CN108977647A - 锅炉受热面销钉焊后热处理专用工装及热处理方法 - Google Patents

锅炉受热面销钉焊后热处理专用工装及热处理方法 Download PDF

Info

Publication number
CN108977647A
CN108977647A CN201811129249.7A CN201811129249A CN108977647A CN 108977647 A CN108977647 A CN 108977647A CN 201811129249 A CN201811129249 A CN 201811129249A CN 108977647 A CN108977647 A CN 108977647A
Authority
CN
China
Prior art keywords
heat treatment
heating surface
pin
bracket
heater
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811129249.7A
Other languages
English (en)
Other versions
CN108977647B (zh
Inventor
张立祥
史小猛
庞继勇
李孟良
赵华
陈瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEPCO Electric Power Construction Co Ltd
Original Assignee
SEPCO Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SEPCO Electric Power Construction Co Ltd filed Critical SEPCO Electric Power Construction Co Ltd
Priority to CN201811129249.7A priority Critical patent/CN108977647B/zh
Priority to PCT/CN2018/112034 priority patent/WO2020062382A1/zh
Publication of CN108977647A publication Critical patent/CN108977647A/zh
Application granted granted Critical
Publication of CN108977647B publication Critical patent/CN108977647B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D9/00Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor
    • C21D9/50Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor for welded joints
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D1/00General methods or devices for heat treatment, e.g. annealing, hardening, quenching or tempering
    • C21D1/34Methods of heating
    • C21D1/40Direct resistance heating
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/25Process efficiency

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Crystallography & Structural Chemistry (AREA)
  • Mechanical Engineering (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Heat Treatment Of Articles (AREA)
  • Thermotherapy And Cooling Therapy Devices (AREA)

Abstract

本发明涉及焊接处理技术,具体是锅炉受热面销钉焊后热处理专用工装及热处理方法。该工装包括两个履带式的加热器、至少一对铠装热电偶和用于放置加热器的至少两组支架;每对所述热电偶在受热面任意一个销钉根部呈上下对称布置,所述热电偶通过铁丝与销钉根部连接,所述铁丝缠绕在两个销钉根部上;两个所述加热器分别放置在待处理受热面的上下两侧。热处理方法采用电加热方式,比火焰加热更加均匀、升降温速率和恒温温度处于受控状态,便于跟踪热处理状态。

Description

锅炉受热面销钉焊后热处理专用工装及热处理方法
技术领域
本发明涉及焊接处理技术,具体是一种循环流化床锅炉受热面销钉焊后热处理专用工装及方法。
背景技术
在火力发电厂建设中,流化床锅炉的中温过热器、高温过热器及高温再热器管子为SA213-T91、销钉材质为12Cr18Ni9,地面组合进行销钉焊接后需进行热处理。锅炉受热面销钉焊接后热处理时,目前常采用局部支撑或夹具固定的方式固定加热器,容易受重力、通电热胀因素下坠,无法与受热面销钉贴合紧密;在超宽受热面上进行局部热处理采用夹具装置固定加热器的操作难度较大。经常因操作 困难、固定效果不强造成热处理加热器脱落、温度测量不准等问题。
现有技术中主要是针对热处理前的螺柱焊的研究,然而SA-213T91与12Cr18Ni9销钉焊接时,SA-213T91钢材对线能量比较敏感,淬硬性大,裂纹倾向大。销钉焊接线能量过大会容易发生裂纹,因此销钉焊接完毕后需要进行热处理。目前国内外在销钉焊接热处理工艺研究方面基本属于空白。现有的技术方案:销钉焊接完毕后,使用火焰加热至300℃-400℃ 半小时后使用保温棉进行缓冷。使用火焰加热其升降温速度无法控制、热处理温度不均匀、处于外部环境中恒温效果不佳,并且受人为因素影响,热处理工艺不满足ASME标准对于91材质焊接必须要进行热处理的工艺要求,易产生裂纹,同时因热处理加热不均产生变形或母材损伤。
发明内容
为了解决上述问题,本发明提供了一种循环流化床锅炉受热面销钉焊后热处理专用工装以及热处理方法,本发明采用的技术方案如下:
锅炉受热面销钉焊后热处理专用工装,包括两个履带式的加热器、至少一对铠装热电偶和用于放置加热器的至少两组支架;
每对所述热电偶在受热面任意一个销钉根部呈上下对称布置,所述热电偶通过铁丝与销钉根部连接,所述铁丝缠绕在两个销钉根部上;两个所述加热器分别放置在待处理受热面的上下两侧;
所述支架包括水平设置的托架和两个分别竖直连接在托架前后两侧的支腿,所述支腿包括水平的支撑用底座、连杆、两个调整螺栓和与托架螺接的连接梁,两个所述调整螺栓对称螺接在连杆的上下两端,下方的调整螺栓与底座连接。
上述锅炉受热面销钉焊后热处理专用工装,所述托架为框架结构,所述加热器规格选用10KW,所述加热器的外部设有保温棉,所述加热器与热处理工频机连接以加热。
一种使用上述专用工装对锅炉受热面销钉焊后的热处理方法,包括如下步骤:
S1选用两对铠装热电偶,每对铠装热电偶的两个接线端分别用铁丝固定呈上下对称布置于销钉根部;
S2在受热面的上下面均铺设加热器以包覆住受热面销钉,用保温棉包覆住加热器后放置在支架上;
S3将铠装热电偶通过测温线、加热器通过导线分别连接至热处理工频机,在热处理工频机上输入热处理工艺参数,先以105~120℃/h的速度升温,在730~760℃范围内保温至少一小时,然后以130~150℃/h的速度降温至300℃后,关闭热处理工频机。
本发明的有益效果为:
本工装采用模块化设置,可根据需要将多组装置组装为一体,满足施工中热处理长度不同的情况,本工装易制作、牢固可靠、造价低、便于搬运等优势。
用电加热方式进行热处理,比火焰加热更加均匀、升降温速率和恒温温度处于受控状态,便于跟踪热处理状态。履带式加热器可 进行局部热处理,可区域化处理,提升工作效率。热处理工频机控制热处理工艺参数,降低人为因素的影响,使热处理过程满足工艺要求。该热处理方法提升了质量,优化了质量控制措施,一次成优,有利于节约施工成本。
附图说明
图1为本发明实施例支架的立体示意图;
图2为本发明实施例支架的主视示意图;
图3为本发明实施例支架的俯视示意图;
图4为本发明实施例的热处理状态主视示意图;
图5为本发明实施例的热电偶安装示意图;
图6为本发明实施例的热电偶安装位置截面示意图;
图7为本发明实施例的热电偶安装点放大示意图;
图8为本发明实施例的加热器安装示意图图;
图9为本发明实施例的热处理工艺参数图。
图中:1为支腿、11为底座、12为连杆、13为调整螺栓、14为连接梁、2为托架、3为保温棉、4为加热器、5为受热面、6为销钉、7为铠装热电偶、8为铁丝、9为鳍片。
具体实施方式
下面结合附图对本发明进一步解释说明。
本实施例锅炉受热面销钉焊后热处理专用工装,包括两个履带式的加热器4、两对对铠装热电偶7和用于放置加热器4的三组支架;结合图5和图6,受热面5上下均焊接有数个销钉,相邻受热面5之间通过鳍片9连接。
结合图7,每对所述热电偶7在受热面任意一个销钉根部呈上下对称布置,所述热电偶7通过铁丝8与销钉根部连接,所述铁丝8缠绕在两个销钉根部上;两个所述加热器4分别放置在待处理受热面的上下两侧;
所述支架包括水平设置的托架2和两个分别竖直连接在托架2前后两侧的支腿1,所述支腿1包括水平的支撑用底座11、连杆12、两个调整螺栓13和与托架2螺接的连接梁14,两个所述调整螺栓13对称螺接在连杆12的上下两端,下方的调整螺栓13与底座11连接。
所述托架2为框架结构,所述加热器4规格选用10KW,所述加热器4的外部设有保温棉3,所述加热器4与热处理工频机连接以加热。
实施例一
使用上述专用工装对锅炉受热面销钉焊后的热处理方法,包括如下步骤:
S1选用两对铠装热电偶7,每对铠装热电偶7的两个接线端分别用铁丝8固定呈上下对称布置于销钉根部;
S2在受热面的上下面均铺设加热器4以包覆住受热面销钉,用保温棉3包覆住加热器4后放置在支架上;
S3将铠装热电偶7通过测温线、加热器4通过导线分别连接至热处理工频机,在热处理工频机上输入热处理工艺参数,先以110℃/h的速度升温,在750℃保温1~2小时,然后以140℃/h的速度降温至300℃后,关闭热处理工频机。
实施例二
本实施例与上述实施例一的区别在于热处理工艺参数:先以120℃/h的速度升温,在760℃保温1.5小时,然后以150℃/h的速度降温至300℃后,关闭热处理工频机。
实施例三
本实施例与上述实施例一的区别在于热处理工艺参数:先以105℃/h的速度升温,在730℃保温3小时,然后以130℃/h的速度降温至300℃后,关闭热处理工频机。

Claims (3)

1.锅炉受热面销钉焊后热处理专用工装,其特征在于:包括两个履带式的加热器(4)、至少一对铠装热电偶(7)和用于放置加热器(4)的至少两组支架;
每对所述热电偶(7)在受热面任意一个销钉根部呈上下对称布置,所述热电偶(7)通过铁丝(8)与销钉根部连接,所述铁丝(8)缠绕在两个销钉根部上;两个所述加热器(4)分别放置在待处理受热面的上下两侧;
所述支架包括水平设置的托架(2)和两个分别竖直连接在托架(2)前后两侧的支腿(1),所述支腿(1)包括水平的支撑用底座(11)、连杆(12)、两个调整螺栓(13)和与托架(2)螺接的连接梁(14),两个所述调整螺栓(13)对称螺接在连杆(12)的上下两端,下方的调整螺栓(13)与底座(11)连接。
2.根据权利要求1所述的锅炉受热面销钉焊后热处理专用工装,其特征在于:所述托架(2)为框架结构,所述加热器(4)规格选用10KW,所述加热器(4)的外部设有保温棉(3),所述加热器(4)与热处理工频机连接以加热。
3.一种使用权利要求2所述专用工装对锅炉受热面销钉焊后的热处理方法,其特征在于,包括如下步骤:
S1选用两对铠装热电偶(7),每对铠装热电偶(7)的两个接线端分别用铁丝(8)固定呈上下对称布置于销钉根部;
S2在受热面的上下面均铺设加热器(4)以包覆住受热面销钉,用保温棉(3)包覆住加热器(4)后放置在支架上;
S3将铠装热电偶(7)通过测温线、加热器(4)通过导线分别连接至热处理工频机,在热处理工频机上输入热处理工艺参数,先以105~120℃/h的速度升温,在730~760℃范围内保温至少一小时,然后以130~150℃/h的速度降温至300℃后,关闭热处理工频机。
CN201811129249.7A 2018-09-27 2018-09-27 锅炉受热面销钉焊后热处理专用工装及热处理方法 Active CN108977647B (zh)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201811129249.7A CN108977647B (zh) 2018-09-27 2018-09-27 锅炉受热面销钉焊后热处理专用工装及热处理方法
PCT/CN2018/112034 WO2020062382A1 (zh) 2018-09-27 2018-10-26 锅炉受热面销钉焊后热处理专用工装及热处理方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811129249.7A CN108977647B (zh) 2018-09-27 2018-09-27 锅炉受热面销钉焊后热处理专用工装及热处理方法

Publications (2)

Publication Number Publication Date
CN108977647A true CN108977647A (zh) 2018-12-11
CN108977647B CN108977647B (zh) 2023-09-22

Family

ID=64543050

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811129249.7A Active CN108977647B (zh) 2018-09-27 2018-09-27 锅炉受热面销钉焊后热处理专用工装及热处理方法

Country Status (2)

Country Link
CN (1) CN108977647B (zh)
WO (1) WO2020062382A1 (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110132437A (zh) * 2019-06-20 2019-08-16 福建晋江热电有限公司 一种串接入履带式加热器中的热电偶安装块
CN110146187A (zh) * 2019-06-20 2019-08-20 福建晋江热电有限公司 一种串接入履带式加热器中的热电偶安装块
CN110157885A (zh) * 2019-06-20 2019-08-23 福建晋江热电有限公司 一种履带式加热器
CN110699519A (zh) * 2019-11-28 2020-01-17 中国电建集团山东电力建设第一工程有限公司 一种中小径异形管件热处理加热器

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU1899276A (en) * 1975-10-30 1978-05-04 Thompsons Byron Jackson Method of treating the heat affected zone adjacent to a weld
JP2001262235A (ja) * 2000-03-14 2001-09-26 Hitachi Ltd 配管・容器局部熱処理装置
JP2003155522A (ja) * 2001-11-15 2003-05-30 Kobe Steel Ltd 金属ビレットの連続加熱法
JP2004211187A (ja) * 2003-01-08 2004-07-29 Hitachi Ltd 配管系の熱処理方法および熱処理装置
CN101265515A (zh) * 2007-12-26 2008-09-17 上海电气电站设备有限公司 汽轮机转子局部去应力热处理方法
JP2009092301A (ja) * 2007-10-05 2009-04-30 Ngk Insulators Ltd 熱処理炉
CN203625440U (zh) * 2013-11-07 2014-06-04 吴江荣峰电热电器有限公司 一种压力容器热处理非标电加热工装
CN104032119A (zh) * 2014-06-18 2014-09-10 山东电力建设第一工程公司 锅炉受热面管排伸缩式热处理夹具
CN105671297A (zh) * 2014-11-19 2016-06-15 重庆尚科机械制造有限公司 一种大型管子的焊后热处理工艺
CN105986109A (zh) * 2015-01-30 2016-10-05 重庆广鼎道路设施有限公司 一种焊接后热处理工艺
RU166498U1 (ru) * 2016-03-22 2016-11-27 Акционерное общество "Инжиниринговая компания "АЭМ-технологии" (АО "АЭМ-технологии") Установка для местной термической обработки сварных соединений серийных крупногабаритных изделий
GB201621951D0 (en) * 2016-12-22 2017-02-08 Rolls Royce Plc Method of heat treatment
CN207239539U (zh) * 2017-08-28 2018-04-17 中国电建集团山东电力建设第一工程有限公司 一种镀铜圆钢接地焊接专用固定装置
CN207862412U (zh) * 2017-12-15 2018-09-14 山东鲁能光大钢结构有限公司 焊后热处理支撑工具及焊后热处理支撑装置
CN208883944U (zh) * 2018-09-27 2019-05-21 中国电建集团山东电力建设第一工程有限公司 锅炉受热面销钉焊后热处理专用工装

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1015644B (zh) * 1990-11-03 1992-02-26 机械电子工业部哈尔滨焊接研究所 摩擦焊焊接接头形变热处理的方法及装置
AT6941U3 (de) * 2004-02-23 2005-03-25 Plasser Bahnbaumasch Franz Schweissaggregat zur verschweissung von zwei schienen eines gleises und verfahren
RU2661199C2 (ru) * 2014-04-08 2018-07-16 Ниппон Стил Энд Сумитомо Метал Корпорейшн Устройство для термической обработки, способ термической обработки и рельсовая сталь
CN105695715B (zh) * 2016-03-30 2017-08-11 江苏界达特异新材料股份有限公司 大口径薄壁管的热处理防变形装置及其工艺方法

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU1899276A (en) * 1975-10-30 1978-05-04 Thompsons Byron Jackson Method of treating the heat affected zone adjacent to a weld
JP2001262235A (ja) * 2000-03-14 2001-09-26 Hitachi Ltd 配管・容器局部熱処理装置
JP2003155522A (ja) * 2001-11-15 2003-05-30 Kobe Steel Ltd 金属ビレットの連続加熱法
JP2004211187A (ja) * 2003-01-08 2004-07-29 Hitachi Ltd 配管系の熱処理方法および熱処理装置
JP2009092301A (ja) * 2007-10-05 2009-04-30 Ngk Insulators Ltd 熱処理炉
CN101265515A (zh) * 2007-12-26 2008-09-17 上海电气电站设备有限公司 汽轮机转子局部去应力热处理方法
CN203625440U (zh) * 2013-11-07 2014-06-04 吴江荣峰电热电器有限公司 一种压力容器热处理非标电加热工装
CN104032119A (zh) * 2014-06-18 2014-09-10 山东电力建设第一工程公司 锅炉受热面管排伸缩式热处理夹具
CN105671297A (zh) * 2014-11-19 2016-06-15 重庆尚科机械制造有限公司 一种大型管子的焊后热处理工艺
CN105986109A (zh) * 2015-01-30 2016-10-05 重庆广鼎道路设施有限公司 一种焊接后热处理工艺
RU166498U1 (ru) * 2016-03-22 2016-11-27 Акционерное общество "Инжиниринговая компания "АЭМ-технологии" (АО "АЭМ-технологии") Установка для местной термической обработки сварных соединений серийных крупногабаритных изделий
GB201621951D0 (en) * 2016-12-22 2017-02-08 Rolls Royce Plc Method of heat treatment
CN207239539U (zh) * 2017-08-28 2018-04-17 中国电建集团山东电力建设第一工程有限公司 一种镀铜圆钢接地焊接专用固定装置
CN207862412U (zh) * 2017-12-15 2018-09-14 山东鲁能光大钢结构有限公司 焊后热处理支撑工具及焊后热处理支撑装置
CN208883944U (zh) * 2018-09-27 2019-05-21 中国电建集团山东电力建设第一工程有限公司 锅炉受热面销钉焊后热处理专用工装

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110132437A (zh) * 2019-06-20 2019-08-16 福建晋江热电有限公司 一种串接入履带式加热器中的热电偶安装块
CN110146187A (zh) * 2019-06-20 2019-08-20 福建晋江热电有限公司 一种串接入履带式加热器中的热电偶安装块
CN110157885A (zh) * 2019-06-20 2019-08-23 福建晋江热电有限公司 一种履带式加热器
CN110157885B (zh) * 2019-06-20 2023-07-04 福建晋江热电有限公司 一种履带式加热器
CN110132437B (zh) * 2019-06-20 2024-05-24 福建晋江热电有限公司 一种串接入履带式加热器中的热电偶安装块
CN110146187B (zh) * 2019-06-20 2024-05-24 福建晋江热电有限公司 一种串接入履带式加热器中的热电偶安装块
CN110699519A (zh) * 2019-11-28 2020-01-17 中国电建集团山东电力建设第一工程有限公司 一种中小径异形管件热处理加热器

Also Published As

Publication number Publication date
WO2020062382A1 (zh) 2020-04-02
CN108977647B (zh) 2023-09-22

Similar Documents

Publication Publication Date Title
CN108977647A (zh) 锅炉受热面销钉焊后热处理专用工装及热处理方法
CN105200224A (zh) 一种调质材料制超大型容器的局部焊后热处理方法
CN102605158A (zh) 现场工况厚壁p92管道局部热处理方法
CN110373525A (zh) 一种大型压力容器局部热处理过程优化及自动控温方法
CN104404216A (zh) 用于焊接筒体的局部热处理工艺
CN208883944U (zh) 锅炉受热面销钉焊后热处理专用工装
CN109880993A (zh) 不等厚度接头局部焊后热处理温度场调控的装置和方法
CN104789749B (zh) 一种用于管屏焊缝热处理的方法
CN106862753A (zh) 一种能降低搅拌摩擦焊接板材残余应力的方法及装置
CN107828958A (zh) 焊后热处理支撑工具及焊后热处理支撑装置
CN205085564U (zh) 一体式动态感应焊接预热装置
CN204209247U (zh) 精确控温加热平台
CN105424746A (zh) 电站锅炉水冷壁管传热特性的监测系统与监测方法
CN206169161U (zh) 一种炉温自动调节系统的锻造加热炉
CN104844248A (zh) 半导体致冷件焊接机
CN104289782A (zh) 一种转子焊接工艺
CN207862412U (zh) 焊后热处理支撑工具及焊后热处理支撑装置
CN204589010U (zh) 半导体致冷件焊接机
CN201235452Y (zh) 用于焊接大型钢构件的焊接保温炉
CN206348681U (zh) 温度控制系统
CN206077717U (zh) 大型钢制容器可移动式电磁感应加热系统及加热装置
CN210856260U (zh) 一种密排管道焊接接头非接触式热处理装置
CN213086050U (zh) 一种高温受热面焊口及鳍片焊缝焊后热处理装置
CN208713255U (zh) 一种钢结构的焊接装置
CN106440366A (zh) 一种热效率高的电加热器

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant