CN109447479B - Project management system based on three-dimensional visualization - Google Patents

Project management system based on three-dimensional visualization Download PDF

Info

Publication number
CN109447479B
CN109447479B CN201811291495.2A CN201811291495A CN109447479B CN 109447479 B CN109447479 B CN 109447479B CN 201811291495 A CN201811291495 A CN 201811291495A CN 109447479 B CN109447479 B CN 109447479B
Authority
CN
China
Prior art keywords
module
dimensional
engineering
construction
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811291495.2A
Other languages
Chinese (zh)
Other versions
CN109447479A (en
Inventor
林广泰
王建军
冯春萌
解威威
池浩
孙辉
陈孝强
李雍友
陆进
欧晨丰
陈旺平
梁承斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Road and Bridge Engineering Group Co Ltd
Original Assignee
Guangxi Road and Bridge Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Road and Bridge Engineering Group Co Ltd filed Critical Guangxi Road and Bridge Engineering Group Co Ltd
Priority to CN201811291495.2A priority Critical patent/CN109447479B/en
Publication of CN109447479A publication Critical patent/CN109447479A/en
Application granted granted Critical
Publication of CN109447479B publication Critical patent/CN109447479B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to the technical field of engineering management, in particular to a project management system based on three-dimensional visualization. The BIM three-dimensional model building method comprises a BIM three-dimensional model building module; a GIS three-dimensional topographic map building module; the real three-dimensional engineering model establishing module is used for combining the BIM three-dimensional model establishing module with the GIS three-dimensional topographic map establishing module to generate a real three-dimensional engineering model; the construction information input module is used for inputting construction progress and construction process records; the engineering management platform is used for managing the engineering project through a manager terminal; the three-dimensional engineering model display module is used for combining the construction information input module data, the engineering management platform data and the true three-dimensional engineering model building module and realizing the sharing of the engineering component information; and the database server is used for storing and sending data. The invention can facilitate the management and planning of the engineering by the managers and the reporting of the engineering construction condition information by the workers.

Description

Project management system based on three-dimensional visualization
Technical Field
The invention relates to the technical field of engineering management, in particular to a project management system based on three-dimensional visualization.
Background
The construction progress management of the engineering project is an important link of the engineering project management, and the traditional progress management method has the characteristics of information lag, low informatization degree and the like, and restricts the development of the engineering progress management level. In addition, the conventional project management technologies are many, but most of the conventional project management technologies are based on two-dimensional plane drawings, and the complex construction drawings given by the conventional project management technologies are difficult for general personnel to understand and are not as intuitive and effective as those given by a three-dimensional model.
At present, the management level can be improved through a building information model, which is called building information modeling for short, and is a complete information model, and engineering information, processes and resources of engineering projects at different stages in a whole life cycle can be integrated into one model, so that the building information model can be conveniently used by all engineering participants. The real information of the building is simulated through the three-dimensional digital technology, and information models which are coordinated with each other and have consistent interior are provided for engineering design and construction, so that the models achieve the integration of design and construction, and all specialties work together, thereby reducing the engineering production cost and ensuring that the engineering is finished on time according to quality. Although there are many APPs related to project management, each APP has a range of its own application, and the content of all project management cannot be included, so that a manager needs to open different APPs for different services when performing project management, which also causes complexity in operation. The task report and the progress report are filled by an operator after work every day, and the problem of false report and missing report is caused sometimes because the task report and the progress report are not filled in time.
Disclosure of Invention
In order to solve the problems, the invention provides a project management system based on three-dimensional visualization, which can facilitate the management and planning of management personnel on projects and facilitate the reporting of project construction condition information by working personnel.
A project management system based on three-dimensional visualization comprises a true three-dimensional engineering model establishing module, a BIM three-dimensional model establishing module, a GIS three-dimensional topographic map establishing module, a construction information inputting module, an engineering management platform, a three-dimensional engineering model display module, an auxiliary information module and a database server,
the BIM three-dimensional model building module is used for building a BIM three-dimensional model of a project through software and dividing the BIM three-dimensional model into a plurality of project components, and the project components correspond to actual project parts and can be used for inputting information of component names, materials, affiliated positions, project quantities and construction costs;
the GIS three-dimensional topographic map establishing module is used for performing space-three encryption calculation on the field topographic data through Smart3D software to generate point cloud data, and manufacturing an actual topographic map of the engineering field through the point cloud data;
the real three-dimensional engineering model building module is used for combining the data of the BIM three-dimensional model building module with the data of the GIS three-dimensional topographic map building module and generating a real three-dimensional engineering model;
the construction information input module is used for inputting construction progress and construction process records in real time at a worker terminal;
the engineering management platform is used for managing engineering projects through a manager terminal and comprises a progress management module, an equipment management module, a component management module, a personnel management module and a field monitoring module;
the three-dimensional engineering model display module is used for combining the construction information input module data, the engineering management platform data and the true three-dimensional engineering model building module, and the worker terminal and the manager terminal share the information of each engineering component in real time through the three-dimensional engineering model display module;
the auxiliary information module is used for acquiring the attention items of the construction process and the information of labor insurance products and tools required by construction through a machine learning algorithm according to the position of the construction member and the construction project of the construction member acquired by the engineering management platform, transmitting the information to the three-dimensional engineering model display module, and acquiring the information of the auxiliary information module through the three-dimensional engineering model display module by the staff terminal;
and the database server is used for storing and sending the data of the engineering management platform, the three-dimensional engineering model display module and the auxiliary information module.
The system further comprises a supervision module, wherein the supervision module comprises a video acquisition sub-module and a first identification comparison sub-module, and the video acquisition sub-module is used for shooting the wearing information of the labor protection articles and the information of the construction tools of the constructors before starting; the first identification comparison submodule is used for extracting the characteristic image of the video acquisition submodule, comparing the characteristic image of the video acquisition submodule with the information of the auxiliary information module and feeding back the comparison result to a worker.
Further, the GIS three-dimensional topographic map building module obtains field topographic data through an unmanned aerial vehicle aerial photography technology.
Further, the real three-dimensional engineering model building module generates a real three-dimensional engineering model by importing the terrain information of the GIS three-dimensional terrain map building module into Lumion software to be combined with the three-dimensional model of the BIM three-dimensional model building module.
Further, the three-dimensional engineering model display module receives the information of the progress management module and the personnel management module and displays the information in each engineering component in the true three-dimensional model, and a worker carries out construction through the planned progress information and the personnel configuration information acquired by the worker terminal in the three-dimensional engineering model display module; and the manager acquires data of actual construction progress and construction process records from the constructed component of the three-dimensional engineering model display module according to the manager terminal, and performs progress adjustment and personnel arrangement according to big data through the progress management module and the personnel management module.
Further, the construction information input module sends the condition and the use information of the equipment in the construction process to the three-dimensional engineering model display module, and the staff acquires the historical condition and the historical use information of the equipment in the equipment management module through the manager terminal.
Further, the component management module is used for providing information of component name, material, affiliated position, engineering quantity and construction cost of each engineering component for workers through the manager terminal.
Furthermore, the on-site monitoring module is used for remotely monitoring the condition of a construction site and comprises an on-site monitoring camera and a monitoring control submodule, wherein the on-site monitoring camera is arranged in the construction site and corresponds to each engineering component; the monitoring control sub-module is used for controlling the monitoring camera; the site construction condition of the engineering component can be obtained in real time by clicking the site monitoring module of the engineering component in the three-dimensional engineering model display module.
Furthermore, the on-site monitoring module further comprises a second identification comparison module, wherein the second identification comparison module is used for extracting the characteristic image of the video shot by the on-site monitoring camera, comparing the characteristic image of the video shot by the on-site monitoring camera with the information of the auxiliary information module, marking the on-site dressing workers which do not meet the requirements, and feeding back the marks to the worker terminals.
Further, project management using the present system includes the steps of,
s1, establishing a BIM three-dimensional model in a BIM three-dimensional model establishing module according to actual engineering, dividing the BIM three-dimensional model into a plurality of engineering components according to actual engineering positions, and inputting information of component names, materials, affiliated positions, engineering quantities and construction costs of the engineering components;
s2, acquiring field topographic data through an unmanned aerial vehicle aerial photography technology, performing air-to-air encryption calculation on the field topographic data through Smart3D software in the GIS three-dimensional topographic map establishing module to generate point cloud data, and manufacturing an actual topographic map of the engineering field through the point cloud data;
s3, importing terrain information into Lumion software to be combined with the three-dimensional model of the BIM three-dimensional model building module, so that the three-dimensional engineering model display module generates a true three-dimensional engineering model;
s4, a manager carries out construction organization design according to big data through the manager terminal, and records data related to the progress management module, the equipment management module, the component management module and the personnel management module in the three-dimensional engineering model display module;
s5, a worker acquires a construction scheme from the three-dimensional engineering model display module, works according to the construction scheme, and uploads construction progress and construction process records to the construction information input module in real time at a worker terminal;
s6, a worker wears the labor protection article and prepares a tool according to the information provided by the auxiliary information module, the worker takes pictures of the labor protection article and the tool after finishing wearing and the tool preparation, the first identification comparison sub-module compares the characteristic image of the video acquisition sub-module with the information of the auxiliary information module, and when the first identification comparison sub-module is not matched, the first identification comparison sub-module prompts the labor protection article to wear the information which is not qualified and the information of tool missing or error and prompts the worker to take pictures of the unmatched place again;
s7, a manager can acquire the field construction condition of the engineering component in real time by clicking the field monitoring module in the three-dimensional engineering model display module and selecting the construction component to be monitored; the second identification and comparison module compares the characteristic image of the video shot by the on-site monitoring camera with the information of the auxiliary information module, marks the on-site dressing unqualified workers and feeds back the on-site dressing unqualified workers to the worker terminal;
and S8, acquiring data of actual construction progress and construction process records by a manager according to the manager terminal in the constructed member of the three-dimensional engineering model display module, and adjusting progress and arranging personnel according to big data through the progress management module and the personnel management module.
The invention has the beneficial effects that:
the BIM three-dimensional model building module divides the BIM three-dimensional model into a plurality of engineering components, the engineering components correspond to actual engineering parts and can be used for inputting information of component names, materials, affiliated positions, engineering quantities and construction costs, the engineering components are decomposed according to the modules, each module has a label, and statistics of a 0# standing book is facilitated; the GIS three-dimensional topographic map building module obtains field topographic data through an unmanned aerial vehicle aerial photography technology, performs space-three encryption calculation on the field topographic data through Smart3D software to generate point cloud data, and manufactures an actual topographic map of the engineering field through the point cloud data. The true three-dimensional engineering model building module combines the two into visual information for workers and managers, and information can be conveniently obtained.
2. The three-dimensional engineering model display module realizes mutual mapping of WBS and BIM through combination of construction information input module data, engineering management platform data and a true three-dimensional engineering model building module, so that a worker terminal and a manager terminal can share information of each engineering component in real time through the three-dimensional engineering model display module, the worker can know construction requirements conveniently, and the manager can perform progress management, equipment management, component management and personnel management better.
3. The auxiliary information module is used for acquiring the positions of the construction members and the construction projects of the construction members according to the engineering management platform, acquiring the attention items of the construction process and the information of labor insurance products and tools required by construction through a machine learning algorithm, and supervising the preparation work of workers before construction through the supervision module, so that the safety of the workers in the construction process is ensured, and the delay of the progress of the engineering caused by the lack of the tools can be avoided.
4. The on-site monitoring camera is arranged in a construction site and corresponds to each engineering component; the monitoring control submodule is used for controlling the monitoring camera; a manager monitors the engineering component constructed by the on-site monitoring camera through the monitoring control submodule, and can provide technical support in time when an accident or an abnormal condition occurs; the second identification module can extract the characteristic image of the video shot by the field monitoring camera, compares the characteristic image of the video shot by the field monitoring camera with the information of the auxiliary information module, marks the worker who is not qualified in the field dressing and feeds the worker back to the worker terminal, realizes monitoring on the field constructor, avoids accidents caused by the fact that the worker who is in the field construction is not qualified in the dressing, and further ensures the construction safety of the constructor.
Drawings
FIG. 1 is a block diagram of the system architecture of the present invention.
In the figure, 1-a real three-dimensional engineering module building module, 11-a BIM three-dimensional model building module, 12-a GIS three-dimensional model building module, 2-a construction information input module, 21-a worker terminal, 3-an engineering management platform, 31-a progress management module, 32-an equipment management module, 33-a component management module, 34-a personnel management module, 35-a field monitoring module, 351-a field monitoring camera, 352-a monitoring control sub-module, 353-a second identification comparison module, 4-a three-dimensional engineering model display module, 5-an auxiliary information module, 51-a supervision module, 511-a video acquisition sub-module, 512-a first identification comparison sub-module, 6-a database server module and 7-a manager terminal.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. The terminology used in the description of the invention herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.
A project management system based on three-dimensional visualization comprises a true three-dimensional engineering model building module 1, a BIM three-dimensional model building module 11, a GIS three-dimensional topographic map building module 12, a construction information input module 2, an engineering management platform 3, a three-dimensional engineering model display module 4, an auxiliary information module 5 and a database server 6.
The BIM three-dimensional model building module 11 is used for building a BIM three-dimensional model of a project through software, and dividing the BIM three-dimensional model into a plurality of project components, wherein the project components correspond to actual project parts and can be used for inputting information of component names, materials, affiliated positions, project quantities and construction costs. In this embodiment, the BIM three-dimensional model building module 11 builds a BIM three-dimensional model of an engineering through Revit or CATIA software.
The GIS three-dimensional topographic map establishing module 12 is used for performing space-three encryption calculation on the field topographic data through Smart3D software to generate point cloud data, and making an actual topographic map of the engineering field through the point cloud data. In this embodiment, the GIS three-dimensional topographic map building module 12 obtains the field topographic data through the unmanned aerial vehicle aerial photography technology.
The true three-dimensional engineering model building module 1 is used for combining the data of the BIM three-dimensional model building module 11 with the data of the GIS three-dimensional topographic map building module 12 and generating a true three-dimensional engineering model. In this embodiment, the true three-dimensional engineering model building module 1 generates the true three-dimensional engineering model by importing the terrain information of the GIS three-dimensional terrain map building module 12 into Lumion software and combining with the three-dimensional model of the BIM three-dimensional model building module 11.
The BIM three-dimensional model building module 11 divides the BIM three-dimensional model into a plurality of engineering components, the engineering components correspond to actual engineering positions and can carry out information input of component names, materials, affiliated positions, engineering quantities and construction costs; the GIS three-dimensional topographic map establishing module 12 obtains field topographic data through an unmanned aerial vehicle aerial photography technology, performs space-three encryption calculation on the field topographic data through Smart3D software to generate point cloud data, and makes an actual topographic map of the engineering field through the point cloud data. The true three-dimensional engineering model building module 1 combines the two into visual information for workers and managers, and information is convenient to obtain.
The construction information input module 2 is used for inputting the construction progress and the construction process record in real time through the staff terminal 21. Through the system, the traditional task reporting and recording work can be omitted by the staff of the construction information input module 2, the shooting and recording work can be carried out through the platform in real time, and the condition of error caused by untimely recording in the working process is also avoided.
The project management platform 3 is used for managing a project through a manager terminal 7, and includes a schedule management module 31, an equipment management module 32, a component management module 33, a personnel management module 34, and a field monitoring module 35.
The three-dimensional engineering model display module 4 is used for combining the data of the construction information input module 2 and the data of the engineering management platform 3 with the true three-dimensional engineering model building module 1, and the worker terminal 21 and the manager terminal 7 share the information of each engineering component in real time through the three-dimensional engineering model display module 4.
The three-dimensional engineering model display module 4 receives the information of the progress management module 31 and the personnel management module 34 and displays the information in each engineering component in the true three-dimensional model, and the staff carries out construction through the planned progress information and the personnel configuration information which are acquired by the staff terminal 21 in the three-dimensional engineering model display module 4; the manager obtains data of actual construction progress and construction process records from the constructed components of the three-dimensional engineering model display module 4 according to the manager terminal 7, and performs progress adjustment and personnel arrangement according to the big data through the progress management module 31 and the personnel management module 34.
The construction information input module 2 sends the condition and the use information of the equipment in the construction process to the three-dimensional engineering model display module 4, and the staff acquires the historical condition and the historical use information of the equipment in the equipment management module 32 through the manager terminal 7.
The component management module 33 is used for providing information of component name, material, belonging position, project amount and construction cost of each project component for the staff through the manager terminal 7.
In this embodiment, the three-dimensional engineering model display module combines the data of the construction information input module 2 and the data of the engineering management platform 3 with the true three-dimensional engineering model building module 1 through 4, so that the worker terminal 21 and the manager terminal 7 share the information of each engineering component in real time through the three-dimensional engineering model display module 4, thereby facilitating the worker to know the construction requirement and enabling the manager to better perform progress management, equipment management, component management and personnel management.
The auxiliary information module 5 is used for acquiring the attention items of the construction process and the information of labor insurance products and tools required by construction through a machine learning algorithm according to the position of the construction member and the construction project of the construction member acquired by the engineering management platform 3, transmitting the information to the three-dimensional engineering model display module 4, and acquiring the information of the auxiliary information module 5 through the three-dimensional engineering model display module 4 by the staff terminal 21.
