CN109680905A - 一种高寒地区地下室彩色防裂混凝土地坪施工方法 - Google Patents
一种高寒地区地下室彩色防裂混凝土地坪施工方法 Download PDFInfo
- Publication number
- CN109680905A CN109680905A CN201910017935.3A CN201910017935A CN109680905A CN 109680905 A CN109680905 A CN 109680905A CN 201910017935 A CN201910017935 A CN 201910017935A CN 109680905 A CN109680905 A CN 109680905A
- Authority
- CN
- China
- Prior art keywords
- concrete
- thickness
- curing agent
- basement
- making
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/12—Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/18—Separately-laid insulating layers; Other additional insulating measures; Floating floors
- E04F15/181—Insulating layers integrally formed with the flooring or the flooring elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F21/00—Implements for finishing work on buildings
- E04F21/20—Implements for finishing work on buildings for laying flooring
- E04F21/24—Implements for finishing work on buildings for laying flooring of masses made in situ, e.g. smoothing tools
- E04F21/245—Rotary power trowels, i.e. helicopter trowels
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
本发明提供了一种高寒地区地下室彩色防裂混凝土地坪施工方法,采取以下步骤:铺筑C20混凝土垫层;粘贴防水卷材,涂刷防水涂料;浇筑C252细石混凝土保护层;施工基础底板,戈壁土分层回填;铺筑C25混凝土保护层;铺筑C25混凝土,散石英砂,打磨、固化、抛光,涂刷固化剂;中磨研处理,涂刷固化剂;用500号、800号、1000号磨料号段进行细磨研处理,涂刷固化剂;用2000号磨料号段进行抛光处理,成品保护;切割分格缝,冲洗干净,成品保护。本发明不仅在高寒地区低温季节的情况下保持混凝土的正常施工,提高了混凝土的抗压强度、劈裂抗拉强度和防冻性能,同时提高了施工效率。
Description
技术领域
本发明涉及建筑施工技术领域,尤其涉及一种高寒地区地下室彩色防裂混凝土地坪施工方法。
背景技术
混凝土地坪是指使用特定材料和工艺对原有混凝土地面进行施工处理并呈现出一定装饰性和功能性的地面。在高寒地区气温低下,混凝土硬化慢,从而影响混凝土强度。所以高寒地区的混凝土地坪如何施工,是工程界十分关注、又非常棘手的一个问题。
发明内容
为解决上述缺陷,本发明的目的是在于提供一种高寒地区地下室彩色防裂混凝土地坪施工方法,采用该施工方法,不仅在高寒地区低温季节的情况下保持混凝土地坪的正常施工,提高了混凝土地坪的抗压强度、劈裂抗拉强度和防冻性。
本发明的上述技术目的是通过以下技术方案得以实现的:一种高寒地区地下室彩色防裂混凝土地坪施工方法,包括如下步骤:
(1)在整平的地基土上铺筑90-110㎜厚C20混凝土垫层,先用直尺刮平,再用木抹子磨压平整,洒水覆盖养护5-10天;
(2)C20混凝土垫层养护后,粘贴1.3-1.8㎜厚LJ高分子自粘防水卷材,再涂刷1.8-2.5㎜厚非固化橡胶沥青防水涂料;
(3)橡胶沥青防水涂料干硬后,浇筑30-50㎜厚C25细石混凝土保护层,二次磨压平整,覆盖洒水养护5-10天;
(4)C25细石混凝土保护层养护后,施工基础底板,待基础底板混凝土强度达到设计强度的100%后,用戈壁土分层回填,戈壁土中大于60㎜的石块去掉,每层虚铺厚度为200-300㎜,夯实,至环刀取样检测密度合格;
(5)戈壁土回填土达到标高后,整平拍实,铺筑70-90㎜厚C25混凝土保护层拍实压平;再铺筑50-70㎜厚C25混凝土,刮平压实,散石英砂,圆盘机碾磨平整,铁抹子收光,覆盖洒水养护12-16天;
(6)混凝土养护后,再对混凝土地面进行打磨、固化、抛光,粗磨整平光滑后,涂刷第一遍混凝土密封固化剂,保持1-1.5小时湿润状态;待固化剂施工地面完全干燥后,进行中磨研磨处理,再涂刷第二遍混凝土密封固化剂,保持1-1.5小时湿润状态;待固化剂完全干燥后,用500号、800号、1000号磨料号段进行细磨研处理,磨至混凝土表面出现拆射光,涂刷第三遍混凝土密封固化剂;待混凝土密封固化剂完全干燥后,用2000号磨料号段进行抛光处理,最后做好成品保护;
(7)抛光后24小时内切割分格缝,缝宽4-5㎜,深度40㎜,间距4-6m,柱周边切分割缝,冲洗干净后做好成品保护。
进一步地,所述步骤(4)中,环刀取样检测密度具体为分层取样,检测4-6次,共取100-150个点,检测结果干密度最大值为2.30g/㎝³,最小值≧2.10g/㎝³为合格,同时压实系数不小于0.94。
本发明的有益效果:不仅能在高寒地区低温季节的情况下保持混凝土的正常施工,而且有效提高混凝土的抗压强度、劈裂抗拉强度和防冻性能,同时提高了施工效率。
附图说明
图1为本发明中混凝土地坪施工流程节点大样图。
其中:1、混凝土地面,2、石英砂,3、C25混凝土,4、戈壁土,5、基础底板,6、C25细石混凝土,71、橡胶沥青防水涂料,72、LJ高分子自粘防水卷材,8、C20混凝土垫层,9、地基土。
具体实施方式
以下结合附图对本发明作进一步详细说明。
如图1所示,一种高寒地区地下室彩色防裂混凝土地坪施工方法,包括如下步骤:
(1)在整平的地基土9上铺筑90-110㎜厚C20混凝土垫层8,先用直尺刮平,再用木抹子磨压平整,洒水覆盖养护5-10天;
(2)C20混凝土垫层8养护后,粘贴1.3-1.8㎜厚LJ高分子自粘防水卷材72,再涂刷1.8-2.5㎜厚非固化橡胶沥青防水涂料71;
(3)橡胶沥青防水涂料71干硬后,浇筑30-50㎜厚C25细石混凝土6保护层,二次磨压平整,覆盖洒水养护5-10天;
(4)C25细石混凝土6保护层养护后,施工基础底板5,待基础底板5混凝土强度达到设计强度的100%后,用戈壁土4分层回填,戈壁土4中大于60㎜的石块去掉,每层虚铺厚度为200-300㎜,夯实,至环刀取样检测密度合格;
(5)戈壁土4回填土达到标高后,整平拍实,铺筑70-90㎜厚C25混凝土3保护层拍实压平;再铺筑50-70㎜厚C25混凝土3,刮平压实,散石英砂2,圆盘机碾磨平整,铁抹子收光,覆盖洒水养护12-16天;
(6)混凝土养护后,再对混凝土地面1进行打磨、固化、抛光,粗磨整平光滑后,涂刷第一遍混凝土密封固化剂,保持1-1.5小时湿润状态;待固化剂施工地面完全干燥后,进行中磨研磨处理,再涂刷第二遍混凝土密封固化剂,保持1-1.5小时湿润状态;待固化剂完全干燥后,用500号、800号、1000号磨料号段进行细磨研处理,磨至混凝土表面出现拆射光,涂刷第三遍混凝土密封固化剂;待混凝土密封固化剂完全干燥后,用2000号磨料号段进行抛光处理,最后做好成品保护;
(7)抛光后24小时内切割分格缝,缝宽4-5㎜,深度40㎜,间距4-6m,柱周边切分割缝,冲洗干净后做好成品保护。
其中,步骤(4)中,环刀取样检测密度具体为分层取样,检测4-6次,共取100-150个点,检测结果干密度最大值为2.30g/㎝³,最小值≧2.10g/㎝³为合格,同时压实系数不小于0.94。
Claims (2)
1.一种高寒地区地下室彩色防裂混凝土地坪施工方法,其特征在于采取以下步骤 :
(1)在整平的地基土上铺筑90-110㎜厚C20混凝土垫层,先用直尺刮平,再用木抹子磨压平整,洒水覆盖养护5-10天;
(2)C20混凝土垫层养护后,粘贴1.3-1.8㎜厚LJ高分子自粘防水卷材,再涂刷1.8-2.5㎜厚非固化橡胶沥青防水涂料;
(3)橡胶沥青防水涂料干硬后,浇筑30-50㎜厚C25细石混凝土保护层,二次磨压平整,覆盖洒水养护5-10天;
(4)C25细石混凝土保护层养护后,施工基础底板,待基础底板混凝土强度达到设计强度的100%后,用戈壁土分层回填,戈壁土中大于60㎜的石块去掉,每层虚铺厚度为200-300㎜,夯实,至环刀取样检测密度合格;
(5)戈壁土回填土达到标高后,整平拍实,铺筑70-90㎜厚C25混凝土保护层拍实压平;再铺筑50-70㎜厚C25混凝土,刮平压实,散石英砂,圆盘机碾磨平整,铁抹子收光,覆盖洒水养护12-16天;
(6)混凝土养护后,再对混凝土地面进行打磨、固化、抛光,粗磨整平光滑后,涂刷第一遍混凝土密封固化剂,保持1-1.5小时湿润状态;待固化剂施工地面完全干燥后,进行中磨研磨处理,再涂刷第二遍混凝土密封固化剂,保持1-1.5小时湿润状态;待固化剂完全干燥后,用500号、800号、1000号磨料号段进行细磨研处理,磨至混凝土表面出现拆射光,涂刷第三遍混凝土密封固化剂;待混凝土密封固化剂完全干燥后,用2000号磨料号段进行抛光处理,最后做好成品保护;
(7)抛光后24小时内切割分格缝,缝宽4-5㎜,深度40㎜,间距4-6m,柱周边切分割缝,冲洗干净后做好成品保护。
2.根据权利要求1所述的高寒地区地下室彩色防裂混凝土地坪施工方法,其特征在于:所述步骤(4)中,环刀取样检测密度具体为分层取样,检测4-6次,共取100-150个点,检测结果干密度最大值为2.30g/㎝³,最小值≧2.10g/㎝³为合格,同时压实系数不小于0.94。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910017935.3A CN109680905A (zh) | 2019-01-09 | 2019-01-09 | 一种高寒地区地下室彩色防裂混凝土地坪施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910017935.3A CN109680905A (zh) | 2019-01-09 | 2019-01-09 | 一种高寒地区地下室彩色防裂混凝土地坪施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109680905A true CN109680905A (zh) | 2019-04-26 |
Family
ID=66192048
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910017935.3A Pending CN109680905A (zh) | 2019-01-09 | 2019-01-09 | 一种高寒地区地下室彩色防裂混凝土地坪施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109680905A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110981543A (zh) * | 2020-02-27 | 2020-04-10 | 佛山市东鹏陶瓷有限公司 | 一种生态石表面处理工艺 |
CN114525843A (zh) * | 2022-03-01 | 2022-05-24 | 瑞洲建设集团有限公司 | 地下室施工方法 |
CN115627122A (zh) * | 2022-10-13 | 2023-01-20 | 黄鑫 | 一种无机纳米树脂固化剂及其制备方法和施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107060271A (zh) * | 2017-04-24 | 2017-08-18 | 无锡市华灿化工有限公司 | 一种防尘硬化耐磨地坪施工方法 |
CN107514009A (zh) * | 2017-06-26 | 2017-12-26 | 上海二十冶建设有限公司 | 一种基坑底板大体积混凝土冬季施工裂缝的综合控制方法 |
CN108149569A (zh) * | 2018-01-25 | 2018-06-12 | 中铁二十二局集团第工程有限公司 | 用于严寒地区高速铁路桥面防水封闭体系及其施工方法 |
CN108301320A (zh) * | 2018-01-30 | 2018-07-20 | 中铁二十二局集团第工程有限公司 | 基于c40细石纤维混凝土的防水封闭层的铺装方法 |
CN108952080A (zh) * | 2018-08-29 | 2018-12-07 | 启东建筑集团有限公司 | 混凝土密封固化剂耐磨地坪整体施工方法 |
CN108951637A (zh) * | 2018-07-24 | 2018-12-07 | 四川大航建设工程有限公司 | 高寒地区低温季节混凝土施工方法 |
-
2019
- 2019-01-09 CN CN201910017935.3A patent/CN109680905A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107060271A (zh) * | 2017-04-24 | 2017-08-18 | 无锡市华灿化工有限公司 | 一种防尘硬化耐磨地坪施工方法 |
CN107060271B (zh) * | 2017-04-24 | 2019-04-23 | 无锡市华灿化工有限公司 | 一种防尘硬化耐磨地坪施工方法 |
CN107514009A (zh) * | 2017-06-26 | 2017-12-26 | 上海二十冶建设有限公司 | 一种基坑底板大体积混凝土冬季施工裂缝的综合控制方法 |
CN108149569A (zh) * | 2018-01-25 | 2018-06-12 | 中铁二十二局集团第工程有限公司 | 用于严寒地区高速铁路桥面防水封闭体系及其施工方法 |
CN108301320A (zh) * | 2018-01-30 | 2018-07-20 | 中铁二十二局集团第工程有限公司 | 基于c40细石纤维混凝土的防水封闭层的铺装方法 |
CN108951637A (zh) * | 2018-07-24 | 2018-12-07 | 四川大航建设工程有限公司 | 高寒地区低温季节混凝土施工方法 |
CN108952080A (zh) * | 2018-08-29 | 2018-12-07 | 启东建筑集团有限公司 | 混凝土密封固化剂耐磨地坪整体施工方法 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110981543A (zh) * | 2020-02-27 | 2020-04-10 | 佛山市东鹏陶瓷有限公司 | 一种生态石表面处理工艺 |
CN114525843A (zh) * | 2022-03-01 | 2022-05-24 | 瑞洲建设集团有限公司 | 地下室施工方法 |
CN114525843B (zh) * | 2022-03-01 | 2024-02-06 | 瑞洲建设集团有限公司 | 地下室施工方法 |
CN115627122A (zh) * | 2022-10-13 | 2023-01-20 | 黄鑫 | 一种无机纳米树脂固化剂及其制备方法和施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8381483B1 (en) | Terrazzo process for existing concrete surfaces | |
US4748788A (en) | Surface seeded exposed aggregate concrete and method of producing same | |
US8684627B2 (en) | Decorative concrete and method of installing the same | |
US6016635A (en) | Surface seeded aggregate and method of forming the same | |
CN109680905A (zh) | 一种高寒地区地下室彩色防裂混凝土地坪施工方法 | |
CN104153400B (zh) | 一种软土地基灌注桩头防水的施工方法 | |
CN109653529A (zh) | 历史建筑清水砖墙修缮施工方法 | |
CN103806356B (zh) | 一种装饰性混凝土地面结构的制作方法 | |
CN104032930A (zh) | 压模混凝土地面施工工法 | |
CN1982541A (zh) | 水电站地下廊道及洞室群防水堵漏的施工技术 | |
CN106884535A (zh) | 一种仿石材自流平防水砂浆的施工工艺 | |
US20070248411A1 (en) | Concrete template and method of use | |
CN110144790A (zh) | 一种透水砼的施工方法 | |
US20160122950A1 (en) | Method of reducing alkali-silica reaction for embedding aggregate in concrete and mitigating detrimental effects of freeze-thaw in concrete | |
CN107587398A (zh) | 金刚砂地面固化剂的施工方法 | |
CN105625140A (zh) | 一种透气排水自结纹复合塑胶跑道的施工方法 | |
CN108301320A (zh) | 基于c40细石纤维混凝土的防水封闭层的铺装方法 | |
CN107137913B (zh) | 网球场以及网球场的施工工艺 | |
CN113250033A (zh) | 改性透水地坪施工工艺 | |
CN107540314A (zh) | 一种后浇带基面处理剂及其施工方法 | |
CN114876155A (zh) | 不发火细石混凝土磨光地面施工工艺 | |
CN109653473A (zh) | 一种高寒地区屋面停车场抗裂彩色镜面混凝土地坪做法 | |
JP4030574B1 (ja) | 土系舗装材 | |
CN108264291A (zh) | 一种不发火混凝土浇筑施工方法 | |
US20110008594A1 (en) | Concrete template and method of use |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190426 |
|
RJ01 | Rejection of invention patent application after publication |