CN108952733A - Separate launching shield technique application construction method in municipal sewerage engineering - Google Patents

Separate launching shield technique application construction method in municipal sewerage engineering Download PDF

Info

Publication number
CN108952733A
CN108952733A CN201710348004.2A CN201710348004A CN108952733A CN 108952733 A CN108952733 A CN 108952733A CN 201710348004 A CN201710348004 A CN 201710348004A CN 108952733 A CN108952733 A CN 108952733A
Authority
CN
China
Prior art keywords
shield
shield machine
soil
foam
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710348004.2A
Other languages
Chinese (zh)
Inventor
张涛
杨成夫
孟凡宁
赵洋帆
刘长军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Political Foundation Engineering Co Ltd
Shenyang Municipal Group Co Ltd
Original Assignee
Shenyang Political Foundation Engineering Co Ltd
Shenyang Municipal Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Political Foundation Engineering Co Ltd, Shenyang Municipal Group Co Ltd filed Critical Shenyang Political Foundation Engineering Co Ltd
Priority to CN201710348004.2A priority Critical patent/CN108952733A/en
Publication of CN108952733A publication Critical patent/CN108952733A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to technical field of civil engineering, are suitable for city internal drainage pipeline Project Shield and construct, especially narrow on construction ground, can not disposably install the engineering of whole Suporting structures.Separate launching shield technique application construction method step in municipal sewerage engineering includes: starting well arrangement, facility arrangement in starting well, shield machine examination is hung, shield machine lifting is gone into the well, the installation of hole soil stabilization, hole rubber cord, hole bored concrete pile are cut, the preparation of delivery arrangement, shield launching, initial tunneling construction, shield trolley originate.Separate launching shield technique application construction method in municipal sewerage engineering provided by the invention can effectively reduce the size for originating vertical shaft using shield machine separate launching technology, reduce engineering cost, while can also reduce the influence to surrounding enviroment to greatest extent.

Description

Separate launching shield technique application construction method in municipal sewerage engineering
Technical field
The present invention relates to technical field of civil engineering, are specifically related to separate launching shield technique in municipal sewerage engineering Application construction method is suitable for city internal drainage pipeline Project Shield and constructs, especially narrow on construction ground, can not be disposable The engineering of whole shield driving equipment is installed.
Background technique
With the variation of weather in recent years, Severe rainstorm weather often occurs, and urban waterlogging phenomenon aggravates, especially old city Area's inner water drainage system is unable to satisfy draining needs already.The continuous increase of newly-built drainage pipeline caliber, traditional handicraft can not expire The existing engineering construction requirement of foot.Since shield technique is applied widely, construction caliber it is big the advantages that, gradually be applied to drainage system In.
The technical requirements of each construction link of shield technique are relatively high, and especially shield launching link is that shield is applied A key link in work.In subway work, shield launching is shield launching is aimed at using station or build perpendicular It is carried out in well.But municipal sewerage engineering is often in city, and the place that can be used in large-area construction land used is few, and considers The occupied area of economic factor, starting well is relatively small, prevents shield machine from routinely integrally originating, it is necessary to be begun using seperated Hair.
I has carried out separate launching technical research and application in construction early period and construction at unit, it is established that a whole set of is perfect Construction technology and core technology, through summarize form the present invention, achieve good effect in practical applications.
Summary of the invention
In view of the above drawbacks of the prior art, separate launching shield technique provided by the invention is answered in municipal sewerage engineering The size for originating vertical shaft can be effectively reduced using shield machine separate launching technology with construction method, reduce engineering cost, simultaneously The influence to surrounding enviroment can also be reduced to greatest extent.
In order to achieve the above object, the invention provides the following technical scheme:
Separate launching shield technique application construction method in municipal sewerage engineering, step include:
1), starting well is arranged:
Shield machine length is 10m, and 1#-14# trolley need to be placed on ground, shield having a size of 16m*8m by launching shaft Machine can just originate in short vertical shaft;
2), facility is arranged in starting well:
(1), shield reaction frame: using diagonal brace reaction shelf of door type, and material is the 20 of Q235#H profile steel welding composition, reaction frame are prefabricated After forming, axial location and elevation are provided by survey crew, vertical shaft is hung in by crane, and carry out installation reinforcing, after the installation is completed The verticality of reaction frame is detected, guarantee that reaction frame is vertical with shield driving axis;
(2), shield machine pedestal is installed: shield machine pedestal is girder made of being welded as fashioned iron, and the above is two rail, as Guide rail when shield machine is appeared;Shield machine pedestal will be welded with the embedded iron on starting well bottom plate, and with fashioned iron and the borehole wall Top jail;When shield machine pedestal elevation is installed, it is to be ensured that it is 15mm higher than design altitude after shield machine is in place, at the beginning of adjusting shield machine Begin the posture tunneled;
3), shield machine examination is hung:
Shield machine is sling into liftoff 0.2m, is hovered 5 minutes, checks that confirmation shield machine, hoist cable, supporting surface, crane, foundation pit side-wall are equal It is intact it is without exception after, and held with cable wind rope and hung shield machine held stationary, lifting can be commanded to run;
4), shield machine lifting is gone into the well:
Shield machine diameter 4.13m, long 10.5m, weight 110t use 350t crane when lifting, and shield machine center be in crane 8m and makees In industry radius;Shield machine both ends are fastened with traction rope, and shield machine keeps horizontal after lifting, and crane makes shield by rotation, luffing After machine reaches well head, slow off the hook;After shield machine and base into contact, constantly amendment, adjustment attitude of shield machine, it is ensured that shield master Machine transfers designated position;After shield machine is stablized, U-shaped card ring is removed, shield machine lifting finishes;
5), hole soil stabilization:
It in order to guarantee the stabilization of hole surrounding soil, is reinforced using rotary churning pile form, rotary churning pile spacing are as follows: outside pumping plant portal 550@400 are used in 3 meters, remaining is 550@600;
Reinforcing scope are as follows:
Starting well: 8m on the outside of bored concrete pile, pipe centerline each 4m up and down;
Received well: 12m on the outside of received well, pipe centerline each 4m up and down;
6), rubber cord in hole is installed:
Rubber cord is hung on the pre-buried steel loop in hole with bolt, and is fixed with arc keeper plate of steel, then again in arc-shaped steel pressure Prefabricated foldable fan-shaped steel plate is installed outside plate;When cutter head of shield machine enters hole, adjustment fanning strip to shield machine shell Distance be 10mm or so, rubber curtain and fan type steel plate are headed into and are curved inwardly by the shell of shield machine, when shield machine shield tail steel When wire brush has just enter into hole exposing section of jurisdiction, then fanning strip is adjusted, falls in it on section of jurisdiction, rubber is removed after the completion of initially tunneling Cord;
7), hole bored concrete pile is cut:
7 days progress portal bored concrete piles are cut before originating, and using pneumatic pick according to from bottom to top, are carried out from both sides toward intermediate sequence Manually cut;
8), delivery arrangement:
(1), earthwork transportation
After battery truck delivery soil bucket to soil outlet, soil bucket is put upside down to collection heatable adobe sleeping platform, dregs transportation vehicle collective conveyance by 100t crane To spoil ground;
(2), section of jurisdiction is transported
Precast concrete section of jurisdiction is transported to behind construction site and first deposits in live section of jurisdiction storage pad, and when use is put with crane handling to electricity On the flat car of bottle vehicle traction, and it is transported into pipeline;
(3), other goods transportations
The big part material of rail, sleeper is put with crane to fixation on flat car, is transported into pipeline within the pipe sheet assembling time;Even It connects pressing plate, clamping plate and the bolt of rail and the arch screw bolt of pipeline driving, Seal Oil, lubricating oil smallclothes auxiliary material is used After special implement installs, put by crane to being transported into pipeline in battery truck;
9), shield launching prepares:
Pipeline and cable link to shield machine shield body by active well, guarantee shield machine just using connection, all pipelines are extended Often work;
10), initial tunneling construction:
(1), negative ring pipe sheet assembling
Before negative ring pipe sheet assembling, should in tail sealing brush fill plug seal grease, after the negative endless tube piece of the first ring is assembled into, use 4~5 groups of jack complete moving back for section of jurisdiction;
(2), shield driving parameter setting
1., driving speed
According to the driving speed of shield machine, geological state, duration schedule requirement factor, and previous shield-tunneling construction experience is referred to, just Beginning section driving speed primarily determines as 15~50mm/min;
2., in soil pressure storehouse plus foam, mud
Mud additional amount: part of path penetrating ground predominantly circle gravel, gravel layer adds mud amount to tunnel according to past construction experiences Every ring cutting cuts 6~10% calculating of soil body volume, and the mud injection rate for tunneling every ring is 1m3~1.5m3
Add mud pressure: the soil pressure in the general a little higher than native storehouse of the injection pressure of mud, mud injection pressure takes 0.15~ 0.25MPa;
Foam additional amount: the composition ratio of foam is as follows: the composition of foam solution: additive foam 5%~7%, water 93%~95%; Foam composition: it is mixed by 90~95% compressed airs and 5%~10% foam solution;Foam additional amount is cut with tunneling every ring cutting The 1.25%~1.88% of soil body volume calculates, and the every ring of Shield Construction Method Used need to add the amount of foam solution to be 0.2m3~0.3m;
Add foam pressure: the soil pressure in the general a little higher than native storehouse of injection pressure, foam injection pressure is set as 0.28~ 0.37MPa;
3., grouting at the tail of the shield machine pressure and grouting amount
Grouting pressure: injection pressure size is ordinarily selected to the sum that stratum soil pressure adds 0.1~0.2MPa, according to this bid section Stratum soil property condition grouting pressure is tentatively set to 0.25MPa;
Grouting amount: grouting amount should be controlled 107%~128%;Secondary after-teeming slurry should find not to be filled up completely according to the measurement on ground Position carry out second pulp feeding construction in time, dosage is determined according to actual conditions;
11), shield trolley originates:
After the completion of originating driving, the lengthening pipeline between shield machine and 1# trolley is removed, negative ring, reaction frame and shield are removed Originate pedestal;Again it sets up track connecting bridge, belt conveyor, 1#~14# trolley are transformed into tunnel, adjustment track is high Degree, carries out the driving of normal phase.
The beneficial effects of the present invention are:
1, the present invention uses shield machine separate launching technology, and large shield machine segmental hoisting is entered and originates vertical shaft, can effectively be subtracted The small size for originating vertical shaft;
2, the present invention can save the Suporting structure set-up time, be rapidly completed and originate stage driving, reduce shield launching hole branch Protection structure exposure duration reduces risk;
3, for the present invention by the equipment separate launching such as shield body and subsequent trolley, construction method is flexible, and it is convenient to operate, and effectively reduces and applies Work cost and operation difficulty.
For further understanding of the features and technical contents of the present invention, it please refers to below in connection with of the invention detailed Illustrate and attached drawing, however, the drawings only provide reference and explanation, is not intended to limit the present invention.
Detailed description of the invention
With reference to the accompanying drawing, by the way that detailed description of specific embodiments of the present invention, technical solution of the present invention will be made And other beneficial effects are apparent.
Fig. 1 is the flow chart of separate launching shield technique application construction method in municipal sewerage engineering of the present invention.
Specific embodiment
Further to illustrate technological means and its effect adopted by the present invention, below in conjunction with preferred implementation of the invention Example and its attached drawing are described in detail.
Separate launching shield technique application construction method in municipal sewerage engineering, step include:
1), starting well is arranged:
Shield machine length is 10m, and 1#-14# trolley need to be placed on ground, shield having a size of 16m*8m by launching shaft Machine can just originate in short vertical shaft;
2), facility is arranged in starting well:
(1), shield reaction frame: using diagonal brace reaction shelf of door type, and material is the 20 of Q235#H profile steel welding composition, reaction frame are prefabricated After forming, axial location and elevation are provided by survey crew, vertical shaft is hung in by crane, and carry out installation reinforcing, after the installation is completed The verticality of reaction frame is detected, guarantee that reaction frame is vertical with shield driving axis;
(2), shield machine pedestal is installed: shield machine pedestal is girder made of being welded as fashioned iron, and the above is two rail, as Guide rail when shield machine is appeared;Shield machine pedestal will be welded with the embedded iron on starting well bottom plate, and with fashioned iron and the borehole wall Top jail;When shield machine pedestal elevation is installed, it is to be ensured that it is 15mm higher than design altitude after shield machine is in place, at the beginning of adjusting shield machine Begin the posture tunneled;
3), shield machine examination is hung:
Shield machine is sling into liftoff 0.2m, is hovered 5 minutes, checks that confirmation shield machine, hoist cable, supporting surface, crane, foundation pit side-wall are equal It is intact it is without exception after, and held with cable wind rope and hung shield machine held stationary, lifting can be commanded to run;
4), shield machine lifting is gone into the well:
Shield machine diameter 4.13m, long 10.5m, weight 110t use 350t crane when lifting, and shield machine center be in crane 8m and makees In industry radius;Shield machine both ends are fastened with traction rope, and shield machine keeps horizontal after lifting, and crane makes shield by rotation, luffing After machine reaches well head, slow off the hook;After shield machine and base into contact, constantly amendment, adjustment attitude of shield machine, it is ensured that shield master Machine transfers designated position;After shield machine is stablized, U-shaped card ring is removed, shield machine lifting finishes;
5), hole soil stabilization:
It in order to guarantee the stabilization of hole surrounding soil, is reinforced using rotary churning pile form, rotary churning pile spacing are as follows: outside pumping plant portal 550@400 are used in 3 meters, remaining is 550@600;
Reinforcing scope are as follows:
Starting well: 8m on the outside of bored concrete pile, pipe centerline each 4m up and down;
Received well: 12m on the outside of received well, pipe centerline each 4m up and down;
6), rubber cord in hole is installed:
Rubber cord is hung on the pre-buried steel loop in hole with bolt, and is fixed with arc keeper plate of steel, then again in arc-shaped steel pressure Prefabricated foldable fan-shaped steel plate is installed outside plate;When cutter head of shield machine enters hole, adjustment fanning strip to shield machine shell Distance be 10mm or so, rubber curtain and fan type steel plate are headed into and are curved inwardly by the shell of shield machine, when shield machine shield tail steel When wire brush has just enter into hole exposing section of jurisdiction, then fanning strip is adjusted, falls in it on section of jurisdiction, rubber is removed after the completion of initially tunneling Cord;
7), hole bored concrete pile is cut:
7 days progress portal bored concrete piles are cut before originating, and using pneumatic pick according to from bottom to top, are carried out from both sides toward intermediate sequence Manually cut;
8), delivery arrangement:
(1), earthwork transportation
After battery truck delivery soil bucket to soil outlet, soil bucket is put upside down to collection heatable adobe sleeping platform, dregs transportation vehicle collective conveyance by 100t crane To spoil ground;
(2), section of jurisdiction is transported
Precast concrete section of jurisdiction is transported to behind construction site and first deposits in live section of jurisdiction storage pad, and when use is put with crane handling to electricity On the flat car of bottle vehicle traction, and it is transported into pipeline;
(3), other goods transportations
The big part material of rail, sleeper is put with crane to fixation on flat car, is transported into pipeline within the pipe sheet assembling time;Even It connects pressing plate, clamping plate and the bolt of rail and the arch screw bolt of pipeline driving, Seal Oil, lubricating oil smallclothes auxiliary material is used After special implement installs, put by crane to being transported into pipeline in battery truck;
9), shield launching prepares:
Pipeline and cable link to shield machine shield body by active well, guarantee shield machine just using connection, all pipelines are extended Often work;
10), initial tunneling construction:
(1), negative ring pipe sheet assembling
Before negative ring pipe sheet assembling, should in tail sealing brush fill plug seal grease, after the negative endless tube piece of the first ring is assembled into, use 4~5 groups of jack complete moving back for section of jurisdiction;
(2), shield driving parameter setting
1., driving speed
According to the driving speed of shield machine, geological state, duration schedule requirement factor, and previous shield-tunneling construction experience is referred to, just Beginning section driving speed primarily determines as 15~50mm/min;
2., in soil pressure storehouse plus foam, mud
Mud additional amount: part of path penetrating ground predominantly circle gravel, gravel layer adds mud amount to tunnel according to past construction experiences Every ring cutting cuts 6~10% calculating of soil body volume, and the mud injection rate for tunneling every ring is 1m3~1.5m3
Add mud pressure: the soil pressure in the general a little higher than native storehouse of the injection pressure of mud, mud injection pressure takes 0.15~ 0.25MPa;
Foam additional amount: the composition ratio of foam is as follows: the composition of foam solution: additive foam 5%~7%, water 93%~95%; Foam composition: it is mixed by 90~95% compressed airs and 5%~10% foam solution;Foam additional amount is cut with tunneling every ring cutting The 1.25%~1.88% of soil body volume calculates, and the every ring of Shield Construction Method Used need to add the amount of foam solution to be 0.2m3~0.3m;
Add foam pressure: the soil pressure in the general a little higher than native storehouse of injection pressure, foam injection pressure is set as 0.28~ 0.37MPa;
3., grouting at the tail of the shield machine pressure and grouting amount
Grouting pressure: injection pressure size is ordinarily selected to the sum that stratum soil pressure adds 0.1~0.2MPa, according to this bid section Stratum soil property condition grouting pressure is tentatively set to 0.25MPa;
Grouting amount: grouting amount should be controlled 107%~128%;Secondary after-teeming slurry should find not to be filled up completely according to the measurement on ground Position carry out second pulp feeding construction in time, dosage is determined according to actual conditions;
11), shield trolley originates:
After the completion of originating driving, the lengthening pipeline between shield machine and 1# trolley is removed, negative ring, reaction frame and shield are removed Originate pedestal;Again it sets up track connecting bridge, belt conveyor, 1#~14# trolley are transformed into tunnel, adjustment track is high Degree, carries out the driving of normal phase.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain Lid is within protection scope of the present invention.Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (1)

1. separate launching shield technique application construction method in municipal sewerage engineering, which is characterized in that step includes:
1), starting well is arranged:
Shield machine length is 10m, and 1#-14# trolley need to be placed on ground, shield having a size of 16m*8m by launching shaft Machine can just originate in short vertical shaft;
2), facility is arranged in starting well:
(1), shield reaction frame: using diagonal brace reaction shelf of door type, and material is the 20 of Q235#H profile steel welding composition, reaction frame are prefabricated After forming, axial location and elevation are provided by survey crew, vertical shaft is hung in by crane, and carry out installation reinforcing, after the installation is completed The verticality of reaction frame is detected, guarantee that reaction frame is vertical with shield driving axis;
(2), shield machine pedestal is installed: shield machine pedestal is girder made of being welded as fashioned iron, and the above is two rail, as Guide rail when shield machine is appeared;Shield machine pedestal will be welded with the embedded iron on starting well bottom plate, and with fashioned iron and the borehole wall Top jail;When shield machine pedestal elevation is installed, it is to be ensured that it is 15mm higher than design altitude after shield machine is in place, at the beginning of adjusting shield machine Begin the posture tunneled;
3), shield machine examination is hung:
Shield machine is sling into liftoff 0.2m, is hovered 5 minutes, checks that confirmation shield machine, hoist cable, supporting surface, crane, foundation pit side-wall are equal It is intact it is without exception after, and held with cable wind rope and hung shield machine held stationary, lifting can be commanded to run;
4), shield machine lifting is gone into the well:
Shield machine center is in crane 8m operating radius;Shield machine both ends are fastened with traction rope, and shield machine keeps water after lifting It is flat, after crane makes shield machine reach well head by rotation, luffing, slow off the hook;After shield machine and base into contact, constantly repair Just, attitude of shield machine is adjusted, it is ensured that shield host transfers designated position;After shield machine is stablized, U-shaped card ring, shield machine are removed Rigging out;
5), hole soil stabilization:
It in order to guarantee the stabilization of hole surrounding soil, is reinforced using rotary churning pile form, rotary churning pile spacing are as follows: outside pumping plant portal 550@400 are used in 3 meters, remaining is 550@600;
Reinforcing scope are as follows:
Starting well: 8m on the outside of bored concrete pile, pipe centerline each 4m up and down;
Received well: 12m on the outside of received well, pipe centerline each 4m up and down;
6), rubber cord in hole is installed:
Rubber cord is hung on the pre-buried steel loop in hole with bolt, and is fixed with arc keeper plate of steel, then again in arc-shaped steel pressure Prefabricated foldable fan-shaped steel plate is installed outside plate;When cutter head of shield machine enters hole, adjustment fanning strip to shield machine shell Distance be 10mm or so, rubber curtain and fan type steel plate are headed into and are curved inwardly by the shell of shield machine, when shield machine shield tail steel When wire brush has just enter into hole exposing section of jurisdiction, then fanning strip is adjusted, falls in it on section of jurisdiction, rubber is removed after the completion of initially tunneling Cord;
7), hole bored concrete pile is cut:
7 days progress portal bored concrete piles are cut before originating, and using pneumatic pick according to from bottom to top, are carried out from both sides toward intermediate sequence Manually cut;
8), delivery arrangement:
(1), earthwork transportation
After battery truck delivery soil bucket to soil outlet, soil bucket is put upside down to collection heatable adobe sleeping platform, dregs transportation vehicle collective conveyance by 100t crane To spoil ground;
(2), section of jurisdiction is transported
Precast concrete section of jurisdiction is transported to behind construction site and first deposits in live section of jurisdiction storage pad, and when use is put with crane handling to electricity On the flat car of bottle vehicle traction, and it is transported into pipeline;
(3), other goods transportations
The big part material of rail, sleeper is put with crane to fixation on flat car, is transported into pipeline within the pipe sheet assembling time;Even It connects pressing plate, clamping plate and the bolt of rail and the arch screw bolt of pipeline driving, Seal Oil, lubricating oil smallclothes auxiliary material is used After special implement installs, put by crane to being transported into pipeline in battery truck;
9), shield launching prepares:
Pipeline and cable link to shield machine shield body by active well, guarantee shield machine just using connection, all pipelines are extended Often work;
10), initial tunneling construction:
(1), negative ring pipe sheet assembling
Before negative ring pipe sheet assembling, should in tail sealing brush fill plug seal grease, after the negative endless tube piece of the first ring is assembled into, use 4~5 groups of jack complete moving back for section of jurisdiction;
(2), shield driving parameter setting
1., driving speed
According to the driving speed of shield machine, geological state, duration schedule requirement factor, and previous shield-tunneling construction experience is referred to, just Beginning section driving speed primarily determines as 15~50mm/min;
2., in soil pressure storehouse plus foam, mud
Mud additional amount: part of path penetrating ground predominantly circle gravel, gravel layer adds mud amount to cut soil body volume to tunnel every ring cutting 6~10% calculate, and the mud injection rate for tunneling every ring is 1m3~1.5m3
Add mud pressure: the soil pressure in the general a little higher than native storehouse of the injection pressure of mud, mud injection pressure takes 0.15~ 0.25MPa;
Foam additional amount: the composition ratio of foam is as follows: the composition of foam solution: additive foam 5%~7%, water 93%~95%; Foam composition: it is mixed by 90~95% compressed airs and 5%~10% foam solution;Foam additional amount is cut with tunneling every ring cutting The 1.25%~1.88% of soil body volume calculates, and the every ring of Shield Construction Method Used need to add the amount of foam solution to be 0.2m3~0.3m;
Add foam pressure: the soil pressure in the general a little higher than native storehouse of injection pressure, foam injection pressure is set as 0.28~ 0.37MPa;
3., grouting at the tail of the shield machine pressure and grouting amount
Grouting pressure: injection pressure size is ordinarily selected to the sum that stratum soil pressure adds 0.1~0.2MPa, according to this bid section Stratum soil property condition grouting pressure is tentatively set to 0.25MPa;
Grouting amount: grouting amount should be controlled 107%~128%;Secondary after-teeming slurry should find not to be filled up completely according to the measurement on ground Position carry out second pulp feeding construction in time, dosage is determined according to actual conditions;
11), shield trolley originates:
After the completion of originating driving, the lengthening pipeline between shield machine and 1# trolley is removed, negative ring, reaction frame and shield are removed Originate pedestal;Again it sets up track connecting bridge, belt conveyor, 1#~14# trolley are transformed into tunnel, adjustment track is high Degree, carries out the driving of normal phase.
CN201710348004.2A 2017-05-17 2017-05-17 Separate launching shield technique application construction method in municipal sewerage engineering Pending CN108952733A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710348004.2A CN108952733A (en) 2017-05-17 2017-05-17 Separate launching shield technique application construction method in municipal sewerage engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710348004.2A CN108952733A (en) 2017-05-17 2017-05-17 Separate launching shield technique application construction method in municipal sewerage engineering

Publications (1)

Publication Number Publication Date
CN108952733A true CN108952733A (en) 2018-12-07

Family

ID=64461347

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710348004.2A Pending CN108952733A (en) 2017-05-17 2017-05-17 Separate launching shield technique application construction method in municipal sewerage engineering

Country Status (1)

Country Link
CN (1) CN108952733A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109695455A (en) * 2018-12-21 2019-04-30 中铁十二局集团有限公司 Method of reseptance in a kind of earth pressure balanced shield, EPBS pure water
CN109763827A (en) * 2019-03-29 2019-05-17 中山大学 A kind of vertical shaft shield construction method and vertical shaft shield machine
CN110185458A (en) * 2019-07-04 2019-08-30 中建五局土木工程有限公司 Two-way shield launching method
CN110924960A (en) * 2019-11-25 2020-03-27 中铁十六局集团北京轨道交通工程建设有限公司 Subway construction method for shield starting before constructing station structure
CN111058860A (en) * 2019-12-10 2020-04-24 中铁十四局集团隧道工程有限公司 Cave opening construction method
CN111140240A (en) * 2020-01-03 2020-05-12 中交一公局第三工程有限公司 Split starting construction method for large-diameter earth pressure balance shield curve of sandy cobble stratum
CN111173528A (en) * 2020-01-06 2020-05-19 中交一公局第三工程有限公司 Large-diameter long-interval tunnel shield construction method for water-rich sandy gravel stratum
CN111350523A (en) * 2020-03-27 2020-06-30 中建八局轨道交通建设有限公司 Construction method and device for dismantling negative ring in limited space
CN112081595A (en) * 2019-06-14 2020-12-15 宏润建设集团股份有限公司 Shield construction method, and waterproof and monitoring method for shield construction
CN113006808A (en) * 2021-04-23 2021-06-22 中铁六局集团有限公司交通工程分公司 Construction method for viscous geological shield initial section to penetrate shallow soil-covered river channel downwards
CN113236264A (en) * 2021-04-28 2021-08-10 中铁六局集团有限公司交通工程分公司 Split starting construction method for shield of small clearance, upper soft and lower hard stratum
CN113833480A (en) * 2021-09-29 2021-12-24 成都建工第九建筑工程有限公司 Shield initial tunneling and arrival construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005042546A (en) * 2004-11-15 2005-02-17 Kajima Corp Branch type propulsive excavator
CN102425433A (en) * 2011-12-30 2012-04-25 中铁一局集团有限公司 Minus-ring-free originating construction method for constructing sectional shield tunnel
CN103711499A (en) * 2014-01-08 2014-04-09 中铁十三局集团第六工程有限公司 Shield tunneling machine split starting construction method
CN203891897U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Grouting system of split starting shield tunneling machine
CN203891887U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Split starting shield tunneling machine
CN104775825A (en) * 2015-05-06 2015-07-15 中铁四局集团有限公司 Shield machine single well overall originating construction method
CN104912560A (en) * 2015-06-11 2015-09-16 北京市市政四建设工程有限责任公司 Small-radius shield curve launching construction technology on gravel clay layer
CN105221153A (en) * 2015-09-16 2016-01-06 中铁十局集团第三建设有限公司 The overall station-crossing construction method of shield machine
CN105298503A (en) * 2015-09-16 2016-02-03 中铁十局集团第三建设有限公司 Separate launching construction method of shield tunneling machine in narrow space

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005042546A (en) * 2004-11-15 2005-02-17 Kajima Corp Branch type propulsive excavator
CN102425433A (en) * 2011-12-30 2012-04-25 中铁一局集团有限公司 Minus-ring-free originating construction method for constructing sectional shield tunnel
CN103711499A (en) * 2014-01-08 2014-04-09 中铁十三局集团第六工程有限公司 Shield tunneling machine split starting construction method
CN203891897U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Grouting system of split starting shield tunneling machine
CN203891887U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Split starting shield tunneling machine
CN104775825A (en) * 2015-05-06 2015-07-15 中铁四局集团有限公司 Shield machine single well overall originating construction method
CN104912560A (en) * 2015-06-11 2015-09-16 北京市市政四建设工程有限责任公司 Small-radius shield curve launching construction technology on gravel clay layer
CN105221153A (en) * 2015-09-16 2016-01-06 中铁十局集团第三建设有限公司 The overall station-crossing construction method of shield machine
CN105298503A (en) * 2015-09-16 2016-02-03 中铁十局集团第三建设有限公司 Separate launching construction method of shield tunneling machine in narrow space

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109695455A (en) * 2018-12-21 2019-04-30 中铁十二局集团有限公司 Method of reseptance in a kind of earth pressure balanced shield, EPBS pure water
CN109763827A (en) * 2019-03-29 2019-05-17 中山大学 A kind of vertical shaft shield construction method and vertical shaft shield machine
CN112081595A (en) * 2019-06-14 2020-12-15 宏润建设集团股份有限公司 Shield construction method, and waterproof and monitoring method for shield construction
CN112081595B (en) * 2019-06-14 2022-09-23 宏润建设集团股份有限公司 Shield construction method, and waterproof and monitoring method for shield construction
CN110185458A (en) * 2019-07-04 2019-08-30 中建五局土木工程有限公司 Two-way shield launching method
CN110924960A (en) * 2019-11-25 2020-03-27 中铁十六局集团北京轨道交通工程建设有限公司 Subway construction method for shield starting before constructing station structure
CN111058860A (en) * 2019-12-10 2020-04-24 中铁十四局集团隧道工程有限公司 Cave opening construction method
CN111140240A (en) * 2020-01-03 2020-05-12 中交一公局第三工程有限公司 Split starting construction method for large-diameter earth pressure balance shield curve of sandy cobble stratum
CN111173528A (en) * 2020-01-06 2020-05-19 中交一公局第三工程有限公司 Large-diameter long-interval tunnel shield construction method for water-rich sandy gravel stratum
CN111350523B (en) * 2020-03-27 2021-07-13 中建八局轨道交通建设有限公司 Construction method and device for dismantling negative ring in limited space
CN111350523A (en) * 2020-03-27 2020-06-30 中建八局轨道交通建设有限公司 Construction method and device for dismantling negative ring in limited space
CN113006808A (en) * 2021-04-23 2021-06-22 中铁六局集团有限公司交通工程分公司 Construction method for viscous geological shield initial section to penetrate shallow soil-covered river channel downwards
CN113236264A (en) * 2021-04-28 2021-08-10 中铁六局集团有限公司交通工程分公司 Split starting construction method for shield of small clearance, upper soft and lower hard stratum
CN113833480A (en) * 2021-09-29 2021-12-24 成都建工第九建筑工程有限公司 Shield initial tunneling and arrival construction method
CN113833480B (en) * 2021-09-29 2024-05-24 成都建工第九建筑工程有限公司 Construction method for initial tunneling and arrival of shield

Similar Documents

Publication Publication Date Title
CN108952733A (en) Separate launching shield technique application construction method in municipal sewerage engineering
CN100501124C (en) Construction method for tunnel contact passage in shield section of underground railway
CN104265321B (en) Ultra-large type tunneling boring rectangular top pipe tunneling construction method
CN104343455B (en) Long-distance curved jacking pipe and pipe roof construction technique
CN102277898B (en) Drain pipe jacking construction method
CN102251530B (en) Construction process of double-wall steel cofferdam for construction of pier bearing platform in main river water of Yellow River
CN102080548B (en) Construction method of tunnel to cross airport runway by shield method
CN207777770U (en) A kind of precast spliced pipe fitting jacking system
CN113833480A (en) Shield initial tunneling and arrival construction method
CN108678756A (en) It closes on rivers highly permeable stratum major diameter slurry shield and originates construction safely
CN112012753B (en) Shield tunneling machine starting method based on special-shaped extension steel ring
CN109505613A (en) Originating method in the hole of earth pressure balanced shield, EPBS in small space
CN106223963A (en) A kind of shield machine air pushing construction method by subsurface excavation method tunnel
CN107795749A (en) A kind of precast spliced pipe fitting jacking system and its construction method
CN110924961B (en) Construction method for starting shield tunneling machine to pass through existing station
CN104989873B (en) Penstock oblique-pulling inversion assembling method
CN101907202A (en) Portable support type jack-based pipe installation construction method
CN104594379A (en) Heat insulation culvert pipe system between internal lines in railway station and burial and construction method
CN107131000B (en) Intelligent jet filling mining equipment for underground coal mine
CN208058113U (en) A kind of amendment construction system of construction push pipe
CN211144498U (en) Novel shield cutter head
CN109695455B (en) Method for receiving soil pressure balance shield in pure water
CN112922610A (en) Construction method for special railway line for downward passing freight by using shield tunneling machine
CN111928014A (en) Pipe jacking engineering construction method
CN110985017B (en) Construction method for shield tunneling of rainwater box culvert under expansive soil stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181207