In this embodiment, the monitoring module 51 includes a video capturing sub-module 511 and a first identifying and comparing sub-module 512, and the video capturing sub-module 511 is used for shooting the wearing information of the labor insurance products and the information of the construction tools of the constructors before starting; the first recognition and comparison sub-module 512 is configured to extract a feature image of the video capture sub-module 511, compare the feature image of the video capture sub-module 511 with information of the auxiliary information module 5, and feed back a comparison result to a worker. The preparation work before the construction of the workers is supervised by the supervision module 51, so that the safety of the workers in the construction process is ensured, and the delay of the progress of the project caused by the lack of tools can be avoided.
And the database server 6 is used for storing and sending data of the engineering management platform 3, the three-dimensional engineering model display module 4 and the auxiliary information module 5.
The on-site monitoring module 35 is used for remotely monitoring the condition of a construction site, and comprises an on-site monitoring camera 351 and a monitoring control submodule 352, wherein the on-site monitoring camera 351 is arranged in the construction site and corresponds to each engineering component; the monitoring control sub-module 352 is used for controlling the monitoring camera 351; the site construction condition of the engineering component can be obtained in real time by clicking the site monitoring module 35 of the engineering component in the three-dimensional engineering model display module 4. A manager controls the field monitoring camera 351 through the monitoring control sub-module 352, monitors the constructed engineering component and can provide technical support in time when an accident or an abnormal condition occurs;
the on-site monitoring module 35 further includes a second recognition and comparison module 353, and the second recognition and comparison module 353 is configured to extract a feature image of a video captured by the on-site monitoring camera 351, compare the feature image of the video captured by the on-site monitoring camera 351 with information of the auxiliary information module 5, mark an on-site dressing unsatisfactory worker, and feed back the on-site dressing unsatisfactory worker to the worker terminal 21. The monitoring of field construction personnel is realized, accidents caused by the fact that the dressing of field construction personnel is not in accordance with the standard are avoided, and the construction safety of the personnel is further guaranteed.
When a certain component needs to be constructed, a manager acquires data of actual construction progress and construction process records from the constructed component of the three-dimensional engineering model display module 4 according to the manager terminal 7, and sets progress and arranges personnel through the progress management module 31 and the personnel management module 34. And the staff performs construction through the plan progress information and the staff configuration information acquired by the staff terminal 21 in the three-dimensional engineering model display module 4. In the construction process, according to the construction progress information updated in real time on the three-dimensional engineering model display module 4, the staff adjusts the progress and rearranges the staff through the progress management module 31 and the staff management module 34, and the staff performs construction according to the latest information obtained on the three-dimensional engineering model display module 4.
Project management using the present system includes the following steps,
s1, building a BIM three-dimensional model in a BIM three-dimensional model building module 11 according to actual engineering, dividing the BIM three-dimensional model into a plurality of engineering components according to actual engineering positions, and inputting information of component names, materials, affiliated positions, engineering quantities and construction costs of the engineering components;
s2, acquiring field topographic data through an unmanned aerial vehicle aerial photography technology, performing air-to-air encryption calculation on the field topographic data through Smart3D software in a GIS three-dimensional topographic map establishing module 12 to generate point cloud data, and manufacturing an actual topographic map of the engineering field through the point cloud data;
s3, importing the terrain information into Lumion software to be combined with the three-dimensional model of the BIM three-dimensional model building module 11, so that the three-dimensional engineering model display module 4 generates a true three-dimensional engineering model;
s4, construction organization design is carried out by a manager through a manager terminal 7 according to big data, and data related to a progress management module 31, an equipment management module 32, a component management module 33 and a personnel management module 34 in the three-dimensional engineering model display module 4 are input;
s5, the worker obtains a construction scheme in the three-dimensional engineering model display module 4 and executes work according to the construction scheme, and the worker uploads construction progress and construction process records to the construction information input module 2 in real time at the worker terminal 21;
s6, a worker wears the labor protection product and prepares a tool according to the information provided by the auxiliary information module 5, the worker takes pictures of the labor protection product after wearing and the tool is prepared, the first identification comparison sub-module 512 compares the characteristic image of the video acquisition sub-module 511 with the information of the auxiliary information module 5, and when the first identification comparison sub-module 512 is not matched, the first identification comparison sub-module 512 prompts the information that the wearing of the labor protection product is not qualified and the information that the tool is lacked or wrong, and prompts the unmatched place to be taken again;
s7, a manager can acquire the field construction condition of the engineering component in real time by clicking the field monitoring module 35 in the three-dimensional engineering model display module 4 and selecting the construction component to be monitored; the second identification comparison module 353 compares the characteristic image of the video shot by the field monitoring camera 351 with the information of the auxiliary information module 5, and marks and feeds back the staff which is not qualified for field dressing to the staff terminal 21;
and S8, acquiring data of actual construction progress and construction process records from the constructed component of the three-dimensional engineering model display module 4 by a manager according to the manager terminal 7, and adjusting the progress and arranging the personnel according to the big data through the progress management module 31 and the personnel management module 34.
The invention digitalizes and informationizes the whole project, and can change the project at any time according to the actual situation of the project, thereby saving the complex flow of the traditional map changing.
The system integrates the content of all project management, and project managers can know the detailed condition of the whole project through the system, so that the condition that a plurality of APPs are used simultaneously and information is repeated and disordered due to different main function emphasis points of a software platform is avoided.

Claims (6)

1. A project management system based on three-dimensional visualization is characterized by comprising a true three-dimensional engineering model establishing module (1), a BIM three-dimensional model establishing module (11), a GIS three-dimensional topographic map establishing module (12), a construction information input module (2), an engineering management platform (3), a three-dimensional engineering model display module (4), an auxiliary information module (5) and a database server (6),
the BIM three-dimensional model building module (11) is used for building a BIM three-dimensional model of a project through software, and dividing the BIM three-dimensional model into a plurality of project components, wherein the project components correspond to actual project parts and can be used for inputting information of component names, materials, affiliated positions, project quantities and construction costs;
the GIS three-dimensional topographic map establishing module (12) is used for performing space-three encryption calculation on the field topographic data through Smart3D software to generate point cloud data, and manufacturing an actual topographic map of the engineering field through the point cloud data;
the real three-dimensional engineering model building module (1) is used for combining the data of the BIM three-dimensional model building module (11) with the data of the GIS three-dimensional topographic map building module (12) and generating a real three-dimensional engineering model;
the construction information input module (2) is used for inputting construction progress and construction process records in real time through a worker terminal (21);
the project management platform (3) is used for managing project projects through a manager terminal (7), and comprises a progress management module (31), an equipment management module (32), a component management module (33), a personnel management module (34) and a field monitoring module (35);
the three-dimensional engineering model display module (4) is used for combining the data of the construction information input module (2) and the data of the engineering management platform (3) with the true three-dimensional engineering model building module (1), and the worker terminal (21) and the manager terminal (7) share the information of each engineering component in real time through the three-dimensional engineering model display module (4);
the auxiliary information module (5) is used for acquiring the positions of the construction components and the construction projects of the construction components according to the engineering management platform (3) through a machine learning algorithm to acquire the attention matters of the construction process and the information of labor insurance products and tools required by construction, transmitting the information to the three-dimensional engineering model display module (4), and the staff terminal (21) acquires the information of the auxiliary information module (5) through the three-dimensional engineering model display module (4);
the database server (6) is used for storing and sending data of the engineering management platform (3), the three-dimensional engineering model display module (4) and the auxiliary information module (5);
the construction safety and safety product monitoring system is characterized by further comprising a supervision module (51), wherein the supervision module (51) comprises a video acquisition sub-module (511) and a first identification comparison sub-module (512), and the video acquisition sub-module (511) is used for shooting the wearing information of the construction safety and safety product and the construction tool information of construction personnel before starting; the first identification comparison submodule (512) is used for extracting a characteristic image of the video acquisition submodule (511), comparing the characteristic image of the video acquisition submodule (511) with the information of the auxiliary information module (5), and feeding back a comparison result to a worker;
the on-site monitoring module (35) is used for remotely monitoring the condition of a construction site and comprises an on-site monitoring camera (351) and a monitoring control sub-module (352), wherein the on-site monitoring camera (351) is arranged in the construction site and corresponds to each engineering component; the monitoring control sub-module (352) is used for controlling the monitoring camera (351); the site construction condition of the engineering component can be obtained in real time by clicking the site monitoring module (35) of the engineering component in the three-dimensional engineering model display module (4);
the on-site monitoring module (35) further comprises a second identification comparison module (353), wherein the second identification comparison module (353) is used for extracting a characteristic image of a video shot by the on-site monitoring camera (351), comparing the characteristic image of the video shot by the on-site monitoring camera (351) with the information of the auxiliary information module (5), marking an on-site dressing worker which does not meet requirements, and feeding back the worker to the worker terminal (21);
a project management based on a three-dimensional visualization project management system includes the following steps,
s1, building a BIM three-dimensional model in a BIM three-dimensional model building module (11) according to actual engineering, dividing the BIM three-dimensional model into a plurality of engineering components according to actual engineering positions, and inputting information of component names, materials, affiliated positions, engineering quantities and construction costs of the engineering components;
s2, acquiring field topographic data through an unmanned aerial vehicle aerial photography technology, performing air-to-three encryption calculation on the field topographic data through Smart3D software in the GIS three-dimensional topographic map establishing module (12) to generate point cloud data, and manufacturing an actual topographic map of the engineering field through the point cloud data;
s3, importing terrain information into Lumion software to be combined with the three-dimensional model of the BIM three-dimensional model building module (11) so that the three-dimensional engineering model display module (4) generates a true three-dimensional engineering model;
s4, construction organization design is carried out by a manager through the manager terminal (7) according to big data, and data related to the progress management module (31), the equipment management module (32), the component management module (33) and the personnel management module (34) in the three-dimensional engineering model display module (4) are input;
s5, a worker acquires a construction scheme from the three-dimensional engineering model display module (4), executes work according to the construction scheme, and uploads construction progress and construction process records to the construction information input module (2) in real time at a worker terminal (21);
s6, a worker wears the labor protection supplies and prepares tools according to the information provided by the auxiliary information module (5), the worker takes pictures through the video acquisition submodule (511) after finishing wearing the labor protection supplies and finishing preparing the tools, the first identification comparison submodule (512) compares the characteristic image of the video acquisition submodule (511) with the information of the auxiliary information module (5), and when the first identification comparison submodule (512) is not matched, the first identification comparison submodule (512) prompts the labor protection supplies to wear information which is not qualified and information which is missing or wrong of the tools, and prompts the unmatched places to be taken again;
s7, a manager can acquire the field construction condition of the engineering component in real time by clicking the field monitoring module (35) in the three-dimensional engineering model display module (4) and selecting the construction component to be monitored; the second identification comparison module (353) compares the characteristic image of the video shot by the field monitoring camera (351) with the information of the auxiliary information module (5), and marks and feeds back the staff which is not qualified for field dressing to the staff terminal (21);
and S8, acquiring data of actual construction progress and construction process records from the constructed component of the three-dimensional engineering model display module (4) by a manager according to the manager terminal (7), and adjusting progress and arranging personnel according to big data through the progress management module (31) and the personnel management module (34).
2. The project management system based on three-dimensional visualization of claim 1, wherein: the GIS three-dimensional topographic map establishing module (12) obtains field topographic data through an unmanned aerial vehicle aerial photography technology.
3. The project management system based on three-dimensional visualization of claim 1, wherein: the real three-dimensional engineering model building module (1) leads the terrain information of the GIS three-dimensional terrain map building module (12) into Lumion software to be combined with the three-dimensional model of the BIM three-dimensional model building module (11) to generate a real three-dimensional engineering model.
4. The project management system based on three-dimensional visualization of claim 1, wherein: the three-dimensional engineering model display module (4) receives information of the progress management module (31) and the personnel management module (34) and displays the information in each engineering component in the true three-dimensional model, and a worker carries out construction on the planned progress information and the personnel configuration information acquired by the three-dimensional engineering model display module (4) through the worker terminal (21); and the manager acquires data of actual construction progress and construction process records from the constructed components of the three-dimensional engineering model display module (4) according to the manager terminal (7), and performs progress adjustment and personnel arrangement according to big data through the progress management module (31) and the personnel management module (34).
5. The project management system based on three-dimensional visualization of claim 1, wherein: the construction information input module (2) sends the condition and the use information of equipment in the construction process to the three-dimensional engineering model display module (4), and a worker obtains the historical condition and the historical use information of the equipment in the equipment management module (32) through the manager terminal (7).
6. The project management system based on three-dimensional visualization of claim 1, wherein: the component management module (33) is used for providing information of component name, material, affiliated position, engineering quantity and construction cost of each engineering component for workers through the manager terminal (7).
CN201811291495.2A 2018-10-31 2018-10-31 Project management system based on three-dimensional visualization Active CN109447479B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811291495.2A CN109447479B (en) 2018-10-31 2018-10-31 Project management system based on three-dimensional visualization

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811291495.2A CN109447479B (en) 2018-10-31 2018-10-31 Project management system based on three-dimensional visualization

Publications (2)

Publication Number Publication Date
CN109447479A CN109447479A (en) 2019-03-08
CN109447479B true CN109447479B (en) 2021-12-21

Family

ID=65549500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811291495.2A Active CN109447479B (en) 2018-10-31 2018-10-31 Project management system based on three-dimensional visualization

Country Status (1)

Country Link
CN (1) CN109447479B (en)

Families Citing this family (37)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109917708A (en) * 2019-03-13 2019-06-21 武汉零点视觉数字科技有限公司 A kind of three-dimensional scenic display systems of engineering informationization construction
CN109949018A (en) * 2019-04-17 2019-06-28 河北方舟工程项目管理有限公司 Construction-engineering project management overall process tracing system
CN110158607A (en) * 2019-04-25 2019-08-23 广东景源建设工程有限公司 Supporting pile construction method and system
CN110070307B (en) * 2019-05-05 2022-07-05 广西路桥工程集团有限公司 Information visualization management system based on WBS
CN110084526B (en) * 2019-05-05 2022-05-31 广西路桥工程集团有限公司 BIM + WBS-based visual project management monitoring system
CN110096814B (en) * 2019-05-05 2022-08-16 广西路桥工程集团有限公司 Digital bridge construction system based on BIM model
CN110084527B (en) * 2019-05-05 2022-05-31 广西路桥工程集团有限公司 Digital construction management system based on BIM model
CN110232558A (en) * 2019-05-10 2019-09-13 林同棪国际工程咨询(中国)有限公司 Engineering project progress msg monitoring method
CN110398982A (en) * 2019-06-21 2019-11-01 万翼科技有限公司 A kind of method for inspecting and system of unmanned plane
CN110457410A (en) * 2019-06-28 2019-11-15 杭州鲁尔物联科技有限公司 A kind of construction method and system of three-dimensional GIS platform
CN110490415B (en) * 2019-07-15 2023-07-14 同济大学 Building progress assessment method for visual coordination of multiple unmanned aerial vehicles
CN110457759A (en) * 2019-07-17 2019-11-15 北京朗道新科智能科技有限公司 A kind of road construction management method, system and computer storage medium
CN110472375A (en) * 2019-09-18 2019-11-19 中国十七冶集团有限公司 A kind of asymmetric suspension bridge construction management-control method based on BIM
CN110580397A (en) * 2019-09-23 2019-12-17 重庆渝高科技产业(集团)股份有限公司 display system for engineering project centralized display platform
CN111008237B (en) * 2019-09-27 2023-06-23 重庆渝高科技产业(集团)股份有限公司 Big data platform command center
CN110751725B (en) * 2019-10-18 2022-10-28 青岛理工大学 Disaster occurrence tracing method based on BIM + GIS fusion technology
CN110991982A (en) * 2019-10-28 2020-04-10 中船重工海鑫工程管理(北京)有限公司 Construction project building information management method and system
CN111062686A (en) * 2019-12-10 2020-04-24 广州电力工程监理有限公司 Mobile intelligent supervision and control method and system based on digital model
CN111105323B (en) * 2019-12-20 2022-06-24 广西路桥工程集团有限公司 Engineering management system based on WBS
CN111246083B (en) * 2020-01-03 2022-03-15 广西路桥工程集团有限公司 Real-time live broadcast system is patrolled and examined in 5G unmanned aerial vehicle building site
CN111401765B (en) * 2020-03-24 2024-01-16 重庆德生鼎盛实业发展有限公司 Engineering progress supervision system based on big data
CN111445218A (en) * 2020-04-22 2020-07-24 中铁二十一局集团电务电化工程有限公司 BIM-based project progress management method, device, equipment and storage medium
CN111445219A (en) * 2020-05-14 2020-07-24 河北建设集团股份有限公司 RTK technology-based field plane arrangement system and arrangement method
CN111625891B (en) * 2020-05-27 2023-02-07 广东金盛世生态环境有限公司 Virtual garden landscape digital modeling method of information acquisition equipment based on BIM technology
CN112149212B (en) * 2020-09-22 2022-08-05 广西路桥工程集团有限公司 Visual construction management platform for engineering project
CN112132543A (en) * 2020-09-25 2020-12-25 广西路桥工程集团有限公司 Engineering project progress management system
CN112348473A (en) * 2020-11-10 2021-02-09 湖北福泰建筑装饰工程有限公司 Engineering management information visualization software
CN112488547A (en) * 2020-12-09 2021-03-12 黑龙江建筑职业技术学院 Distribution management system based on engineering project management
CN112766883A (en) * 2021-01-06 2021-05-07 苏州隶匠科技有限公司 Construction project supervision method
CN112926841A (en) * 2021-02-05 2021-06-08 国家电网有限公司 Engineering construction quality process data integration monitoring method and system
CN112884444B (en) * 2021-03-10 2023-07-18 苏州思萃融合基建技术研究所有限公司 Intelligent system for managing construction site personnel based on digital twin technology
CN113409462A (en) * 2021-05-28 2021-09-17 湖北中金匠建设工程有限公司 Municipal engineering construction safety control method and system based on 3DGIS and BIM technology
CN113723786B (en) * 2021-08-20 2024-02-02 寰球孪生空间设计(云南)有限公司 Visual planning auxiliary system based on three-dimensional GIS
CN113935859A (en) * 2021-09-10 2022-01-14 中建三局集团有限公司 Intelligent construction site system based on BIM model
CN113536071B (en) * 2021-09-15 2021-12-28 国能大渡河大数据服务有限公司 System for comprehensive management of hydropower engineering
CN116645069B (en) * 2023-07-26 2023-12-22 东莞市鹏锦机械科技有限公司 Engineering project management system based on machine vision
CN116957291B (en) * 2023-08-10 2024-05-07 湛江市广厦施工图审查服务中心 Intelligent management system and method for engineering management data

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107037881A (en) * 2017-03-24 2017-08-11 广西七三科技有限公司 The interactive demonstration method and system of GIS and BIM augmented realities in piping lane, subway work
CN107680220A (en) * 2017-09-28 2018-02-09 朱明增 A kind of operation unlawful practice intelligent identification Method based on machine vision technique
CN107729609A (en) * 2017-09-14 2018-02-23 北京致臻智造科技有限公司 The display methods and system that a kind of building decoration technology is told somebody what one's real intentions are
CN108319926A (en) * 2018-02-12 2018-07-24 安徽金禾软件股份有限公司 A kind of the safety cap wearing detecting system and detection method of building-site
CN108549963A (en) * 2018-02-22 2018-09-18 北京中建建筑设计院有限公司 A kind of novel execution management method therefor based on BIM information flow standards
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107037881A (en) * 2017-03-24 2017-08-11 广西七三科技有限公司 The interactive demonstration method and system of GIS and BIM augmented realities in piping lane, subway work
CN107729609A (en) * 2017-09-14 2018-02-23 北京致臻智造科技有限公司 The display methods and system that a kind of building decoration technology is told somebody what one's real intentions are
CN107680220A (en) * 2017-09-28 2018-02-09 朱明增 A kind of operation unlawful practice intelligent identification Method based on machine vision technique
CN108319926A (en) * 2018-02-12 2018-07-24 安徽金禾软件股份有限公司 A kind of the safety cap wearing detecting system and detection method of building-site
CN108549963A (en) * 2018-02-22 2018-09-18 北京中建建筑设计院有限公司 A kind of novel execution management method therefor based on BIM information flow standards
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
无人机遥感在地面目标变化监测中的应用研究;喻静敏等;《电子测量技术》;20180531;第41卷(第9期);第95-98页 *

Also Published As

Publication number Publication date
CN109447479A (en) 2019-03-08

Similar Documents

Publication Publication Date Title
CN109447479B (en) Project management system based on three-dimensional visualization
CN109377065B (en) Project construction progress management and cost control system based on three-dimensional visualization
CN109446664B (en) On-site progress management display equipment system
CN110084526B (en) BIM + WBS-based visual project management monitoring system
CN109978409B (en) Multi-engineering enterprise-level intelligent construction site block chain management method
CN111598734A (en) Intelligent building site integrated management system of BIM and Internet of things
CN109559379B (en) Panorama house-seeing method and device based on assembly type building platform
CN108596423A (en) A kind of trackways engineering construction progress msg management method based on BIM
CN109557934B (en) Unmanned aerial vehicle cruise control method and device based on fabricated building platform
US20210349476A1 (en) Method and apparatus for controlling cruise of unmanned air vehicle based on prefabricated construction platform
CN109409840A (en) A kind of Highway Project management system and method combined based on BIM with WBS
CN107862153A (en) A kind of transformer station digitizes managing and control system
CN111241618A (en) Intelligent construction site information processing method and system based on BIM model and application
CN111125236B (en) Three-dimensional dynamic information physical system based on GIS
CN109710696A (en) The System and method for the mobile operation of unusual fluctuation is verified for power equipment
CN114326517B (en) Remote management method and system based on virtual reality
CN104392311A (en) Intelligent production scheduling method based on state driving
CN111369150A (en) Intelligent management system for engineering construction projects
CN107422710A (en) The method and system of assembling product or plant maintenance are aided in based on AR
Wohlfeld et al. Digital Shadow–From production to product
CN106547943A (en) A kind of assembling progress monitoring method and device based on threedimensional model
CN115049306A (en) Overall process engineering consultation management system
CN115511322A (en) Intelligent construction site and intelligent construction management system
KR20160069008A (en) Project management system based information and communication technology
CN109471913B (en) Road network management and maintenance information system based on BIM

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant