly connected, and all bearing bars 61 are all fixedly connected with itself by bearer network 62, while bearer network 62 extends to kerbstone 5 It place and is fixedly connected with kerbstone 5, bearing bar 61, which is inserted into underlayment 1 and base 2, realizes that position is fixed, while bearer network 62 The tensile force of itself also links together all carrier bars, and the position for improving carrier bar is stablized, in addition multiple carrier bars Similarly it is to be fixed to bearer network 62, reduces after it is pressurized and large area stretcher strain occur, and then reached and mentioned Rise the effect of ground structure intensity.
As shown in Figure 1, can generally be laminated equipped with multiple bearer networks 62, be held by multiple when being laid with diafiltration ground The tensile force of support grid 62 is equipped with several reinforcements to further increase the structural strength on ground between adjacent two panels bearer network 62 Bar 63 realizes the multi-point support to bearer network 62 by reinforcing rod 63, also reduces bearer network 62 and occurs generating shape after being pressurized The case where change.Bearing bar 61 is combined with reinforcing rod 63 also functions to the effect for sharing pressure on road surface, improves the structure on ground Intensity.
As shown in Figure 1, being additionally provided with strainer 7 between adjacent bearer network 62, strainer 7 is woven by carbon fiber, on strainer 7 Mesh be triangle.Carbon fiber has certain intensity, and braiding forms the strainer 7 of carbon fiber, and the structure for increasing strainer 7 is strong Degree cooperates mesh setting triangular in shape, while guaranteeing seepage rate, to reach the structural strength for improving road surface.Bearer network 62 are evenly distributed in filter layer 3 with 7 vertical direction of strainer, the bearer network 62 and strainer 7 of multilayer setting, central filler filter layer 3, reducing the compression of filter layer 3, deformation occurs, further improves the structural strength on ground.
As shown in Figure 1, bearing bar 61 or reinforcing rod 63 are pressurized after generating skew, the structural strength of meeting road pavement entirety is generated It influences, reinforcing rib 611 is equipped between adjacent bearing bar 61, the reinforcing rib 611 and kerbstone 5 at kerbstone 5 are fixed to be connected It connects.Tensioning chain 631 is equipped between adjacent reinforcing rod 63, the tensioning chain 631 at kerbstone 5 is fixedly connected with kerbstone 5.It is logical It crosses reinforcing rib 611 to be again coupled to all bearing bars 61 together, and is connected all reinforcing rods 63 by tensioning chain 631 It is connected together, has reached the situation for reducing bearing bar 61 and the compression of reinforcing rod 63 and generating skew, improved road surface to reach Structural strength.
As shown in Figure 1, being equipped with reinforcing network in water penetration ground 4 to further improve the strength structure on ground 41, vertical direction is equipped with several hollow permeable columns 42 in water penetration ground 4.Reinforcing network 41 has tensile force, with reducing water penetration For 4 stress of face there is a situation where being cracked, hollow permeable column 42 is realizing that the support that ground also may be implemented is made while seeping water effect With.Reinforcing network 41 and hollow permeable column 42 combine, and further improve the intensity on ground, while hollow permeable column 42 also increases The seepage of water on water penetration ground 4.
Another object of the present invention is intended to provide a kind of construction method of sponge urban ecology diafiltration ground structure, specific real Apply that steps are as follows:
S1, underlayment 1 and base 2 are laid with;The laying that underlayment 1 and base 2 are carried out according to the safety standard of construction, according to design Requirement excavate roadbed, clear up the earthwork, check longitudinal slope, horizontal slope and sideline, modify roadbed, levelling grinding compacting, compacting factor is extremely Less up to 95%, underlayment 1 is laid with above the roadbed excavated, underlayment 1 is by lime, flyash and local soil type at lime, fine coal The weight ratio of ash and soil is 10:24:66, completes levelling compacting after underlayment 1, and compacting factor is at least up to 95%, is terminated rolling Before, once making its longitudinal direction pleasantly with land leveller is flat eventually, road camber and superelevation meet design requirement, pine is gently finally harrowed on surface, And it is wet to sprinkle water, and is then laid with base 2, base 2 is cement stabilized macadam layer, is stablized with cement, flyash, cement and accurately mistake of gathering materials Scale is blended according to continuous grading ratio, and record mixing time plus water time and amount of water guarantee blending quality, after uniformly paving Levelling compacting, compacting factor are at least up to 93%, and compacting rear surface answers smooth no wheelmark or protuberance, and section is correct, and road camber meets It is required that the surface of Construction of Cement Stabilized Macadam should keep smooth, cleaning after completion of works.
S2, embedded kerbstone 5;By the inside of one third the embedment underlayment 1 and base 2 of 5 height of kerbstone, kerbstone 5 are fabricated to bottom setting triangular in shape during prefabricated;Advantageously ensure that kerbstone 5 was arranged by the pedestal of triangle Stability reduces the inclination due to kerbstone 5 and influences the structural strength on whole ground.
S3, reinforcement assembly 6 and filter layer 3 are laid with;Filter layer 3 is mixed by natural material;For natural sandy soil, boiling Stone, quartz sand, timber, meadow soil or sub- sandy soil, obsolete material are coal ash, crab shell or solid waste, and artificial material is fibre Film, active carbon or Zero-valent Iron are tieed up, according to percolation effect, in conjunction with economy, the material of natural material, obsolete material and artificial material Proportion is 7:1-2:0 .5-1.
A, carrier bar is uniformly fixed to the inside for being inserted into underlayment 1 and base 2, is laid with what a piece of and base 2 contradicted The connection of first of reinforcing rib 611 is arranged on reinforcing rod 63, is connected all reinforcing rods 63 by reinforcing rib 611 for bearer network 62 It is connected together, the reinforcing rib 611 at kerbstone 5 is fixedly connected with kerbstone 5, and filter layer 3 is laid on bearer network 62;
B, reinforcing rod 63 is uniformly inserted into filter layer 3, reinforcing rod 63 extends upward filter layer 3, is arranged on reinforcing rod 63 It is tensioned chain 631;All reinforcing rods 63 are linked together by tensioning chain 631, while the tensioning chain at kerbstone 5 631 are fixedly connected with kerbstone 5,
C, strainer 7 is laid on filter layer 3, strainer 7 is fixedly connected with reinforcing rod 63;Strainer 7 extends to fixed company at kerbstone 5 It connects;
D, it is laid with filter layer 3 again on strainer 7 and thickness is lower than the top of reinforcing rod 63;
E, it is laid with bearer network 62 again on filter layer 3, extends at kerbstone 5 and be fixedly connected after being fixedly connected with carrier bar.
S4, it is laid with water penetration ground 4;Several hollow permeable columns 42, permeable column and carrying are first uniformly inserted into filter layer 3 Net 62 is fixedly connected, and re-lays fixed net, and fixed net extends at kerbstone 5 to be fixedly connected with kerbstone 5, is then carried out permeable Property ground 4 be laid with.
S5, catch basin 51 is opened up close to the side on road surface in kerbstone 5, the draining extended transversely through is opened up in catch basin 51 Hole 52, catch basin 51 are connected to municipal Storm Sewer Network.When the hypervolia on ground can not permeate in time, water can be along collection Sink flows into city planting ductwork, while having the rainwater of part to enter in the soil of ground two sides by drainage hole 52.
According to construction environment difference, the ruggedized construction multilayer setting in filter layer 3 walks so that ground structure intensity increases B-d in rapid S3 is repeated as many times the laying for realizing filter layer 3.The thickness on filter layer 3 and water penetration ground 4 and it is lower than kerbstone 5 Height, be conducive to kerbstone 5 to ground realize reinforce effect, reduce ground be pressurized after occur to two sides collapse the case where. The integral thickness of filter layer 3 is lower than the height of the exposing base 2 of bearing bar 61, so that bearing bar 61 has part that can extend into In aqueous ground 4, and then the position for improving bearing bar 61 is stablized, to achieve the effect that improve ground structure intensity.
This specific embodiment is only explanation of the invention, is not limitation of the present invention, those skilled in the art Member can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but as long as at this All by the protection of Patent Law in the scope of the claims of invention.

Claims (10)

1. a kind of sponge urban ecology is percolated ground structure, including be arranged from bottom to up underlayment (1), be arranged in underlayment (1) base (2) on, setting on base (2) filter layer (3), be arranged on filter layer (3) water penetration ground (4), set It sets in base (2) two sides kerbstone (5), it is characterised in that: be equipped with reinforcement assembly (6) in the filter layer (3), the reinforcing group Part (6) includes the bearing bar (61) being vertically arranged, bearer network (62) is arranged on carrier bar, and the bearing bar (61) extends embedded To underlayment (1) and base (2), bearer network (62) vertical direction is equipped with multilayer and is fixedly connected with bearing bar (61), Several reinforcing rods (63) are equipped between bearer network described in adjacent two panels (62), the bearer network (62) and kerbstone (5) fixed company It connects.
2. a kind of sponge urban ecology according to claim 1 is percolated ground structure, it is characterised in that: the adjacent load-bearing Reinforcing rib (611) are equipped between bar (61), the reinforcing rib (611) and kerbstone (5) at the kerbstone (5) are fixed to be connected It connects.
3. a kind of sponge urban ecology according to claim 1 is percolated ground structure, it is characterised in that: the adjacent reinforcement Tensioning chain (631) is equipped between bar (63), the tensioning chain (631) and kerbstone (5) at the kerbstone (5) are fixed to be connected It connects.
4. a kind of sponge urban ecology according to claim 1 is percolated ground structure, it is characterised in that: the adjacent carrying Strainer (7) are equipped between net (62), the strainer (7) is woven by carbon fiber, and the mesh on the strainer (7) is triangle Shape.
5. a kind of sponge urban ecology according to claim 4 is percolated ground structure, it is characterised in that: the bearer network (62) it is evenly distributed on strainer (7) vertical direction in filter layer (3).
6. a kind of sponge urban ecology according to claim 1 is percolated ground structure, it is characterised in that: the water penetration It is equipped with reinforcing network (41) in face (4), the interior vertical direction of the water penetration ground (4) is equipped with several hollow permeable columns (42).
7. a kind of construction method of sponge urban ecology diafiltration ground structure, it is characterised in that: any one including claim 1-6 Sponge urban ecology described in is percolated ground structure, and specific implementation step is as follows:
S1, underlayment (1) and base (2) are laid with;
S2, embedded kerbstone (5);By the inside of one third embedment underlayment (1) and base (2) of kerbstone (5) height, road Kerb (5) is fabricated to bottom setting triangular in shape during prefabricated;
S3, reinforcement assembly (6) and filter layer (3) are laid with;Filter layer (3) is mixed by natural material;
A, carrier bar is uniformly fixed to the inside for being inserted into underlayment (1) and base (2), a piece of and base (2) is laid with and contradicts Bearer network (62), be arranged on reinforcing rod (63) first of reinforcing rib (611) connection, be laid with filter layer on bearer network (62) (3);
B, it is uniformly inserted into filter layer (3) reinforcing rod (63), reinforcing rod (63) extends upward filter layer (3), in reinforcing rod (63) setting tensioning chain (631) on;
C, strainer (7) are laid on filter layer (3), strainer (7) is fixedly connected with reinforcing rod (63);
D, it is laid with filter layer (3) again on strainer (7) and thickness is lower than the top of reinforcing rod (63);
E, it is laid with again on filter layer (3) bearer network (62);
S4, water penetration ground (4) are laid with;First uniformly be inserted into several hollow permeable columns (42) in filter layer (3), permeable column with hold Support grid (62) is fixedly connected, and re-lays fixed net, is then carried out water penetration ground (4) and is laid with;
S5, catch basin (51) are opened up close to the side on road surface in kerbstone (5), the drainage hole extended transversely through is opened up in catch basin (52).
8. a kind of construction method of sponge urban ecology diafiltration ground structure according to claim 7, it is characterised in that: root Factually border is laid with the requirement on ground, and the b-d in step S3 is repeated as many times the laying for realizing filter layer (3).
9. a kind of construction method of sponge urban ecology diafiltration ground structure according to claim 7, it is characterised in that: institute It states the thickness of filter layer (3) and water penetration ground (4) and is lower than the height of kerbstone (5).
10. a kind of construction method of sponge urban ecology diafiltration ground structure according to claim 7, it is characterised in that: Height of the integral thickness of the filter layer (3) lower than the exposing base (2) of bearing bar (61).
CN201811654608.0A 2018-12-28 2018-12-28 A kind of sponge urban ecology diafiltration ground structure and its construction method Pending CN109853323A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811654608.0A CN109853323A (en) 2018-12-28 2018-12-28 A kind of sponge urban ecology diafiltration ground structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811654608.0A CN109853323A (en) 2018-12-28 2018-12-28 A kind of sponge urban ecology diafiltration ground structure and its construction method

Publications (1)

Publication Number Publication Date
CN109853323A true CN109853323A (en) 2019-06-07

Family

ID=66893734

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811654608.0A Pending CN109853323A (en) 2018-12-28 2018-12-28 A kind of sponge urban ecology diafiltration ground structure and its construction method

Country Status (1)

Country Link
CN (1) CN109853323A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110273345A (en) * 2019-07-20 2019-09-24 江苏懿必合建筑结构优化有限公司 Automatic luminous formula sponge road that drinks water of soil and comprehensive building rubbish preparation
CN113186778A (en) * 2021-05-07 2021-07-30 贵州省遵义公路管理局 Road surface rainwater concealed type permeation structure and construction process

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050047866A1 (en) * 2003-09-02 2005-03-03 Chen Jui Wen Construction of environmental and water-permeable paving
KR20110027540A (en) * 2009-09-09 2011-03-16 호용종합건설주식회사 The asphalted road and the method using the sheet
CN204780508U (en) * 2015-07-06 2015-11-18 江苏北辰新材料科技有限公司 Novel asphalt base road surface structure
CN205368928U (en) * 2016-01-22 2016-07-06 山西大学 A bituminous pavement structure for cement concrete pavement reforms transform
CN105887609A (en) * 2016-04-13 2016-08-24 浙江泽汉环境科技有限公司 Method for constructing ecological infiltration pavement in sponge city
CN106337346A (en) * 2016-09-21 2017-01-18 安徽瀚景观规划设计院有限公司 City landscape architecture pavement construction structure
CN107740322A (en) * 2017-09-19 2018-02-27 无锡市交通工程有限公司 Pavement disease control structure and its construction method
CN207159735U (en) * 2017-08-18 2018-03-30 远洋园林工程有限公司 Permeable road and sponge city
CN207259890U (en) * 2017-08-14 2018-04-20 天津北方创业市政工程集团有限公司 A kind of road foundation
CN108193577A (en) * 2017-12-20 2018-06-22 花王生态工程股份有限公司 A kind of permeable pavement system of ecological, environmental protective

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050047866A1 (en) * 2003-09-02 2005-03-03 Chen Jui Wen Construction of environmental and water-permeable paving
KR20110027540A (en) * 2009-09-09 2011-03-16 호용종합건설주식회사 The asphalted road and the method using the sheet
CN204780508U (en) * 2015-07-06 2015-11-18 江苏北辰新材料科技有限公司 Novel asphalt base road surface structure
CN205368928U (en) * 2016-01-22 2016-07-06 山西大学 A bituminous pavement structure for cement concrete pavement reforms transform
CN105887609A (en) * 2016-04-13 2016-08-24 浙江泽汉环境科技有限公司 Method for constructing ecological infiltration pavement in sponge city
CN106337346A (en) * 2016-09-21 2017-01-18 安徽瀚景观规划设计院有限公司 City landscape architecture pavement construction structure
CN207259890U (en) * 2017-08-14 2018-04-20 天津北方创业市政工程集团有限公司 A kind of road foundation
CN207159735U (en) * 2017-08-18 2018-03-30 远洋园林工程有限公司 Permeable road and sponge city
CN107740322A (en) * 2017-09-19 2018-02-27 无锡市交通工程有限公司 Pavement disease control structure and its construction method
CN108193577A (en) * 2017-12-20 2018-06-22 花王生态工程股份有限公司 A kind of permeable pavement system of ecological, environmental protective

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110273345A (en) * 2019-07-20 2019-09-24 江苏懿必合建筑结构优化有限公司 Automatic luminous formula sponge road that drinks water of soil and comprehensive building rubbish preparation
CN113186778A (en) * 2021-05-07 2021-07-30 贵州省遵义公路管理局 Road surface rainwater concealed type permeation structure and construction process

Similar Documents

Publication Publication Date Title
CN105887609B (en) A kind of construction method on sponge urban ecology diafiltration ground
CN102227534B (en) Road surfacing, method of constructing road surfacing, and concrete form
CN206352331U (en) The concave herbaceous field structure of sponge the idea of the city
CN106149625B (en) A kind of ecological self-purification type landscape revetment reconstruction structure and its construction method
CN107034767A (en) A kind of full pervious concrete pavement structure of regeneration aggregate and its construction method
CN108425298A (en) Assembled interlocks gap porous pavement system and its construction method
CN109853323A (en) A kind of sponge urban ecology diafiltration ground structure and its construction method
CN206736675U (en) A kind of cell pavement
CN105970764B (en) A kind of laying method of drainage pavement
CN207700330U (en) A kind of concave herbaceous field grass-planting ecological ditch
CN107268373A (en) A kind of water permeability asphalt concrete road and its construction method
CN104594155A (en) Permeable pavement laying method
CN204608556U (en) A kind of water permeable pavement
CN204608544U (en) A kind of water conservation layer of water permeable pavement
CN208884292U (en) Soft soil roadbed and normal roadbed intersection anti-settling structure
CN207793792U (en) A kind of road surface permeable pavement structure
CN110295573A (en) Adapt to the channel revetment project post-evaluation structure of construction time severe hydrometeorological condition
CN212895900U (en) Gravity type U-shaped abutment rear drainage structure
CN101892675B (en) Flexible retaining wall with rigid support
TWM621567U (en) High-intensity road for water resource adaptive system in response to climate change
CN207919270U (en) A kind of sponge city, which can ooze, can arrange water-permeable pavement
CN209338948U (en) A kind of water-permeable pavement structure
CN208486146U (en) A kind of novel filter infiltration garden road step and sunk type square laying structure
CN108951332B (en) Construction waste improvement inflation dirt road bed structure
CN208363444U (en) A kind of light fill manually makes somebody a mere figurehead basal disc greening structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: No. 11, Hubin Road, Wuxi, Jiangsu Province, 214000

Applicant after: Jiangsu Chenggui Design Co.,Ltd.

Address before: No. 11, Hubin Road, Wuxi, Jiangsu Province, 214000

Applicant before: WUXI CG DESIGN Co.,Ltd.

CB02 Change of applicant information
RJ01 Rejection of invention patent application after publication